Name of work : Name of work: Special Repairs to Bhuvanagiri-Melamanagudi road km 3/0-5/0

Work Code : 01-SR-16-17-S-0001


Estimate Amont : Rs. 30.00 Lakhs
Basic data adopted in preparation of estimate for the above work
Schedule of Rates Adopted in Estimate: 2016-17
I Emulsion / Bitumen
Rate exculding taxes
1 Bitumen Source: Manali
VG10 Rs. 26866.00 /MT
VG30 Rs. 27666.00 /MT
VG40 Rs. 26786.00 /MT
Lead to mid point of project road 245.00 Km
2 Emulsion Source: Irunkattukottai
Slow Setting Rs. 51432.00 /MT
Rapid Setting Rs. 31539.00 /MT
Lead to mid point of project road 214.00 Km

3 Lead to CMP
Metal Plain:27, Hills:0
Bitumen 231.00 Km
Lead from CMP site to work site 40 Km
II Terrain Classification (For conveyance) Plain

III Cost of Fuel


Furnace oil Rs. 34576.61
Deisel Rs. 58.85
Kerosene Rs. 52.03
IV Data for Bitumen Data for Emulsion
Excise Duty % 14.00 Excise Duty % 14.00
Educational Cess % 0.00 VAT % 14.50
VAT % 5.00 Storage % 5.00
Storage % 5.00 Drum cost(-) 1500
Conveyance factor 0.99924 Conveyance factor 1.69

V Data for other Allowances


Night Component No
Area Normal Location

VI Metal lead to Site


Chainage Name/ location of quarry Metal lead
km 3/0-4/0 Metal Quarry 1 at 3/2 of A-Sathanur-Pudukazhani road
Plain:66, Hills:0
km 4/0-5/0 Metal Quarry 1 at 3/2 of A-Sathanur-Pudukazhani road
Plain:67, Hills:0

Road Data - Rev-16.2 1 Revised during - Jan. 2017


km Metal Quarry 2 at __ Plain:0, Hills:0
km Metal Quarry 2 at __ Plain:0, Hills:0
km Metal Quarry 2 at __ Plain:0, Hills:0
km Metal Quarry 2 at __ Plain:0, Hills:0
km Metal Quarry 2 at __ Plain:0, Hills:0
km Metal Quarry 2 at __ Plain:0, Hills:0
km Metal Quarry 2 at __ Plain:0, Hills:0
km Metal Quarry 3 at __ Plain:0, Hills:0

VIII Gravel lead to site


Name/ location of quarry Gravel lead
km 3/0-4/0 Gravel quarry at 2/2 of Vanathirayapuram quarry Plain:29, Hills:0
km 4/0-5/0 Gravel quarry at 2/2 of Vanathirayapuram quarry Plain:30, Hills:0
km Gravel quarry at Plain:0, Hills:0
km Gravel quarry at Plain:0, Hills:0
km Gravel quarry at Plain:0, Hills:0
km Gravel quarry at Plain:0, Hills:0
km Gravel quarry at Plain:0, Hills:0
km Gravel quarry at Plain:0, Hills:0
km Gravel quarry at Plain:0, Hills:0
km Gravel quarry at Plain:0, Hills:0

IX Sand lead to site


Name/ location of quarry Sand lead
km 3/0-4/0 Sand quarry at __ Plain:0, Hills:0
km 4/0-5/0 Sand quarry at __ Plain:0, Hills:0
km Sand quarry at __ Plain:0, Hills:0
km Sand quarry at __ Plain:0, Hills:0
km Sand quarry at __ Plain:0, Hills:0
km Sand quarry at __ Plain:0, Hills:0
km Sand quarry at __ Plain:0, Hills:0
km Sand quarry at __ Plain:0, Hills:0
km Sand quarry at __ Plain:0, Hills:0
km Sand quarry at __ Plain:0, Hills:0

X Carted Earth lead to site


Name/ location of quarry Carted Earth lead
km 3/0-4/0 Earth quarry at __ Plain:0, Hills:0
km 4/0-5/0 Earth quarry at __ Plain:0, Hills:0
km Earth quarry at __ Plain:0, Hills:0
km Earth quarry at __ Plain:0, Hills:0
km Earth quarry at __ Plain:0, Hills:0
km Earth quarry at __ Plain:0, Hills:0

Road Data - Rev-16.2 2 Revised during - Jan. 2017


km Earth quarry at __ Plain:0, Hills:0
km Earth quarry at __ Plain:0, Hills:0
km Earth quarry at __ Plain:0, Hills:0
km Earth quarry at __ Plain:0, Hills:0

Road Data - Rev-16.2 3 Revised during - Jan. 2017


Highways Schedule of Rates 2016 - 2017
IRC HBG Metal Rates for 2016 - 2017
Area : Normal , Location :0, Locally Quarried Materials:No
Size Rate
90mm 385.00
75mm 430.00
63mm 557.00
53mm 677.00
46.50mm 908.00
45mm 908.00
37.50mm 927.00
26.50mm 876.00
25mm 876.00
22.40mm 1271.00
13.20mm 1179.00
11.20mm 800.00
6.70mm 594.00
6mm 594.00
5.60mm 594.00
4.75mm & Below 526.00

Labour Charges
Description Rate
Bitumen Sprayer Man 407.00
Bitumen Raker Man 424.00
Heat Master Operator 424.00
Mini Hot Mix Plant Operator 424.00
Gunnuting Plant Operator 355.00
Gunnuting Gun Operator 386.00
Road Mazdoor Gr.- I 350.00
Road Mazdoor Gr.-II 314.00
Head Mazdoor 361.00

Local Rates of Materials


Kerosene 52.03
Deisel 58.85
Furnace Oil 33.17
Hire Charges for Power Roller 828.00
Fuel For Roller per Hour 2.50
Hire Charges for Water Sprinkler per Day 1159.00
Fuel For Water Sprinkler per Hour (WBM) 3.50
Hire Charges for Mini Hot Mix Plant per Day 1674.00
Fuel for Mini Hot Mix Plant per Hour 15.00
Hire Charges for Bitumen Boiler per Day 202.00
Fuel for Bitumen Boiler per Day 25.00
Hire Charges for Vibrator Roller/ Hr 678.50
Water / KL 130.00
Fuel For Water Sprinkler per Hour (others) 3.25
Fuel For heating aggregate 45.00

Road Data - Rev-16.2 4 Revised during - Jan. 2017


Hire charges for machinery

Central Hot Mixing Plant-per day 9696


Vibratory Roller-per day 5428
Paver Finisher-per day 2447
Tipper Trucks-per day (10 Tonnes) 1094
Loader 5 cum capacity-per day 1205
Water tanker -per day 855
Motor grader-per day (110 HP) 13533
Pug mill-per day 6679
Generator-per day 5179
Tractor per hour 353
Tipper Trucks-per tonne /km 2
Fuel for water tanker per day 25
Rotovator per hour 17
Wet Mix Plant 75 tonne capacity/ day 8933
Bitumen emulsion sprayer / 10 sqm 15
Paver Finisher (9m)-per hour -including fuel 2674
Pneumatic tyred roller including fuel per hr 1243
Tractor - Rotovator (including fuel per day) 2824
Water tanker for Mix in place method 2005
CHENNAI
VG 10 26866.00
VG 30 27666.00
VG 40 26786.00

Road Data - Rev-16.2 5 Revised during - Jan. 2017


PWD Schedule of Rates 2016 - 2017
ISS HBG Metal Rates
Area : Normal , Location :0, Locally Quarried Materials:No
Size Rate
90mm 382.00 /Cum.
80mm 428.00 /Cum.
63mm 494.00 /Cum.
50mm 573.00 /Cum.
40mm 890.00 /Cum.
25mm 765.00 /Cum.
20mm 1239.00 /Cum.
12mm 1149.00 /Cum.
10mm 846.00 /Cum.
6mm 573.00 /Cum.
3mm 516.00 /Cum.
Rough Stone (Masonry) 394.00 /Cum.
Rough Stone (Revetment) 341.00 /Cum.
Bond Stones 540.00 /Cum.

Labour Charges
Description Rate
Carpenter - Ist Class 485.00 /Day
Carpenter - IInd Class 444.00 /Day
Fitter Ist Class (Pipe Laying/ Bar Bending) 431.00 /Day
Fitter II Class (Pipe Laying/ Bar Bending) 400.00 /Day
Mason I Class 496.00 /Day
Mason II Class 444.00 /Day
Mazdoor I Class 310.00 /Day
Mazdoor II Class 280.00 /Day
Head Mazdoor 321.00 /Day
Painter / Varnisher I Class 397.00 /Day
Painter / Varnisher II Class 369.00 /Day
Wodder 321.00 /Day

Rate of Materials (Other than Stones)


Description Rate
Gravel 169.50 /Cum.
Well Gravel 139.30 /Cum.
Quarry Rubbish 85.20 /Cum.
Stone Dust 109.00 /Cum.
Sand for Mortar 176.40 /Cum.
Sand for Filling 176.40 /Cum.
Shell Lime (Slaked & Screened) 1285.00 /Cum.
Binding Wire (Black 18G) 44.00 /Kg
Binding Wire (Galvanised - 18G) 44.00 /Kg
Cost of Cement (including storage 5%) 7057.09 /MT
Cost of Steel (including storage 5%) 43249.13 /MT
Cost of Earth (as per GO (D) 214 Industries 70.00 /Cum.
(MMC.2) Department dated 3.11.2015)

Road Data - Rev-16.2 6 Revised during - Jan. 2017


Rates of Works

Description Rate
Clearing Heavy Jungle 4.05 /Sqm.
Clearing Light Jungle 3.05 /Sqm.
Clearing Scrub Jungle 2.80 /Sqm.
Earth Work Excavation SS 20A 59.20 /Cum.
Earth Work Excavation SS 20B 55.60 /Cum.
Earth Work Excavation SS 20B for Foundation 111.20 /Cum.
Refilling with excavated Sand 17.10 /Cum.
Refilling with excavated soil (other than Sand ) 19.50 /Cum.
Vibrator Charges for PCC rate per Cum. 34.80 /Cum.
Vibrator Charges for RCC rate per Cum. 46.80 /Cum.
Mixing Mortar Cement by Manual 57.60 /Cum.
Mixing Mortar Cement by Machine 76.50 /Cum.

Conveyance Charges for Plains and Hills


Rough Stone, Jelly,Sand,Gravel
Km Plain Hills unit
0 - 10 Km 8.86 17.72 /km
10-20 Km 7.59 15.18 /km
20-40 Km 6.53 13.06 /km
40-80 Km 6.12 12.24 /km
80 & Above 5.14 10.28 /km

Road Data - Rev-16.2 7 Revised during - Jan. 2017


Name of work : Name of work: Special Repairs to Bhuvanagiri-Melamanagudi road km 3/0-5/0

Work Code : 01-SR-16-17-S-0001 Estimate Amount : Rs. 30.00 Lakhs

DATA ABSTRACT

Sl
Description Unit Rate
No.
GENERAL RATES (As Per Schedule of Rates)

1 Clearing Heavy Jungle /Sqm. 4.05

2 Clearing Light Jungle /Sqm. 3.05

3 Clearing Scrub Jungle /Sqm. 2.80

4 Earth Work Excavation SS 20A /Cum. 59.20

5 Earth Work Excavation SS 20B /Cum. 55.60

6 Earth Work Excavation SS 20B For Foundation /Cum. 111.20

7 Refilling With Excavated Sand /Cum. 17.10

8 Refilling With Excavated Soil (Other Than Sand ) /Cum. 19.50

9 Picking the Existing BT Surface /Sqm. 9.45

USING PLANT MIX / CENTRAL HOT MIX PLANT

10 GSB Grade - V Plant Mix /Cum. 1565.68

11 GSB Grade - III Plant Mix /Cum. 1645.58

Road Data - Rev-16.2 8 Revised during - Jan. 2017


Sl
Description Unit Rate
No.
12 WET MIX MACADAM /Cum. 1700.37

13 Crusher Run Macadam 300mm Thick /Cum. 1614.84

14 Prime Coat Over WBM / WMM Surface /Sqm. 69.06

15 Prime Coat Over CRM Surface /Sqm. 82.77

16 Tack Coat Over Primed Non-Bituminous GB /Sqm. 13.79

17 Tack Coat Over Existing BT Surface /Sqm. 16.46

18 Tack Coat Over Dry Lean Cement Surface /Sqm. 15.87

19 Dense Bituminous Macadam 50mm Thick Using CMP /Cum. 7299.54

20 Dense Bituminous Macadam 75mm Thick Using CMP /Cum. 6810.05

21 Bituminous Macadam 50mm Thick Using CMP /Cum. 6150.38

22 Bituminous Macadam 80mm Thick Using CMP /Cum. 6251.83

23 Premix Carpet With Seal Coat Type-A 20mm Thick (CMP) /Sqm. 177.72

24 Close Graded Premix Carpet 20mm Thick (CMP) /Sqm. 143.23

25 C.G.P.C. 20mm Thick (CMP) Using Plastic Waste /Sqm. 141.52

26 Bituminous Concrete 30/ 40mm Thick Using CMP /Cum. 7864.05

27 B.C. 30/ 40mm Thick (CMP) Using Plastic Waste /Cum. 7751.08

28 Bituminous Concrete 50mm Thick Using CMP /Cum. 7579.94

Road Data - Rev-16.2 9 Revised during - Jan. 2017


Sl
Description Unit Rate
No.
KM 3/0-4/0 4/0-5/0
27 PATCH WORK USING 45MM IRC METAL /Cum. 3091.00 3097.12 2636.78 2636.78 2636.78
28 PATCH WORK USING 13.20MM IRC METAL /Cum. 3362.00 3368.12 2907.78 2907.78 2907.78
29 WATER BOUND MACADAM GRADE-II /Cum. 2093.75 2103.99 1416.67 1416.67 1416.67
30 WATER BOUND MACADAM GRADE-III /Cum. 2393.21 2403.45 1716.13 1716.13 1716.13
31 PREMIX CARPET WITH SEAL COAT /Sqm. 194.65 194.87 178.30 178.30 178.30
32 PREMIX CARPET /Sqm. 138.66 138.83 126.40 126.40 126.40
33 GSB MIX IN PLACE /Cum. 1607.59 1615.41 1027.40 1027.40 1027.40
34 BITUMINOUS MACADAM 50mm Thick (For Patch Work) /Cum. 5987.70 5996.38 5342.68 5342.68 5342.68
35 Dense Bituminous Macadam 50mm Thick /Cum. 7037.66 7046.30 6395.66 6395.66 6395.66
36 Dry Lean Cement Concrete for Sub-Base (CC 1:4:8) /Cum. 3307.38 3312.89 2898.58 2898.58 2898.58

KM
27 PATCH WORK USING 45MM IRC METAL /Cum. 2636.78 2636.78 2636.78 2636.78 2636.78
28 PATCH WORK USING 13.20MM IRC METAL /Cum. 2907.78 2907.78 2907.78 2907.78 2907.78
29 WATER BOUND MACADAM GRADE-II /Cum. 1416.67 1416.67 1416.67 1416.67 1416.67
30 WATER BOUND MACADAM GRADE-III /Cum. 1716.13 1716.13 1716.13 1716.13 1716.13
31 PREMIX CARPET WITH SEAL COAT /Sqm. 178.30 178.30 178.30 178.30 178.30
32 PREMIX CARPET /Sqm. 126.40 126.40 126.40 126.40 126.40
33 GSB MIX IN PLACE /Cum. 1027.40 1027.40 1027.40 1027.40 1027.40
34 BITUMINOUS MACADAM 50mm Thick (For Patch Work) /Cum. 5342.68 5342.68 5342.68 5342.68 5342.68
35 Dense Bituminous Macadam 50mm Thick /Cum. 6395.66 6395.66 6395.66 6395.66 6395.66

Road Data - Rev-16.2 10 Revised during - Jan. 2017


Sl
Description Unit Rate
No.
36 Dry Lean Cement Concrete for Sub-Base (CC 1:4:8) /Cum. 2898.58 2898.58 2898.58 2898.58 2898.58

Road Data - Rev-16.2 11 Revised during - Jan. 2017


ROAD METAL RATE - CMP

Cost of
Lead in Km Stacking
Reach in Km Cost of material Conveyance Total
(Plain, Hills) Materials
charges
To CMP site 27,0 53 - 9.5mm(GSB-V) 935.78 210.21 -- 1145.99
27,0 9.50-2.36mm(GSB-V) 566.80 210.21 -- 777.01
27,0 2.36mm & Below(GSB-V) 526.00 210.21 -- 736.21
27,0 46.5 - 26.5 mm(GSB-III) 904.75 210.21 -- 1114.96
27,0 26.50 - 4.75 mm(GSB-III) 844.00 210.21 -- 1054.21
27,0 4.75 mm&below (GSB-III) 526.00 210.21 -- 736.21
27,0 45 - 22.40mm(WMM) 971.60 210.21 -- 1181.81
27,0 22.40-2.36mm(WMM) 794.00 210.21 -- 1004.21
27,0 2.36 & below(WMM) 526.00 210.21 -- 736.21
27,0 53 - 45 mm(CRM) 831.00 210.21 -- 1041.21
27,0 45 - 22.40mm(CRM) 971.60 210.21 -- 1181.81
27,0 22.40 - 5.6 mm(CRM) 752.20 210.21 -- 962.41
27,0 26.50-13.20mm(BM) 1160.01 210.21 -- 1370.22
27,0 13.20-2.36mm(BM) 580.49 210.21 -- 790.70
27,0 2.36 & below(BM) 526.00 210.21 -- 736.21
27,0 37.5 - 13.20mm(BM) 1002.09 210.21 -- 1212.30
27,0 13.20 - 2.36 mm(BM) 605.35 210.21 -- 815.56
27,0 2.36 mm & below(BM) 526.00 210.21 -- 736.21
27,0 26.50-13.20mm(DBM) 1091.49 210.21 -- 1301.70
27,0 13.20-2.36mm(DBM) 578.58 210.21 -- 788.79
27,0 2.36 & below(DBM) 526.00 210.21 -- 736.21
27,0 Stone Dust(DBM) 109.00 144.53 -- 253.53
27,0 37.50-13.20mm(DBM) 969.23 210.21 -- 1179.44
27,0 13.20-2.36mm(DBM) 561.37 210.21 -- 771.58
27,0 2.36 & below(DBM) 526.00 210.21 -- 736.21
27,0 13.20mm-11.20mm(CGPS) 800.00 210.21 -- 1010.21
27,0 11.20mm-5.60mm (CGPS) 594.00 210.21 -- 804.21
27,0 5.60mm-2.8mm (CGPS) 526.00 210.21 -- 736.21
27,0 2.80mm and below (CGPS) 526.00 210.21 -- 736.21
27,0 13.20mm 1179.00 210.21 -- 1389.21
27,0 11.20mm 800.00 210.21 -- 1010.21
27,0 6.70mm 594.00 210.21 -- 804.21
27,0 2.36 & below (BC 50) 526.00 210.21 -- 736.21
27,0 26.50 - 13.20mm(BC 50) 1162.12 210.21 -- 1372.33
27,0 13.20-2.36mm(BC 50) 595.79 210.21 -- 806.00
27,0 2.36 & below (BC) 526.00 210.21 -- 736.21
27,0 19.00-9.50mm(BC) 890.96 210.21 -- 1101.17
27,0 9.50-2.36mm(BC) 559.66 210.21 -- 769.87

Road Data - Rev-16.2 12 Revised during - Jan. 2017


BITUMEN RATE TO CMP SITE
VG 40 VG 30 VG10

Basic Rate 26786.00 27666.00 26866.00


Excise Duty 14.00% 3750.04 3873.24 3761.24
Educational Cess on ED 0.00%
30536.04 31539.24 30627.24
VAT 5.00% 1526.80 1576.96 1531.36
32062.84 33116.20 32158.60
Storage Charges 5% of basic price 1339.30 1383.30 1343.30
33402.14 34499.50 33501.90

Conveyance at Rs.0.99924per km for 231 km 461.65 461.65 461.65


33863.79 34961.15 33963.55

Selected Grade of Bitumen VG30 34961.15

Road Data - Rev-16.2 13 Revised during - Jan. 2017


WORKING OUT METAL RATE FOR BM 50mm thick

For 26.50 mm to 13.20 mm IRC


0.180 Cum Cost of 25 & 22.40mm IRC at Rs. 1073.50 /cum. = 193.23
0.820 Cum Cost of 13.20mm IRC at Rs. 1179.00 /cum. = 966.78
Rate of metal 26.50-13.20mm for BM 50mm Rs. 1160.01

For 13.20 mm to 2.36 mm IRC


0.570 Cum Cost of 11.2, 6.70, 6, 5.6 & 4.75 mm IRC at Rs. 621.60 /cum. = 354.31
0.430 Cum Cost of 2.36mm IRC at Rs. 526.00 /cum. = 226.18
Rate of metal 13.20 - 2.36 mm for BM 50mm Rs. 580.49

For 2.36 mm & below


1.000 Cum Cost of 2.36mm IRC at Rs. 526.00 /cum. = 526.00

Road Data - Rev-16.2 14 Revised during - Jan. 2017


WORKING OUT METAL RATE FOR DBM 50mm thick

For 26.50mm to 13.20mm IRC


0.160 Cum Cost of 26.50 mm IRC at Rs. 876.00 /cum. = 140.16
0.370 Cum Cost of 25 & 22.40mm IRC at Rs. 1073.50 /cum. = 397.20
0.470 Cum Cost of 13.20mm IRC at Rs. 1179.00 /cum. = 554.13
Rate of metal 26.50-13.20mm for DBM 50mm Rs. 1091.49

For 13.20 mm to 2.36 mm IRC


0.550 Cum Cost of 11.2, 6.70, 6, 5.6 & 4.75 mm IRC at Rs. 621.60 /cum. = 341.88
0.450 Cum Cost of 2.36mm IRC at Rs. 526.00 /cum. = 236.70
Rate of metal 13.20-2.36mm for DBM 50mm Rs. 578.58

For 2.36mm & below


1.000 Cum Cost of 2.36mm IRC at Rs. 526.00 /cum. = 526.00

Road Data - Rev-16.2 15 Revised during - Jan. 2017


WORKING OUT METAL RATE FOR BC 40mm thick

For 19.00 mm to 9.50 mm IRC


0.240 Cum Cost of 13.20mm IRC at Rs. 1179.00 /cum. = 282.96
0.760 Cum Cost of 11.20mm IRC at Rs. 800.00 /cum. = 608.00
Rate of Metal For 19.00 mm to 9.50 mm IRC BC (40mm thick) Rs. 890.96

For 9.50 mm to 2.36 mm IRC


0.660 Cum Cost of 6.70, 6, 5.6 & 4.75 mm IRC at Rs. 577.00 /cum. = 380.82
0.340 Cum Cost of 2.36mm IRC at Rs. 526.00 /cum. = 178.84
Rate of Metal For 9.50 mm to 2.36 mm IRC BC (40mm thick) Rs. 559.66

For 2.36mm & below


1.000 Cum Cost of 2.36mm IRC at Rs. 526.00 /cum. = 526.00

Road Data - Rev-16.2 16 Revised during - Jan. 2017


WORKING OUT METAL RATE FOR
WET MIX MACADAM

Cost of 45mm to 22.40mm Broken Stone

Cost of 45mmMetal @Rs 908.00 /Cum.


