You are on page 1of 8

350 IEEE TRANSACTIONS ON SUSTAINABLE ENERGY, VOL. 4, NO.

2, APRIL 2013

Steady-State Analysis of Maximum Photovoltaic


Penetration Levels on Typical Distribution Feeders
Anderson Hoke, Student Member, IEEE, Rebecca Butler, Joshua Hambrick, Member, IEEE, and
Benjamin Kroposki, Senior Member, IEEE

AbstractThis paper presents simulation results for a taxonomy and are best interpreted as indicating that steady-state voltage
of typical distribution feeders with various levels of photovoltaic and current do not limit PV penetration in the relevant cases,
(PV) penetration. For each of the 16 feeders simulated, the max- not that very high PV penetrations are necessarily achievable.
imum PV penetration that did not result in a steady-state voltage
or current violation is presented for several PV location scenarios: Previous reports have looked at various penetrations of PV on
clustered near the feeder source, clustered near the midpoint of a single feeder in steady state, concluded that reverse power flow
the feeder, clustered near the end of the feeder, randomly located, can cause overvoltages, and examined methods of resolving this
and evenly distributed. In addition, the maximum level of PV is problem [4], [5]. In [6], reverse power flow due to evenly dis-
presented for single, large PV systems at each location. Maximum tributed generation was shown to exceed transformer thermal
PV penetration was determined by requiring that feeder voltages
stay within ANSI Range A and that feeder currents stay within the ratings on a sample feeder. Many other papers have focused on
ranges determined by overcurrent protection devices. Generation power curtailment or provision of reactive power to alleviate
ramp rates, protection and coordination, and other factors that feeder voltage problems that arise with high PV penetrations
may impact maximum PV penetrations are not considered here. on single representative feeders, e.g., [7][9]. Other works have
Simulations were run in GridLAB-D using hourly time steps over a examined various PV penetrations in specific locations, e.g.,
year with randomized load profiles based on utility data and typical
meteorological year weather data. For 86% of the 336 cases simu- [10], [11], or in simplified feeder models with only a few buses
lated, maximum PV penetration was at least 30% of peak load. [12]. The study described here appears to be the first to evaluate
maximum steady-state PV penetrations at several locations on
Index TermsDistributed power generation, photovoltaic (PV)
systems, power distribution, power system simulation. a range of circuits designed to be representative of all U.S. ra-
dial feeders. This work does not consider the use of PV-based
reactive power or other PV-based means of regulating voltage.
I. INTRODUCTION A commonly used rule of thumb in the U.S. allows distributed
PV systems with peak powers up to 15% of the peak load on a
feeder (or line section) to be installed without a detailed dis-

A S THE portion of electrical energy produced by dis-


tributed resources increases, concerns heighten over the
potential for such resources to create steady-state voltage or
tribution system impact study [13]. This necessarily conserva-
tive rule has been a useful way to allow many distributed PV
systems to be installed without costly and time-consuming dis-
current violations on electrical distribution feeders [1][3]. tribution system impact studies. However, as total distributed
When power generated from distributed resources exceeds the PV power increases on many feeders, and as PV systems whose
load on a feeder line section, voltages may rise on that section. peak power is a significant fraction of feeder capacity become
In addition, significant aggregations of distributed resources more common, a more rigorous study of the impacts of various
may cause feeder currents to approach or exceed conductor PV penetration levels on feeder voltages and currents is justi-
and protection limitations. In order to determine which levels fied.
of photovoltaic (PV) penetration create voltage or current To model the effects of various PV penetration levels across
problems, this study simulates various levels of PV penetration the wide spectrum of U.S. distribution feeder architectures,
on 16 typical distribution feeders. The PV generation is simu- this study employs a publicly available taxonomy of 24 radial
lated at a variety of locations on each feeder in a steady-state distribution feeder models developed at Pacific Northwest
analysis. This work does not consider generation ramp rates, National Laboratory (PNNL) [14]. The 24 models represent
protection and coordination, or other issues that also might detailed utility feeder types, which statistically represent typ-
impact maximum feeder PV penetration levels. Some of the ical radial distribution feeders from five U.S. climate regions.
maximum PV penetration results presented here are very high The models are based on 575 utility feeder models gathered
from 17 electric utilities including public, municipal, and
Manuscript received July 20, 2012; revised September 21, 2012; accepted Oc- investor-owned utilities, as well as Rural Electrification Asso-
tober 09, 2012. Date of publication November 20, 2012; date of current version
ciation (cooperative) members. The taxonomy feeders do not
March 18, 2013. This work was supported by the U.S. Department of Energy
under Contract DE-AC36-08GO28308. contain geospatial information, as a condition of the agreement
The authors are with the National Renewable Energy Laboratory, Golden, CO under which the utilities provided the models. Due to software
80401 USA (e-mail: andy.hoke@nrel.gov).
limitations, eight of the 24 feeders were not used in this study.
Color versions of one or more of the figures in this paper are available online
at http://ieeexplore.ieee.org. The simulation platform used to model the feeders is PNNLs
Digital Object Identifier 10.1109/TSTE.2012.2225115 GridLAB-D version 2.2 [15]. GridLAB-D uses an unbalanced

