You are on page 1of 14

SPE 25582

Evaluation of Pipeline Integrity by On-line Inspection (Revised version)


F. HERAIBA * ZAKUM DEVELOPMENT COMPANY
*SPE Member

Copyright 1993, Society of Petroleum Engineers, Inc,

This paper was prepared for presentation at the SPE Middle East Oil Technical Conference & Exhibition held in Bahrain, 3-6 April 1993.

This paper was selected for presentation by an SPE Program Committee following review of information contained in an abstract submitted by the author(s). Contents of the paper,
as presented, have not been reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material, as presented, does not necessarily reflect
any position of the Society of Petroleum Engineers, its officers. or members. Papers presented at SPE meetings are subject to publication review by Editorial Committees of the Society
of Petroleum Engineers. Permission to copy is restricted to an abstract of not more than 300 words. Illustrations may not be copied. The abstract should contain conspicuous acknowledgment
of where and by whom the paper is presented. Write Librarian, SPE, P.O. Box 833836, Richardson, TX 75083-3836, U.S.A., Telex, 163245 SPEUT.

ABSTRACT These facilities are connected by huge pipeline


network cons i st ing of 177 1ines. The wa n th ickness
Advanced On-line inspection tools coupled with of these pipeline was selected to satisfy a design
reliable interpretation of inspection data and factor of 72% SMYS; maximum anticipated design
adequate reporting formats are required to evaluate pressure and corros ion a llowance which varies
the structural integrity of the pipeline. This according to the nature of flu id flowing in each
evaluation is a vital requirement for pipeline line.
operators in order to define necessary preventive
measures and repairs required to avoid line rupture The most important pipeline of this network is the
or leakage. Main Oil Line connecting ZAKUM Central Complex to
lIRKU onshore processing terminal. This line is 42 H
H
ZADCO is operating a large pipeline network (1067 mm) diameter, of 0.562 (l4.27 mm) wall
transferring crude oil, gas and injection water thickness and extends for about 60 km length. The
under a wide range of operating conditions. 1ine had been insta lled in December 1979 and was
filled by sea water treated with biocide, corrosion
In order to evaluate the integrity of this network, inhibitor and oxygen scavenger. It was assumed that
lADCO had conducted several surveys using different this treatment would provide sufficient protection
types of inspection tools. for more than one year.

This paper presents an operator's point of view The sea water was renewed in July 1981 and regular
about the capabilities and limitations of the samples were collected which indicated that 10 to 70
different tools and the reporting formats submitted Sulphate Reducing Bacteria(SRB) colonies per
from inspection contractors. milliliter were found in the water.

The paper provides recommendation about methodology Consequently higher dosage of biocide was added to
for selecting the most appropriate tool for a renewed water. The water was finally displaced by
specific job. crude oi 1 when product ion started from Upper lAKUM
Field on 23rd December 1982.
INTRODUCTION
Pipeline pigging was adopted as routine cleaning
lADCO operates three offshore fields located in the operation since March 1983. The frequency of pigging
ARABIAN GULF Offshore ABU DHABI. The facilities in varied from once per month to four times per month
these fields compromise wellhead platforms. and this arrangement was interrupted occasionally
separation satellites and Central Complexes. for durat ions of about three months due to leak ing
valves at either the pig launcher or receiver.
2 EVALUATION OF PIPELINE INTEGRITY BY ON-LINE INSPECTION SPE 25582

On July 1985, UMM AL-DALKH (UA) field started TYPES AND PRINCIPLE OF OPERATION FOR
product ion and its crude 0 i 1 was pumped to ZIRKU INSPECTION TOOLS
through the 42" ZAKUM line. This crude oil was
associated with formation water since the early Magnetic Flux Leakage (MFL) inspection technology
stage of production. Since the production rate of was introduced to the market in 1965 to provide cost
UA field represented only small portion of the mixed effective alternative to the hydrostatic testing
stream flowing in the 42" line; the water content in ,required to evaluate the pipeline integrity while
the crude mixture reaching ZIRKU varied from less the line is in service.
than 0.1% to a maximum of 0.3%. However slugs of
water were always received in front of each pigging The recent development of on-board scann i ng sensors
operation indicating that the major part of the and micro processor technology resulted in highly
water separated in the line due to low velocity. The sophisticated and more powerful inspection systems.
water accumulated at the lower sections of the line These include advanced MFL tools and tools based on
and was removed only when the line was pigged. Ultrasonic Technology.