Cost of 37.50mmMetal @Rs 927.00 /Cum.
Cost of 26.50mmMetal @Rs 876.00 /Cum.
Cost of 25mmMetal @Rs 876.00 /Cum.
Cost of 22.40mmMetal @Rs 1271.00 /Cum.

Average Rate @Rs 971.60 /Cum.

Cost of 22.40mm to 2.36mm Broken Stone

Cost of 22.40mm Metal @Rs 1271.00 /Cum.


Cost of 13.20mm Metal @Rs 1179.00 /Cum.
Cost of 11.20mm Metal @Rs 800.00 /Cum.
Cost of 6.70mm Metal @Rs 594.00 /Cum.
Cost of 6mm Metal @Rs 594.00 /Cum.
Cost of 5.60mm Metal @Rs 594.00 /Cum.
Cost of 4.75mm Metal @Rs 526.00 /Cum.

Average Rate @Rs 794.00 /Cum.

Road Data - Rev-16.2 17 Revised during - Jan. 2017


WORKING OUT METAL RATE FOR BM75mm thick

For 37.5 mm to 13.20 mm IRC


0.100 Cum Cost of 37.50 mm IRC at Rs. 927.00 /cum. = 92.70
0.380 Cum Cost of 26.50mm IRC at Rs. 876.00 /cum. = 332.88
0.520 Cum Cost of 25, 22.40 & 13.20 mm IRC at Rs. 1108.67 /cum. = 576.51
Rate of Metal For 37.5 mm to 13.20 mm IRC BM (75mm thick) Rs. 1002.09

For 13.20 mm to 2.36 mm IRC


0.830 Cum Cost of 11.2, 6.70, 6, 5.6 & 4.75 mm IRC at Rs. 621.60 /cum. = 515.93
0.170 Cum Cost of 2.36mm IRC at Rs. 526.00 /cum. = 89.42
Rate of Metal For 13.20 mm to 2.36 mm IRC BM (75mm thick) Rs. 605.35

For 2.36mm & below

1.000 Cum Cost of 2.36mm IRC at Rs. 526.00 /cum. = 526.00


Rate of Metal For 2.36mm & belowBM (75mm thick) Rs. 526.00

Road Data - Rev-16.2 18 Revised during - Jan. 2017


WORKING OUT METAL RATE FOR DBM 75mm thick

For 37.50 mm to 13.20 mm IRC


0.140 Cum Cost of 37.50 mm IRC at Rs. 927.00 /cum. = 129.78
0.490 Cum Cost of 26.50mm IRC at Rs. 876.00 /cum. = 429.24
0.370 Cum Cost of 25, 22.40 & 13.20 mm IRC at Rs. 1108.67 /cum. = 410.21
Rate of Metal For 37.50 mm to 13.20 mm IRC DBM (75mm thick) Rs. 969.23

For 13.20 mm to 2.36 mm IRC

0.370 Cum Cost of 11.2, 6.70, 6, 5.6 & 4.75 mm IRC at Rs. 621.60 /cum. = 229.99
0.630 Cum Cost of 2.36mm IRC at Rs. 526.00 /cum. = 331.38
Rate of Metal For 13.20 mm to 2.36 mm IRC DBM (75mm thick) Rs. 561.37

For 2.36mm & below

1.00 Cum Cost of 2.36mm IRC at Rs. 526.00 /cum. = 526.00

Road Data - Rev-16.2 19 Revised during - Jan. 2017


WORKING OUT METAL RATE FOR GRANULAR SUB BASE

Granular Sub Base Grade - V

Cost of 53mm to 9.50mm Broken Stone

Cost of 53mmMetal @Rs 677.00 /Cum.


Cost of 46.50mmMetal @Rs 908.00 /Cum.
Cost of 45mmMetal @Rs 908.00 /Cum.
Cost of 37.50mmMetal @Rs 927.00 /Cum.
Cost of 26.50mmMetal @Rs 876.00 /Cum.
Cost of 25mmMetal @Rs 876.00 /Cum.
Cost of 22.40mmMetal @Rs 1271.00 /Cum.
Cost of 13.20mmMetal @Rs 1179.00 /Cum.
Cost of 11.20mmMetal @Rs 800.00 /Cum.

Average Rate @Rs 935.78 /Cum.

Cost of 9.50mm to 2.36mm Broken Stone

Cost of 6.70mm Metal @Rs 594.00 /Cum.


Cost of 6mm Metal @Rs 594.00 /Cum.
Cost of 5.60mm Metal @Rs 594.00 /Cum.
Cost of 4.75mm Metal @Rs 526.00 /Cum.
Cost of 2.36mm Metal @Rs 526.00 /Cum.

Average Rate @Rs 566.80 /Cum.

Cost of 2.36mm & Below of Sand

Cost of 4.75mm & BelowMetal @Rs 526.00 /Cum.

Average Rate @Rs 526.00 /Cum.

Road Data - Rev-16.2 20 Revised during - Jan. 2017


METAL RATE FOR GRANULAR SUB BASE (TABLE NO.400.1)

Granular Sub Base Grade - III

Cost of 46.50 - 26.50 mm Broken Stone


Cost of 46.50mmMetal @Rs 908.00 /Cum.
Cost of 45mmMetal @Rs 908.00 /Cum.
Cost of 37.50mmMetal @Rs 927.00 /Cum.
Cost of 26.50mmMetal @Rs 876.00 /Cum.
Average Rate of 46.50 - 26.50 mm @Rs 904.75 /Cum.

Cost of 26.50 - 4.75mm Broken Stone


Cost of 25mmMetal @Rs 876.00 /Cum.
Cost of 22.40mmMetal @Rs 1271.00 /Cum.
Cost of 13.20mmMetal @Rs 1179.00 /Cum.
Cost of 11.20mmMetal @Rs 800.00 /Cum.
Cost of 6.70mmMetal @Rs 594.00 /Cum.
Cost of 6mmMetal @Rs 594.00 /Cum.
Cost of 5.60mmMetal @Rs 594.00 /Cum.
Average Rate of 26.50 - 4.75 mm @Rs 844.00 /Cum.

Cost of 4.75mm & Below of Sand

Cost of 4.75mm & BelowMetal @Rs 526.00 /Cum.


Average Rate of 2.36 & Below @Rs 526.00 /Cum.

Road Data - Rev-16.2 21 Revised during - Jan. 2017


WORKING OUT METAL RATE FOR
CRUSHER RUN MACADAM

Cost of 53mm to 45 mm Broken Stone


Cost of 53mmMetal @Rs 677.00 /Cum.
Cost of 46.50mmMetal @Rs 908.00 /Cum.
Cost of 45mmMetal @Rs 908.00 /Cum.
Average Rate of 53-45 mm @Rs 831.00 /Cum.

Cost of 45mm - 22.40mm Broken Stone


Cost of 45mmMetal @Rs 908.00 /Cum.
Cost of 37.50mm Metal @Rs 927.00 /Cum.
Cost of 26.50mm Metal @Rs 876.00 /Cum.
Cost of 25.00mm Metal @Rs 876.00 /Cum.
Cost of 22.40mm Metal @Rs 1271.00 /Cum.
Average Rate of 45mm - 22.40mm
@Rs 971.60 /Cum.

Cost of 22.40 mm to 5.60mm Broken Stone


Cost of 13.20mm Metal @Rs 1179.00 /Cum.
Cost of 11.20mm Metal @Rs 800.00 /Cum.
Cost of 6.70mm Metal @Rs 594.00 /Cum.
Cost of 6 mm Metal @Rs 594.00 /Cum.
Cost of 5.6 mm Metal @Rs 594.00 /Cum.
Average Rate of 22.40mm - 5.60mm 752.20

Cost of 4.75mm & below @Rs 526.00 /Cum.

Road Data - Rev-16.2 22 Revised during - Jan. 2017


WORKING OUT METAL RATE FOR
CLOSED GRADED PREMIX CARPET
Cost of 13.20 mm to 11.20mm Broken Stone
Cost of 11.20 mm Metal @Rs 800.00 /Cum.

Average Rate of 13.20 - 11.20mm @Rs 800.00 /Cum.

Cost of 11.20 mm to 5.60 mm Broken Stone


Cost of 6.7 mm Metal @Rs 594.00 /Cum.
Cost of 6 mm Metal @Rs 594.00 /Cum.
Cost of 5.6 mm Metal @Rs 594.00 /Cum.

Average Rate of 11.20-5.6mm @Rs 594.00 /Cum.

Cost of 5.6 mm to 2.80mm Broken Stone

Cost of 4.75mm & below metal @Rs 526.00 /Cum.

Average Rate of 5.60-2.80mm @Rs 526.00 /Cum.

Road Data - Rev-16.2 23 Revised during - Jan. 2017


DENSE BITUMINOUS MACADAM 50MM THICK USING CMP
Providing and laying 50mm consolidated thick Dense Bituminous Macadam using 0.24 cum of 26.50-
13.20mm, 0..25cum of 13.20-2.36mm and 0.23cum of 2.36mm & below and with 53.20 Kgs of VG30/
VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site,
heating the bitumen and aggregate to required temperature and mixing them in required temperature in
central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to work site, spreading the
mix to uniform thickness of 50mm with paver to the specified grades and cross sections and compacted
by Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver at
site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks,
Paver Finisher / 9m paver finisher, Vibratory / Pneumatic rollers and all other tools and plant required,
including fuel and all other incidental charges etc., complete as per specification using CMP as per
clause 505 MORTH Rev-5

No
HIRE CHARGES FOR MACHINERIES
1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 58.85 /lit =Rs. 1765.50
For heating the bitumen 25 litres of furnace oil 33.17 /lit =Rs. 829.25
For heating the aggregates : 170 litres of furnace oil 33.17 /lit =Rs. 5638.90
Hire Charges including fuel charges per hour Rs. 9445.65
Out turn of CMP per Hour for BM = 135sqm. of 50 mm thick

Hire Charges for CMP per 10sqm. = 9445.65 X 10 =Rs. 699.68


135
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is not
necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 58.85 /lit =Rs. 147.13
Hire Charges including fuel charges per hour Rs. 825.63
Out turn of Vibrator Roller per hour= 320sqm. of 50 mm thick

Hire Charges for Vibrator roller per 10sqm. = 825.63 X 10 =Rs. 25.80
320

4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 58.85 /lit =Rs. 353.10
Hire Charges including fuel charges per hour Rs. 658.98
Out turn of Paver Finisher per hour = 135 sqm. of 50 mm thick

Hire Charges for paver finisher per 10sqm. = 658.98 X 10 =Rs. 48.81
135

Road Data - Rev-16.2 24 Revised during - Jan. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 58.85 /lit =Rs. 191.26
Hire Charges including fuel charges per DAY Rs. 328.01
Out turn of Tipper Truck per hour = 135 sqm. of 50 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 328.01 x6x10 =Rs. 145.78
135

Total hire charges for machineries per 10 sqm = 699.68+ 25.80+ 48.81+ 145.78
= 920.07 /10sqm
LABOUR CHARGES PER 1200SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 11550.00
25.00 Nos Mazdoor IInd Class @Rs. 314.00 /each = 7850.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 3500.00
Total Labour Charges per 1200sqm = 22900.00

Labour Charges per 10sqm. = 22900.00 X 10 =Rs. 190.83


1200

RATE PER CUM OF 50MM THICK DENSE BITUMINOUS MACADAM

0.240 Cum Cost of 26.50 - 13.20mm IRC at Rs. 1301.70 /cum. = 312.41
0.250 Cum Cost of 13.20-2.36mm IRC at Rs. 788.79 /cum. = 197.20
0.230 Cum Cost of 2.36mm & below IRC at Rs. 736.21 /cum. = 169.33
0.000 Cum Cost of Stone Dust (Filling mat.) at Rs. 253.53 /cum. = 0.00
53.20 Kg Cost of VG30 Bitumen at Rs. 34961.15 /MT = 1859.93
10.00 Sqm Hire charges at Rs. 920.07 /10sqm = 920.07
10.00 Sqm Labour charges at Rs. 190.83 /10sqm = 190.83
Rate for 10 sqm =Rs. 3649.77

Rate per cum of 50 mm thick = 3649.77 = Rs. 7299.54


0.50

Road Data - Rev-16.2 25 Revised during - Jan. 2017


DENSE BITUMINOUS MACADAM 75MM THICK USING CMP
Providing and laying 75mm consolidated thick Dense Bituminous macadam using 0.40 cum fo 37.50-
13.20mm, 0.35 cum of 13.20-2.36mm and 0.36 cum of 2.36mm & below size IRC metal with 71.30 kgs
of VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to
CMP site, heating the bitumen and aggregate to required temperature and mixing them in required
temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site,
spreading the mix to uniform thickness of 75mm with mechanical paver to the specified grades and cross
sections and consolidated by 8-10 tonne Vibratory / Pneumatic Roller to the required density etc.,
including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t
CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic roller
and all other tools and plant required, including fuel and all other incidental charges etc., complete as
per specification using CMP as per clause 505 of MORTH rev-5.

HIRE CHARGES FOR MACHINERIES


1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 58.85 /lit =Rs. 1765.50
For heating the bitumen 25 litres of furnace oil 33.17 /lit =Rs. 829.25
For heating the aggregates : 170 litres of furnace oil 33.17 /lit =Rs. 5638.90
Hire Charges including fuel charges per hour Rs. 9445.65
Out turn of CMP per Hour for DBM = 90sqm. of 75 mm thick

Hire Charges for CMP per 10sqm. = 9445.65 X 10 =Rs. 1049.52


90
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is not
necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 58.85 /lit =Rs. 147.13
Hire Charges including fuel charges per hour Rs. 825.63
Out turn of Vibrator Roller per hour= 220sqm. of 75 mm thick

Hire Charges for Vibrator roller per 10sqm. = 825.63 X 10 =Rs. 37.53
220

4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 58.85 /lit =Rs. 353.10
Hire Charges including fuel charges per hour Rs. 658.98
Out turn of Paver Finisher per hour = 90 sqm. of 75 mm thick

Hire Charges for paver finisher per 10sqm. = 658.98 X 10 =Rs. 73.22
90

Road Data - Rev-16.2 26 Revised during - Jan. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 58.85 /lit =Rs. 191.26
Hire Charges including fuel charges per DAY Rs. 328.01
Out turn of Tipper Truck per hour = 90 sqm. of 75 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 328.01 x6x10 =Rs. 218.67
90

Total hire charges for machineries per 10 sqm =1049.52 37.53 73.22 218.67
= 1378.94 /10sqm
LABOUR CHARGES PER 1000SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 11550.00
25.00 Nos Mazdoor IInd Class @Rs. 314.00 /each = 7850.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 3500.00
Total Labour Charges per 1000sqm = 22900.00

Labour Charges per 10sqm. = 22900.00 X 10 =Rs. 229.00


1000

RATE PER CUM OF 75MM THICK DENSE BITUMINOUS MACADAM

0.400 Cum Cost of 37.50-13.20mm IRC at Rs. 1179.44 /cum. = 471.78


0.350 Cum Cost of 13.20-2.36mm IRC at Rs. 771.58 /cum. = 270.05
0.360 Cum Cost of 2.36mm & Below IRC at Rs. 736.21 /cum. = 265.04
0.000 Cum Cost of Stone Dust (Filling mat.) at Rs. 253.53 /cum. = 0.00
71.30 Kg Cost of VG30 Bitumen at Rs. 34961.15 /MT = 2492.73
10.00 Sqm Hire charges at Rs. 1378.94 /10sqm = 1378.94
10.00 Sqm Labour charges at Rs. 229.00 /10sqm = 229.00
Rate for 10 sqm =Rs. 5107.54

Rate per cum of 75 mm thick = 5107.54 = Rs. 6810.05


0.75

Road Data - Rev-16.2 27 Revised during - Jan. 2017


BITUMINOUS MACADAM 50MM THICK USING CMP
Providing and laying 50mm consolidated thick bituminous macadam using 0.20 cum fo 26.50-
13.20mm, 0.43 cum of 13.20-2.36mm and 0.08 cum of 2.36mm & below size IRC metal with 37
Kgs of VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance of all
materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them
in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper
trucks to paver site, spreading the mix to uniform thickness of 50mm with mechanical paver to the
specified grades and cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic Roller to
the required density etc., including labour for attending to paver to site etc., including hire charges
and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver
finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all
other incidental charges etc., complete as per specification using CMP as per clause 504 of
MORTH Rev-5

HIRE CHARGES FOR MACHINERIES


1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 58.85 /lit =Rs. 1765.50
For heating the bitumen 25 litres of furnace oil 33.17 /lit =Rs. 829.25
For heating the aggregates : 170 litres of furnace oil 33.17 /lit =Rs. 5638.90
Hire Charges including fuel charges per hour Rs. 9445.65
Out turn of CMP per Hour for BM = 135sqm. of 50 mm thick

Hire Charges for CMP per 10sqm. = 9445.65 X 10 =Rs. 699.68


135
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is
not necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 58.85 /lit =Rs. 147.13
Hire Charges including fuel charges per hour Rs. 825.63
Out turn of Vibrator Roller per hour= 350sqm. of 50 mm thick

Hire Charges for Vibrator roller per 10sqm. = 825.63 X 10 =Rs. 23.59
350

4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 58.85 /lit =Rs. 353.10
Hire Charges including fuel charges per hour Rs. 658.98
Out turn of Paver Finisher per hour = 135 sqm. of 50 mm thick

Hire Charges for paver finisher per 10sqm. = 658.98 X 10 =Rs. 48.81
135

Road Data - Rev-16.2 28 Revised during - Jan. 2017


4. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 58.85 /lit =Rs. 191.26
Hire Charges including fuel charges per hour Rs. 328.01
Out turn of Tipper Truck per hour = 135 sqm. of 50 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 328.01 x6x10 =Rs. 145.78
135

Total hire charges for machineries per 10 sqm =699.68+ 23.59+ 48.81+ 145.78
= 917.86 /10sqm
LABOUR CHARGES PER 1200SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 11550.00
25.00 Nos Mazdoor IInd Class @Rs. 314.00 /each = 7850.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 3500.00
Total Labour Charges per 1200sqm = 22900.00

Labour Charges per 10sqm. = 22900.00 X 10 =Rs. 190.83


1200

RATE PER CUM OF 50MM THICK BITUMINOUS MACADAM

0.200 Cum Cost of 26.5-13.20mm IRC at Rs. 1370.22 /cum. = 274.04


0.430 Cum Cost of 13.20-2.36mm IRC at Rs. 790.70 /cum. = 340.00
0.080 Cum Cost of 2.36mm & below IRC at Rs. 736.21 /cum. = 58.90
37.00 Kg Cost of VG30 Bitumen at Rs. 34961.15 /MT = 1293.56
10.00 Sqm Hire charges at Rs. 917.86 /10sqm = 917.86
10.00 Sqm Labour charges at Rs. 190.83 /10sqm = 190.83
Rate for 10 sqm =Rs. 3075.19

Rate per cum of 50 mm thick = 3075.19 = Rs. 6150.38


0.50

Road Data - Rev-16.2 29 Revised during - Jan. 2017


BITUMINOUS MACADAM 80MM THICK USING CMP
Providing and laying 80mm consolidated thick bituminous macadam using 0.64 cum fo 37.5 -
13.20mm, 0.44 cum of 13.2 - 2.36mm and 0.13 cum of 2.36mm and below size IRC metal with 62
Kgs of VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance of all
materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them
in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper
trucks to paver site, spreading the mix to uniform thickness of 80mm with mechanical paver to the
specified grades and cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic Roller to
the required density etc., including labour for attending to paver to site etc., including hire charges
and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks,Paver Finisher / 9m paver
finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all
other incidental charges etc., complete as per specification using CMP as per clause 504 of
MORTH Rev-5.

HIRE CHARGES FOR MACHINERIES


1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 58.85 /lit =Rs. 1765.50
For heating the bitumen 25 litres of furnace oil 33.17 /lit =Rs. 829.25
For heating the aggregates : 170 litres of furnace oil 33.17 /lit =Rs. 5638.90
Hire Charges including fuel charges per hour Rs. 9445.65
Out turn of CMP per Hour for BM = 90sqm. of 75 mm thick

Hire Charges for CMP per 10sqm. = 9445.65 X 10 =Rs. 1049.52


90
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is
not necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 58.85 /lit =Rs. 147.13
Hire Charges including fuel charges per hour Rs. 825.63
Out turn of Vibrator Roller per hour= 250sqm. of 80 mm thick

Hire Charges for Vibrator roller per 10sqm. = 825.63 X 10 =Rs. 33.03
250

4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 58.85 /lit =Rs. 353.10
Hire Charges including fuel charges per hour Rs. 658.98
Out turn of Paver Finisher per hour = 90 sqm. of 80 mm thick

Hire Charges for paver finisher per 10sqm. = 658.98 X 10 =Rs. 73.22
90

Road Data - Rev-16.2 30 Revised during - Jan. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 58.85 /lit =Rs. 191.26
Hire Charges including fuel charges per DAY Rs. 328.01
Out turn of Tipper Truck per hour = 90 sqm. of 75 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 328.01 x6x10 =Rs. 218.67
90

Total hire charges for machineries per 10 sqm 1049.52


= +33.03 +73.22 +218.67
= 1374.44 /10sqm
LABOUR CHARGES PER 1000SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 11550.00
25.00 Nos Mazdoor IInd Class @Rs. 314.00 /each = 7850.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 3500.00
Total Labour Charges per 1000sqm = 22900.00

Labour Charges per 10sqm. = 22900.00 X 10 =Rs. 229.00


1000

RATE PER CUM OF 80MM THICK BITUMINOUS MACADAM

0.640 Cum Cost of 37.50-13.20mm IRC at Rs. 1212.30 /cum. = 775.87


0.440 Cum Cost of 13.20-2.36mm IRC at Rs. 815.56 /cum. = 358.85
0.130 Cum Cost of 2.36mm & below at Rs. 736.21 /cum. = 95.71
62.00 Kg Cost of VG30 Bitumen at Rs. 34961.15 /MT = 2167.59
10.00 Sqm Hire charges at Rs. 1374.44 /10sqm = 1374.44
10.00 Sqm Labour charges at Rs. 229.00 /10sqm = 229.00
Rate for 10 sqm =Rs. 5001.46

Rate per cum of 80 mm thick = 5001.46 = Rs. 6251.83


0.80

Road Data - Rev-16.2 31 Revised during - Jan. 2017


PREMIX CARPET WITH SEAL COAT TYPE - A 20MM THICK USING CMP
Providing and laying Premix Carpet with Seal Coat Type - A to 20 mm thick using 0.18 cum
of 13.20mm,0.09 cum of 11.20mm and 0.09 cum of 6.70mm with 24.40 kgs of VG30 bitumen
for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating
the bitumen and aggregate to required temperature and mixing them in required temperature
in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site,
spreading the mix to uniform thickness of 50mm with mechanical paver to the specified
grades and cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic Roller to the
required density etc., including labour for attending to paver to site etc., including hire
charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks,Paver Finisher /
9m paver finisher, Vibratory / Pneumatic roller and all other tools and plant required,
including fuel and all other incidental charges etc., complete as per specification using CMP
as per MORTH Rev-5
HIRE CHARGES FOR MACHINERIES
1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 58.85 /lit =Rs. 1765.50
For heating the bitumen 25 litres of furnace oil 33.17 /lit =Rs. 829.25
For heating the aggregates : 170 litres of furnace oil 33.17 /lit =Rs. 5638.90
Hire Charges including fuel charges per hour Rs. 9445.65
Out turn of CMP per Hour for PCSC = 325sqm. of 20 mm thick