U.S. Government work not protected by U.S. copyright.


HOKE et al.: STEADY-STATE ANALYSIS OF MAXIMUM PV PENETRATION LEVELS 351

three-phase power flow solver that has been validated against


standard distribution power flow simulation and analysis tools
using the IEEE Radial Test Feeders [16].
For this study, each of the load points in the 16 taxonomy
feeders was populated with hourly averaged load data from a
utility in the feeders geographical region [14], scaled and ran-
domized to emulate real load profiles. PV systems driven by typ-
ical meteorological year (TMY2) [17] weather data were then
inserted in each feeder model according to each of the loca-
tion scenarios described in Section II. For each combination of
feeder and PV location scenario, annual simulations were per-
formed at PV capacity penetration levels of 15% of peak load,
30% of peak load, 45% of peak load, etc. Maximum and min-
imum feeder voltages were recorded for each simulation, and Fig. 1. Maximum feeder loads found by simulation versus nominal feeder
simulations were continued at increasing PV penetration levels loads.
until voltage exceeded ANSI Range A [18] or current exceeded
the overcurrent protection rating at some location in the circuit.
In this manner, maximum PV penetrations were determined for
each feeder under each PV location scenario. This process is
described in detail in Section II, and results are presented in
Sections III and IV.

II. METHODOLOGY
In this study, PV penetration is defined as the ratio of total
peak PV power to peak load apparent power on the feeder Fig. 2. Linear fit of nominal load to maximum feeder load found by simulation.

(1)
load given in [14].1 Fig. 2 shows an analysis of the corre-
lation between maximum scaled feeder loads as found by
simulation and nominal feeder loads. While overall corre-
A. Feeder Loading lation between simulated maximum load and nominal load
The taxonomy feeders used for this study do not incor- is relatively strong, certain individual feeder peak loads di-
porate time-varying load information. Annual load profiles verge significantly from nominal loads because the same
(8760 hourly loads) were developed for each load location loading algorithm was applied to all feeders. This has a sig-
using three steps: nificant impact on PV penetration results and contributes to
1) An appropriate averaged load profile for each load class some anomalous results discussed later in this paper; for
(commercial and residential) was obtained from a utility example, feeder R1-12.47-3 has relatively low load so its
in the feeders geographical region, as defined in [14]. For maximum PV penetration as calculated from (1) is skewed
region 5, comprising the far Southeast near the Gulf of high.
Mexico, no load profile information was publicly avail- 3) To reflect the stochastic nature of real loads, the load pro-
able, so load profile data from neighboring region 4 was files were then randomized. Each of the 8760 scaled annual
used. Commercial loads were assigned a load profile from load values for each load point was multiplied by a factor
the utilitys commercial or industrial load class, and resi- sampled from a Gaussian (normal) distribution. The stan-
dential loads were assigned a load profile from the residen- dard deviation of the Gaussian distribution was 0.2, and its
tial load class. mean value was 1.0. This resulted in a load diversity factor
2) The load profiles were then scaled by a feeder-specific of about 1.3 for each load class. Each transformer feeds
scale factor and by the transformer capacity at each exactly one load, indicating that the creators of the feeders
load point. In this study, is defined as the ratio of peak may have consolidated the feeder loads. To account for this
apparent load power to total rated load transformer ap- consolidation, a nominal residential load size of 5 kVA was
parent power. For each feeder, was determined by run- assumed, and randomization was applied to each 5-kVA in-
ning multiple yearly simulations with one-hour time steps, crement for residential transformers. No typical load size
varying . A bisection search was used to find the max- was assumed for commercial transformers because com-
imum for each feeder that maintained load voltages mercial loads vary widely in size. Hence, the amplitude of
within ANSI Range A, line currents below their respective random hour-to-hour fluctuations in commercial loads is
continuous current ratings, and fuse currents below fuse much larger than for residential loads, and also larger than
amperage ratings. Fig. 1 shows the maximum scaled load 1The nominal feeder loads used here are as given in [14, Table 10] and are
found by simulation for each feeder alongside its nominal the peak planning loads [19].
352 IEEE TRANSACTIONS ON SUSTAINABLE ENERGY, VOL. 4, NO. 2, APRIL 2013

