You are on page 1of 5

Proceedings of Indian Geotechnical Conference

December 22-24,2013, Roorkee

GEOTECHNICAL ASPECTS OF HIGHWAY CONSTRUCTION ALONG THE


CANAL

Daljeet Singh, A.E. PWD,B&R Punjab, daljitsidhu@hotmail.com


J.N.Jha, Professor and Head Deptt.of Civil Engg.,GNDEC,Ludhiana,India, Email: jagadanand@gmail.com
K.S.Gill,, Associate Professor,Deptt. Of Civil Engg.GNDEC,Ludhiana,India, Email:kulbirgillkulbir@yahoo.co.in

ABSTRACT: Government of Punjab (GOP), in their 10th Five-Year Plan identified road sector as one of
the main component to boost the growth rate in the state. Because of low land to population ratio, land
cost is very high and ribbon development along road sides has further complicated the process of up-
gradation and widening of the existing roads of Punjab. Keeping in view the above , the government of
Punjab has proposed to develop a new road network along the major canals where sufficient land is
available to construct roads. But it has been observed in the past that failure of roads along water bodies
such as canal, lake and pond etc.is very common. Therefore it becomes utmost important to identify the
causes of road failures along the canal and to find their possible solutions. During the construction of
canal embankments, economic considerations compels the designer to utilize the locally available soil
from cutting and only the balance required soil is transported from some borrow areas. Thus the final
embankment always consists of different types of soil which will exhibit different engineering
characteristics when subjected to loads. The index and other engineering properties of such soils which
actually act as subgrade for roads are highly erratic. Paper reports the correlations of CBR value with
DCPI both in the field and laboratory.

INTRODUCTION saturated for an appreciable length of time. During


The fluctuating location of phreatic line, variation the design of new pavements or strengthening of
in capillary saturation zone leads to moisture existing one worst possible environmental
content variation in the subgrade soil which condition to be faced by the highway during its
adversely affects the physical properties of the soil design life should be simulated. Therefore in situ
causing failure of roads at such locations. As the CBR tests has to be conducted after saturating the
canals are aligned keeping in view the irrigation existing subgrade. However, it is very difficult to
requirement of any area and the natural slope of the conduct a field soaked CBR test and is almost
terrain governs the cutting and filling along that impractical in many situations where effective
particular alignment. Basically most of the soil drainage layer is available and water table or
deposits in Punjab consist of alluvial soils which capillary saturation zone is at depth. On the other
are highly heterogeneous in nature both in hand in case of a laboratory CBR test specimens
horizontal and vertical direction.The design of new after being moulded at insitu density tend to give
flexible pavements and rehabilitation of existing higher values of CBR than those obtained in the
pavements needs an accurate estimation of CBR field especially for sandy soils [1]. The difference
value. The California Bearing Ratio (CBR) is a is due to the confining effect of rigid mould in
measure of the strength of the sub- grade and is laboratory tests. Again in field CBR tests, many
used to design the thickness of road pavements times misleading CBR value is obtained, whenever
built over the soil. However, the strength of the piston tip rests on a small stone present in the
sub-grade and hence its CBR value are affected subgrade soil. In the design of overlays generally
by the soil moisture content and can decrease Benkelmans beam method and Falling Weight
significantly, if the sub-grade soil remains Deflectometer (FWD) are used but these methods