Hire Charges for CMP per 10sqm. = 9445.65 X 10 =Rs. 290.64


325
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is
not necessary

3.VIBRATORY ROLLERS :
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 58.85 /lit =Rs. 147.13
Hire Charges including fuel charges per Hour Rs. 825.63
Out turn of Vibrator Roller per hour= 1000sqm. of 20 mm thick premix carpet

Hire Charges for Vibrator roller per 10sqm. = 825.63 X 10 =Rs. 8.26
1000
Out turn of Vibratory Roller per Hr.SC = 500sqm

Hire Charges for Vibratory roller per 10sqm.for SC = 825.63 X 10 =Rs. 16.51
500
4. PAVER FINISHER
Hire charges excluding fuel charges per hour 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 58.85 /lit =Rs. 353.10
Hire Charges including fuel charges per hour Rs. 658.98
Out turn of Paver Finisher per hour = 325 sqm. of 20mm thick

Hire Charges for paver finisher per 10sqm. = 658.98 X 10 =Rs. 20.28
325

Road Data - Rev-16.2 32 Revised during - Jan. 2017


4. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 58.85 /lit =Rs. 191.26
Hire Charges including fuel charges per DAY Rs. 328.01
Out turn of Tipper Truck per hour = 325 sqm. of 20 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 328.01 x6x10 =Rs. 60.56
325

Total hire charges for machineries per 10 sqm = 290.64 +24.77 +20.28 +60.56
= 396.25 /10sqm
LABOUR CHARGES PER 2000SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 11550.00
25.00 Nos Mazdoor IInd Class @Rs. 314.00 /each = 7850.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 3500.00
Total Labour Charges per 2000sqm = 22900.00

Labour Charges per 10sqm. = 22900.00 X 10 =Rs. 114.50


2000

RATE PER SQM OF PREMIX CARPET WITH SEAL COAT 20MM THICK

0.18 cum. Cost of 13.20mm IRC at Rs. 1389.21 /cum. = 250.06


0.09 cum. Cost of 11.20mm IRC at Rs. 1010.21 /cum. = 90.92
0.09 cum Cost of 6.70 mm IRC at Rs. 804.21 /cum. = 72.38
24.40 Kg Cost of VG30 Bitumen at Rs. 34961.15 /MT = 853.05
10.00 sqm Hire charges at Rs. 396.25 /10sqm = 396.25
10.00 sqm. Labour charges at Rs. 114.50 /10sqm = 114.50
Rate for 10 sqm =Rs. 1777.16

Rate per sqm of 20 mm thick = 1777.16 = Rs. 177.72


10

Road Data - Rev-16.2 33 Revised during - Jan. 2017


WET MIX MACADAM
Providing and laying, spreading and compacting graded stone aggregates to Wet Mix Macadam
250 mm thick specification including premixing the materials with water at OMC in mechnanical
mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in Sub
Base/ Base course on well prepared surface and compacting with vibratory roller to acheive the
desired density including cost of material, labour charges, rentals for machinery, fuel and all other
incidental charges etc., complete as per clause 406 of MORTH Rev-5

Hire charges for Machineries


Loader 5 Cum. Capacity
Hire charges excluding fuel charges per day =Rs. 1205.00
Fuel charges per day 80 lit.of diesel 58.85 /lit =Rs. 4708.00

Total Hire charges per day including Fuel =Rs. 5913.00


Total Hire charges per Hour including Fuel =Rs. 739.13

Tipper
Hire charges excluding fuel charges per day =Rs. 1094.00
Fuel charges per day 3.25lit.of diesel x 8hrs 58.85 /lit =Rs. 1530.10
Total Hire charges per day including Fuel =Rs. 2624.10
Total Hire charges per Hour including Fuel =Rs. 328.01

Water Tankers
Hire charges excluding fuel charges per day =Rs. 855.00
Fuel charges per day 25lit.of diesel 58.85 /lit =Rs. 1471.25
Total Hire charges per day including Fuel =Rs. 2326.25
Total Hire charges per Hour including Fuel =Rs. 290.78
Vibratory Power Roller 8-10 tonne
Hire charges excluding fuel charges per day =Rs. 5428.00
Fuel charges per day 3.00lit.of diesel x 8hrs 58.85 /lit =Rs. 1412.40
Total Hire charges per day including Fuel =Rs. 6840.40
Total Hire charges per Hour including Fuel =Rs. 855.05

Motor Grader including fuel per Hour (Local Rate) =Rs. 1691.63
Base Mix Plant (pug mill) including fuel per hour (local rate) =Rs. 834.88

Total Hire Charges for machineries for 100 Cum of WMM


1. Loader for 6 Hours 739.13 /hr. =Rs. 4434.75
2. Base Mix Plant (Pug Mill) for 6 Hours 834.88 /hr. =Rs. 5009.28
3. Tipper for 24 Hours 328.01 /hr. =Rs. 7872.30
4. Water Tanker for 24 Hours 290.78 /hr. =Rs. 6978.75
5. Motor Grader for 4 Hours 1691.63 /hr. =Rs. 6766.52
6. Vibratory Roller for 6 Hours 855.05 /hr. =Rs. 5130.30
Total Hire Charges for machineries for 100 Cum of WMM =Rs. 36191.90

Total Hire Charges for machineries for 1.00 Cum of WMM =Rs. 361.92 /Cum.

Road Data - Rev-16.2 34 Revised during - Jan. 2017


Labour Charges for 100 cum of WMM
0.50 Nos. of Head Mazdoor @ Rs. 361.00 /E =Rs. 180.50
8.63 Nos. of Mazdoor Ist Class @ Rs. 350.00 /E =Rs. 3020.50
2.00 Nos. of Mazdoor IIst Class @ Rs. 314.00 /E =Rs. 628.00
Total Labour Charges of 100 cum of WMM =Rs. 3829.00

Total Labour Charges of 1.00 cum of WMM =Rs. 38.29 /Cum.


Total Hire and Labour charges = 361.92 + 38.29 =Rs. 400.21 /Cum.

WET MIX MACADAM 250 mm thick

0.396 Cum. Cost of 45-22.40mm IRC at Rs. 1181.81 /cum.= 468.00


0.528 Cum. Cost of 22.40-2.36mm IRC at Rs. 1004.21 /cum.= 530.22
0.396 Cum. Cost of 2.36mm IRC at Rs. 736.21 /cum.= 291.54
0.08 KL Cost of water at Rs. 130.00 / KL = 10.40
1.00 cum. Hire & Labour charges at Rs. 400.21 /cum.= 400.21
Rate for 1.00 cum. Rs. 1700.37

Road Data - Rev-16.2 35 Revised during - Jan. 2017


BITUMINOUS CONCRETE 40MM THICK USING CMP
Providing and laying Bituminous Concrete to 40 mm thick using 0.13 cum of 19.00-9.50mm,
0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30 kgs of VG30/ VG40
bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site,
heating the bitumen and aggregate to required temperature and mixing them in required
temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to
paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the
specified grades and cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic Roller
to the required density etc., including labour for attending to paver to site etc., including hire
charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m
paver finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel
and all other incidental charges etc., complete as per specification using CMP as per clause 507
of MORTH Rev-5
HIRE CHARGES FOR MACHINERIES
1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 58.85 /lit =Rs. 1765.50
For heating the bitumen 25 litres of furnace oil 33.17 /lit =Rs. 829.25
For heating the aggregates : 170 litres of furnace oil 33.17 /lit =Rs. 5638.90
Hire Charges including fuel charges per hour Rs. 9445.65
Out turn of CMP per Hour for BC = 170sqm. of 40 mm thick

Hire Charges for CMP per 10sqm. = 9445.65 X 10 =Rs. 555.63


170
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is not
necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 58.85 /lit =Rs. 147.13
Hire Charges including fuel charges per hour Rs. 825.63
Out turn of Vibrator Roller per hour= 400sqm. of 40 mm thick

Hire Charges for Vibrator roller per 10sqm. = 825.63 X 10 =Rs. 20.64
400

4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 58.85 /lit =Rs. 353.10
Hire Charges including fuel charges per hour Rs. 658.98
Out turn of Paver Finisher per hour = 170 sqm. of 40 mm thick

Hire Charges for paver finisher per 10sqm. = 658.98 X 10 =Rs. 38.76
170

Road Data - Rev-16.2 36 Revised during - Jan. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 58.85 /lit =Rs. 191.26
Hire Charges including fuel charges per DAY Rs. 328.01
Out turn of Tipper Truck per hour = 170 sqm. of 40 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 328.01 x6x10 =Rs. 115.77
170

Total hire charges for machineries per 10 sqm =555.63+ 20.64+ 38.76+ 115.77
= 730.80 /10sqm
LABOUR CHARGES PER 1200 SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 11550.00
25.00 Nos Mazdoor IInd Class @Rs. 314.00 /each = 7850.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 3500.00
Total Labour Charges per 1200sqm = 22900.00

Labour Charges per 10sqm. = 22900.00 X 10 =Rs. 190.83


1200

RATE PER SQM OF BITUMINOUS CONCRETE 40MM THICK

0.130 Cum Cost of 19.00-9.50mm IRC at Rs. 1101.17 /cum. = 143.15


0.170 Cum Cost of 9.50 - 2.36mm IRC at Rs. 769.87 /cum. = 130.88
0.260 Cum Cost of 2.36 mm and below at Rs. 736.21 /cum. = 191.41
50.30 Kg Cost of VG30 Bitumen at Rs. 34961.15 /MT = 1758.55
10.00 Sqm Hire charges at Rs. 730.80 /10sqm = 730.80
10.00 Sqm Labour charges at Rs. 190.83 /10sqm = 190.83
Rate for 10 sqm =Rs. 3145.62

Rate per cum = 3145.62/(10x0.04) = 7864.05

Road Data - Rev-16.2 37 Revised during - Jan. 2017


CRUSHER RUN MACADAM THICK
Providing and laying, spreading and compacting graded stone aggregates to Crusher Run
Macadam specification including premixing the materials with water at OMC in mechnanical mix
plant carriage of mixed material by tipper to site laying in uniform layers with pavers in Sub
Base/ Base course on well prepared surface and compacting with vibratory roller to acheive the
desired density including cost of material, labour charges, rentals for machinery, fuel and all
other incidental charges etc., complete as per Clause 407 of MORTH Rev-5
Hire charges for Machineries
Loader 5 Cum. Capacity
Hire charges excluding fuel charges per day =Rs. 1205.00
Fuel charges per day 80 lit.of diesel 58.85 /lit =Rs. 4708.00

Total Hire charges per day including Fuel =Rs. 5913.00


Total Hire charges per Hour including Fuel =Rs. 739.13

Tipper
Hire charges excluding fuel charges per day =Rs. 1094.00
Fuel charges per day 3.25lit.of diesel x 8hrs 58.85 /lit =Rs. 1530.10
Total Hire charges per day including Fuel =Rs. 2624.10
Total Hire charges per Hour including Fuel =Rs. 328.01

Water Tankers
Hire charges excluding fuel charges per day =Rs. 855.00
Fuel charges per day 25lit.of diesel 58.85 /lit =Rs. 1471.25
Total Hire charges per day including Fuel =Rs. 2326.25
Total Hire charges per Hour including Fuel =Rs. 290.78
Vibratory Power Roller 8-10 tonne
Hire charges excluding fuel charges per day =Rs. 5428.00
Fuel charges per day 3.00lit.of diesel x 8hrs 58.85 /lit =Rs. 1412.40
Total Hire charges per day including Fuel =Rs. 6840.40
Total Hire charges per Hour including Fuel =Rs. 855.05

Motor Grader including fuel per Hour =Rs. 1691.63

Total Hire Charges for machineries for 100 Cum of CRM


1. Loader for 6 Hours 739.13 /hr. =Rs. 4434.75
2. Tipper for 24 Hours 328.01 /hr. =Rs. 7872.30
3. Water Tanker for 24 Hours 290.78 /hr. =Rs. 6978.72
4. Motor Grader for 4 Hours 1691.63 /hr. =Rs. 6766.52
5. Vibratory Roller for 6 Hours 855.05 /hr. =Rs. 5130.30
Total Hire Charges for machineries for 100 Cum of CRM =Rs. 31182.59

Total Hire Charges for machineries for 1.00 Cum of CRM =Rs. 311.83 /Cum.

Road Data - Rev-16.2 38 Revised during - Jan. 2017


Labour Charges for 100 cum of CRM
0.50 Nos. of Head Mazdoor @ Rs. 361.00 /E =Rs. 180.50
8.63 Nos. of Mazdoor Ist Class @ Rs. 350.00 /E =Rs. 3020.50
2.00 Nos. of Mazdoor IIst Class @ Rs. 314.00 /E =Rs. 628.00
Total Labour Charges of 100 cum of CRM =Rs. 3829.00

Total Labour Charges of 1.00 cum of CRM =Rs. 38.29


Total Hire and Labour charges = 311.83 + 38.29 =Rs. 350.12 /Cum.

CRUSHER RUN MACADAM 300mm THICK

0.09 Cost of 53-45mm IRC (7%) 0.090 @Rs 1041.21 /cum 93.71
0.46 Cost of 45-22.40mm IRC (35%) 0.460 @Rs 1181.81 /cum 543.63
0.30 22.40-5.6mm IRC Metal (23%) 0.300 @Rs 962.41 /cum 288.72
0.46 Cost of 900mm Micron and below (35%) 0.460 @Rs 736.21 /cum 338.66
1 Cum Hire & Labour charges 1 @Rs 350.12 /cum 350.12
Rate for 1.00 cum. Rs. 1614.84

Road Data - Rev-16.2 39 Revised during - Jan. 2017


Granular Sub Base Grade - I
Hire charges for Machineries
BY PLANT MIX METHOD

Motor Grader including fuel / Hour (Local Rate) =Rs. 1691.63 /Hour
Wet Mix Plant 75 tonne capacity/ hr (Local Rate) =Rs. 1116.63 /Hour
Vibrator Roller
Hire charges excluding fuel charges per day =Rs. 5428.00
Fuel charges per day (Diesel) 2.50 lit/Hr x 8.00 Hrs. x 58.85 /lit =Rs. 1177.00
Total Hire charges per day including Fuel =Rs. 6605.00

Hire charges of Vibrator Roller per Hour 6605.00 / 8 =Rs. 825.63 /Hour
Tipper Trucks
Hire charges excluding fuel charges per Hour 1094.00 / 8 =Rs. 136.75
Fuel charges per day (Diesel) 3.25 lit/Hr x 58.85 /lit =Rs. 191.26
Total Hire charges per Hour including Fuel =Rs. 328.01 /Hour

Water Tanker
Hire charges excluding fuel charges per day =Rs. 855.00
Fuel charges per day (Diesel) 25.00 /Day 58.85 /lit =Rs. 1471.25
Total Hire charges per day including Fuel =Rs. 2326.25

Hire Charges for Water Tanker per Hour 2326.25 / 8 =Rs. 290.78 /Hour
Front end loader 5 cum capacity
Hire charges excluding fuel charges per day =Rs. 1205.00
Fuel charges per day (Diesel)10.00 lit/Hr x 8.00 Hrs. x 58.85 /lit =Rs. 4708.00
Total Hire charges per day including Fuel =Rs. 5913.00

Hire charges of Vibrator Roller per Hour 5913.00 / 8 =Rs. 739.13 /Hour

Road Data - Rev-16.2 40 Revised during - Jan. 2017


BITUMINOUS CONCRETE 40MM THICK USING CMP (using Plastic Waste)
Providing and laying Bituminous Concrete to 40 mm thick using 0.13 cum of 19.00-9.50mm,
0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30/ VG40
bitumen and 3.02Kgs of Waste Plastic for premixing per 10sqm including cost and conveyance
of all materials to CMP site, heating the bitumen and aggregate to required temperature and
mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the
mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with
mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne
Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver
to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper
trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic roller and all other tools and
plant required, including fuel and all other incidental charges etc., complete as per specification
using CMP as per clause 507 of MORTH Rev-5
HIRE CHARGES FOR MACHINERIES
1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 58.85 /lit =Rs. 1765.50
For heating the bitumen 25 litres of furnace oil 33.17 /lit =Rs. 829.25
For heating the aggregates : 170 litres of furnace oil 33.17 /lit =Rs. 5638.90
Hire Charges including fuel charges per hour Rs. 9445.65
Out turn of CMP per Hour for BC = 170sqm. of 40 mm thick

Hire Charges for CMP per 10sqm. = 9445.65 X 10 =Rs. 555.63


170
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is not
necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 58.85 /lit =Rs. 147.13
Hire Charges including fuel charges per hour Rs. 825.63
Out turn of Vibrator Roller per hour= 400sqm. of 40 mm thick

Hire Charges for Vibrator roller per 10sqm. = 825.63 X 10 =Rs. 20.64
400

4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 58.85 /lit =Rs. 353.10
Hire Charges including fuel charges per hour Rs. 658.98
Out turn of Paver Finisher per hour = 170 sqm. of 40 mm thick

Hire Charges for paver finisher per 10sqm. = 658.98 X 10 =Rs. 38.76
170

Road Data - Rev-16.2 41 Revised during - Jan. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 58.85 /lit =Rs. 191.26
Hire Charges including fuel charges per DAY Rs. 328.01
Out turn of Tipper Truck per hour = 170 sqm. of 40 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 328.01 x6x10 =Rs. 115.77
170

Total hire charges for machineries per 10 sqm =555.63+ 20.64+ 38.76+ 115.77
= 730.80 /10sqm
LABOUR CHARGES PER 1200 SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 11550.00
25.00 Nos Mazdoor IInd Class @Rs. 314.00 /each = 7850.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 3500.00
Total Labour Charges per 1200sqm = 22900.00

Labour Charges per 10sqm. = 22900.00 X 10 =Rs. 190.83


1200

RATE PER SQM OF BITUMINOUS CONCRETE 40MM THICK (Using Plastic Waste)

0.130 Cum Cost of 19.00-9.50mm IRC at Rs. 1101.17 /cum. = 143.15


0.170 Cum Cost of 9.50 - 2.36mm IRC at Rs. 769.87 /cum. = 130.88
0.260 Cum Cost of 2.36 mm and below at Rs. 736.21 /cum. = 191.41
47.28 Kg Cost of VG30 Bitumen at Rs. 34961.15 /MT = 1652.96
3.02 Kg Cost of Waste Plastic at Rs. 20.00 /Kg = 60.40
10.00 Sqm Hire charges at Rs. 730.80 /10sqm = 730.80
10.00 Sqm Labour charges at Rs. 190.83 /10sqm = 190.83
Rate for 10 sqm =Rs. 3100.43

Rate per cum = 3100.43/(10x0.04) = 7751.08

Road Data - Rev-16.2 42 Revised during - Jan. 2017


CLOSE GRADED PREMIX SURFACING 20MM THICK (Using Plastic Waste)
Providing laying and rolling of close graded premix carpet of compacted 20mm thickness using
using 0.0162 cum of 13.20-11.20mm, 0.1404 cum of 11.2-5.6mm, 0.0729 cum of 5.60-2.80mm,
0.0405 cum of 2.80mm and below (Type B) graded HBG metal using 17.86kgs of VG30
bitumen and 1.14Kgs of Waste Plastic for 10sqm including premixing at CMP, conveyance by
tipper lorry, laying by paver finisher and rolling by Vibratory Roller including cost and
conveyance of all materials, hire charges of all T&P all labour charges, fuel and and all other
incidental charges etc., Complete as per specification using CMP as per clause 508 of MORTH
Rev-5
HIRE CHARGES FOR MACHINERIES
1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 58.85 /lit =Rs. 1765.50
For heating the bitumen 25 litres of furnace oil 33.17 /lit =Rs. 829.25
For heating the aggregates : 170 litres of furnace oil 33.17 /lit =Rs. 5638.90
Hire Charges including fuel charges per hour Rs. 9445.65
Out turn of CMP per Hour for SDBC = 270sqm. of 25 mm thick

Hire Charges for CMP per 10sqm. = 9445.65 X 10 =Rs. 349.84


270
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is not
necessary

3.VIBRATORY ROLLERS :
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 58.85 /lit =Rs. 147.13
Hire Charges including fuel charges per Hour Rs. 825.63
Out turn of Vibratory Roller per hour= 500sqm. of 25 mm thick

Hire Charges for Vibratory roller per 10sqm. = 825.63 X 10 =Rs. 16.51
500

4. PAVER FINISHER
Hire charges excluding fuel charges per hour 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 58.85 /lit =Rs. 353.10
Hire Charges including fuel charges per DAY Rs. 658.98
Out turn of Paver Finisher per hour = 270 sqm. of 25 mm thick

Hire Charges for paver finisher per 10sqm. = 658.98 X 10 =Rs. 24.41
270

Road Data - Rev-16.2 43 Revised during - Jan. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 58.85 /lit =Rs. 191.26
Hire Charges including fuel charges per DAY Rs. 328.01
Out turn of Tipper Truck per hour = 270 sqm. of 25 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 328.01 x6x10 =Rs. 72.89
270

Total hire charges for machineries per 10 sqm = 349.84 16.51 24.41 72.89
= 463.65 /10sqm
LABOUR CHARGES PER 2000SQM
For loading materials into CMP
26.40 Nos Mazdoor Ist Class @Rs. 350.00 /each = 9240.00
20.00 Nos Mazdoor IInd Class @Rs. 314.00 /each = 6280.00
For attending Paver Finisher
8.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 2800.00
Total Labour Charges per 2000sqm = 18320.00

Labour Charges per 10sqm. = 18320.00 X 10 =Rs. 91.60


2000

RATE 10SQM OF CLOSE GRADED PREMIX SURFACING 20MM THICK (Using Plastic waste)

0.0162 Cum Cost of 13.20mm -11.20mm Metal at Rs. 1010.21 /Cum. = 16.37
0.1404 Cum Cost of 11.20mm-5.6mm Metal at Rs. 804.21 /Cum. = 112.91
0.0729 Cum Cost of 5.60mm-2.80 Metal at Rs. 736.21 /Cum. = 53.67
0.0405 Cum Cost of 2.80mm and below Metal at Rs. 736.21 /Cum. = 29.82
17.86 Kg Cost of VG30 grade Bitumen at Rs. 34961.15 /MT = 624.41
1.14 Kg Cost of Waste Plastic at Rs. 20.00 /Kg = 22.80
10.00 Sqm Hire charges at Rs. 463.65 /10sqm = 463.65
10.00 Sqm Labour charges at Rs. 91.60 /10sqm = 91.60
Rate for 10 sqm =Rs. 1415.23