one PV system per feeder. The methodologies used to produce


these nine PV location scenarios are as follows.
Distributed PV: The first five location scenarios all involve
several distributed PV systems on the same feeder. In these sce-
narios, each PV system is installed at the location of an existing
load and is scaled according to the load size and the desired PV
penetration level. The distributed PV scenarios are:
1) PV clustered near the substation source;
2) PV clustered near the midpoint of the feeder;
3) PV clustered near the end of the feeder;
4) PV evenly distributed throughout the feeder;
5) PV randomly distributed throughout the feeder.
To produce scenarios 1, 2, and 3, the existing load points on a
Fig. 3. Total normalized residential and commercial loads for feeder feeder were sorted according to distance from the feeder source,
R1-12.47-4 over two days (one weekend day and one weekday), plotted with defined as the total conductor length from the source to the load
the normalized residential and commercial reference load profiles for region
1. The total residential load follows its reference profile much more closely in question. A PV system was added at the load point that best
than the commercial load profile because this feeder has more residential fits the desired location criterion, sized with peak PV power at
transformers, and because the residential transformers are randomized in 80% of the loads transformer rating. Another PV system was
5-kVA increments. With just 12 commercial transformers on this feeder, the
largest transformers dominate the total load, so random variations applied to then added at the next-best-fitting load point, sized in the same
those loads lead to significant deviations from the reference load profile. way. This process continued until the desired PV penetration
was reached. For example, to produce scenario 2 (PV near the
midpoint), the load closest to the middle of the feeder received
it would be in a typical feeder. Some of the random vari- PV first, then the load second-nearest to the middle of the feeder
ations in load profiles disappear when they are aggregated received PV, and so on, until the desired PV penetration was
into a total feeder load profile. Randomizing loads after ap- reached. For PV penetrations exceeding 70%, the PV systems
plication of the scaling factor caused some minimum an- added to each load point were sized at 1.5 times the desired PV
nual load voltages to drop below ANSI Range A, but re- penetration multiplied by , multiplied by the respective load
main within ANSI Range B, which reflects the conditions transformer rating.
on physical feeders. Occasionally, randomization of loads To produce scenario 4, PV was added at all load points. The
caused overcurrents in the baseline (no PV) year-long sim- peak PV power was set equal to the desired PV penetration,
ulation. In those cases, all loads on the feeder were reduced multiplied by , multiplied by the applicable load transformer
by 25% and the baseline case was resimulated. Finally, a rating. As a result, each load point has a PV system sized in pro-
power factor of 0.9 was applied to all loads. Fig. 3 shows portion to its transformer size to achieve the desired PV pene-
final scaled and randomized total load profiles (residential tration.
and commercial) for one feeder over two days, compared To produce scenario 5, the various load points were sorted
to the reference load profiles for the feeders region. into a random order and PV was added to successive load points
until the desired PV penetration was reached.
In all scenarios 1, 2, 3, and 5, the size of the final PV system
B. PV Model
added was scaled down to achieve the desired PV penetration
This study used the built-in PV system model provided in exactly.
GridLAB-D version 2.2. Each PV system is represented as a Note that clustering PV near the end of a feeder does not nec-
current source at unity power factor. The magnitude of the PV essarily result in PV systems that are physically or electrically
current is determined from the equation , where close together. For example, in scenario 3, a feeder with two
is the grid voltage, is the total surface area of PV array branches of approximately equal length would receive some PV
cells, is the global solar irradiance as provided by the TYM2 near the end of each branch.
data, and is the total conversion efficiency from cell to inverter Single PV system: The remaining four location scenarios all
output power. This very simple PV model neglects effects such involve a single, large PV system on a feeder.2 In these sce-
as temperature and array orientation. The effect of these sim- narios, the PV system was not installed at the location of an ex-
plifications is that simulated PV power is nearly always a few isting load, but rather was installed on its own transformer that
percent greater than actual PV output power would be, leading was added specifically for the PV system. This transformer is
to slightly conservative estimates of maximum PV penetration. not included in the total load transformer power. The single PV
system scenarios are:
C. PV Location Scenarios 6) single PV system close to the feeder source;
7) single PV system near the feeder midpoint;
After applying appropriately scaled and randomized load 8) single PV system at the end of the feeder;
profiles, each feeder was simulated at various PV penetrations 2These scenarios are also representative of cases where many PV systems are
under several PV location scenarios. The scenarios studied interconnected on the same bus. Simulated large PV system sizes range from
include five distributed PV scenarios and four scenarios with 75 kW to tens of MW.
HOKE et al.: STEADY-STATE ANALYSIS OF MAXIMUM PV PENETRATION LEVELS 353