Starting from 1987, samples of debris were collected The basic principle of both systems is simple. The
from the slugs of water. The analysis of ' the debris difficulty is how to design a vehicle to suit the
indicated the presence of corrosion products. In difficult environment inside the pipeline.
addition, the inspection of one 42" isolation valve
installed upstream the reCe1Vlng trap revealed
pitting corrosion upto 2 mm in depth at the 6
1). MAGNETIC FLUX LEAKAGE (MFL) TOOLS
O'clock position of both sides of the valve's ball.
The MFL tool uses the principle of magnetic flux
leakage to detect defects and anomalies in the pipe
Due to the corrosion findings; ZADCO decided to
wall.
conduct corrosion survey for the Main Oil Line
using in-line inspection tool (intelligent pig).
A magnet izing system induces a saturated magnet ic
fie ld in the pipewa 11. Anoma 1ies in the pipe wa 11
The selection of the most appropriate inspection
divert the magnetic field outside the boundaries of
too 1 was a difficu 1t task due to lack of object ive
the pipe wall at the location of the anomaly and
informat ion which demonstrate the rea 1 capabi 1ities
this phenomenon is called "flux leakage" and is
and limitations of the available tools. Consequently
illustrated in Figure 1.
it took a lmost about two years during which ZADCO
conducted market survey and communicated with
The change in the magnetic field induces a signal
severa 1 pipe 1ine operators whom accepted to adv ise
which is detected by sensors mounted between the
their personal experiences informally.
magnetizing poles. The signals are electronically
processed, recorded and reproduced in a different
EFFECT OF PIPELINE CONDITIONS ON reporting formats.
PERFORMANCE OF INSPECTION TOOLS
Different MFL tools are currently available in the
Most of the pipelines represent a very difficult market. Some of these tools belong to what is called
env ironment for any inspect ion too 1. Th is i s first generation and advanced types belong to second
explained by the fact that the inspection tool moves generation.
at high speed passing through bends, girth welds,
solid particulates, and wax deposits. Although some The performance of inspection tool depends on
of these contaminants can be removed by running several factors which include but not limited to the
brush pigs; it is impossible to guarantee the degree following:-
of internal cleanliness of the line. While moving in
these conditions, the tool should keep in contact 1. The magnetizing system should provide sufficient
with or in close proximity to the internal surface amount of magnetic driving force to completely
of a pipe 1i ne to ensure fu 11 c i rcumferent ia1 saturate the pipe wall. If a pipe wall is not
coverage. fully saturated. the magnetic field will not
"leak" even at a thinned section and hence some
Any inspection job should be planned with this in defects may not be detected.
mind and the selected tool should be able to
accommodate the expected internal conditions of the
pipeline.
SPE 25582 F. HERAIBA 3

The limited magnetic strength of some tools is The same transducer that emits the pulse can also
the reason why they can not be used to inspect detect the reflected pulses. The time elapsed from
heavy pipe walls. Advanced MFL tools use special receiving the interior reflection and receiving the
types of extremely strong magnets to achieve full exterior reflection provides a direct measure of the
magnetic saturation for the inspected pipeline. wa 11 thickness.