Rate per sqm of 20 mm thick = 1415.23 = Rs. 141.52


10

Road Data - Rev-16.2 44 Revised during - Jan. 2017


CLOSE GRADED PREMIX SURFACING 20MM COMPACTED THICK
Providing laying and rolling of close graded premix carpet of compacted 20mm thickness using
using 0.0162 cum of 13.20-11.20mm, 0.1404 cum of 11.2-5.6mm, 0.0729 cum of 5.60-2.80mm,
0.0405 cum of 2.80mm and below (Type B) graded HBG metal using 19kg of VG30 bitumen for
10sqm including premixing at CMP, conveyance by tipper lorry, laying by paver finisher and
rolling by Vibratory Roller including cost and conveyance of all materials, hire charges of all
T&P all labour charges, fuel and and all other incidental charges etc., Complete as per
specification using CMP as per clause 508 of MORTH Rev-5
HIRE CHARGES FOR MACHINERIES
1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 58.85 /lit =Rs. 1765.50
For heating the bitumen 25 litres of furnace oil 33.17 /lit =Rs. 829.25
For heating the aggregates : 170 litres of furnace oil 33.17 /lit =Rs. 5638.90
Hire Charges including fuel charges per hour Rs. 9445.65
Out turn of CMP per Hour for SDBC = 270sqm. of 25 mm thick

Hire Charges for CMP per 10sqm. = 9445.65 X 10 =Rs. 349.84


270
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is not
necessary

3.VIBRATORY ROLLERS :
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 58.85 /lit =Rs. 147.13
Hire Charges including fuel charges per Hour Rs. 825.63
Out turn of Vibratory Roller per hour= 500sqm. of 25 mm thick

Hire Charges for Vibratory roller per 10sqm. = 825.63 X 10 =Rs. 16.51
500

4. PAVER FINISHER
Hire charges excluding fuel charges per hour 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 58.85 /lit =Rs. 353.10
Hire Charges including fuel charges per DAY Rs. 658.98
Out turn of Paver Finisher per hour = 270 sqm. of 25 mm thick

Hire Charges for paver finisher per 10sqm. = 658.98 X 10 =Rs. 24.41
270

Road Data - Rev-16.2 45 Revised during - Jan. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 58.85 /lit =Rs. 191.26
Hire Charges including fuel charges per DAY Rs. 328.01
Out turn of Tipper Truck per hour = 270 sqm. of 25 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 328.01 x6x10 =Rs. 72.89
270

Total hire charges for machineries per 10 sqm = 349.84 16.51 24.41 72.89
= 463.65 /10sqm
LABOUR CHARGES PER 2000SQM
For loading materials into CMP
26.40 Nos Mazdoor Ist Class @Rs. 350.00 /each = 9240.00
20.00 Nos Mazdoor IInd Class @Rs. 314.00 /each = 6280.00
For attending Paver Finisher
8.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 2800.00
Total Labour Charges per 2000sqm = 18320.00

Labour Charges per 10sqm. = 18320.00 X 10 =Rs. 91.60


2000

RATE 10SQM OF CLOSE GRADED PREMIX SURFACING 20MM COMPACTED THICK

0.0162 Cum Cost of 13.20mm -11.20mm Metal at Rs. 1010.21 /Cum. = 16.37
0.1404 Cum Cost of 11.20mm-5.6mm Metal at Rs. 804.21 /Cum. = 112.91
0.0729 Cum Cost of 5.60mm-2.80 Metal at Rs. 736.21 /Cum. = 53.67
0.0405 Cum Cost of 2.80mm and below Metal at Rs. 736.21 /Cum. = 29.82
19 Kg Cost of VG30 grade Bitumen at Rs. 34961.15 /MT = 664.26
10.00 Sqm Hire charges at Rs. 463.65 /10sqm = 463.65
10.00 Sqm Labour charges at Rs. 91.60 /10sqm = 91.60
Rate for 10 sqm =Rs. 1432.28

Rate per sqm of 20 mm thick = 1432.28 = Rs. 143.23


10

Road Data - Rev-16.2 46 Revised during - Jan. 2017


GRANULAR SUB BASE AND BASE COURSE

Rate Cost
Description Unit Quantity
Rs Rs
Granular Sub-Base with Close Graded Material
(Table:- 400-1)
A Plant Mix Method
Construction of granular sub-base by providing close
graded Material, mixing in a mechanical mix plant at
OMC, carriage of mixed Material to work site,
spreading in uniform layers with motor grader on
prepared surface and compacting with vibratory
power roller to achieve the desired density, complete
as per clause 401
Unit = cum
Taking output = 225 cum (450 tonne)
a) Labour
Mate day 0.400 361.00 144.40
Mazdoor skilled day 2.000 350.00 700.00
Mazdoor day 8.000 314.00 2512.00
3356.40
b) Machinery
Wet Mix Plant 75 tonne capacity/ hr hour 6.000 1116.63 6699.78
Electric generator 125 KVA hour 6.000 647.38 3884.28
Water tanker 6 KL capacity 5 km lead with one hour 4.500 290.78 1308.51
trip per hour
Front end loader 1 cum bucket capacity hour 6.000 739.13 4434.78
Tipper 10 tonne; conveyance: 40 km tonne. 450 x L 2.00 36000.00
km
Add 10 per cent of cost of carriage to cover 3600.00
loading and unloading
Motor Grader 110 HP hour 6.000 1691.63 10149.78
Vibratory roller 8-10 t hour 6.000 825.63 4953.78
71030.91
c) Material
Close graded Granular sub-base Material as per table
400-1
For Grading-V Material (Drainage/ Top Layer)

Cost of 53mm to 9.50mm Broken Stone cum 144.000 1145.99 165022.56


Cost of 9.50mm to 2.36mm Broken Stone cum 100.000 777.01 77701.00
Cost of 2.36mm & Below of Sand cum 43.000 736.21 31657.03
Cost of water KL 27.000 130.00 3510.00
277890.59
OR
For Grading-III Material (Bottom Layer if
thickness more than 300mm)
46.5 mm to 26.50 mm cum 101.000 1114.96 112610.96
26.5 mm to 4.75 mm cum 130.000 1054.21 137047.30
4.75 mm below cum 58.000 736.21 42700.18
Cost of water KL 27.000 130.00 3510.00
295868.44
(i) Rate per cum for grading-V Material
Cost for 225 cum = a+b+c 352277.90
Rate per cum = (a+b+c)/225 Rs.1565.68/Cum.

(ii) Rate per cum for grading-III Material


Cost for 225 cum = a+b+c 370255.75
Rate per cum = (a+b+c)/225 Rs.1645.58/Cum.

Road Data - Rev-16.2 47 Revised during - Jan. 2017


ROAD METAL RATE - SITE
Name of work: Name of work: Special Repairs to Bhuvanagiri-Melamanagudi road km 3/0-5/0

Plain
Lead Kind of Cost of Cost of Stacking
Reach in Km Quarry Total
in Km Materials materia Charges
km 3/0-4/0 Metal Quarry 1 at 3/2 of A-Sathanur-Pudukazhani
66,0 63-45mm road 634.81 454.22 3.15 1092.18
66,0 53-22.40mm 859.41 454.22 3.15 1316.78
66,0 53 - 9.5mm(GSB-I) 935.78 454.22 1390.00
66,0 9.50-2.36mm(GSB-I) 566.80 454.22 1021.02
66,0 2.36mm & Below(GSB-I) 526.00 454.22 980.22
66,0 45 mm 908.00 454.22 3.15 1365.37
66,0 26.50-13.20mm(BM) 1160.01 454.22 1614.23
66,0 13.20-2.36mm(BM) 580.49 454.22 1034.71
66,0 2.36 & below(BM) 526.00 454.22 980.22
66,0 26.50-13.20mm(DBM) 1091.49 454.22 1545.71
66,0 13.20-2.36mm(DBM) 578.58 454.22 1032.80
66,0 2.36 & below(DBM) 526.00 454.22 980.22
66,0 Stone Dust(DBM) 109.00 303.78 412.78
66,0 53-22.40mm(BUSG) 1042.31 454.22 1496.53
66,0 22.40-2.80mm(BUSG) 1010.96 454.22 1465.18
66,0 13.20mm 1179.00 454.22 3.15 1636.37
66,0 11.20mm 800.00 454.22 3.15 1257.37
66,0 6.70mm 594.00 454.22 3.15 1051.37
66,0 25 mm IS metal (DLC) 765.00 454.22 1219.22
Gravel quarry at 2/2 of Vanathirayapuram
29,0 Gravel
quarry 169.50 223.27 3.05 395.82
Sand quarry at __ 0,0 Sand 176.40 3.05 179.45
km 4/0-5/0 Metal Quarry 1 at 3/2 of A-Sathanur-Pudukazhani
67,0 63-45mm road 634.81 460.34 3.15 1098.30
67,0 53-22.40mm 859.41 460.34 3.15 1322.90
67,0 53 - 9.5mm(GSB-I) 935.78 460.34 1396.12
67,0 9.50-2.36mm(GSB-I) 566.80 460.34 1027.14
67,0 2.36mm & Below(GSB-I) 526.00 460.34 986.34
67,0 45 mm 908.00 460.34 3.15 1371.49
67,0 26.50-13.20mm(BM) 1160.01 460.34 1620.35
67,0 13.20-2.36mm(BM) 580.49 460.34 1040.83
67,0 2.36 & below(BM) 526.00 460.34 986.34
67,0 26.50-13.20mm(DBM) 1091.49 460.34 1551.83
67,0 13.20-2.36mm(DBM) 578.58 460.34 1038.92
67,0 2.36 & below(DBM) 526.00 460.34 986.34
67,0 Stone Dust(DBM) 109.00 307.66 416.66
67,0 53-22.40mm(BUSG) 1042.31 460.34 1502.65
67,0 22.40-2.80mm(BUSG) 1010.96 460.34 1471.30
67,0 13.20mm 1179.00 460.34 3.15 1642.49
67,0 11.20mm 800.00 460.34 3.15 1263.49
67,0 6.70mm 594.00 460.34 3.15 1057.49
67,0 25 mm IS metal (DLC) 765.00 460.34 1225.34
Gravel quarry at 2/2 of Vanathirayapuram
30,0 Gravel
quarry 169.50 229.80 3.05 402.35
Sand quarry at __ 0,0 Sand 176.40 3.05 179.45

Road Data - Rev-16.2 48 Revised during - Jan. 2017


ROAD METAL RATE - SITE
Name of work: Name of work: Special Repairs to Bhuvanagiri-Melamanagudi road km 3/0-5/0

Plain
Lead Kind of Cost of Cost of Stacking
Reach in Km Quarry Total
in Km Materials materia Charges
km Metal Quarry 2 at __ 0,0 63-45mm 634.81 3.15 637.96
0,0 53-22.40mm 859.41 3.15 862.56
0,0 53 - 9.5mm(GSB-I) 935.78 935.78
0,0 9.50-2.36mm(GSB-I) 566.80 566.80
0,0 2.36mm & Below(GSB-I) 526.00 526.00
0,0 45 mm 908.00 3.15 911.15
0,0 26.50-13.20mm(BM) 1160.01 1160.01
0,0 13.20-2.36mm(BM) 580.49 580.49
0,0 2.36 & below(BM) 526.00 526.00
0,0 26.50-13.20mm(DBM) 1091.49 1091.49
0,0 13.20-2.36mm(DBM) 578.58 578.58
0,0 2.36 & below(DBM) 526.00 526.00
0,0 Stone Dust(DBM) 109.00 109.00
0,0 53-22.40mm(BUSG) 1042.31 1042.31
0,0 22.40-2.80mm(BUSG) 1010.96 1010.96
0,0 13.20mm 1179.00 3.15 1182.15
0,0 11.20mm 800.00 3.15 803.15
0,0 6.70mm 594.00 3.15 597.15
0,0 25 mm IS metal (DLC) 765.00 765.00
Gravel quarry at 0,0 Gravel 169.50 3.05 172.55
Sand quarry at __ 0,0 Sand 176.40 3.05 179.45
km Metal Quarry 2 at __ 0,0 63-45mm 634.81 3.15 637.96
0,0 53-22.40mm 859.41 3.15 862.56
0,0 53 - 9.5mm(GSB-I) 935.78 935.78
0,0 9.50-2.36mm(GSB-I) 566.80 566.80
0,0 2.36mm & Below(GSB-I) 526.00 526.00
0,0 45 mm 908.00 3.15 911.15
0,0 26.50-13.20mm(BM) 1160.01 1160.01
0,0 13.20-2.36mm(BM) 580.49 580.49
0,0 2.36 & below(BM) 526.00 526.00
0,0 26.50-13.20mm(DBM) 1091.49 1091.49
0,0 13.20-2.36mm(DBM) 578.58 578.58
0,0 2.36 & below(DBM) 526.00 526.00
0,0 Stone Dust(DBM) 109.00 109.00
0,0 53-22.40mm(BUSG) 1042.31 1042.31
0,0 22.40-2.80mm(BUSG) 1010.96 1010.96
0,0 13.20mm 1179.00 3.15 1182.15
0,0 11.20mm 800.00 3.15 803.15
0,0 6.70mm 594.00 3.15 597.15
0,0 25 mm IS metal (DLC) 765.00 765.00
Gravel quarry at 0,0 Gravel 169.50 3.05 172.55
Sand quarry at __ 0,0 Sand 176.40 3.05 179.45

Road Data - Rev-16.2 49 Revised during - Jan. 2017


ROAD METAL RATE - SITE
Name of work: Name of work: Special Repairs to Bhuvanagiri-Melamanagudi road km 3/0-5/0

Plain
Lead Kind of Cost of Cost of Stacking
Reach in Km Quarry Total
in Km Materials materia Charges
km Metal Quarry 2 at __ 0,0 63-45mm 634.81 3.15 637.96
0,0 53-22.40mm 859.41 3.15 862.56
0,0 53 - 9.5mm(GSB-I) 935.78 935.78
0,0 9.50-2.36mm(GSB-I) 566.80 566.80
0,0 2.36mm & Below(GSB-I) 526.00 526.00
0,0 45 mm 908.00 3.15 911.15
0,0 26.50-13.20mm(BM) 1160.01 1160.01
0,0 13.20-2.36mm(BM) 580.49 580.49
0,0 2.36 & below(BM) 526.00 526.00
0,0 26.50-13.20mm(DBM) 1091.49 1091.49
0,0 13.20-2.36mm(DBM) 578.58 578.58
0,0 2.36 & below(DBM) 526.00 526.00
0,0 Stone Dust(DBM) 109.00 109.00
0,0 53-22.40mm(BUSG) 1042.31 1042.31
0,0 22.40-2.80mm(BUSG) 1010.96 1010.96
0,0 13.20mm 1179.00 3.15 1182.15
0,0 11.20mm 800.00 3.15 803.15
0,0 6.70mm 594.00 3.15 597.15
0,0 25 mm IS metal (DLC) 765.00 765.00
Gravel quarry at 0,0 Gravel 169.50 3.05 172.55
Sand quarry at __ 0,0 Sand 176.40 3.05 179.45
km Metal Quarry 2 at __ 0,0 63-45mm 634.81 3.15 637.96
0,0 53-22.40mm 859.41 3.15 862.56
0,0 53 - 9.5mm(GSB-I) 935.78 935.78
0,0 9.50-2.36mm(GSB-I) 566.80 566.80
0,0 2.36mm & Below(GSB-I) 526.00 526.00
0,0 45 mm 908.00 3.15 911.15
0,0 26.50-13.20mm(BM) 1160.01 1160.01
0,0 13.20-2.36mm(BM) 580.49 580.49
0,0 2.36 & below(BM) 526.00 526.00
0,0 26.50-13.20mm(DBM) 1091.49 1091.49
0,0 13.20-2.36mm(DBM) 578.58 578.58
0,0 2.36 & below(DBM) 526.00 526.00
0,0 Stone Dust(DBM) 109.00 109.00
0,0 53-22.40mm(BUSG) 1042.31 1042.31
0,0 22.40-2.80mm(BUSG) 1010.96 1010.96
0,0 13.20mm 1179.00 3.15 1182.15
0,0 11.20mm 800.00 3.15 803.15
0,0 6.70mm 594.00 3.15 597.15
0,0 25 mm IS metal (DLC) 765.00 765.00
Gravel quarry at 0,0 Gravel 169.50 3.05 172.55
Sand quarry at __ 0,0 Sand 176.40 3.05 179.45

Road Data - Rev-16.2 50 Revised during - Jan. 2017


ROAD METAL RATE - SITE
Name of work: Name of work: Special Repairs to Bhuvanagiri-Melamanagudi road km 3/0-5/0

Plain
Lead Kind of Cost of Cost of Stacking
Reach in Km Quarry Total
in Km Materials materia Charges
km Metal Quarry 2 at __ 0,0 63-45mm 634.81 3.15 637.96
0,0 53-22.40mm 859.41 3.15 862.56
0,0 53 - 9.5mm(GSB-I) 935.78 935.78
0,0 9.50-2.36mm(GSB-I) 566.80 566.80
0,0 2.36mm & Below(GSB-I) 526.00 526.00
0,0 45 mm 908.00 3.15 911.15
0,0 26.50-13.20mm(BM) 1160.01 1160.01
0,0 13.20-2.36mm(BM) 580.49 580.49
0,0 2.36 & below(BM) 526.00 526.00
0,0 26.50-13.20mm(DBM) 1091.49 1091.49
0,0 13.20-2.36mm(DBM) 578.58 578.58
0,0 2.36 & below(DBM) 526.00 526.00
0,0 Stone Dust(DBM) 109.00 109.00
0,0 53-22.40mm(BUSG) 1042.31 1042.31
0,0 22.40-2.80mm(BUSG) 1010.96 1010.96
0,0 13.20mm 1179.00 3.15 1182.15
0,0 11.20mm 800.00 3.15 803.15
0,0 6.70mm 594.00 3.15 597.15
0,0 25 mm IS metal (DLC) 765.00 765.00
Gravel quarry at 0,0 Gravel 169.50 3.05 172.55
Sand quarry at __ 0,0 Sand 176.40 3.05 179.45
km Metal Quarry 2 at __ 0,0 63-45mm 634.81 3.15 637.96
0,0 53-22.40mm 859.41 3.15 862.56
0,0 53 - 9.5mm(GSB-I) 935.78 935.78
0,0 9.50-2.36mm(GSB-I) 566.80 566.80
0,0 2.36mm & Below(GSB-I) 526.00 526.00
0,0 45 mm 908.00 3.15 911.15
0,0 26.50-13.20mm(BM) 1160.01 1160.01
0,0 13.20-2.36mm(BM) 580.49 580.49
0,0 2.36 & below(BM) 526.00 526.00
0,0 26.50-13.20mm(DBM) 1091.49 1091.49
0,0 13.20-2.36mm(DBM) 578.58 578.58
0,0 2.36 & below(DBM) 526.00 526.00
0,0 Stone Dust(DBM) 109.00 109.00
0,0 53-22.40mm(BUSG) 1042.31 1042.31
0,0 22.40-2.80mm(BUSG) 1010.96 1010.96
0,0 13.20mm 1179.00 3.15 1182.15
0,0 11.20mm 800.00 3.15 803.15
0,0 6.70mm 594.00 3.15 597.15
0,0 25 mm IS metal (DLC) 765.00 765.00
Gravel quarry at 0,0 Gravel 169.50 3.05 172.55
Sand quarry at __ 0,0 Sand 176.40 3.05 179.45

Road Data - Rev-16.2 51 Revised during - Jan. 2017


ROAD METAL RATE - SITE
Name of work: Name of work: Special Repairs to Bhuvanagiri-Melamanagudi road km 3/0-5/0

Plain
Lead Kind of Cost of Cost of Stacking
Reach in Km Quarry Total
in Km Materials materia Charges
km Metal Quarry 2 at __ 0,0 63-45mm 634.81 3.15 637.96
0,0 53-22.40mm 859.41 3.15 862.56
0,0 53 - 9.5mm(GSB-I) 935.78 935.78
0,0 9.50-2.36mm(GSB-I) 566.80 566.80
0,0 2.36mm & Below(GSB-I) 526.00 526.00
0,0 45 mm 908.00 3.15 911.15
0,0 26.50-13.20mm(BM) 1160.01 1160.01
0,0 13.20-2.36mm(BM) 580.49 580.49
0,0 2.36 & below(BM) 526.00 526.00
0,0 26.50-13.20mm(DBM) 1091.49 1091.49
0,0 13.20-2.36mm(DBM) 578.58 578.58
0,0 2.36 & below(DBM) 526.00 526.00
0,0 Stone Dust(DBM) 109.00 109.00
0,0 53-22.40mm(BUSG) 1042.31 1042.31
0,0 22.40-2.80mm(BUSG) 1010.96 1010.96
0,0 13.20mm 1179.00 3.15 1182.15
0,0 11.20mm 800.00 3.15 803.15
0,0 6.70mm 594.00 3.15 597.15
0,0 25 mm IS metal (DLC) 765.00 765.00
Gravel quarry at 0,0 Gravel 169.50 3.05 172.55
Sand quarry at __ 0,0 Sand 176.40 3.05 179.45
km Metal Quarry 2 at __ 0,0 63-45mm 634.81 3.15 637.96
0,0 53-22.40mm 859.41 3.15 862.56
0,0 53 - 9.5mm(GSB-I) 935.78 935.78
0,0 9.50-2.36mm(GSB-I) 566.80 566.80
0,0 2.36mm & Below(GSB-I) 526.00 526.00
0,0 45 mm 908.00 3.15 911.15
0,0 26.50-13.20mm(BM) 1160.01 1160.01
0,0 13.20-2.36mm(BM) 580.49 580.49
0,0 2.36 & below(BM) 526.00 526.00
0,0 26.50-13.20mm(DBM) 1091.49 1091.49
0,0 13.20-2.36mm(DBM) 578.58 578.58
0,0 2.36 & below(DBM) 526.00 526.00
0,0 Stone Dust(DBM) 109.00 109.00
0,0 53-22.40mm(BUSG) 1042.31 1042.31
0,0 22.40-2.80mm(BUSG) 1010.96 1010.96
0,0 13.20mm 1179.00 3.15 1182.15
0,0 11.20mm 800.00 3.15 803.15
0,0 6.70mm 594.00 3.15 597.15
0,0 25 mm IS metal (DLC) 765.00 765.00
Gravel quarry at 0,0 Gravel 169.50 3.05 172.55
Sand quarry at __ 0,0 Sand 176.40 3.05 179.45
Conveyance of earth for embankment and berms

Road Data - Rev-16.2 52 Revised during - Jan. 2017


ROAD METAL RATE - SITE
Name of work: Name of work: Special Repairs to Bhuvanagiri-Melamanagudi road km 3/0-5/0

Plain
Lead Kind of Cost of Cost of Stacking
Reach in Km Quarry Total
in Km Materials materia Charges
km 3/0-4/0 Earth quarry at __ 0,0 Carted Earth
km 4/0-5/0 Earth quarry at __ 0,0 Carted Earth
km Earth quarry at __ 0,0 Carted Earth
km Earth quarry at __ 0,0 Carted Earth
km Earth quarry at __ 0,0 Carted Earth
km Earth quarry at __ 0,0 Carted Earth
km Earth quarry at __ 0,0 Carted Earth
km Earth quarry at __ 0,0 Carted Earth
km Earth quarry at __ 0,0 Carted Earth
km Earth quarry at __ 0,0 Carted Earth

Road Data - Rev-16.2 53 Revised during - Jan. 2017


BITUMEN RATE TO SITE
VG 10 VG 30
CRMB 55
Basic Rate 26866.00 27666.00 18590.00
Excise Duty 14.00% 3761.24 3873.24 2974.40
Educational Cess on ED 0.00% 89.23
30627.24 31539.24 21653.63
VAT 5.00% 1531.36 1576.96 866.15
32158.60 33116.20 22519.78
Storage Charges 5% of basic price 1343.30 1383.30 929.50
33501.90 34499.50 23449.28