TABLE I
MAXIMUM PV PENETRATION FOR ALL DISTRIBUTED PV SCENARIOS (IN % OF PEAK LOAD)

9) single PV system at a randomly selected point. where the PV penetration reached higher than 100% of peak
To site the single PV system in scenarios 6, 7, and 8, all load, the step size was increased to 50%. A bisection search was
three-phase nodes on the circuit were sorted by distance from then conducted to define the maximum PV penetration more
the feeder source and the PV system and its transformer were narrowly. The resolution of the bisection search for PV pen-
installed at the location that best fit the desired scenario. For etrations below 150% was 5 percentage points. Above 150%
example, to produce scenario 8, a single PV system and trans- penetration, the resolution began rising based on the assumption
former were installed at the farthest three-phase node from the that, for these very high penetration cases, the exact maximum
source. For scenario 6, the node where the PV system was in- penetration is not as relevant as the insight that maximum PV
stalled was required to be at least 300 feet from the source to penetration is not limited by steady-state voltage or current. The
ensure that the system was downstream from all substation com- maximum search resolution was 30 percentage points.
ponents. The maximum PV penetration results listed here have been
To produce scenario 9, the PV system and transformer were spot-checked for power flow solution errors using hand anal-
placed at a randomly selected three-phase node, again with the ysis and automated error-checking. No errors were found. While
requirement that the node be at least 300 feet from the feeder it would be ideal to verify each result via theoretical analysis,
source. doing so is not practical given the complexity of the feeders,
For each of these scenarios, the PV system was sized so that which contain hundreds of nodes and thousands of components
it alone would meet the desired PV penetration level. The trans- simulated at 8760 time points for each scenario. Efforts are un-
former was sized to have a rated apparent power 20% larger derway to experimentally verify the effects of high PV pene-
than the PV system peak rated power. During simulation of trations, determine maximum allowable penetration levels, and
scenarios 69, current was monitored in the line immediately verify models in high penetration scenarios [20][23]. These
upstream from the PV system and compared to the continuous studies focus on specific geographic locations or feeders. In
summer current rating of the line. Voltage was monitored at the physical experiments, it is not practical to test the wide variety
PV system point of common coupling (and as in all scenarios, of PV location and penetration level scenarios tested here. We,
the voltages at all loads and the states of all fuses were moni- therefore, must rely on the accuracy of GridLAB-Ds power
tored). flow solutions and the correct construction of the taxonomy
All PV systems simulated were installed at locations chosen feeders, which have been thoroughly verified [14], [15].
by a computer algorithm that, to avoid introducing bias, did
not evaluate the suitability of the locations for PV. For the dis- III. DISTRIBUTED PV RESULTS AND ANALYSIS
tributed PV cases all load points were considered, and for the
single PV system simulations all three-phase nodes were con- This section describes simulation results for the distributed
sidered. On real feeders distribution engineers typically avoid PV location scenarios (scenarios 15). Scenarios 1 through 4
allowing significant PV interconnection in poor locations, so were simulated once for each feeder, and the random location
some of the lowest maximum penetration limits found in this scenario was simulated five times for each feeder.
study may be overly conservative. Table I lists the maximum PV penetration results for the var-
ious distributed PV scenarios. The number preceded by R
D. PV Penetration Levels in each feeder name indicates its geographical region. Values
of maximum PV penetration obtained vary widely among the
For each of the nine scenarios and 16 feeders, GridLAB-D feeders, reflecting the diversity of physical feeder configura-
simulations were performed at PV penetrations of 0% (the base tions. Maximum PV penetration also varied widely from one
case), 15%, 30%, and so on, with 15% steps until an overvoltage location to another on most feeders. All feeders tolerated at least
or overcurrent was detected at any point during the year. In cases 75% PV penetration in at least one case.
354 IEEE TRANSACTIONS ON SUSTAINABLE ENERGY, VOL. 4, NO. 2, APRIL 2013