Page 1 of 5
Daljeet Singh, J.N.Jha & K.S.Gill

are sophisticated and time consuming. In the repeated use and inadequate fall of hammer were
present scenario when roads are to be constructed overcomed.
along canal banks comprehensive quality control
plan needs to be exercised which can only be Experimental Work
possible by exploring the use of simple, less time The DCP tests were conducted according to the
consuming and economical testing techniques. [2] procedure laid down in [5] and [6]. The apparatus
has successfully used dynamic cone consists of 16mm diameter steel rod in which a
penetrometer(DCP) for estimating the strength of tempered steel cone with a 20 mm base diameter
soil. The study was mainly in relation to and a 60 degree point angle is attached. The DCP
application in design and strengthening of existing is driven into the soil by a 8kg hammer with a free
pavements. Some of the work regarding correlation fall of 575mm. The hammer correction factor is
between DCPT and CBR has been reported in unity for 8kg hammer. The DCP index or reading
literature [3,4] but the conditions considered were is defined as the penetration depth (D) in mm for a
not simulating the actual highway condition. single drop of hammer. The cone is driven in to the
Keeping in view the above stated limitations of ground upto the desired depth and average DCP
field as well as laboratory CBR tests, it was index is calculated for a single blow. Depth of
decided to conduct dynamic cone penetration test penetration considered in the study was 300mm,
(DCPT) and CBR tests at similar conditions both two layers of 150 mm each of soil subgrade.
in laboratory and in field simultaneously to find the
possibility of developing simple relationship that Field and Laboratory Tests
could be used to evaluate the field CBR. The DCP Following tests were conducted during the course
test values can be used to estimate the CBR values of this study:
provided an acceptable relationship exists between Sieve analysis
the CBR and the DCPI value. Development of any Atterbergs limit test
such relationship may become very effective tool Modified Procter compaction test
for highway engineers. The other benefits of the In situ density test (Sand replacement
relationship are the following: (a) It may help method)
enhancing highway construction quality control; DCP test (In situ saturated)
(b) It may help ensuring long-term pavement DCP test (mould, in saturated condition)
performance and stability; and (c) It may help in
Laboratory CBR test (at in situ density).
achieving more uniform structural properties. In
In situ CBR test (saturated condition)
the present study DCP tests were conducted along
the 8 Km long stretch of the left bank of Sidhwan
Test Procedure and Sample Preparation
canal passing through the southern part of
The experimental study involved performing a
Ludhiana city (Punjab) for widening and
number of field and laboratory CBR tests and DCP
strengthening of the existing road. Total 8 locations
tests at artificially saturated condition and insitu
were earmarked at an interval of one Km after
dry density of soil subgrade was also determined.
visiting the site. The interval was decided based on
The dynamic cone penetrometer was directly
uniformity of soil available along the whole
placed on the subgrade and the test was started by
stretch. The present study describes a series of
sliding the hammer. Soil resistance was measured
DCP tests conducted at insitu conditions and
in terms of penetration as mm/blow. For every
soaked in situ condition. In addition to the above
location three points were tested and average value
field test, laboratory soaked CBR tests moulded at
was considered for the determination of DCPI.
insitu density were also carried out and the results
Since the imprint area of the cone tip for the first
obtained from the tests were presented and
blow is smaller than that of subsequent blows the
discussed. It is also important to note that by
penetration of the first blow was discounted. The
exercising little extra care some limitations of the
number of blows were counted for top 150 mm
DCP test such as blunting of cone due to its
(designated as the top layer) penetration of the

Page 2 of 5
Geotechnical aspects of highway construction along the canal

cone and penetration per blow was calculated and Y1= 0.1943xm2 - 6.7988xm + 71.628 (1)
the same procedure is repeated for lower 150 mm
layer(designated as bottom layer). The second where
layer was tested to study the effect of underneath Yl = Laboratory CBR at field density saturated for
soft layer on field CBR [7]. To conduct soaked in 24 hours
situ DCP test and in-situ saturated CBR, a small and
area of 3mx3m was flooded with water by making xm =DCPI of soil compacted in mould at field
small dykes around that area. As the soil was silty density and saturated for 24 hours in mm/blow .
sand, water was kept flooded for 24 hours before
conducting the tests. Rest of the field and In Figure-2, field DCPI values were plotted against
laboratory tests were conducted as per the relevant field CBR values of the subgrade soil artificially
Indian Standard Codes. saturated for 24 hours . Similarly the variation can
be expressed by a polynomial equation as given
RESULTS and DISCUSSION below
The most important parameter to evaluate subgrade
strength for the pavement design is the CBR value, yf = 0.1918xf2 - 6.4346xf + 68.081 (2)
that would actually be available to support the
pavement and traffic load. In case strata below the where
subgrade is weak the available subgrade is always yf = Field CBR at surface of subgrade with known
less than the anticipated from laboratory test hence dry density and artificially saturated for 24 hours
the term effective CBR is taking place in pavement and
design. In this study efforts has been made to xf = DCPI of soil at surface of subgrade with
correlate DCPI with effective CBR. The results of known dry density and artificially saturated for 24
various tests conducted in the field and laboratory hours in mm/blow .
are given in Table 1.
It can be observed from the results that soil is
sandy in nature for all the 8 locations with sand
content varying from 63.0% to 90%. The
atterbergs limits indicates that soil is either non
plastic or having a low plasticity index in the range
of
1% to 5%.. The in-situ density is different for
different locations varying from 16.20kN/m3 to
20.30kN/m3. In-situ moisture lies between 2.5 to
8.0%. The results further reveals that soaked
laboratory CBR value is higher than the DCP based
soaked in situ CBR value. This is attributed to the
higher confinement pressure of rigid mould in the
laboratory.

Figure-1 shows the relationship between the Fig-1, Showing the relationship between mould
laboratory DCPI value with the corresponding DCPI andLaboratory CBR
Laboratory CBR value of samples compacted at
field dry density and soaked for 24 hours. This
relationship can be expressed by means of a
polynomial equation as given below.