Conveyance at Rs.0.99924per km for 245 km 489.63 489.63 489.63


140 33991.53 34989.13 23938.91

round 2
LEAD IN KM

EMULSION BITUMEN RATE TO SITE


Slow Setting - Rapid Setting-I
I For Tack for Tack Coat
Coat Application
Application (R/C Drums)
Basic Rate 51432.00 31539.00
Excise Duty 14.00% 7200.00 4415.00
58632.00 35954.00
Sales Tax 14.50% (VAT) 8502.00 5213.00
67134.00 41167.00
Storage Charges 5% of basic price 2572.00 1577.00
Deduct Drum cost -1500.00 -1500.00
Conveyance at Rs.1.69 per km for 214 km 361.66 361.66
68567.66 41605.66

Road Data - Rev-16.2 54 Revised during - Jan. 2017


Prime Coat Over WBM/ WMM Surface

Providing and laying Prime Coat over WBM/ WMM surface using 7 Kg of Emulsion
Bitumen (SS1) per 10 sqm for preparatory to another bituminous construction over it,
including cost of material, labour charges, rentals for machinery, fuel and all other
incidental charges etc., complete as perClause 502 of MORTH Rev-5
Labour Charges per 500 sqm for preparation of surface
10.00 Nos Mazdoor Ist Grade @Rs 350.00 /each =Rs 3500.00
16.00 Nos Mazdoor IIst Grade @Rs 314.00 /each =Rs 5024.00
For Applying Primer
4.00 Nos Mazdoor IIst Grade @Rs 314.00 /each =Rs 1256.00
Total Labour Charges per 500 sqm =Rs 9780.00

Total Labour Charges per 10 sqm = 9780.00 x10 Rs. 195.60


500
Rate for Prime Coat over WBM/ WMM surface

7.00 Kgs Cost of Bitumen Emulsion - SS1 @Rs 68567.66 /MT =Rs 479.97
10.00 Sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 Sqm Labour Charges @Rs 195.60 /10sqm =Rs 195.60
Rate for 10 sqm =Rs 690.57

Rate per 1.00 sqm =Rs 69.06 /sqm

Prime Coat Over CRM/ Gravel base


Providing and laying Prime Coat over CRM/ Gravel base using 9 Kg of Emulsion Bitumen
(SS1) per 10 sqm for preparatory to another bituminous construction over it including cost
of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
complete as perClause 502 of MORTH Rev-5
Labour Charges per 500 sqm for preparation of surface
10.00 Nos Mazdoor Ist Grade @Rs 350.00 /each =Rs 3500.00
16.00 Nos Mazdoor IIst Grade @Rs 314.00 /each =Rs 5024.00
For Applying Primer
4.00 Nos Mazdoor IIst Grade @Rs 314.00 /each =Rs 1256.00
Total Labour Charges per 500 sqm =Rs 9780.00

Total Labour Charges per 10 sqm =


9780.00 x10 Rs. 195.60
500
Rate for Prime Coat over Crusher Run Macadam surface

9.00 Kgs Cost of Bitumen Emulsion (SS1) @Rs 68567.66 /MT =Rs 617.11
10.00 Sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 Sqm Labour Charges @Rs 195.60 /10sqm =Rs 195.60
Rate for 10 sqm =Rs 827.71
Rate per 1.00 sqm =Rs 82.77 /sqm

Road Data - Rev-16.2 55 Revised during - Jan. 2017


Tack Coat over Dry Lean Cement Concrete Surface

Providing and laying Tack Coat over Dry Lean Cement Concrete surface using 3.00 Kg of
Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction
over it including cost of material, labour charges, rentals for machinery, fuel and all other
incidental charges etc., complete as perClause 503 of MORTH Rev-5
Labour Charges per 500 sqm

3.00 Nos Mazdoor IInd Grade(Applying TC)@Rs 314.00 /each =Rs 942.00
Total Labour Charges per 500 sqm =Rs 942.00

Total Labour Charges per 10 sqm =942.00 x10 Rs. 18.84


500
Rate for Tack Coat over Dry Lean Cement Concrete Surface

3.00 Kgs Cost of RS-I Bitumen emulsion @Rs 41605.66 /MT =Rs 124.82
10.00 Sqm Hire for bitumen boiler @Rs /10sqm =Rs
10.00 Sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 Sqm Labour Charges @Rs 18.84 /10sqm =Rs 18.84
Rate for 10 sqm =Rs 158.66

Rate per 1.00 sqm =Rs 15.87 /sqm

Road Data - Rev-16.2 56 Revised during - Jan. 2017


Tack Coat Over Existing BT Surface

Providing and laying Tack Coat over Existing BT surface using 2 Kg of Bitumen
Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it
including cost of material, labour charges, rentals for machinery, fuel and all other
incidental charges etc., complete as perClause 503 of MORTH Rev-5

Labour Charges per 500 sqm


5.00 Nos Mazdoor Ist Grade Preparing Surface @Rs 350.00 /each =Rs 1750.00
5.00 Nos Mazdoor IIst Grade(Applying TC)@Rs 314.00 /each =Rs 1570.00
Total Labour Charges per 500 sqm =Rs 3320.00

Total Labour Charges per 10 sqm = 3320.00 x10 Rs. 66.40


500
Rate for Tack Coat over Existing BT surface

2.00 Kgs Cost of RS-I Bitumen emulsion @Rs 41605.66 /MT =Rs 83.21
10.00 Sqm Hire for bitumen boiler @Rs /10sqm =Rs
10.00 sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 sqm Labour Charges @Rs 66.40 /10sqm =Rs 66.40
Rate for 10 sqm =Rs 164.61

Rate per 1.00 sqm =Rs 16.46 /sqm

Tack Coat Over Primed Surface

Providing and laying Tack Coat over WBM/ WMM surface (treated with primer) using
2.50 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous
construction over it including cost of material, labour charges, rentals for machinery,
fuel and all other incidental charges etc., complete as perClause 503 of MORTH Rev-5
Labour Charges per 500 sqm
3.00 Nos Mazdoor IInd Grade(Applying TC)@Rs 314.00 /each =Rs 942.00
Total Labour Charges per 500 sqm =Rs 942.00

Total Labour Charges per 10 sqm =


942.00 x10 Rs. 18.84
500
Rate for Tack Coat over primed WBM / WMM Surface

2.50 Kgs Cost of RS-I Bitumen emulsion @Rs 41605.66 /MT =Rs 104.01
10.00 Sqm Hire for bitumen boiler @Rs /10sqm =Rs
10.00 Sqm Hire for Bitumen Sprayer @Rs 15.00 /10sqm =Rs 15.00
10.00 Sqm Labour Charges @Rs 18.84 /10sqm =Rs 18.84
Rate for 10 sqm =Rs 137.85

Rate per 1.00 sqm =Rs 13.79 /sqm

Road Data - Rev-16.2 57 Revised during - Jan. 2017


METAL RATE
METAL RATE FOR GRANULAR SUB BASE (TABLE NO.400.1)

Granular Sub Base Grade - I

Cost of 53mm to 22.40mm Broken Stone

Cost of 53mmMetal @Rs 677.00 /Cum.


Cost of 46.50mmMetal @Rs 908.00 /Cum.
Cost of 45mmMetal @Rs 908.00 /Cum.
Cost of 37.50mmMetal @Rs 927.00 /Cum.
Cost of 26.50mmMetal @Rs 876.00 /Cum.
Cost of 25mmMetal @Rs 876.00 /Cum.
Cost of 22.40mmMetal @Rs 1271.00 /Cum.
Average Rate of 53-22.40mm @Rs 920.43 /Cum.

WATER BOUND MACADAM GRADE - I


0.050 Cum. Cost of 125mm IRC at Rs. 385.00 /cum. = 19.25
0.525 Cum. Cost of 90mm IRC at Rs. 385.00 /cum. = 202.13
0.350 Cum. Cost of 63mm IRC at Rs. 557.00 /cum. = 194.95
0.050 Cum. Cost of 45mm IRC at Rs. 908.00 /cum. = 45.40
0.025 Cum. Cost of 22.40mm IRC at Rs. 1271.00 /cum. = 31.78
Rate of Metal 90-45mm for G-I Rs. 493.51

WATER BOUND MACADAM GRADE - II


0.05 Cum Cost of 90mm IRC at Rs. 385.00 /cum. = 19.25
0.45 Cum Cost of 63mm IRC at Rs. 557.00 /cum. = 250.65
0.425 Cum Cost of 53mm IRC at Rs. 677.00 /cum. = 287.73
0.05 Cum Cost of 45mm IRC at Rs. 908.00 /cum. = 45.40
0.025 Cum Cost of 22.40mm IRC at Rs. 1271.00 /cum. = 31.78
Rate of Metal 63-45mm for G-II Rs. 634.81

WATER BOUND MACADAM GRADE - III


0.025 Cum Cost of 63mm IRC at Rs. 557.00 /cum. = 13.93
0.20 Cum Cost of 53mm IRC at Rs. 677.00 /cum. = 135.40
0.725 Cum Cost of 45mm IRC at Rs. 908.00 /cum. = 658.30
0.025 Cum Cost of 22.40mm IRC at Rs. 1271.00 /cum. = 31.78
0.025 Cum Cost of 11.20mm IRC at Rs. 800.00 /cum. = 20.00
Rate of Metal 53-22.40mm for G-III Rs. 859.41

Road Data - Rev-16.2 58 Revised during - Jan. 2017


Labour Charges for Patch Work with Bituminous Premix Materials
for 0.625 cum of Bituminous Materials
Picking the road surface 2" to 3" deep
1. In patches and cutting Mazdoor Ist Class 1.08 x 1/6 x 350.00 /No - 63.00

2. Removing the Picked up stuff Mazdoor Ist 1.08x1/8x 350.00 /No - 47.25

3. Brushing and Cleaning the Surface - - L. S. - - - 3.78

4. Spreading the Bitumen for Tack Coat excluding cost of Bitumen -L.S.- - 3.10

5. Premixing the chips with hot Bitumen in the drum mixer and laying
0.625 cum of metal with 44 kg per cum of chips excluding the cost of the
bitumen - - L. S. - - - 15.75

6. Levelling and tamping the premix in the patches and pot holes rolling etc- 4.73

7 Special tools such as wire brushes etc., - L. S. - - - 2.31

8. Regulation of Traffic - - L.S. - - - 2.50

9. Sundries such as barricading arrangements - L. S. - - - 1.33

Labour for laying 0.625 cum of Bituminlous materials - 143.75

Therefore for laying 1.00 cum of Bituminous materials 143.75/0.625 = 230.00

Rs. 230.00 /Cum.

For Premix carpet

Road Data - Rev-16.2 59 Revised during - Jan. 2017


WATER BOUND MACADAM GRADE - II & III
Providing and laying Water Bound Macadam Grading - II & III consisting of clean, crushed aggregates
mechanically interlocked by rolling and bonding together with screening binding material and finished
in accordance with the requirements of the specification and thickness as per approved plans or as
directed by the Engineer (in two layers), as per clause 404 of MORTH revision V (Mix-in-place
method)

Hire charges for Machineries

Power Roller 8-10 tonne


Hire charges excluding fuel charges per day =Rs. 828.00
Fuel charges per day (Diesel) 2.50 lit/Hr x 8.00 Hrs. x 58.85 /lit =Rs. 1177.00
Total Hire charges per day including Fuel =Rs. 2005.00
Daily Out turn 450 sqm of 75mm thick

Hire charges of Power Roller per 10 sqm. 2005.00 x 10 =Rs. 44.56 /10sqm
450
Water Sprinklers
Hire charges excluding fuel charges per day =Rs. 1159.00
Fuel charges per day (Diesel) 3.50 lit/Hr x 8.00 Hrs. x 58.85 /lit =Rs. 1647.80
Total Hire charges per day including Fuel =Rs. 2806.80
Daily Out turn 450 sqm of 75mm

Hire charges of Water Sprinklers per 10 sqm. 2806.80 x 10 =Rs. 62.37 /10sqm
450

Total Hire charges for Machineries per10sqm = 44.56 + 62.37 =Rs. 106.93 /10sqm

Labour Charges for spreading 10 sqm of 75mm thick:

1.08 x 3/16 of Mazdoor Ist class @ Rs. 350.00 /E =Rs 70.88


1.08 x 1/4 of Mazdoor IInd class @ Rs. 314.00 /E =Rs 84.78
1.08 x 1/3 of Mazdoor IIIrd class @ Rs. 314.00 /E =Rs 113.04

b.Forming edge bunds L.S =Rs 1.50

c.Maintaining berms for traffic barricading, providing danger linghts etc., L.S =Rs 1.50

d. Watering and keeping the surface moist for 15 days when water is available =Rs 1.50
within 200m L.S
e. Rent for tools including basket sharpening Pick-axes etc. L.S =Rs 1.50

f.Sundries such as ropes water pots etc., L.S =Rs 1.50


Total =Rs 276.20

Total Hire and Labour charges per 10sqm = 106.93 + 276.20 =Rs 383.13 /10sqm
of 75mm thick

Road Data - Rev-16.2 60 Revised during - Jan. 2017


PREMIX CARPET WITH SEAL COAT TYPE - A
Providing and laying compacting open graded premix carpet 20mm thick with a liquid seal
coat which shall consist of open graded carpet of 20mm thickness in a single course composed
of suitable small sized aggregates premixed with bituminous binder (VG30) with application of
liquid seal coat for sealing the voids in a bituminous surface conforming to the specifications
including cost of material, labour charges, rentals for machinery, fuel and all other incidental
charges etc., complete as per MORTH Rev-5 (Mix-in-place method)
Hire charges for Machineries
Mini Hot Mix Plant
Hire charges excluding fuel charges per hour 1674 /8 =Rs. 209.25
Fuel charges per hour diesel (running plant) 15.00 Lit x 58.85 /lit =Rs. 882.75
Fuel for heating aggregates per hour 45.00 Lit x 33.17 /lit =Rs. 1492.65
Total Hire charges including Fuel =Rs. 2584.65
Daily Out turn for Premix Carpet = 180 sqm.
Hire charges of Mini Hot Mix Plantper 10 sqm. 2584.65 x 10 =Rs. 143.59 /10sqm
180
Power Roller 8-10 tonne
Hire charges excluding fuel charges per day =Rs. 828.00
Fuel charges per day (Diesel) 2.50 lit/Hr x 8.00 Hrs. x 58.85 /lit =Rs. 1177.00
Total Hire charges per day including Fuel =Rs. 2005.00
Daily Out turn of road roller for Premix Carpet = 500 sqm
Daily Out turn for Seal Coat = 1000 sqm
Hire charges for Premix Carpet per 10 sqm. 2005.00 x 10 =Rs. 40.10 /10sqm
500
Hire charges for Seal Coat per 10 sqm. 2005.00 x 10 =Rs. 20.05 /10sqm
1000
Total hire charges for power roller (pc+sc) = = 40.1.00 + 20.05.00 =Rs. 60.15 /10sqm
Bitumen Boiler 750 lit capacity
Hire charges excluding fuel charges per day =Rs. 202.00
Fuel charges per day Kerosene 25.00 Lit x 52.03 /lit =Rs. 1300.75
Total Hire charges per day including Fuel =Rs. 1502.75
For Premix carpet
Daily Out turn of Bitumen Boiler per hour 125 Kg.
Bitumen to be utilised for PC (14.6 kgs) 125x10/14.6 = 85.62 sqm
Hire charges for PC per 10 sqm = 1502.75x10 = 15027.50 = 21.94 /10sqm
8x85.62 684.96
For seal coat
Daily Out turn of Bitumen Boiler per hour 125 Kg.
Bitumen to be utilised for SC (9.80 kgs) 125x10/9.8 = 127.551 sqm
Hire charges for seal coat/ 10sqm = 1502.75x10 = 15027.50 = 14.73 /10sqm
8x127.551 1020.41
Total Hire Charges for Machineries per 10 sqm (PC+SC) = 143.59+60.15+21.94+14.73
Total Hire Charges for Machineries per 10 sqm (PC+SC) =Rs. 240.41 /10sqm
Labour charges for Premix Carpet with Seal Coat per 10sqm
0.75 Nos. of Mazdoor Ist Class @Rs. 350.00 /E =Rs. 262.50
0.25 Nos. of Mazdoor Ist Class @Rs. 350.00 /E =Rs. 87.50
Total Labour charges for Premix Carpet and Seal Coat per 10sqm =Rs. 350.00

Total Hire and Labour charges = 240.41 + 350.00 =Rs. 590.41 /10sqm

Road Data - Rev-16.2 61 Revised during - Jan. 2017


Granular Sub Base Grade - I
Providing and laying Granular Sub Base (GSB) to required thickness on the prepared sub
grade minimun CBR value 30 Grading conorming to table 400-1/200-2 of MORTH - Revision
- IV with sand, gravel, crushed stone or quarry fines and or any other granular material or
combination to given CBR of 30 on prepared sub grade in accordance with the requirements of
the specifications including cost of material, labour charges, rentals for machinery, fuel and all
other incidental charges etc., complete as per clause 401 of MORTH Rev-5 (Mix-in-place
Hire charges for Machineries and Labour Charges for 300 cum.
BY MIX IN PLACE METHOD

Motor Grader including fuel / Hour 13533 / 8 =Rs. 1691.63 /Hour


Vibratory Roller
Hire charges excluding fuel charges per day =Rs. 5428.00
Fuel charges per day (Diesel) 2.50 lit/Hr x 8.00 Hrs. x 58.85 /lit =Rs. 1177.00
Total Hire charges per day including Fuel =Rs. 6605.00

Hire charges of Vibrator Roller per Hour 6605.00 / 8 =Rs. 825.63 /Hour

Tractor + Rotovator
Hire charges for Tractor-Rotovator including fuel per hour 353.00

Total Hire charges for Tractor Rotovator per hour 353

Water Tanker
Hire charges excluding fuel charges per day =Rs. 2005.00
Fuel charges per day (Diesel) 25.00 /Day 58.85 /lit =Rs. 1471.25
Total Hire charges per day including Fuel =Rs. 3476.25

Hire Charges for Water Tanker per Hour 3476.25 / 8 =Rs. 434.53 /Hour

Hire and Fuel charges for Machineries for 300 cum of GSB Grade - I

1. Motor Grader 6.00 Hours Rs. 1691.63 /Hour =Rs. 10149.78


2. Vibratory Roller 6.00 Hours Rs. 825.63 /Hour =Rs. 4953.78
3. Tractor Rotovator 6.00 Hours Rs. 353.00 /Hour =Rs. 2118.00
4. Water Tanker 3.00 Hours Rs. 434.53 /Hour =Rs. 1303.59
Total Hire Charges for Machineries per 300 cum of GSB Gr-I =Rs. 18525.15

LABOUR CHARGES FOR 300 CUM.


1. Mate 0.48 Nos. Rs. 361.00 /Hour =Rs. 173.28
2. Mazdoor Ist Class 2.00 Nos. Rs. 350.00 /Hour =Rs. 700.00
3. Mazdoor II nd Class 10.00 Hours Rs. 314.00 /Hour =Rs. 3140.00
Total Labour Charges per 300 cum of GSB Gr-I =Rs. 4013.28

Total Hire and Labour Charges for 300 Cum of GSB Grade-I = Rs.22538.43 /300Cum.
Total Hire and Labour Charges per Cum of GSB Grade-I = Rs.75.13 /Cum.

Road Data - Rev-16.2 62 Revised during - Jan. 2017


PREMIX CARPET
Providing and laying compacting open graded premix carpet 20mm thick which shall consist of
open graded carpet of 20mm thickness in a single course composed of suitable small sized
aggregates premixed with bituminous binder (VG30) with application for sealing the voids in a
bituminous surface conforming to the specifications including cost of material, labour charges,
rentals for machinery, fuel and all other incidental charges etc., complete as per MORTH Rev-
5 (Mix-in-place method)
Hire charges for Machineries

Mini Hot Mix Plant


Hire charges excluding fuel charges per hour 1674 /8 =Rs. 209.25
Fuel charges per hour diesel (running plant) 15.00 Lit x 58.85 /lit =Rs. 882.75
Fuel for heating aggregates per hour 45.00 Lit x 33.17 /lit =Rs. 1492.65
Total Hire charges including Fuel =Rs. 2584.65
Daily Out turn for Premix Carpet = 180 sqm.
Hire charges of Mini Hot Mix Plantper 10 sqm. 2584.65 x 10 =Rs. 143.59 /10sqm
180
Power Roller 8-10 tonne
Hire charges excluding fuel charges per day =Rs. 828.00
Fuel charges per day (Diesel) 2.50 lit/Hr x 8.00 Hrs. x 58.85 /lit =Rs. 1177.00
Total Hire charges per day including Fuel =Rs. 2005.00
Daily Out turn of road roller for Premix Carpet = 500 sqm
Hire charges for Premix Carpet per 10 sqm. 2005.00 x 10 =Rs. 40.10 /10sqm
500
Bitumen Boiler 750 lit capacity
Hire charges excluding fuel charges per day =Rs. 202.00
Fuel charges per day Kerosene 25.00 Lit x 52.03 /lit =Rs. 1300.75
Total Hire charges per day including Fuel =Rs. 1502.75
Daily Out turn of Bitumen Boiler per hour 125 Kg.
Hire and fuel charges of boiler per hour = 1502.75 /8 =Rs. 187.84
Out turn of Bitumen boiler per Kg = 187.84 /125 = 1.5
Hire charges of Bitumen boiler per 10sqm = 14.60 x 1.5 =Rs. 21.9 /10sqm

Total Hire Charges for Machineries per 10 sqm =Rs. 205.59 /10sqm

Labour charges for Premix Carpet per 10sqm


0.75 Nos. of Mazdoor Ist Class @Rs. 350.00 /E =Rs. 262.50
Total Labour charges for Premix Carpet per 10sqm =Rs. 262.50

Total Hire and Labour charges = 205.59 + 262.50 =Rs. 468.09 /10sqm

Road Data - Rev-16.2 63 Revised during - Jan. 2017


BITUMINOUS MACADAM 50MM THICK USING MINI HOT MIX PLANT
Providing and Laying 50mm thick Bituminous Macadam using course aggregate and VG30 bitumen
which shall consist of construction in a single course base/binder course confirming to the specfication
on a previously prepared base.(using Mini Hot Mix Plant and Power Roller) including cost of material,
labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause
504 MORTH Rev-5 (Mix-in-place method) (For Patch Works)
Hire charges for Machineries