addition to these feeders, two cases of maximum PV penetra-


tion below 50% remain: PV at mid-feeder and end-of-feeder on
R1-12.47-2. Notably, these are the same two outlier cases that
appear in the lower left corner of Fig. 4. Both cases are limited
by overcurrent conditions.
For the feeders that exhibit low PV tolerance, all are most
tolerant of evenly distributed PV. In fact, maximum penetration
for evenly distributed PV is at least 75% in all cases. However,
encouraging or enforcing the even distribution of PV on a feeder
would likely be difficult in practice.
The five simulations involving randomly located distributed
PV on feeder R1-12.47-2 all resulted in maximum penetrations
above 50%, and four of the five were above 100%. In addi-
tion, the feeders limit for single large PV systems was above
100% in all scenarios, indicating that the feeder does tolerate
Fig. 4. Maximum distributed PV penetration versus maximum baseline load large amounts of distributed PV in most scenarios. The two
voltage with linear fits shown for each location scenario. cases of low maximum PV penetration on feeder R1-12.47-2
are due to overcurrent and appear to result from weak spots on
Maximum PV penetration for many feeder-location combi- smaller branches of the distribution feeder. For the mid-feeder
nations reaches well over 100%. For these very large PV pene- case, voltage was not a problem until PV penetration was over
trations, it is likely that other effects not modeled in this study 100%. For the end-of-feeder case, overvoltages occurred for PV
would limit physical PV penetration levels. For example, the penetrations above 34%, indicating that this feeder has a low tol-
taxonomy feeders do not include models of the substation trans- erance for PV located far from the source from both voltage and
former connecting the distribution feeder to the transmission current perspectives.
system. This transformers power rating would likely become Because switched capacitors can influence feeder voltages
a limiting factor in cases of very large PV penetration. Also, the significantly, the relationship between maximum PV penetra-
transmission system is represented as an ideal voltage source in tion and the presence of switched capacitors performing voltage
GridLAB-D, so any voltage rise it may experience due to very control was also examined. No notable correlation was found.
high PV penetrations is neglected. Similarly, dynamic concerns
such as generator ramp rates are neglected. Other factors that IV. SINGLE PV SYSTEM RESULTS AND ANALYSIS
are not addressed in this study and may limit PV penetration This section describes simulation results for the PV loca-
at moderate penetrations include protection, coordination, and tion scenarios involving a single PV system per feeder (sce-
power quality issues [24], [25]. Therefore, in very high penetra- narios 69). Each of scenarios 68 was simulated once for each
tion cases, it is more appropriate to conclude that steady-state feeder, and the random location scenario was simulated nine
voltage and current are not the limiting factors than that the times for each feeder.
feeder can actually tolerate such high levels of PV. Table II lists the maximum PV penetration results for all
While, in general, maximum PV penetration results were feeders and all single PV system scenarios simulated. The
quite high, several feeders, especially those in region 5, show maximum penetrations in Table II tend to be higher than those
relatively low limits to PV penetration. In general, these found for the distributed PV scenarios. In several cases, the
feeders exhibited very high hourly average and maximum load maximum penetration was over 500% of peak load, which, for
voltages even when simulated without PV. The five feeders the reasons listed in Section III, is a much larger PV system
with the lowest limits to PV penetration (feeders R2-25.00-1, than would be considered for installation.
R5-12.47-4, R5-12.47-5, R5-25.00-1, and R5-35.00-1) all have The highest maximum penetration result was 1680% for
maximum baseline (no PV) meter voltages above 1.037 pu. The the case of a single large PV system near the source of feeder
possibility that maximum baseline meter voltages are high due R1-12.47-3. Feeder R1-12.47-3 was a lightly loaded feeder, so
to under-loading of these feeders by the loading methodology quantifying PV penetration relative to load (rather than some
has been eliminated by examining minimum baseline hourly measure of feeder capacity) is partly responsible for the very
average meter voltages, which range from 0.96 to 0.99 pu on high penetration value. The peak load of this feeder is 34% of
these five feeders. Fig. 4 examines the relationship between total load transformer rating, so 1680% of peak load represents
maximum baseline feeder load voltage and maximum PV pen- 570% of the feeders total load transformer rating, which is still
etration. The data in Fig. 4 suggest that while a high baseline a very high penetration. As mentioned in Section II, the single
voltage does not guarantee a low limit to PV penetration, a low PV system installed in PV location scenarios 69 is installed on
limit is more likely. its own new transformer (and this transformers power rating
Fig. 5 shows maximum PV penetration results by feeder for is not included in the total load transformer rating). The rated
the nonrandom location scenarios. PV penetration limits are peak dc power of the PV system is 9.2 MW, and the maximum
above 50% except for a few outliers. Most of the outliers cor- measured ac output power of the PV system was 7.5 MW.
respond to the previously identified five feeders where max- The maximum measured currents on the three phases of the
imum and average baseline load voltages are relatively high. In line immediately upstream from the PV system were 334, 325,
HOKE et al.: STEADY-STATE ANALYSIS OF MAXIMUM PV PENETRATION LEVELS 355

