Professional Documents
Culture Documents
D
uring preconstruction testing and mockups, production rate. Therefore, it is reasonable for
as well as during shotcrete production, a contractors to want to extract cores at the earliest
minimum specified compressive strength age. However, it is not uncommon to find
is always required in the project specification. The damage to cores that are extracted too early, such
specified compressive strength is used to qualify as less than 1 day. Alternatively, when cores are
the concrete mixture, the shotcrete nozzlemen, extracted too late, such as more than 2 days, the
and the shotcreting equipment, as well as for decision of the production rate and the adjustment
quality control of the shotcrete production. of the construction schedule are delayed. The
Compressive strength is commonly tested at question, at least from the contractors perspective,
3, 7, and 28 days using 3 or 4 in. (75 or 100 mm) is: When should cores be extracted to meet
diameter cores (ASTM C1604) from standard requirements for both quality control testing and
shotcrete test panels (ASTM C1140). Compressive the construction schedule?
strength at other ages, such as 1 or 5 days, might
also be required, depending on project application Coring at 1 Day
needs. Typically, contractors prefer to evaluate In a recent underground shotcrete project,
the shotcretes compressive strength as early as cores were extracted at less than 24 hours. The
possible, which requires early extraction and project used silica fume-modified wet-mix shotcrete
testing of cores. When compressive strength tests and added an alkali-free accelerator for overhead
meet the required strength at 1, 3, and 7 days, application. Shotcrete preconstruction test panels
shotcrete is considered to have met the quality were shot with accelerator dosages of 4, 6, and
control requirement, and the construction 8% by mass of cement. Shooting started on
schedule can be adjusted using an increased Monday afternoon at 2:00 p.m., and a total of
six test panels were shot, which allowed two
panels for each accelerator dosage. The project
took place in May, and temperatures were
approximately 59 to 68F (15 to 20C). All panels
were covered with wet burlap and plastic sheeting
for overnight protection. A restricted area was
constructed for the test panels, and no rainfall
occurred. Coring activity began the next morning
at 7:00 a.m. By 10:00 p.m., all cores were
extracted and a very dark slurry came from the
core drilling water. Cores were delivered to the
laboratory for standard curing and were tested at
3, 5, 7, 14, and 28 days. The results are shown in
Fig. 1. The 5-day compressive strength test results
confirmed that the coring had significantly damaged
the cores, which produced low strength results.
Coring at 2 Days
The same ACI Certified Nozzleman shot the
same shotcrete mixture using the same equipment,
Fig. 1: Compressive strength development for shotcrete with accelerators; including the shotcrete pump and the accelerator
cores extracted at less than 24 hours of age dosing pump with accelerator dosages of 4, 6, and
References
1. ACI 506.5R-09, Guide for Specifying Underground
Shotcrete, American Concrete Institute, Farmington Hills,
MI, 2009, 52 pp.
2. Heere, R., and Morgan, D. R., Determination of Early
Age Compressive Strength of Shotcrete, Shotcrete, V. 4,
No. 2, Spring 2002, pp. 28-31.
Fig. 4: Early-age compressive strength when tested with end beam tester