Mini Hot Mix Plant


Hire charges excluding fuel charges per hour 1674 /8 =Rs. 209.25
Fuel charges per hour diesel (running plant) 15.00 Lit x 58.85 /lit =Rs. 882.75
Fuel for heating aggregates per hour 45.00 Lit x 33.17 /lit =Rs. 1492.65
Total Hire charges including Fuel =Rs. 2584.65
Daily Out turn for BM 50mm thick = 75 sqm.
Hire charges of Mini Hot Mix Plantper 10 sqm. 2584.65 x 10 =Rs. 344.62 /10sqm
75
Power Roller 8-10 tonne
Hire charges excluding fuel charges per day =Rs. 828.00
Fuel charges per day (Diesel) 2.50 lit/Hr x 8.00 Hrs. x 58.85 /lit =Rs. 1177.00
Total Hire charges per day including Fuel =Rs. 2005.00
Daily Out turn for BM 50mm thick = 300 sqm
Hire charges for BM 50mm thick per 10 sqm. 2005.00 x 10 =Rs. 66.83 /10sqm
300
Bitumen Boiler 750 lit capacity
Hire charges excluding fuel charges per day =Rs. 202.00
Fuel charges per day Kerosene 25.00 Lit x 52.03 /lit =Rs. 1300.75
Total Hire charges per day including Fuel =Rs. 1502.75
Hire and fuel charges of boiler per hour = 1502.75 /8 =Rs. 187.84
Daily Out turn of Bitumen Boiler per hour = 125 Kg.
Bitumen Required for BM 50mm thick per 10 sqm = 37 kg
Bitumen to be utilised for PC (14.6 kgs) 125x10/37 = 33.784 sqm
Hire charges for PC per 10 sqm = 1502.75x10 = 15027.50 = 55.6 /10sqm
8x33.784 270.27
Total Hire Charges for Machineries per 10 sqm =Rs. 467.05 /10sqm

Labour charges for BM 50mm thick per 1200sqm


83 Nos. Cost of Mazdoor Ist Class @Rs. 350.00 /E =Rs. 29050.00
55 Nos. Cost of Mazdoor IInd Class @Rs. 314.00 /E =Rs. 17270.00
Total Labour charges for BM 50mm thick per 1200sqm =Rs. 46320.00

Labour charges for BM 50mm thick per 10 sqm. 46320.00 x 10 =Rs. 386.00 /10sqm
1200

Total Hire and Labour charges = 467.05 + 386.00 =Rs. 853.05 /10sqm

DENSE BITUMINOUS MACADAM 50MM THICK USING MINI HOT MIX PLANT

Road Data - Rev-16.2 64 Revised during - Jan. 2017


Providing and laying 50mm consolidated thick Dense Bituminous Macadam using 0.35 cum of 26.50-
13.20mm, 0.21cum of 13.20-2.36mm and 0.14cum of 2.36mm & below with 0.01cum.of Filling
materials and with 49.50 Kgs of VG30 bitumen for premixing per 10sqm including cost and
conveyance of all materials to work site, heating the bitumen and aggregate to required temperature
and mixing them in required temperature in mini hot mix plant, spreading the mix to uniform thickness
of 50mm to the specified grades and cross sections and consolidated by 8-10 tonne power roller to the
required density etc., including all labour for laying, spreading etc., including hire charges and fuel
charges for mini hot mix plant with bitumen boiler, power rollers and all other tools and plant required,
including all other incidental charges etc., complete as per specification using mini hot mix plant clause
505 of MORTH. (Mix-in-place method)
Hire charges for Machineries
Mini Hot Mix Plant
Hire charges excluding fuel charges per hour 1674 /8 =Rs. 209.25
Fuel charges per hour diesel (running plant) 15.00 Lit x 58.85 /lit =Rs. 882.75
Fuel for heating aggregates per hour 45.00 Lit x 33.17 /lit =Rs. 1492.65
Total Hire charges including Fuel =Rs. 2584.65
Daily Out turn for DBM 50mm thick = 75 sqm.
Hire charges of Mini Hot Mix Plantper 10 sqm. 2584.65 x 10 =Rs. 344.62 /10sqm
75
Power Roller 8-10 tonne
Hire charges excluding fuel charges per day =Rs. 828.00
Fuel charges per day (Diesel) 2.50 lit/Hr x 8.00 Hrs. x 58.85 /lit =Rs. 1177.00
Total Hire charges per day including Fuel =Rs. 2005.00
Daily Out turn for DBM 50mm thick = 300 sqm
Hire charges for DBM 50mm thick per 10 sqm. 2005.00 x 10 =Rs. 66.83 /10sqm
300
Bitumen Boiler 750 lit capacity
Hire charges excluding fuel charges per day =Rs. 202.00
Fuel charges per day Kerosene 25.00 Lit x 52.03 /lit =Rs. 1300.75
Total Hire charges per day including Fuel =Rs. 1502.75
Hire and fuel charges of boiler per hour = 1502.75 /8 =Rs. 187.84
Daily Out turn of Bitumen Boiler per hour = 125 Kg.
Bitumen Required for DBM 50mm thick per 10 sqm = 60 kg
Bitumen to be utilised for PC (14.6 kgs) 125x10/60 = 20.833 sqm
Hire charges for PC per 10 sqm = 1502.75x10 = 15027.50 = 90.17 /10sqm
8x20.833 166.66

Total Hire Charges for Machineries per 10 sqm =Rs. 501.62 /10sqm

Labour charges for DBM 50mm thick per 1200sqm


83 Nos. Cost of Mazdoor Ist Class @Rs. 350.00 /E =Rs. 29050.00
55 Nos. Cost of Mazdoor Ist Class @Rs. 314.00 /E =Rs. 17270.00
Total Labour charges for DBM 50mm thick per 1200sqm =Rs. 46320.00

Labour charges for DBM 50mm thick per 10 sqm. 46320.00 x 10 =Rs. 386.00 /10sqm
1200

Total Hire and Labour charges = 501.62 + 386.00 =Rs. 887.62 /10sqm

Road Data - Rev-16.2 65 Revised during - Jan. 2017


PROVIDING GRAVEL FOR BERMS INCL. COMPACTION
Providing and laying of Gravel including cost and conveyance of the same to work site from
approved quarry including stacking the same to departemental gauge for premeasurement including
all labour charges for laying, spreading etc., complete and as directed by the departmental engineers
for making up of low berms

Hire charges for Machineries

Power Roller 8-10 tonne


Hire charges excluding fuel charges per day =Rs. 828.00
Fuel charges per day (Diesel) 2.50 lit/Hr x 8.00 Hrs. x 58.85 /lit =Rs. 1177.00
Total Hire charges per day including Fuel =Rs. 2005.00
Daily Out turn 425 Cum.

Hire charges of Power Roller per 10 sqm. 2005.00 =Rs. 4.72 /Cum
425
Water Sprinklers
Hire charges excluding fuel charges per day =Rs. 1159.00
Fuel charges per day (Diesel) 3.25 lit/Hr x 8.00 Hrs. x 58.85 /lit =Rs. 1530.10
Total Hire charges per day including Fuel =Rs. 2689.10
Daily Out turn 1000 Cum.

Hire charges of Water Sprinklers per 10 sqm. 2689.10 =Rs. 2.69 /Cum
1000

Total Hire charges for Machineries per10sqm = 4.72 + 2.69 =Rs. 7.41 /Cum

Labour charges for Laying U.S. Gravel for 100cum


2.00 Nos. of Mazdoor Ist Class @Rs. 350.00 /E =Rs. 700.00
Total Labour charges for laying gravel per 100cum =Rs. 700.00

Total Labour charges for laying gravel per Cum 700.00 =Rs. 7 /Cum
100
Total Hire and Labour charges = 7.41 + 7.00 =Rs. 14.41 /Cum

Road Data - Rev-16.2 66 Revised during - Jan. 2017


DRY LEAN CEMENT CONCRETE 1:4:8
Quantit Unit Rate Unit Amount
y Dry Lean Cement Concrete Sub- base
Construction of dry lean cement concrete Sub- base over a
prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed
15:1, aggregate gradation after blending to be as per table
600-1, cement content not to be less than 150 kg/ cum,
concrete strength not to be less than 10 Mpa at 7 days,
mixed at site, compacted using vibrator, finishing and
output = 10 cum
a) Labour
1.800 day Mason II CLass 444.00 /day 799.20
17.700 day Mazdoor I CLass 310.00 /day 5487.00
14.100 day Mazdoor II CLass 280.00 /day 3948.00
b) Machinery
10.000 cum Vibrator Charges 34.80 /cum 348.00

Road Data - Rev-16.2 67 Revised during - Jan. 2017


Patch work using 45mm IRC metal

km 3/0-4/0
1.00 Cum. Cost of 45mm IRC at Rs. 1365.37 /cum. = 1365.37
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 3091.00

km 4/0-5/0 21
1.00 Cum. Cost of 45mm IRC at Rs. 1371.49 /cum. = 1371.49
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 3097.12

km 42
1.00 Cum. Cost of 45mm IRC at Rs. 911.15 /cum. = 911.15
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 2636.78

km 63
1.00 Cum. Cost of 45mm IRC at Rs. 911.15 /cum. = 911.15
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 2636.78

km 84
1.00 Cum. Cost of 45mm IRC at Rs. 911.15 /cum. = 911.15
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 2636.78

km 105
1.00 Cum. Cost of 45mm IRC at Rs. 911.15 /cum. = 911.15
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 2636.78

km 126
1.00 Cum. Cost of 45mm IRC at Rs. 911.15 /cum. = 911.15
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 2636.78

Road Data - Rev-16.2 68 Revised during - Jan. 2017


Patch work using 45mm IRC metal
km 147
1.00 Cum. Cost of 45mm IRC at Rs. 911.15 /cum. = 911.15
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 2636.78

km 168
1.00 Cum. Cost of 45mm IRC at Rs. 911.15 /cum. = 911.15
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 2636.78

km 189
1.00 Cum. Cost of 45mm IRC at Rs. 911.15 /cum. = 911.15
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 2636.78

Road Data - Rev-16.2 69 Revised during - Jan. 2017


Patch work using 13.20mm IRC metal

km 3/0-4/0
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1636.37 /cum. = 1636.37
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 3362.00

km 4/0-5/0 21
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1642.49 /cum. = 1642.49
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 3368.12

km 42
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1182.15 /cum. = 1182.15
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 2907.78

km 63
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1182.15 /cum. = 1182.15
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 2907.78

km 84
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1182.15 /cum. = 1182.15
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 2907.78

km 105
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1182.15 /cum. = 1182.15
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 2907.78

km 126
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1182.15 /cum. = 1182.15
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 2907.78

Road Data - Rev-16.2 70 Revised during - Jan. 2017


Patch work using 13.20mm IRC metal
km 147
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1182.15 /cum. = 1182.15
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 2907.78

km 168
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1182.15 /cum. = 1182.15
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 2907.78

km 189
1.00 Cum. Cost of 13.20 mm IRC at Rs. 1182.15 /cum. = 1182.15
44 Kg Cost of VG10 Bitumen at Rs. 33991.53 /MT = 1495.63
1.00 Cum. Labour charges at Rs. 230.00 /cum. = 230.00
Rate for 1.00 cum. Rs. 2907.78

Road Data - Rev-16.2 71 Revised during - Jan. 2017


WATER BOUND MACADAM GRADE-II
km 3/0-4/0
1.00 Cum. Cost of 63-45mm IRC at Rs. 1092.18 /cum. = 1092.18
0.24 Cum. Cost of Gravel at Rs. 395.82 /cum. = 95.00
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1570.31
Rate for 1.00 cum. 1570.31 = Rs. 2093.75
0.75
km 4/0-5/0 21
1.00 Cum. Cost of 63-45mm IRC at Rs. 1098.30 /cum. = 1098.30
0.24 Cum. Cost of Gravel at Rs. 402.35 /cum. = 96.56
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1577.99
Rate for 1.00 cum. 1577.99 = Rs. 2103.99
0.75
km 42
1.00 Cum. Cost of 63-45mm IRC at Rs. 637.96 /cum. = 637.96
0.24 Cum. Cost of Gravel at Rs. 172.55 /cum. = 41.41
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1062.50
Rate for 1.00 cum. 1062.50 = Rs. 1416.67
0.75
km 63
1.00 Cum. Cost of 63-45mm IRC at Rs. 637.96 /cum. = 637.96
0.24 Cum. Cost of Gravel at Rs. 172.55 /cum. = 41.41
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1062.50
Rate for 1.00 cum. 1062.50 = Rs. 1416.67
0.75
km 84
1.00 Cum. Cost of 63-45mm IRC at Rs. 637.96 /cum. = 637.96
0.24 Cum. Cost of Gravel at Rs. 172.55 /cum. = 41.41
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1062.50
Rate for 1.00 cum. 1062.50 = Rs. 1416.67
0.75
km 105
1.00 Cum. Cost of 63-45mm IRC at Rs. 637.96 /cum. = 637.96
0.24 Cum. Cost of Gravel at Rs. 172.55 /cum. = 41.41
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1062.50
Rate for 1.00 cum. 1062.50 = Rs. 1416.67
0.75

Road Data - Rev-16.2 72 Revised during - Jan. 2017


WATER BOUND MACADAM GRADE-II
km 126
1.00 Cum. Cost of 63-45mm IRC at Rs. 637.96 /cum. = 637.96
0.24 Cum. Cost of Gravel at Rs. 172.55 /cum. = 41.41
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1062.50
Rate for 1.00 cum. 1062.50 = Rs. 1416.67
0.75
km 147
1.00 Cum. Cost of 63-45mm IRC at Rs. 637.96 /cum. = 637.96
0.24 Cum. Cost of Gravel at Rs. 172.55 /cum. = 41.41
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1062.50
Rate for 1.00 cum. 1062.50 = Rs. 1416.67
0.75
km 168
1.00 Cum. Cost of 63-45mm IRC at Rs. 637.96 /cum. = 637.96
0.24 Cum. Cost of Gravel at Rs. 172.55 /cum. = 41.41
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1062.50
Rate for 1.00 cum. 1062.50 = Rs. 1416.67
0.75
km 189
1.00 Cum. Cost of 63-45mm IRC at Rs. 637.96 /cum. = 637.96
0.24 Cum. Cost of Gravel at Rs. 172.55 /cum. = 41.41
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1062.50
Rate for 1.00 cum. 1062.50 = Rs. 1416.67
0.75

Road Data - Rev-16.2 73 Revised during - Jan. 2017


WATER BOUND MACADAM GRADE-III
km 3/0-4/0
1.00 Cum. Cost of 53-2.40mm IRC at Rs. 1316.78 /cum. = 1316.78
0.24 Cum. Cost of Gravel at Rs. 395.82 /cum. = 95.00
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1794.91
Rate for 1.00 cum. 1794.91 = Rs. 2393.21
0.75
km 4/0-5/0 21
1.00 Cum. Cost of 53-2.40mm IRC at Rs. 1322.90 /cum. = 1322.90
0.24 Cum. Cost of Gravel at Rs. 402.35 /cum. = 96.56
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1802.59
Rate for 1.00 cum. 1802.59 = Rs. 2403.45
0.75
km 42
1.00 Cum. Cost of 53-2.40mm IRC at Rs. 862.56 /cum. = 862.56
0.24 Cum. Cost of Gravel at Rs. 172.55 /cum. = 41.41
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1287.10
Rate for 1.00 cum. 1287.10 = Rs. 1716.13
0.75
km 63
1.00 Cum. Cost of 53-2.40mm IRC at Rs. 862.56 /cum. = 862.56
0.24 Cum. Cost of Gravel at Rs. 172.55 /cum. = 41.41
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1287.10
Rate for 1.00 cum. 1287.10 = Rs. 1716.13
0.75
km 84
1.00 Cum. Cost of 53-2.40mm IRC at Rs. 862.56 /cum. = 862.56
0.24 Cum. Cost of Gravel at Rs. 172.55 /cum. = 41.41
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1287.10
Rate for 1.00 cum. 1287.10 = Rs. 1716.13
0.75
km 105
1.00 Cum. Cost of 53-2.40mm IRC at Rs. 862.56 /cum. = 862.56
0.24 Cum. Cost of Gravel at Rs. 172.55 /cum. = 41.41
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1287.10
Rate for 1.00 cum. 1287.10 = Rs. 1716.13
0.75

Road Data - Rev-16.2 74 Revised during - Jan. 2017


WATER BOUND MACADAM GRADE-III
km 126
1.00 Cum. Cost of 53-2.40mm IRC at Rs. 862.56 /cum. = 862.56
0.24 Cum. Cost of Gravel at Rs. 172.55 /cum. = 41.41
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1287.10
Rate for 1.00 cum. 1287.10 = Rs. 1716.13
0.75
km 147
1.00 Cum. Cost of 53-2.40mm IRC at Rs. 862.56 /cum. = 862.56
0.24 Cum. Cost of Gravel at Rs. 172.55 /cum. = 41.41
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1287.10
Rate for 1.00 cum. 1287.10 = Rs. 1716.13
0.75
km 168
1.00 Cum. Cost of 53-2.40mm IRC at Rs. 862.56 /cum. = 862.56
0.24 Cum. Cost of Gravel at Rs. 172.55 /cum. = 41.41
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1287.10
Rate for 1.00 cum. 1287.10 = Rs. 1716.13
0.75
km 189
1.00 Cum. Cost of 53-2.40mm IRC at Rs. 862.56 /cum. = 862.56
0.24 Cum. Cost of Gravel at Rs. 172.55 /cum. = 41.41
10.00 Sqm Hire & Labour charges at Rs. 383.13 /10sqm. = 383.13
Rate for 10.0 sqm. Rs. 1287.10
Rate for 1.00 cum. 1287.10 = Rs. 1716.13
0.75

Road Data - Rev-16.2 75 Revised during - Jan. 2017


Premix carpet with Seal Coat
km 3/0-4/0
0.18 Cum. Cost of 13.20mm IRC at Rs. 1636.37 /cum.= 294.55
0.09 Cum. Cost of 11.20mm IRC at Rs. 1257.37 /cum. = 113.16
0.09 Cum. Cost of 6.70mm IRC at Rs. 1051.37 /cum. = 94.62
24.40 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 853.73
10.00 Sqm Hire and Labour Charges at Rs. 590.41 /10sqm. = 590.41
Rate for 10 sqm. = 1946.47
Rate for 1 sqm. =Rs. 194.65 /sqm.
km 4/0-5/0 21
0.18 Cum. Cost of 13.20mm IRC at Rs. 1642.49 /cum.= 295.65
0.09 Cum. Cost of 11.20mm IRC at Rs. 1263.49 /cum. = 113.71
0.09 Cum. Cost of 6.70mm IRC at Rs. 1057.49 /cum. = 95.17
24.40 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 853.73
10.00 Sqm Hire and Labour Charges at Rs. 590.41 /10sqm. = 590.41
Rate for 10 sqm. = 1948.67
Rate for 1 sqm. =Rs. 194.87 /sqm.
km 42
0.18 Cum. Cost of 13.20mm IRC at Rs. 1182.15 /cum.= 212.79
0.09 Cum. Cost of 11.20mm IRC at Rs. 803.15 /cum. = 72.28
0.09 Cum. Cost of 6.70mm IRC at Rs. 597.15 /cum. = 53.74
24.40 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 853.73
10.00 Sqm Hire and Labour Charges at Rs. 590.41 /10sqm. = 590.41
Rate for 10 sqm. = 1782.95
Rate for 1 sqm. =Rs. 178.30 /sqm.
km 63
0.18 Cum. Cost of 13.20mm IRC at Rs. 1182.15 /cum.= 212.79
0.09 Cum. Cost of 11.20mm IRC at Rs. 803.15 /cum. = 72.28
0.09 Cum. Cost of 6.70mm IRC at Rs. 597.15 /cum. = 53.74
24.40 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 853.73
10.00 Sqm Hire and Labour Charges at Rs. 590.41 /10sqm. = 590.41
Rate for 10 sqm. = 1782.95
Rate for 1 sqm. =Rs. 178.30 /sqm.
km 84
0.18 Cum. Cost of 13.20mm IRC at Rs. 1182.15 /cum.= 212.79
0.09 Cum. Cost of 11.20mm IRC at Rs. 803.15 /cum. = 72.28
0.09 Cum. Cost of 6.70mm IRC at Rs. 597.15 /cum. = 53.74
24.40 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 853.73
10.00 Sqm Hire and Labour Charges at Rs. 590.41 /10sqm. = 590.41
Rate for 10 sqm. = 1782.95
Rate for 1 sqm. =Rs. 178.30 /sqm.

Road Data - Rev-16.2 76 Revised during - Jan. 2017


Premix carpet with Seal Coat
km 105
0.18 Cum. Cost of 13.20mm IRC at Rs. 1182.15 /cum.= 212.79
0.09 Cum. Cost of 11.20mm IRC at Rs. 803.15 /cum. = 72.28
0.09 Cum. Cost of 6.70mm IRC at Rs. 597.15 /cum. = 53.74
24.40 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 853.73
10.00 Sqm Hire and Labour Charges at Rs. 590.41 /10sqm. = 590.41
Rate for 10 sqm. = 1782.95
Rate for 1 sqm. =Rs. 178.30 /sqm.

km 126
0.18 Cum. Cost of 13.20mm IRC at Rs. 1182.15 /cum.= 212.79
0.09 Cum. Cost of 11.20mm IRC at Rs. 803.15 /cum. = 72.28
0.09 Cum. Cost of 6.70mm IRC at Rs. 597.15 /cum. = 53.74
24.40 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 853.73
10.00 Sqm Hire and Labour Charges at Rs. 590.41 /10sqm. = 590.41
Rate for 10 sqm. = 1782.95
Rate for 1 sqm. =Rs. 178.30 /sqm.
km 147
0.18 Cum. Cost of 13.20mm IRC at Rs. 1182.15 /cum.= 212.79
0.09 Cum. Cost of 11.20mm IRC at Rs. 803.15 /cum. = 72.28
0.09 Cum. Cost of 6.70mm IRC at Rs. 597.15 /cum. = 53.74
24.40 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 853.73
10.00 Sqm Hire and Labour Charges at Rs. 590.41 /10sqm. = 590.41
Rate for 10 sqm. = 1782.95
Rate for 1 sqm. =Rs. 178.30 /sqm.
km 168
0.18 Cum. Cost of 13.20mm IRC at Rs. 1182.15 /cum.= 212.79
0.09 Cum. Cost of 11.20mm IRC at Rs. 803.15 /cum. = 72.28
0.09 Cum. Cost of 6.70mm IRC at Rs. 597.15 /cum. = 53.74
24.40 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 853.73
10.00 Sqm Hire and Labour Charges at Rs. 590.41 /10sqm. = 590.41
Rate for 10 sqm. = 1782.95
Rate for 1 sqm. =Rs. 178.30 /sqm.
km 189
0.18 Cum. Cost of 13.20mm IRC at Rs. 1182.15 /cum.= 212.79
0.09 Cum. Cost of 11.20mm IRC at Rs. 803.15 /cum. = 72.28
0.09 Cum. Cost of 6.70mm IRC at Rs. 597.15 /cum. = 53.74
24.40 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 853.73
10.00 Sqm Hire and Labour Charges at Rs. 590.41 /10sqm. = 590.41
Rate for 10 sqm. = 1782.95
Rate for 1 sqm. =Rs. 178.30 /sqm.