Fig. 5. Maximum PV penetration for all nonrandom, distributed location scenarios. Columns with an asterisk (*) above indicate cases where PV penetration was
limited by overvoltage; otherwise PV penetration was limited by overcurrent. One result over 300% is truncated.

TABLE II
MAXIMUM PV PENETRATION FOR ALL SINGLE-SYSTEM SCENARIOS (IN % OF PEAK LOAD)

and 333 A, which are just within the per-phase continuous


summer current rating of the line, 334 A. The peak backflow
power was approximately 7.1 MW. The rest of the feeder was,
therefore, drawing MW at the time of peak
backfeed power. The nominal peak feeder load is 1.4 MW,
and the simulated peak feeder load was 0.56 MW. The power
going back into the substation is about 7.1 MW, or 5.1 times
the nominal peak load. Therefore, this feeders maximum PV
penetration for an installation located very near the source
would very likely be limited by substation equipment power
and protection settings to a much lower value than that found
here. The PV system was installed 472 feet from the feeder
source, and the maximum voltage on the PV side of the trans-
former was 1.003 pureasonable given that very little voltage
rise is expected over such a short distance. Fig. 6. Maximum single-system PV penetrations as a function of maximum
baseline load voltage, with linear fits shown for each location scenario.
Feeder R4-25.00-1 showed the same very high maximum
PV penetration of 805% for all single PV system scenarios.
The three-phase section of this feeder (which is the only sec- than those found in this study. The range of maximum PV pen-
tion where our algorithm installed PV in scenarios 69) ex- etration results for each single PV system scenario tends to be
tends only about 1.2 miles and consists of a single line with wider than the range for distributed PV systems. The differ-
one short branch. This line and its branch have the same con- ence in ranges is more than expected based solely on the higher
tinuous summer current rating of 530 A per phase over their number of simulations performed. The wider range of PV tol-
entire lengths, and that current rating was the limiting factor in erances reflects the variation in PV tolerance from one node to
all single PV system scenarios, leading to identical penetration another in the feeder; a node that happens to be on the main
limits in all cases. As in other very high penetration cases, un- feeder line is likely to have a much higher PV tolerance than a
modeled factors would limit PV penetrations to lower values node on a small branch line. In contrast, a distributed group of
356 IEEE TRANSACTIONS ON SUSTAINABLE ENERGY, VOL. 4, NO. 2, APRIL 2013

Fig. 7. Maximum PV penetrations for the 16 taxonomy feeders with single PV systems. Columns with an asterisk (*) above indicate cases where PV penetration
was limited by overvoltage; otherwise PV penetration was limited by overcurrent. Results over 500% are truncated.

Fig. 8. Maximum PV penetrations plotted against conductor distance from PV system to feeder source, by geographic region.