2. The sensors assembly should provide complete The greatest advantage of an ultrasonic inspection
circumferential coverage of the pipe wall even at too 1 is its abi 1ity to produce a quantified
severe dynamic and environmental conditions which measurement of pipe wall thickness.
prevail while running the tool in the pipeline.
The first generation of magnetic flux tools used However the too 1 measures the rema 10 1 ng wa 11
a few number of large sensors arranged in a thickness at discrete points in a closely spaced
single row located between the magnets. This grid around the circumference allover the pipe
design may cause the sensors to miss small size length. The discrete measurement principle produces
defects and hence degrade the quality of measurements at discrete locations and hence the
inspection specially at irregular contours which resolution depends on grid size. Small defects
characterize some of the pipeline defects. This require very small grid spacing and hence large
a lso may exp la in why the old MFL tools can not number of sensors are required to detect them.
detect defects in girth welds.
A draw back of the ultrasonic tool is that the sound
Second generation MFL tools use a primary sensor wave should travel through homogeneous liquid; hence
array having perhaps ten times the number of sensors a continuous liquid coupling is required between the
installed in first generation tools. This primary transducers and the pipe wall. Any impurities such
array of sensors works in conjunction with a similar as gas bubbles, debris, corrosion products,
secondary array to distinguish between internal and wax ... etc will drastically affect the amount and
externa 1 defects. A 12" too 1 of second generat ion shape of the reflected echo and hence wi 11
may have as many as 192 or more sensing channels to deteriorate the quality of the inspection.
achieve axial and circumferential scanning pitch of
few millimeters, providing means to locate and size In addit ion to the above the transducers must be
small metal loss even within the welds. rna inta ined conforming to the surface of the pipe
wall to ensure that both the pulse and its reflected
3. The inspection data should be processed and echo will always be perpindular to the pipe wall.
presented to the pipeline operator in a way that Rough surfaces of irregular shape and contour will
fully satisfies his needs. tend to scatter the ultrasonic signal and hence may
produce false echo.
As a primary objective, the reported data should
locate accurately all defects of prescribed
significance and provide their dimensions with
EXPERIENCE OF OTHER PIPELINE
special emphasis to the depth of metal loss.
OPERATORS
Our market survey for the performance of different
Complementary analytical techniques may be used
inspection systems included the reviewal of the few
to qualify the fitness of the pipeline, using any
published papers covering user's experience with one
of the established codes and standards.
or more systems(l,2,3,4&5). Private contacts with
some operators also provided valuable information.
Ultrasonic In-line Inspection Tools
This survey indicated the following:-
The principle of ultrasonic inspection depends on
generating a short compression wave of sound at 1. Natural Gas Pipeline Company of USA started
frequencies much higher than audible range. using MFL tools since 1968. Their inspection
revealed several locations that required
The pulse is transmitted to the interior pipe wall repa i rs due to disbonded coat ing and externa 1
where most of it is reflected towards the source. A corrosion. Traverse crack caused by a dent was
portion of the signal is transmitted across the pipe located and replaced.
wa 11 to the externa 1 side and port ion of th isis
reflected back towards the source.
4 EVALUATION OF PIPELINE INTEGRITY BY ON-LINE INSPECTION SPE 25582