Road Data - Rev-16.2 77 Revised during - Jan. 2017


Premix Carpet
km 3/0-4/0
0.18 Cum. Cost of 13.20mm IRC at Rs. 1636.37 /cum. = 294.55
0.09 Cum. Cost of 11.20mm IRC at Rs. 1257.37 /cum. = 113.16
14.60 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 510.84
10.00 Sqm Hire and Labour Charges at Rs. 468.09 /10sqm. = 468.09
14.6 Rate for 10 sqm. = 1386.64
Rate for 1 sqm. =Rs. 138.66 /sqm.
km 4/0-5/0 21
0.18 Cum. Cost of 13.20mm IRC at Rs. 1642.49 /cum. = 295.65
0.09 Cum. Cost of 11.20mm IRC at Rs. 1263.49 /cum. = 113.71
14.60 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 510.84
10.00 Sqm Hire and Labour Charges at Rs. 468.09 /10sqm. = 468.09
Rate for 10 sqm. = 1388.29
Rate for 1 sqm. =Rs. 138.83 /sqm.
km 42
0.18 Cum. Cost of 13.20mm IRC at Rs. 1182.15 /cum. = 212.79
0.09 Cum. Cost of 11.20mm IRC at Rs. 803.15 /cum. = 72.28
14.60 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 510.84
10.00 Sqm Hire and Labour Charges at Rs. 468.09 /10sqm. = 468.09
Rate for 10 sqm. = 1264.00
Rate for 1 sqm. =Rs. 126.40 /sqm.
km 63
0.18 Cum. Cost of 13.20mm IRC at Rs. 1182.15 /cum. = 212.79
0.09 Cum. Cost of 11.20mm IRC at Rs. 803.15 /cum. = 72.28
14.60 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 510.84
10.00 Sqm Hire and Labour Charges at Rs. 468.09 /10sqm. = 468.09
Rate for 10 sqm. = 1264.00
Rate for 1 sqm. =Rs. 126.40 /sqm.
km 84
0.18 Cum. Cost of 13.20mm IRC at Rs. 1182.15 /cum. = 212.79
0.09 Cum. Cost of 11.20mm IRC at Rs. 803.15 /cum. = 72.28
14.60 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 510.84
10.00 Sqm Hire and Labour Charges at Rs. 468.09 /10sqm. = 468.09
Rate for 10 sqm. = 1264.00
Rate for 1 sqm. =Rs. 126.40 /sqm.
km 105
0.18 Cum. Cost of 13.20mm IRC at Rs. 1182.15 /cum. = 212.79
0.09 Cum. Cost of 11.20mm IRC at Rs. 803.15 /cum. = 72.28
14.60 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 510.84
10.00 Sqm Hire and Labour Charges at Rs. 468.09 /10sqm. = 468.09
Rate for 10 sqm. = 1264.00
Rate for 1 sqm. =Rs. 126.40 /sqm.

Road Data - Rev-16.2 78 Revised during - Jan. 2017


Premix Carpet
km 126
0.18 Cum. Cost of 13.20mm IRC at Rs. 1182.15 /cum. = 212.79
0.09 Cum. Cost of 11.20mm IRC at Rs. 803.15 /cum. = 72.28
14.60 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 510.84
10.00 Sqm Hire and Labour Charges at Rs. 468.09 /10sqm. = 468.09
Rate for 10 sqm. = 1264.00
Rate for 1 sqm. =Rs. 126.40 /sqm.
km 147
0.18 Cum. Cost of 13.20mm IRC at Rs. 1182.15 /cum. = 212.79
0.09 Cum. Cost of 11.20mm IRC at Rs. 803.15 /cum. = 72.28
14.60 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 510.84
10.00 Sqm Hire and Labour Charges at Rs. 468.09 /10sqm. = 468.09
Rate for 10 sqm. = 1264.00
Rate for 1 sqm. =Rs. 126.40 /sqm.
km 168
0.18 Cum. Cost of 13.20mm IRC at Rs. 1182.15 /cum. = 212.79
0.09 Cum. Cost of 11.20mm IRC at Rs. 803.15 /cum. = 72.28
14.60 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 510.84
10.00 Sqm Hire and Labour Charges at Rs. 468.09 /10sqm. = 468.09
Rate for 10 sqm. = 1264.00
Rate for 1 sqm. =Rs. 126.40 /sqm.
km 189
0.18 Cum. Cost of 13.20mm IRC at Rs. 1182.15 /cum. = 212.79
0.09 Cum. Cost of 11.20mm IRC at Rs. 803.15 /cum. = 72.28
14.60 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 510.84
10.00 Sqm Hire and Labour Charges at Rs. 468.09 /10sqm. = 468.09
Rate for 10 sqm. = 1264.00
Rate for 1 sqm. =Rs. 126.40 /sqm.

Road Data - Rev-16.2 79 Revised during - Jan. 2017


Granular Sub Base
km 3/0-4/0
192.00 Cum. Cost of 53 mm to 9.5 mm metal at Rs. 1390.00 /cum. = 2,66,880.00
76.00 Cum. Cost of 9.5 mm to 2.36 mm metalat Rs. 1021.02 /cum. = 77,597.52
115.20 Cum. Cost of 2.36 mm below metal at Rs. 980.22 /cum. = 112,921.34
18.00 KL. Cost of Water at Rs. 130.00 /cum. = 2340.00
300.00 Cum. Hire and Labour Charges at Rs. 75.13 /cum. = 22538.43
Rate of 300Cum of Granular Sub Base = 4,82,277.29
Rate of Granular Sub Base per Cum. = Rs. 1607.59
km 4/0-5/0 21
192.00 Cum. Cost of 53 mm to 9.5 mm metal at Rs. 1396.12 /cum. = 2,68,055.04
76.00 Cum. Cost of 9.5 mm to 2.36 mm metalat Rs. 1027.14 /cum. = 78,062.64
115.20 Cum. Cost of 2.36 mm below metal at Rs. 986.34 /cum. = 113,626.37
18.00 KL. Cost of Water at Rs. 130.00 /cum. = 2340.00
300.00 Cum. Hire and Labour Charges at Rs. 75.13 /cum. = 22538.43
Rate of 300Cum of Granular Sub Base = 4,84,622.48
Rate of Granular Sub Base per Cum. = Rs. 1615.41
km 42
192.00 Cum. Cost of 53 mm to 9.5 mm metal at Rs. 935.78 /cum. = 1,79,669.76
76.00 Cum. Cost of 9.5 mm to 2.36 mm metalat Rs. 566.80 /cum. = 43,076.80
115.20 Cum. Cost of 2.36 mm below metal at Rs. 526.00 /cum. = 60,595.20
18.00 KL. Cost of Water at Rs. 130.00 /cum. = 2340.00
300.00 Cum. Hire and Labour Charges at Rs. 75.13 /cum. = 22538.43
Rate of 300Cum of Granular Sub Base = 3,08,220.19
Rate of Granular Sub Base per Cum. = Rs. 1027.40
km 63
192.00 Cum. Cost of 53 mm to 9.5 mm metal at Rs. 935.78 /cum. = 1,79,669.76
76.00 Cum. Cost of 9.5 mm to 2.36 mm metalat Rs. 566.80 /cum. = 43,076.80
115.20 Cum. Cost of 2.36 mm below metal at Rs. 526.00 /cum. = 60,595.20
18.00 KL. Cost of Water at Rs. 130.00 /cum. = 2340.00
300.00 Cum. Hire and Labour Charges at Rs. 75.13 /cum. = 22538.43
Rate of 300Cum of Granular Sub Base = 3,08,220.19
Rate of Granular Sub Base per Cum. = Rs. 1027.40
km 84
192.00 Cum. Cost of 53 mm to 9.5 mm metal at Rs. 935.78 /cum. = 1,79,669.76
76.00 Cum. Cost of 9.5 mm to 2.36 mm metalat Rs. 566.80 /cum. = 43,076.80
115.20 Cum. Cost of 2.36 mm below metal at Rs. 526.00 /cum. = 60,595.20
18.00 KL. Cost of Water at Rs. 130.00 /cum. = 2340.00
300.00 Cum. Hire and Labour Charges at Rs. 75.13 /cum. = 22538.43
Rate of 300Cum of Granular Sub Base = 3,08,220.19
Rate of Granular Sub Base per Cum. = Rs. 1027.40

Road Data - Rev-16.2 80 Revised during - Jan. 2017


Granular Sub Base
km 105
192.00 Cum. Cost of 53 mm to 9.5 mm metal at Rs. 935.78 /cum. = 1,79,669.76
76.00 Cum. Cost of 9.5 mm to 2.36 mm metalat Rs. 566.80 /cum. = 43,076.80
115.20 Cum. Cost of 2.36 mm below metal at Rs. 526.00 /cum. = 60,595.20
18.00 KL. Cost of Water at Rs. 130.00 /cum. = 2340.00
300.00 Cum. Hire and Labour Charges at Rs. 75.13 /cum. = 22538.43
Rate of 300Cum of Granular Sub Base = 3,08,220.19
Rate of Granular Sub Base per Cum. = Rs. 1027.40

km 126
192.00 Cum. Cost of 53 mm to 9.5 mm metal at Rs. 935.78 /cum. = 1,79,669.76
76.00 Cum. Cost of 9.5 mm to 2.36 mm metalat Rs. 566.80 /cum. = 43,076.80
115.20 Cum. Cost of 2.36 mm below metal at Rs. 526.00 /cum. = 60,595.20
18.00 KL. Cost of Water at Rs. 130.00 /cum. = 2340.00
300.00 Cum. Hire and Labour Charges at Rs. 75.13 /cum. = 22538.43
Rate of 300Cum of Granular Sub Base = 3,08,220.19
Rate of Granular Sub Base per Cum. = Rs. 1027.40
km 147
192.00 Cum. Cost of 53 mm to 9.5 mm metal at Rs. 935.78 /cum. = 1,79,669.76
76.00 Cum. Cost of 9.5 mm to 2.36 mm metalat Rs. 566.80 /cum. = 43,076.80
115.20 Cum. Cost of 2.36 mm below metal at Rs. 526.00 /cum. = 60,595.20
18.00 KL. Cost of Water at Rs. 130.00 /cum. = 2340.00
300.00 Cum. Hire and Labour Charges at Rs. 75.13 /cum. = 22538.43
Rate of 300Cum of Granular Sub Base = 3,08,220.19
Rate of Granular Sub Base per Cum. = Rs. 1027.40
km 168
192.00 Cum. Cost of 53 mm to 9.5 mm metal at Rs. 935.78 /cum. = 1,79,669.76
76.00 Cum. Cost of 9.5 mm to 2.36 mm metalat Rs. 566.80 /cum. = 43,076.80
115.20 Cum. Cost of 2.36 mm below metal at Rs. 526.00 /cum. = 60,595.20
18.00 KL. Cost of Water at Rs. 130.00 /cum. = 2340.00
300.00 Cum. Hire and Labour Charges at Rs. 75.13 /cum. = 22538.43
Rate of 300Cum of Granular Sub Base = 3,08,220.19
Rate of Granular Sub Base per Cum. = Rs. 1027.40
km 189
192.00 Cum. Cost of 53 mm to 9.5 mm metal at Rs. 935.78 /cum. = 1,79,669.76
76.00 Cum. Cost of 9.5 mm to 2.36 mm metalat Rs. 566.80 /cum. = 43,076.80
115.20 Cum. Cost of 2.36 mm below metal at Rs. 526.00 /cum. = 60,595.20
18.00 KL. Cost of Water at Rs. 130.00 /cum. = 2340.00
300.00 Cum. Hire and Labour Charges at Rs. 75.13 /cum. = 22538.43
Rate of 300Cum of Granular Sub Base = 3,08,220.19
Rate of Granular Sub Base per Cum. = Rs. 1027.40

Road Data - Rev-16.2 81 Revised during - Jan. 2017


BITUMINOUS MACADAM 50MM THICK (For Patch Works)
km 3/0-4/0
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1614.23 /cum. = 322.85
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 1034.71 /cum. = 444.93
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 980.22 /cum. = 78.42
37.00 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1294.60
10.00 Sqm Hire charges at Rs. 467.05 /10sqm = 467.05
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 2993.85

Rate per cum of 50 mm thick = 2993.85 = Rs. 5987.70


0.50
km 4/0-5/0 21
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1620.35 /cum. = 324.07
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 1040.83 /cum. = 447.56
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 986.34 /cum. = 78.91
37.00 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1294.60
10.00 Sqm Hire charges at Rs. 467.05 /10sqm = 467.05
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 2998.19

Rate per cum of 50 mm thick = 2998.19 = Rs. 5996.38


0.50
km 42
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1160.01 /cum. = 232.00
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 580.49 /cum. = 249.61
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 526.00 /cum. = 42.08
37.00 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1294.60
10.00 Sqm Hire charges at Rs. 467.05 /10sqm = 467.05
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 2671.34

Rate per cum of 50 mm thick = 2671.34 = Rs. 5342.68


0.50
km 63
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1160.01 /cum. = 232.00
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 580.49 /cum. = 249.61
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 526.00 /cum. = 42.08
37.00 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1294.60
10.00 Sqm Hire charges at Rs. 467.05 /10sqm = 467.05
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 2671.34

Rate per cum of 50 mm thick = 2671.34 = Rs. 5342.68


0.50

Road Data - Rev-16.2 82 Revised during - Jan. 2017


BITUMINOUS MACADAM 50MM THICK (For Patch Works)
km 84
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1160.01 /cum. = 232.00
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 580.49 /cum. = 249.61
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 526.00 /cum. = 42.08
37.00 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1294.60
10.00 Sqm Hire charges at Rs. 467.05 /10sqm = 467.05
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 2671.34

Rate per cum of 50 mm thick = 2671.34 = Rs. 5342.68


0.50
km 105
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1160.01 /cum. = 232.00
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 580.49 /cum. = 249.61
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 526.00 /cum. = 42.08
37.00 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1294.60
10.00 Sqm Hire charges at Rs. 467.05 /10sqm = 467.05
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 2671.34

Rate per cum of 50 mm thick = 2671.34 = Rs. 5342.68


0.50
km 126
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1160.01 /cum. = 232.00
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 580.49 /cum. = 249.61
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 526.00 /cum. = 42.08
37.00 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1294.60
10.00 Sqm Hire charges at Rs. 467.05 /10sqm = 467.05
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 2671.34

Rate per cum of 50 mm thick = 2671.34 = Rs. 5342.68


0.50
km 147
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1160.01 /cum. = 232.00
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 580.49 /cum. = 249.61
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 526.00 /cum. = 42.08
37.00 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1294.60
10.00 Sqm Hire charges at Rs. 467.05 /10sqm = 467.05
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 2671.34

Rate per cum of 50 mm thick = 2671.34 = Rs. 5342.68


0.50

Road Data - Rev-16.2 83 Revised during - Jan. 2017


BITUMINOUS MACADAM 50MM THICK (For Patch Works)
km 168
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1160.01 /cum. = 232.00
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 580.49 /cum. = 249.61
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 526.00 /cum. = 42.08
37.00 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1294.60
10.00 Sqm Hire charges at Rs. 467.05 /10sqm = 467.05
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 2671.34

Rate per cum of 50 mm thick = 2671.34 = Rs. 5342.68


0.50
km 189
0.20 Cum. Cost of 26.5-13.20mm IRC at Rs. 1160.01 /cum. = 232.00
0.43 Cum. Cost of 13.20-2.36mm IRC at Rs. 580.49 /cum. = 249.61
0.08 Cum. Cost of 2.36mm & below IRC at Rs. 526.00 /cum. = 42.08
37.00 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1294.60
10.00 Sqm Hire charges at Rs. 467.05 /10sqm = 467.05
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 2671.34

Rate per cum of 50 mm thick = 2671.34 = Rs. 5342.68


0.50

Road Data - Rev-16.2 84 Revised during - Jan. 2017


RATE PER CUM OF 50MM THICK DENSE BITUMINOUS MACADAM
km 3/0-4/0
0.35 Cum. Cost of 26.50 - 13.20mm IRC at Rs. 1545.71 /cum. = 541.00
0.21 Cum. Cost of 13.20-2.36mm IRC at Rs. 1032.80 /cum. = 216.89
0.14 Cum. Cost of 2.36mm & below IRC at Rs. 980.22 /cum. = 137.23
0.01 Cum. Cost of Stone Dust (Filling mat.)at Rs. 412.78 /cum. = 4.13
49.50 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1731.96
10.00 Sqm Hire charges at Rs. 501.62 /10sqm = 501.62
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 3518.83

Rate per cum of 50 mm thick = 3518.83 = Rs. 7037.66


0.50
km 4/0-5/0 21
0.35 Cum. Cost of 26.50 - 13.20mm IRC at Rs. 1551.83 /cum. = 543.14
0.21 Cum. Cost of 13.20-2.36mm IRC at Rs. 1038.92 /cum. = 218.17
0.14 Cum. Cost of 2.36mm & below IRC at Rs. 986.34 /cum. = 138.09
0.01 Cum. Cost of Stone Dust (Filling mat.)at Rs. 416.66 /cum. = 4.17
49.50 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1731.96
10.00 Sqm Hire charges at Rs. 501.62 /10sqm = 501.62
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 3523.15

Rate per cum of 50 mm thick = 3523.15 = Rs. 7046.30


0.50
km 42
0.35 Cum. Cost of 26.50 - 13.20mm IRC at Rs. 1091.49 /cum. = 382.02
0.21 Cum. Cost of 13.20-2.36mm IRC at Rs. 578.58 /cum. = 121.50
0.14 Cum. Cost of 2.36mm & below IRC at Rs. 526.00 /cum. = 73.64
0.01 Cum. Cost of Stone Dust (Filling mat.)at Rs. 109.00 /cum. = 1.09
49.50 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1731.96
10.00 Sqm Hire charges at Rs. 501.62 /10sqm = 501.62
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 3197.83

Rate per cum of 50 mm thick = 3197.83 = Rs. 6395.66


0.50
km 63
0.35 Cum. Cost of 26.50 - 13.20mm IRC at Rs. 1091.49 /cum. = 382.02
0.21 Cum. Cost of 13.20-2.36mm IRC at Rs. 578.58 /cum. = 121.50
0.14 Cum. Cost of 2.36mm & below IRC at Rs. 526.00 /cum. = 73.64
0.01 Cum. Cost of Stone Dust (Filling mat.)at Rs. 109.00 /cum. = 1.09
49.50 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1731.96
10.00 Sqm Hire charges at Rs. 501.62 /10sqm = 501.62
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 3197.83

Rate per cum of 50 mm thick = 3197.83 = Rs. 6395.66


0.50

Road Data - Rev-16.2 85 Revised during - Jan. 2017


RATE PER CUM OF 50MM THICK DENSE BITUMINOUS MACADAM
km 84
0.35 Cum. Cost of 26.50 - 13.20mm IRC at Rs. 1091.49 /cum. = 382.02
0.21 Cum. Cost of 13.20-2.36mm IRC at Rs. 578.58 /cum. = 121.50
0.14 Cum. Cost of 2.36mm & below IRC at Rs. 526.00 /cum. = 73.64
0.01 Cum. Cost of Stone Dust (Filling mat.)at Rs. 109.00 /cum. = 1.09
49.50 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1731.96
10.00 Sqm Hire charges at Rs. 501.62 /10sqm = 501.62
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 3197.83

Rate per cum of 50 mm thick = 3197.83 = Rs. 6395.66


0.50
km 105
0.35 Cum. Cost of 26.50 - 13.20mm IRC at Rs. 1091.49 /cum. = 382.02
0.21 Cum. Cost of 13.20-2.36mm IRC at Rs. 578.58 /cum. = 121.50
0.14 Cum. Cost of 2.36mm & below IRC at Rs. 526.00 /cum. = 73.64
0.01 Cum. Cost of Stone Dust (Filling mat.)at Rs. 109.00 /cum. = 1.09
49.50 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1731.96
10.00 Sqm Hire charges at Rs. 501.62 /10sqm = 501.62
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 3197.83

Rate per cum of 50 mm thick = 3197.83 = Rs. 6395.66


0.50
km 126
0.35 Cum. Cost of 26.50 - 13.20mm IRC at Rs. 1091.49 /cum. = 382.02
0.21 Cum. Cost of 13.20-2.36mm IRC at Rs. 578.58 /cum. = 121.50
0.14 Cum. Cost of 2.36mm & below IRC at Rs. 526.00 /cum. = 73.64
0.01 Cum. Cost of Stone Dust (Filling mat.)at Rs. 109.00 /cum. = 1.09
49.50 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1731.96
10.00 Sqm Hire charges at Rs. 501.62 /10sqm = 501.62
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 3197.83

Rate per cum of 50 mm thick = 3197.83 = Rs. 6395.66


0.50
km 147
0.35 Cum. Cost of 26.50 - 13.20mm IRC at Rs. 1091.49 /cum. = 382.02
0.21 Cum. Cost of 13.20-2.36mm IRC at Rs. 578.58 /cum. = 121.50
0.14 Cum. Cost of 2.36mm & below IRC at Rs. 526.00 /cum. = 73.64
0.01 Cum. Cost of Stone Dust (Filling mat.)at Rs. 109.00 /cum. = 1.09
49.50 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1731.96
10.00 Sqm Hire charges at Rs. 501.62 /10sqm = 501.62
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 3197.83

Rate per cum of 50 mm thick = 3197.83 = Rs. 6395.66


0.50

Road Data - Rev-16.2 86 Revised during - Jan. 2017


RATE PER CUM OF 50MM THICK DENSE BITUMINOUS MACADAM
km 168
0.35 Cum. Cost of 26.50 - 13.20mm IRC at Rs. 1091.49 /cum. = 382.02
0.21 Cum. Cost of 13.20-2.36mm IRC at Rs. 578.58 /cum. = 121.50
0.14 Cum. Cost of 2.36mm & below IRC at Rs. 526.00 /cum. = 73.64
0.01 Cum. Cost of Stone Dust (Filling mat.)at Rs. 109.00 /cum. = 1.09
49.50 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1731.96
10.00 Sqm Hire charges at Rs. 501.62 /10sqm = 501.62
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 3197.83

Rate per cum of 50 mm thick = 3197.83 = Rs. 6395.66


0.50
km 189
0.35 Cum. Cost of 26.50 - 13.20mm IRC at Rs. 1091.49 /cum. = 382.02
0.21 Cum. Cost of 13.20-2.36mm IRC at Rs. 578.58 /cum. = 121.50
0.14 Cum. Cost of 2.36mm & below IRC at Rs. 526.00 /cum. = 73.64
0.01 Cum. Cost of Stone Dust (Filling mat.)at Rs. 109.00 /cum. = 1.09
49.50 Kgs. Cost of VG30 Bitumen at Rs. 34989.13 /MT = 1731.96
10.00 Sqm Hire charges at Rs. 501.62 /10sqm = 501.62
10.00 Sqm Labour charges at Rs. 386.00 /10sqm = 386.00
Rate for 10 sqm =Rs. 3197.83