PV systems becomes too large when any of the many affected requirement that the system be installed at a three-phase node
points on the feeder experiences overvoltage or overcurrent; the increases the probability of selecting a node near the trunk of
variation from one group to another is smaller due to aggrega- the feeder where voltage is less likely to be an issue.
tion effects. Simulations with single PV systems provide an opportunity
Compared to the distributed PV scenarios, more feeders to examine the relationship between maximum PV penetration
showed minimum PV tolerances of less than 30%. This is and distance from the PV system to the feeder source. This
expected; putting a single PV system sized at more than 30% relationship is shown in Fig. 8, where distance was measured
of the entire feeders peak load on a small branch will cause by following the conductors back to the source. This shows a
voltage and/or current problems. definite trend of decreasing PV tolerance with distance. There
The relationship of maximum PV penetration to maximum are, however, many exceptions to the trend. These exceptions
baseline meter voltage was analyzed (Fig. 6). Again, the trend are largely because some PV systems were installed on smaller
is for PV tolerance to decrease with increasing voltage, although feeder branches by the intentionally unintelligent PV location
there are more outliers than in Fig. 4, reflecting the high case-to- algorithm.
case variation in single PV system scenarios.
Fig. 7 shows the maximum PV penetrations for each feeder V. CONCLUSION
under each nonrandom location scenario. Results over 500% are In this paper, several trends have been noted when consid-
truncated to provide better resolution for more realistic pene- ering maximum PV penetration relative to steady-state voltage
trations. For single PV systems, more scenarios are limited by and overcurrent: For distributed PV systems, maximum PV pen-
current than in the distributed PV scenarios. This is because the etration was nearly always above 50% unless the feeder already
HOKE et al.: STEADY-STATE ANALYSIS OF MAXIMUM PV PENETRATION LEVELS 357