They found internal and external corrosion INSPECTION SURVEYS CARRIED OUT BY
ranging from 150 to 250 mills (3.81 to 6.38 ZADCO
mm) .
1. SURVEYS CARRIED OUT FOR THE 42"
2. NOVA experienced three failures due to corrosion MAIN OIL LINE
in a 20w (508 mm) gas line. Conventional MFL tool
was run in 1984. It identified the location of a Seven contractors were invited to inspect the 42w
large number of corrosion defects. However the line. The scope of work for the inspection comprised
corrosion depths in most locations were the following:-
questionable and large number of exacavations
were required to evaluate the significance of the To detect. size and accurately locate pipeline
defects. Hence a decision was made to run defects.
advanced MFL too 1 of second generat ion to
accurately describe the corrosion defects. To discriminate between internal and external
defects.
The accuracy of the newly reported defects was
first evaluated by exacavation and ultrasonic To report the defects in a format which can be
measurements. Good matching was found when used to evaluate the integrity of the pipeline.
comparing the depth of reported defects versus
the measured depth (Figure 2). Corrosion features The contractors were given the choice to offer any
which required repairs were identified with high type of inspection tool. We requested them to
degree of accuracy. provide detailed information covering the
capabilities and limitations of their tools. and to
3. EKOFISK-EMDEN gas line was inspected initially by explain how the tools can achieve the claimed
conventional MFL tool in 1977 and 1980. Based on capabilities.
the initial findings it was elected to inspect
the line in 1986 using second generation MFL tool Three contractors proposed MFL too 1s of the first
to achieve the specified accuracy. The inspection generation type. They declined to detect defects in
revealed 18 features; five defects were reported girth welds and one of them stated that blind area
to be possible circumferential cracks at girth will exist 6w from each weld. They also advised that
weld locations. The most critcal defect was their tools can not guarantee the discrimination
uncovered and this confirmed presence of 87 mm between internal and external defects.
long by 10 mm deep crack at the edge of an
internal root weld. Two contractors proposed second generation MFL tools
and both guaranteed that their tools will meet most
4. Trans-Alaska Pipeline System (TAPS) was initially of ZADCD quality specification.
inspected by modified MFl tool from the first
generation. In 1987 the pig runs produced 12 The last two contractors proposed Ultrasonic tools.
signals as real defects in addition to several However the possibi 1ity of having free gas in the
pits which were introduced artificially by TAPS. line was considered to be a potential risk which may
affect the reliability of any Ultrasonic tool.
Alyeska choose to excavate each area of the 12
corrosion indications. Of the twelve graded ZADCO selected one of MFL tools belonging to second
corrosion signals. 11 showed no corrosion and one generation; and the selection was based on the
ident ified a non corrosive meta l-loss area following:-
approaching 50% of pipe wall.
Tool belongs to second generation of MFL systems
Alyeska ran an advanced Ultrasonic tool in July which can provide accurate information about the
1989. The survey indicated 408 anomalies ranging condition of the pipeline and location and
from 10 to 20% metal loss. The inspection of 308 magnitude of mechanical defects if any.
anomalies gave Alyeska good confidence about the
capability of the Ultrasonic tool to size defects
even those of small size.
SPE 25582 F. HERAIBA 5

Selected tool is compact, relatively short and Following the results of this inspection survey;
lighter in weight and easy to handle. It does not several corrosion control measures were considered
require any modifications of the traps at both and implemented.
ends of the pipeline. It was also decided to inspect other oil lines
connected to the 42'" Ma i n 0i l l ine; in order to
The contractor uses Electronic Geometry Pig which determine their condition.
is an advanced caliper pig as part of his scope
of work. Two 24'" (609.6 mm) oil trunk lines were inspected by
the same contractor in March 1990. The two
Cost of overa 11 inspect ion was cheaper than the inspection surveys indicated substantial metal loss
offer made by another contractor proposing due to corrosion.
another advanced MFl tool.
The reports which were submitted for each survey
The inspect ion survey was comp leted in August 1989 included the following:-
and it indicated interna 1 meta 1 loss due to
corrosion. The type of corrosion was classified as list of defected areas indicating location.
general corrosion with localized pits. The general orientation-and classification of the defect.
corrosion ranged from 1 to 2 mm thinning. The
localized pits extended to 50 percent of the Contour plots for selected defects (Figure 3).
original wall thickness in worst cases.
Nearly all defects were located in the 6 O'clock Detailed analysis of these reports revealed the
position of the line. The corrosion data charts were following:-
correlated with the line profile maps and
considerable amount of corroded areas were found in 1. The inspection data were relatively reliable in
the low points of the pipeline. The corroded areas locating defects. However the accuracy of
spread over the entire length of the pipeline. measuring the defect depths was questionable.