Rate per cum of 50 mm thick = 3197.83 = Rs. 6395.66


0.50

Road Data - Rev-16.2 87 Revised during - Jan. 2017


DRY LEAN CEMENT CONCRETE 1:4:8
km 3/0-4/0
Cement Mortar 1:4
333.35 kg Cost of cement as per MORT&H Cl 601.3.3 at Rs. 7057.09 /tonne 2352.48
1.00 cum Cost of sand at Rs. 176.40 /cum 176.40
Data for DLC 1:4:8 2528.88
Crushed stone coarse aggregate of 25 mm as 1219.22
9.000 cum at Rs. /cum 10972.98
per table 600-1 and conforming to clause
4.500 cum Cost of CM 1:4 at Rs. 2528.88 /cum 11379.96
1.067 KL Cost of water at Rs. 130.00 /KL 138.67
1.000 cum Hire and labour for DLC (per 10 cum) at Rs. 10582.20 /cum 10582.20
33073.81
Rate per cum =33073.81/10 = 3307.38
km 4/0-5/0 21
Cement Mortar 1:4
333.35 kg Cost of cement as per MORT&H Cl 601.3.3 at Rs. 7057.09 /tonne 2352.48
1.00 cum Cost of sand at Rs. 176.40 /cum 176.40
Data for DLC 1:4:8 2528.88
Data for DLC 1:4:8
Crushed stone coarse aggregate of 25 mm as 1225.34
9.000 cum at Rs. /cum 11028.06
per table 600-1 and conforming to clause
4.500 cum Cost of CM 1:4 at Rs. 2528.88 /cum 11379.96
1.067 KL Cost of water at Rs. 130.00 /KL 138.67
1.000 cum Hire and labour for DLC (per 10 cum) at Rs. 10582.20 /cum 10582.20
33128.89
Rate per cum =33128.89/10 = 3312.89
km 42
Cement Mortar 1:4
333.35 kg Cost of cement as per MORT&H Cl 601.3.3 at Rs. 7057.09 /tonne 2352.48
1.00 cum Cost of sand at Rs. 176.40 /cum 176.40
Data for DLC 1:4:8 2528.88
Crushed stone coarse aggregate of 25 mm as 765.00
9.000 cum at Rs. /cum 6885.00
per table 600-1 and conforming to clause
4.500 cum Cost of CM 1:4 at Rs. 2528.88 /cum 11379.96
1.067 KL Cost of water at Rs. 130.00 /KL 138.67
1.000 cum Hire and labour for DLC (per 10 cum) at Rs. 10582.20 /cum 10582.20
28985.83
Rate per cum =28985.83/10 = 2898.58
km 63
Cement Mortar 1:4
333.35 kg Cost of cement as per MORT&H Cl 601.3.3 at Rs. 7057.09 /tonne 2352.48
1.00 cum Cost of sand at Rs. 176.40 /cum 176.40
Data for DLC 1:4:8 2528.88
Crushed stone coarse aggregate of 25 mm as 765.00
9.000 cum at Rs. /cum 6885.00
per table 600-1 and conforming to clause
4.500 cum Cost of CM 1:4 at Rs. 2528.88 /cum 11379.96
1.067 KL Cost of water at Rs. 130.00 /KL 138.67
1.000 cum Hire and labour for DLC (per 10 cum) at Rs. 10582.20 /cum 10582.20
28985.83
Rate per cum =28985.83/10 = 2898.58

Road Data - Rev-16.2 88 Revised during - Jan. 2017


DRY LEAN CEMENT CONCRETE 1:4:8
km 84
Cement Mortar 1:4
333.35 kg Cost of cement as per MORT&H Cl 601.3.3 at Rs. 7057.09 /tonne 2352.48
1.00 cum Cost of sand at Rs. 176.40 /cum 176.40
Data for DLC 1:4:8 2528.88
Crushed stone coarse aggregate of 25 mm as 765.00
9.000 cum at Rs. /cum 6885.00
per table 600-1 and conforming to clause
4.500 cum Cost of CM 1:4 at Rs. 2528.88 /cum 11379.96
1.067 KL Cost of water at Rs. 130.00 /KL 138.67
1.000 cum Hire and labour for DLC (per 10 cum) at Rs. 10582.20 /cum 10582.20
28985.83
Rate per cum =28985.83/10 = 2898.58
km 105
Cement Mortar 1:4
333.35 kg Cost of cement as per MORT&H Cl 601.3.3 at Rs. 7057.09 /tonne 2352.48
1.00 cum Cost of sand at Rs. 176.40 /cum 176.40
Data for DLC 1:4:8 2528.88
Crushed stone coarse aggregate of 25 mm as 765.00
9.000 cum at Rs. /cum 6885.00
per table 600-1 and conforming to clause
4.500 cum Cost of CM 1:4 at Rs. 2528.88 /cum 11379.96
1.067 KL Cost of water at Rs. 130.00 /KL 138.67
1.000 cum Hire and labour for DLC (per 10 cum) at Rs. 10582.20 /cum 10582.20
28985.83
Rate per cum =28985.83/10 = 2898.58
km 126
Cement Mortar 1:4
333.35 kg Cost of cement as per MORT&H Cl 601.3.3 at Rs. 7057.09 /tonne 2352.48
1.00 cum Cost of sand at Rs. 176.40 /cum 176.40
Data for DLC 1:4:8 2528.88
Crushed stone coarse aggregate of 25 mm as 765.00
9.000 cum at Rs. /cum 6885.00
per table 600-1 and conforming to clause
4.500 cum Cost of CM 1:4 at Rs. 2528.88 /cum 11379.96
1.067 KL Cost of water at Rs. 130.00 /KL 138.67
1.00 cum Hire and labour for DLC (per 10 cum) at Rs. 10582.20 /cum 10582.20
28985.83
Rate per cum =28985.83/10 = 2898.58
km 147
Cement Mortar 1:4
333.35 kg Cost of cement as per MORT&H Cl 601.3.3 at Rs. 7057.09 /tonne 2352.48
1.00 cum Cost of sand at Rs. 176.40 /cum 176.40
Data for DLC 1:4:8 2528.88
Crushed stone coarse aggregate of 25 mm as 765.00
9.000 cum at Rs. /cum 6885.00
per table 600-1 and conforming to clause
4.500 cum Cost of CM 1:4 at Rs. 2528.88 /cum 11379.96
1.067 KL Cost of water at Rs. 130.00 /KL 138.67
1.000 cum Hire and labour for DLC (per 10 cum) at Rs. 10582.20 /cum 10582.20
28985.83
Rate per cum =28985.83/10 = 2898.58

Road Data - Rev-16.2 89 Revised during - Jan. 2017


DRY LEAN CEMENT CONCRETE 1:4:8
km 168
Cement Mortar 1:4
333.35 kg Cost of cement as per MORT&H Cl 601.3.3 at Rs. 7057.09 /tonne 2352.48
1.00 cum Cost of sand at Rs. 176.40 /cum 176.40
Data for DLC 1:4:8 2528.88
Crushed stone coarse aggregate of 25 mm as 765.00
9.000 cum at Rs. /cum 6885.00
per table 600-1 and conforming to clause
4.500 cum Cost of CM 1:4 at Rs. 2528.88 /cum 11379.96
1.067 KL Cost of water at Rs. 130.00 /KL 138.67
1.000 cum Hire and labour for DLC (per 10 cum) at Rs. 10582.20 /cum 10582.20
28985.83
Rate per cum =28985.83/10 = 2898.58
km 189
Cement Mortar 1:4
333.35 kg Cost of cement as per MORT&H Cl 601.3.3 at Rs. 7057.09 /tonne 2352.48
1.00 cum Cost of sand at Rs. 176.40 /cum 176.40
Data for DLC 1:4:8 2528.88
Crushed stone coarse aggregate of 25 mm as 765.00
9.000 cum at Rs. /cum 6885.00
per table 600-1 and conforming to clause
4.500 cum Cost of CM 1:4 at Rs. 2528.88 /cum 11379.96
1.067 KL Cost of water at Rs. 130.00 /KL 138.67
1.000 cum Hire and labour for DLC (per 10 cum) at Rs. 10582.20 /cum 10582.20
28985.83
Rate per cum =28985.83/10 = 2898.58

Road Data - Rev-16.2 90 Revised during - Jan. 2017


WORKING OUT METAL RATE FOR BC 50mm thick

For 26.50 mm to 13.20 mm IRC


0.160 Cum Cost of 25mm & 22.40mm IRC at Rs. 1073.50 /cum. = 171.76
0.840 Cum Cost of 13.20mm IRC at Rs. 1179.00 /cum. = 990.36
Rate of Metal For 26.50 mm to 13.20 mm IRC BC (40mm thick) Rs. 1162.12

For 13.2 mm to 2.36 mm IRC


0.730 Cum Cost of 11.2, 6.70, 6, 5.6 & 4.75 mm IRC at Rs. 621.60 /cum. = 453.77
0.270 Cum Cost of 2.36mm IRC at Rs. 526.00 /cum. = 142.02
Rate of Metal For 13.2 mm to 2.36 mm IRC BC (40mm thick) Rs. 595.79

For 2.36mm & below


1.000 Cum Cost of 2.36mm IRC at Rs. 526.00 /cum. = 526.00

Road Data - Rev-16.2 91 Revised during - Jan. 2017


BITUMINOUS CONCRETE 50MM THICK USING CMP
Providing and laying Bituminous Concrete to 50 mm thick using 0.22 cum of 26.5-
13.20mm, 0.24 cum of 13.20-2.36mm and 0.26cum of 2.36 & below IRC HBG metal with
62.40 kgs of VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance
of all materials to CMP site, heating the bitumen and aggregate to required temperature and
mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying
the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50mm with
mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne
Vibratory / Pneumatic Roller to the required density etc., including labour for attending to
paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen
boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic roller and all
other tools and plant required, including fuel and all other incidental charges etc., complete
as per specification using CMP clause 507 of MORTH.
HIRE CHARGES FOR MACHINERIES
1. CENTRAL HOT MIX PLANT
Hire charges excluding fuel charges per hour 9696 /8 =Rs. 1212.00
Fuel charges per Hour
For running the Plant :30 litres of diesel 58.85 /lit =Rs. 1765.50
For heating the bitumen 25 litres of furnace oil 33.17 /lit =Rs. 829.25
For heating the aggregates : 170 litres of furnace oil 33.17 /lit =Rs. 5638.90
Hire Charges including fuel charges per hour Rs. 9445.65
Out turn of CMP per Hour for BC = 170sqm. of 40 mm thick

Hire Charges for CMP per 10sqm. = 9445.65 X 10 =Rs. 555.63


170.00
2.BITUMEN BOILER
Since Bitumem boiler is attached with CMP unit hire charges for separate bitumen boiler is
not necessary

3.VIBRATOR ROLLERS
Hire charges excluding fuel charges per Hour 5428/8 =Rs. 678.50
Fuel charges per day 2.50 litres x 58.85 /lit =Rs. 147.13
Hire Charges including fuel charges per hour Rs. 825.63
Out turn of Vibrator Roller per hour= 400sqm. of 40 mm thick

Hire Charges for Vibrator roller per 10sqm. = 825.63 X 10 =Rs. 20.64
400.00

4.PAVER FINISHER
Hire charges excluding fuel charges per day 2447.00 /8 =Rs. 305.88
Fuel charges per hour 6 litres per hour X 58.85 /lit =Rs. 353.10
Hire Charges including fuel charges per hour Rs. 658.98
Out turn of Paver Finisher per hour = 170 sqm. of 40 mm thick

Hire Charges for paver finisher per 10sqm. = 658.98 X 10 =Rs. 38.76
170.00

Road Data - Rev-16.2 92 Revised during - Jan. 2017


5. TIPPER TRUCKS
Hire charges excluding fuel charges per hour 1094.00 /8 =Rs. 136.75
Fuel charges per hour 3.25 litres per hour X 58.85 /lit =Rs. 191.26
Hire Charges including fuel charges per DAY Rs. 328.01
Out turn of Tipper Truck per hour = 170 sqm. of 40 mm thick
Number of tipper required per CMP unit = 6 trucks

Hire Charges for Tipper per 10sqm. = 328.01 x6x10 =Rs. 115.77
170.00

Total hire charges for machineries per 10 sqm 555.63+


= 20.64+ 38.76+ 115.77
= 730.80 /10sqm
LABOUR CHARGES PER 1200 SQM
For loading materials into CMP
33.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 11550.00
25.00 Nos Mazdoor IInd Class @Rs. 314.00 /each = 7850.00
For attending Paver Finisher
10.00 Nos Mazdoor Ist Class @Rs. 350.00 /each = 3500.00
Total Labour Charges per 1200sqm = 22900.00

Labour Charges per 10sqm. = 22900.00 X 10 =Rs. 190.83


1200.00

RATE PER SQM OF BITUMINOUS CONCRETE 50MM THICK

0.220 Cum Cost of 26.5 - 13.20mm IRC at Rs. 1372.33 /cum. = 301.91
0.240 Cum Cost of 13.20 - 2.36mm IRC at Rs. 806.00 /cum. = 193.44
0.260 Cum Cost of 2.36 mm and below at Rs. 736.21 /cum. = 191.41
62.40 Kg Cost of VG30 Bitumen at Rs. 34961.15 /MT = 2181.58
10.00 Sqm Hire charges at Rs. 730.80 /10sqm = 730.80
10.00 Sqm Labour charges at Rs. 190.83 /10sqm = 190.83
Rate for 10 sqm =Rs. 3789.97

Rate per sqm of 50 mm thick = 3789.97 = Rs. 379.00


10.00
Rate per cum = 3789.97/(10x0.05) = 7579.94

Road Data - Rev-16.2 93 Revised during - Jan. 2017


CONSTRUCTION OF EARTHEN EMBANKMENT (Only for new formation of subgrade)
Formation of embankment with earth from quarrying place and compaction by power roller
(100% compaction)

Hire charges for Machineries

Power Roller 8-10 tonne


Hire charges excluding fuel charges per day =Rs. 828.00
Fuel charges per day (Diesel) 2.50 lit/Hr x 8.00 Hrs. x 58.85 /lit =Rs. 1177.00
Total Hire charges per day including Fuel =Rs. 2005.00
Daily Out turn 425 Cum.

Hire charges of Power Roller per 10 sqm. 2005.00 =Rs. 4.72 /Cum
425
Water Sprinklers
Hire charges excluding fuel charges per day =Rs. 1159.00
Fuel charges per day (Diesel) 3.25 lit/Hr x 8.00 Hrs. x 58.85 /lit =Rs. 1530.10
Total Hire charges per day including Fuel =Rs. 2689.10
Daily Out turn 1000 Cum.

Hire charges of Water Sprinklers per 10 sqm. 2689.10 =Rs. 2.69 /Cum
1000

Total Hire charges for Machineries per10sqm = 4.72 + 2.69 =Rs. 7.41 /Cum
Labour charges for Laying Earth for 100cum

2.00 Nos. of Mazdoor Ist Class @Rs. 350.00 /E =Rs. 700.00


Total Labour charges for laying earth per 100cum =Rs. 700.00

Total Labour charges for laying earth per Cum 700.00 =Rs. 7 /Cum
100
Total Hire and Labour charges = 7.41 + 7.00 =Rs. 14.41 /Cum

Cost of Earth (as per GO 214, Industries (MMC.2) =Rs. 70.00 /Cum
Department dated 03.11.2015)
Excavation Charges as per PWD rates (SS 20 B) =Rs. 55.60 /Cum
Seigniorage fee per cum ( GO (Ms) No. 6, Industries =Rs. 20.00 /Cum
(MMB1) Department dated 11.1.2001)
Cost of earth per cum at quarrying place =Rs. 145.60 /Cum

Road Data - Rev-16.2 94 Revised during - Jan. 2017


Earthwork for Berms
Earthwork for berms including cost of earthwork, conveyance from quarying place and
compaction by power roller (100% compaction) etc.

Hire charges for Machineries

Power Roller 8-10 tonne


Hire charges excluding fuel charges per day =Rs. 828.00
Fuel charges per day (Diesel) 2.50 lit/Hr x 8.00 Hrs. x 58.85 /lit =Rs. 1177.00
Total Hire charges per day including Fuel =Rs. 2005.00
Daily Out turn 425 Cum.

Hire charges of Power Roller per 10 sqm. 2005.00 =Rs. 4.72 /Cum
425
Water Sprinklers
Hire charges excluding fuel charges per day =Rs. 1159.00
Fuel charges per day (Diesel) 3.25 lit/Hr x 8.00 Hrs. x 58.85 /lit =Rs. 1530.10
Total Hire charges per day including Fuel =Rs. 2689.10
Daily Out turn 1000 Cum.

Hire charges of Water Sprinklers per 10 sqm. 2689.10 =Rs. 2.69 /Cum
1000

Total Hire charges for Machineries per10sqm = 4.72 + 2.69 =Rs. 7.41 /Cum
Labour charges for Laying Earth for 100cum

2.00 Nos. of Mazdoor Ist Class @Rs. 350.00 /E =Rs. 700.00


Total Labour charges for laying earth per 100cum =Rs. 700.00

Total Labour charges for laying earth per Cum 700.00 =Rs. 7 /Cum
100
Total Hire and Labour charges = 7.41 + 7.00 =Rs. 14.41 /Cum

Excavation Charges as per PWD rates (SS 20 B) =Rs. 55.60 /Cum


Cost of earth per cum at worksite =Rs. 55.60 /Cum

Road Data - Rev-16.2 95 Revised during - Jan. 2017


Providing gravel for berms including compaction (100 % Compaction)

km 3/0-4/0 0
1.16 Cum. Cost of Gravel at Rs. 395.82 /cum. = 459.15
1.00 Cum. Hire and Labour chargesat Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 473.56

km 4/0-5/0 21
1.16 Cum. Cost of Gravel at Rs. 402.35 /cum. = 466.73
1.00 Cum. Hire and Labour chargesat Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 481.14

km 42
1.16 Cum. Cost of Gravel at Rs. 172.55 /cum. = 200.16
1.00 Cum. Hire and Labour chargesat Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 214.57

km 63
1.16 Cum. Cost of Gravel at Rs. 172.55 /cum. = 200.16
1.00 Cum. Hire and Labour chargesat Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 214.57

km 84
1.16 Cum. Cost of Gravel at Rs. 172.55 /cum. = 200.16
1.00 Cum. Hire and Labour chargesat Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 214.57

km 105
1.16 Cum. Cost of Gravel at Rs. 172.55 /cum. = 200.16
1.00 Cum. Hire and Labour chargesat Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 214.57

km 126
1.16 Cum. Cost of Gravel at Rs. 172.55 /cum. = 200.16
1.00 Cum. Hire and Labour chargesat Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 214.57

km 147
1.16 Cum. Cost of Gravel at Rs. 172.55 /cum. = 200.16
1.00 Cum. Hire and Labour chargesat Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 214.57

Road Data - Rev-16.2 96 Revised during - Jan. 2017


km 168
1.16 Cum. Cost of Gravel at Rs. 172.55 /cum. = 200.16
1.00 Cum. Hire and Labour chargesat Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 214.57

km 189
1.16 Cum. Cost of Gravel at Rs. 172.55 /cum. = 200.16
1.00 Cum. Hire and Labour chargesat Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 214.57

Road Data - Rev-16.2 97 Revised during - Jan. 2017


Earth work for formation of embankment (100% compaction)
(For new formation of subgrade)
km 3/0-4/0 0
1.16 Cum. Cost of Earth at Rs. 145.60 /cum. = 168.90
1.16 Cum. Cost of conveyance at Rs. 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges at Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 183.31

km 4/0-5/0 21
1.16 Cum. Cost of Earth at Rs. 145.60 /cum. = 168.90
1.16 Cum. Cost of conveyance at Rs. 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges at Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 183.31

km 42
1.16 Cum. Cost of Earth at Rs. 145.60 /cum. = 168.90
1.16 Cum. Cost of conveyance at Rs. 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges at Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 183.31

km 63
1.16 Cum. Cost of Earth at Rs. 145.60 /cum. = 168.90
1.16 Cum. Cost of conveyance at Rs. 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges at Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 183.31

km 84
1.16 Cum. Cost of Earth at Rs. 145.60 /cum. = 168.90
1.16 Cum. Cost of conveyance at Rs. 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges at Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 183.31

km 105
1.16 Cum. Cost of Earth at Rs. 145.60 /cum. = 168.90
1.16 Cum. Cost of conveyance at Rs. 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges at Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 183.31

km 126
1.16 Cum. Cost of Earth at Rs. 145.60 /cum. = 168.90
1.16 Cum. Cost of conveyance at Rs. 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges at Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 183.31

Road Data - Rev-16.2 98 Revised during - Jan. 2017


km 147
1.16 Cum. Cost of Earth at Rs. 145.60 /cum. = 168.90
1.16 Cum. Cost of conveyance at Rs. 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges at Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 183.31

km 168
1.16 Cum. Cost of Earth at Rs. 145.60 /cum. = 168.90
1.16 Cum. Cost of conveyance at Rs. 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges at Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 183.31

km 189
1.16 Cum. Cost of Earth at Rs. 145.60 /cum. = 168.90
1.16 Cum. Cost of conveyance at Rs. 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges at Rs. 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 183.31

Road Data - Rev-16.2 99 Revised during - Jan. 2017


Earth work for berms (100% compaction)

km 3/0-4/0 0
1.16 Cum. Earthwork as per SS20B 55.60 /cum. = 64.50
1.16 Cum. Cost of conveyance 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 78.91

km 4/0-5/0 21
1.16 Cum. Earthwork as per SS20B 55.60 /cum. = 64.50
1.16 Cum. Cost of conveyance 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 78.91

km 42
1.16 Cum. Earthwork as per SS20B 55.60 /cum. = 64.50
1.16 Cum. Cost of conveyance 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 78.91

km 63
1.16 Cum. Earthwork as per SS20B 55.60 /cum. = 64.50
1.16 Cum. Cost of conveyance 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 78.91

km 84
1.16 Cum. Earthwork as per SS20B 55.60 /cum. = 64.50
1.16 Cum. Cost of conveyance 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 78.91

km 105
1.16 Cum. Earthwork as per SS20B 55.60 /cum. = 64.50
1.16 Cum. Cost of conveyance 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 78.91

km 126
1.16 Cum. Earthwork as per SS20B 55.60 /cum. = 64.50
1.16 Cum. Cost of conveyance 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 78.91

Road Data - Rev-16.2 100 Revised during - Jan. 2017


km 147
1.16 Cum. Earthwork as per SS20B 55.60 /cum. = 64.50
1.16 Cum. Cost of conveyance 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 78.91

km 168
1.16 Cum. Earthwork as per SS20B 55.60 /cum. = 64.50
1.16 Cum. Cost of conveyance 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 78.91

km 189
1.16 Cum. Earthwork as per SS20B 55.60 /cum. = 64.50
1.16 Cum. Cost of conveyance 0.00 /cum. = 0.00
1.00 Cum. Hire and Labour charges 14.41 /cum. = 14.41
Rate for 1.00 cum. Rs. 78.91

Road Data - Rev-16.2 101 Revised during - Jan. 2017


Cost of cement
As PWD rates = 6800.00
Deduct Loading/ Unloading = -176.80
= 6623.20
Rate + VAT (14.50 %) = 6623.20
Rate = 6623.2x100/114.50
= 5784.45
Central Excise Duty for Cement - 12.50% = 5784.45x100/112.50
Basic Rate of cement = 5141.73

Add Storage (5%) = 257.09


Total Cost of Cement = 7057.09

Cost of Steel
As PWD rates = 41500.00
Deduct Loading/ Unloading = -176.80
= 41323.20
Rate + VAT (5 %) = 41323.20
Rate = 41323.2x100/105
0.00 = 39355.43
Deduct Central Excise Duty for Steel = 12.50%
Basic rate of steel = 39355.43x100/112.50
34982.60
Add Storage (5%) = 1749.13
Total Cost of Steel = 43249.13

Picking 5cm to 10cm old metalled surface and sectioning 1Sqm.

Labour for 10Sqm.


Mazdoor Class-I
1/4 X 1.08 No. @ 350 Each = 94.5 /10Sqm

Picking 5cm to 10cm old metalled surface and sectioning 1Cum. = 9.45 /Sqm.

Road Data - Rev-16.2 102 Revised during - Jan. 2017