[8] C. H. Lin, W. L. Hsieh, C. S. Chen, C. T. Hsu, and T. T. Ku, Op-


timization of photovoltaic penetration in distribution systems consid-
ering annual duration curve of solar irradiation, IEEE Trans. Power
Syst., vol. 27, no. 2, pp. 10901097, May 2012.
[9] P. M. S. Carvalho, P. F. Corriea, and L. A. F. Ferriera, Distributed
reactive power generation control for voltage rise mitigation in distri-
bution networks, IEEE Trans. Power Syst., vol. 23, no. 2, pp. 766772,
May 2008.
[10] V. Ramachandran, Steady state analysis of three phase unbalanced
distribution systems with interconnection of photovoltaic cells, in
Proc. IEEE Power Systems Conf. and Exposition, Phoenix, AZ, Mar.
2011.
[11] J. E. Quiroz and C. P. Cameron, Technical Analysis of Prospective
Photovoltaic Systems in Utah Sandia National Laboratory report,
SAND2012-1366, Feb. 2012.
[12] A. Faaborg, Impacts of Power Penetration From Photovoltaic Power
Systems in Distribution Networks International Energy Agency report,
Report IEA-PVPS T5-10, Feb. 2002.
[13] IEEE Application Guide for IEEE Std 1547, IEEE Standard for Inter-
connecting Distributed Resources With Electric Power Systems, IEEE
Std. 1547.2-2008, 2009, pp. 1207.
[14] K. Schneider, D. P. Chassin, R. Pratt, D. Engel, and S. Thompson,
Modern Grid Initiative Distribution Taxonomy Final Report PNNL,
Nov. 2008 [Online]. Available: http://www.gridlabd.org/models/
feeders/taxonomy_of_prototypical_feeders.pdf, Accessed Apr. 27,
2012:
Fig. 9. Percentage of simulated cases in which maximum PV penetration fell [15] K. Schneider, D. Chassin, Y. Pratt, and J. C. Fuller, Distribution power
in various ranges for distributed PV (top) and single PV systems (bottom). flow for smart grid technologies, in Proc. IEEE/PES Power Systems
Conf. and Exposition, Seattle, WA, Mar. 2009, pp. 17, 1518.
[16] IEEE radial test feeders [Online]. Available: www.ewh.ieee.org/soc/
exhibited maximum load voltages on the very high end of ANSI pes/dsacom/testfeeders.html
range A without PV. Maximum PV penetration generally de- [17] W. Marion and K. Urban, Users Manual for TYM2s, NREL, Jun. 1995
[Online]. Available: http://rredc.nrel.gov/solar/pubs/tmy2/
creases as the distance from the feeder source to the PV system [18] American national standard for electric power systems and equip-
increases, but most feeders still tolerate moderate to high PV mentVoltage ratings (60 Hz), NEMA, ANSI C84.1-2011.
penetrations even for PV systems near the end of the feeder. [19] J. Fuller [Online]. Available: http://sourceforge.net/projects/gridlab-d/
forums/forum/842562/topic/4719132, personal communication
Fig. 9 illustrates the general trend of very high PV toler- [20] B. Kroposki et al., Integrating high penetrations of PV into Southern
ance with a few notable exceptions. In 86% of all PV loca- California, in Proc. 26th Eur. Photovoltaic Solar Energy Conf. and
tion scenarios on all feeders, the maximum PV penetration was Exhibition, Hamburg, Germany, Sep. 2011, pp. 41974200.
[21] M. H. Coddington, D. Baca, B. D. Kroposki, and T. Basso, Deploying
above 30%. In two-thirds of cases, the maximum penetration high penetration photovoltaic systems: A case study, in Proc. IEEE
was greater than 90%. This does not indicate that two-thirds of Photovoltaic Specialists Conf. (PVSC), Seattle, WA, Jun. 2011, pp.
cases will actually tolerate greater than 90% PV penetration, but 25942599.
[22] SunShot Initiative High Penetration Solar Portal, U.S. Dept. of Energy
rather that steady-state voltage and current are not limiting fac- [Online]. Available: https://solarhighpen.energy.gov/
tors in approximately two-thirds of cases. While the 15% pene- [23] J. Hambrick and D. Narang, High-penetration PV deployment in the
tration rule of thumb was found to be conservative in most cases arizona public service system, phase 1 update, in Proc. 2012 IEEE
Photovoltaic Specialists Conf., Austin, TX, Jun, 2012.
(and sufficient in all single PV system cases), it was actually too [24] J. G. Slootweg and W. L. Kling, Impacts of distributed generation on
high in 16% of the distributed PV cases. power system transient stability, in Proc. IEEE Power Engineering
Society Summer Meeting, Chicago, IL, Jul. 2002, pp. 862867.
REFERENCES [25] M. Begovic, A. Pregelj, A. Rohatgi, and D. Novosel, Impact of re-
newable distributed generation on power systems, in Proc. 34th Ann.
[1] C. L. Masters, Voltage rise: The big issue when connecting embedded
Hawaii Int. Conf. System Sciences, Maui, HI, Jan. 2001, pp. 654663.
generation to long 11 kV overhead lines, IEEE Power Eng. J., vol. 16,
no. 1, pp. 512, Feb. 2002.
[2] Y. Liu, J. Bebic, B. Kroposki, J. de Bedout, and W. Ren, Distribution Anderson Hoke (S10), photograph and biography not available at the time of
system voltage performance analysis for high-penetration PV, in Proc. publication.
IEEE Energy 2030 Conf., Atlanta, GA, Nov. 2008, pp. 18, 1718.
[3] D. Caples, S. Boljevic, and M. F. Conlon, Impact of distributed gener-
ation on voltage profile in 38 kV distribution system, in Proc. 8th Int.
Conf. Eur. Energy Market, Zagreb, Croatia, May 2011, pp. 532536. Rebecca Butler photograph and biography not available at the time of publica-
[4] E. Liu and J. Bebic, Distribution System Voltage Performance Analysis tion.
for High-Penetration Photovoltaics NREL/SR-581-42298, Feb. 2008.
[5] X. Liu, A. Aichhorn, L. Liu, and H. Li, Coordinated control of
distributed energy storage system with tap changer transformers for
voltage rise mitigation under high photovoltaic penetration, IEEE
Trans. Smart Grid, vol. 3, no. 2, pp. 897906, Jun. 2012. Joshua Hambrick (M08), photograph and biography not available at the time
[6] L. M. Cipcigan and P. C. Taylor, Investigation of the reverse power of publication.
flow requirements of high penetrations of small-scale embedded gen-
eration, IET Renew. Power Generat., pp. 160166, Sep. 2007.
[7] T. Stetz, W. Yan, and M. Braun, Voltage control in distribution sys-
tems with high level pv-penetration, in Proc. 25th Eur. PV Solar En- Benjamin Kroposki (S90M92SM00), photograph and biography not
ergy Conf. and Exhibition, Valencia, Spain, Sep. 2010. available at the time of publication.

You might also like