Page 3 of 5
Daljeet Singh, J.N.Jha & K.S.Gill

REFERENCES
1. Haison, J.A. (1987) Correlation Between
California Bearing Ratio and Dynamic Cone
Penetrometer Strength Measurement of Soils
Proceeding, Institution of civil engineering,
83(2), 833-844.
2. Scala, A. J. (1956) Simple Methods of
Flexible Pavement Design Using Cone
Penetrometer.N.Z.Eng..11, No2
3. Smith,R.B and Pratt D.N. (1983) A Field
Study of In situ California Bearing Ratio and
Dynamic Cone Penetrometer Testing for Road
Investigations. Australian Road Research, 13
No.4, 285-294.
Fig-2, Showing the relationship between field 4. Livneh, M. (1989) Validation of Correlations
DCPI and field CBR Between a Number of Penetratin Tests and In
situ California Tests.Transport Research
CONCLUSIONS Record, No1219, 56-67.
Based on the study following conclusions can be 5. ASTM D6951/D6951M November 2009
drawn: Standard Test Method for Use of the Dynamic
1 The in-situ CBR value of sandy soils having Cone Penetrometer in Shallow Pavement
similar degree of saturation can be determined Applications.
quickly and with adequate accuracy using the 6. IRC SP 72-2007 Guidelines for the Design of
DCPT results. Flexible Pavements for Low Volume Rural
2 Once the correlation is established between CBR Roads Indian Roads CONGRESS. 2007.
and DCP index for tests conducted under different 7. IRC:37-2012 Guidelines for the Design of
conditions and compaction level or in-situ density. Flexible Pavements. (Third Revision). Indian
The soaked CBR value in the field can be Roads Congress 2012
determined very quickly by conducting the in-situ 8. Choudhary, A.K., Jha, J.N. & Gill, K.S. (2010)
DCPT for the similar conditions. Utilization of Plastic Waste for Improving the
3 Similarly laboratory soaked CBR value can be Subgrades in Flexible Pavements
evaluated after establishing a correlation between Geotechnical Special Publication, ASCE,
DCPI and CBR sat at different compaction levels in No.203.320-326.
the laboratory. 9. Cone Penetration Report.GL-93-3.
4 Effective CBR of upper layers can be easily Department of Army, Washington DC, 19.
verified with the help of DCPI of individual layers 10. Sawangsuriya, A., Wachiraporn, S. &
from top up to intended depth. Sramoon, W. (2008) Assessment of Modulas
5 For construction of new embankments or and CBR of Pavement Materials for Design
strengthening of existing pavements, DCPT and Construction. Seminar:
will be a very useful tool for evaluating the 11. Bureau of Materials-Analysis and Inspection
strength of sub grade in terms of CBR value. of Highways, Bangkok, Thailand, 31-50.
6 It may helpful in enhancing highway construction
quality control, ensuring long-term pavement
performance, stability and achieving more uniform
structural property.

Page 4 of 5
Geotechnical aspects of highway construction along the canal

Table-1: Test results at different locations (Insitu and laboratory)

Av. Sat. Mould DCPI at field density


Sat. Lab CBR @ insitu dry density

Sat. Mould DCPI at field density


OMC Optimum Moisture Content

Av. Sat. Insitu DCPI


Relative compaction
In situ bulk Density

Max. Dry Density


In situ dry density

Sat. Insitu DCPI


Sat. In situ CBR
In situ moisture
Plasticity Index
Sand content

Liquid Limit
Sample No

Silt + Clay
Layer

* % % ** kN/m3 kN/m3 % % mm/blow

4.25 T 90 10 17 NP 18.5 8 17.1 17.6 15.5 97.0 19.5 29 8.82 8.33


10.66 9.93
4.25 B 90 10 17 3 18 8 16.7 17.6 15.5 95.0 21 12.5 11.53
5.25 T 75 25 22 3 18.8 3.2 18.2 19.91 10.5 91.0 14 15 12.5 11.67
14.58 13.34
5.25 B 75 25 22 NP 19 5 18.1 19.91 10.5 91.0 13 16.66 15
6.25 T 88 12 19 NP 17.55 3.4 17 17.7 14.0 96.0 20 22 11.54 10.71
10.77 10.01
6.25 B 88 12 19 5 18 4 17.3 17.7 14.0 98.0 25 10 9.3
7.25 T 63 37 25 5 19.8 3.8 19.1 20.3 10.0 94.0 33.3 35 7.15 6.81
6.99 6.67
7.25 B 63 37 25 4 20.3 5.8 19.2 20.3 10.0 95.0 36.5 6.82 6.52
8.25 T 73 27 23 4 19.2 2.9 18.7 19.87 10.5 94.0 24.8 32 7.9 7.5
11.45 10.57
8.25 B 73 27 23 1 18.5 4 17.8 19.87 10.5 90.0 16 15 13.63
9.25 T 82 18 20 1 18 3.1 17.5 19.76 11.5 89.0 14.6 17 15 13.63
18.21 16.19
9.25 B 82 18 20 NP 17.5 2.5 17.1 19.76 11.5 87.0 12 21.42 18.75
10.25 T 99 1 16 NP 16.85 7 15.7 16 14.0 98.0 22.4 31 8.33 7.89
9.52 8.95
10.25 B 99 1 16 NP 16.2 5 15.4 16 14.0 96.0 20.6 10.7 10
11.25 T 85 15 17 NP 18.1 3.9 17.4 17.9 15.0 97.0 22.7 27 8.33 7.89
9.92 9.30
11.25 B 85 15 17 NP 17.8 4 17.1 17.9 15.0 96.0 22.3 11.5 10.71

where
*T stands for top layer and B stands for bottom layer ** NP stands for non-plastic soil

Page 5 of 5

You might also like