You are on page 1of 3

February 2000

Process Industry Practices


Electrical

PIP ELSAP01D
Data Sheet for
Battery Chargers for Station Batteries
PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES

In an effort to minimize the cost of process industry facilities, this Practice has
been prepared from the technical requirements in the existing standards of major
industrial users, contractors, or standards organizations. By harmonizing these
technical requirements into a single set of Practices, administrative, application, and
engineering costs to both the purchaser and the manufacturer should be reduced. While
this Practice is expected to incorporate the majority of requirements of most users,
individual applications may involve requirements that will be appended to and take
precedence over this Practice. Determinations concerning fitness for purpose and
particular matters or application of the Practice to particular project or engineering
situations should not be made solely on information contained in these materials. The
use of trade names from time to time should not be viewed as an expression of
preference but rather recognized as normal usage in the trade. Other brands having the
same specifications are equally correct and may be substituted for those named. All
Practices or guidelines are intended to be consistent with applicable laws and
regulations including OSHA requirements. To the extent these Practices or guidelines
should conflict with OSHA or other applicable laws or regulations, such laws or
regulations must be followed. Consult an appropriate professional before applying or
acting on any material contained in or suggested by the Practice.

Process Industry Practices (PIP), Construction Industry Institute, The


University of Texas at Austin, 3208 Red River Street, Suite 300, Austin,
Texas 78705. PIP member companies and subscribers may copy this practice
for their internal use.

Not printed with State funds


PIP ELSAPO1D
February 2000 Data Sheet for Battery Chargers for Station Batteries

Client Engineering Org. Spec. No.


Project Title Location Date
Project Location Contract No. Equip. No.
Proj. No. Specifier Name Tele. No.
P.O. No.
Refer to Specification No. ELSAP01 for General Requirements
Applicable State and Local Codes: ____________________________________________

Data Provided by: ! Buyer " Seller with Proposal # Seller after Order

Site Conditions: Additional Alarms Requirements (4.6.2):


$ Altitude ___________ ft $ Seismic Zone ___________ $ AC Input Failure
$ Ambient Temperature: Max. ________F Min. ________F $ Charger Over-Temperature
$ Overload Shutdown
$ Other ____________________________________________
$ High Output Voltage
Battery Type & Load Requirements: $ Equalize Charge Mode
$ Lead-Calcium $ Lead-Antimony $ Battery End of Discharge
$ Nickel-Cadmium $ Other _____________ $ Output Breaker Open
No. of cells __________ $ Ground Fault Indication Meter (4.8.2)

Capacity __________ Amperes for _________ Hours,


Enclosure (4.11):
Enclosure Type (4.11.1): $ Mfr. Std. $ Other _____
to ________ Final Volts Per Cell (VPC)
Cable Entry (4.11.6): $ Top $ Bottom
Battery Recharge Time (to 90% Capacity) (4.1.4): ______ Hours
Paint Finish (4.12): $ Mfr. Std. $ Other _____
External DC Load (Excluding Battery): ___________Amps Max.
Duty Cycle Description: _______________________________ Nameplates (4.13):
(attach diagram) $ Nameplate Engraving:
Charger Ratings and Requirements: _______________________ _________________________
AC Input (4.3.2): _______ Volts, ______ Phase, ______ Hz _______________________ _________________________
$ Color: $ Black/White $ Other _________________
Available Short Circuit Current ______ Amps RMS Sym
Additional Testing Requirements (5.2):
DC Output Rating _______ Volts
_________________________________________________
$ Battery Eliminator (4.3.6)
_________________________________________________
DC Output Filtering (4.3.7): $ 30 mV $ 100 mV $ 200 mV
Documentation (7.0):
$ Other __________ " Electronic Document Format $ .DXF $ Other ________
$ Battery Temperature Compensation (4.3.11) Manufacturer to Provide:
Output Overcurrent Protection (4.3.16): 1 Reproducible Plus
________ Copies of All Documentation Plus
$ Circuit Breaker $ Fused Disconnect
________ Copies of the Operating Manuals
$ Parallel Operation Required (4.3.17)
Other Requirements:
$ Automatic Equalize Charging (4.4.3)

Process Industry Practices Page 1 of 1