These corroded areas were categorized in terms of This was confirmed when the reported metal losses
severity as follows:- for two externa 1 defects were compared with the
actual measured depths.
1. 1700 meters having metal loss which vary from 30%
to 60%. 2. The contour plots created some confusion since
its colour coding indicated that defects exist
2. 3400 meters having metal loss which vary from 20% with deeper depth compared with the
to 35%. classification given in the list of defected
areas. The exp lanat ion given by the contractor
3. 3600 meters having metal loss which vary from 10% did not clarify the confusion.
to 25%.
Our discussions with the contractor revealed that
An Ultrasonic Scan was performed on selected areas the contour plots display the magnetic flux
at the onshore side of the line to validate the leakage signal amplitude and not the wall
inspection data. The coating was removed and the thickness derived from the analysis of the
pipe was cleaned to a surface suitable to carry out signaPls. The contractor confirmed that these
Ultrasonic inspection. A 30 mm X 30 mm square grid plots produce shape and depth of defect but they.
pattern was mapped onto the pipe to obtain full are not in direct correlation to their
coverage of the defective areas. The Ultrasonic dimensions. This renders the contour plots to be
measurements matched reasonably we 11 with the of limited value in evaluating the integrity of
inspection data. the pipe.

Future operability of the pipeline was calculated 3. The data prov ided in the report can not be used
using ANSI/ASME B-31.4 standard code formula. in determining the severity of any metal loss
damage on the inspected pipe 1i nes based on the
The calculations indicated that the line can be more accurate NG-18 Surface Flaw Formula; which
operated up to a maximum internal pressure of 688 provides an accurate method to predict rupture
psi which is far above the maximum required pressure of corroded pipe.
operating pressure.
6 EVALUATION OF PIPELINE INTEGRITY BY ON-LINE INSPECTION SPE 25582

In spite of the above 1imitations the inspection 3. Metal loss histograms (Figure 7) and scatter
informat ion indicated that there is a substantial graph of cluster average depth versus length
amount of internal corrosion and highlighted the (Figure 8).
importance of inspecting ZADCO pipeline network.
The analysis of corrosion inspection survey
Hence it was dec ided to carry out a second concluded that the line condition is satisfactory
inspection survey for the Main Oil Line using for operations provided that strict corrosion
advanced MFL tool. control is applied.

The superior performance of this tool arises from However to confirm the above conclusion, ZADCO
using extremely powerful magnetizing system; very decided to run another survey within one or two
large number of sensors having circumferential years in order to reassess the line. It was also
spacing of very few millimeters (Figure 4). The decided that same tool should be used to compare
company using this tool has an extensive library of readings and hence evaluate corrosion growth rate.
known signatures of defects having different
configurations. This third inspection survey was completed in
September 1992. The data in the inspection survey
These are compared to the recorded defects, thus report were interpreted us ing an improved software
increasing the accuracy and reliability of the which was introduced at the end of 1990. To ensure
interpreted data. compat ibi 1ity between the 1990 and 1992 inspect ion
surveys, the 1990 data were reprocessed using the
This second survey which was completed in December latest soft ware.
1990 reported 87434 metal loss defects; generally
characteristiced as general corrosion with pitting. The results of the 1992 inspect ion showed a 1imited
further corrosion progress since the previous
The metal loss defects grouped in clusters were inspection in the December 1990.
categorized as fo110ws:-
The histograms and corros ion growth 1ist ing show a
1).21,857 - metal loss clusters ranging from 0.05 to number of spools indicating a decrease in estimated
0.20 of nominal wall thickness. meta 1 loss. These were c la imed by contractor to be
due to a reduction in feature dimension generated by
2).64,448 - metal loss clusters ranging from 0.20 to automatic analysis procedures made by the improved
0.40 of nominal wall thickness. software and hence they considered that 1990
originally processed data to be pessimistic in
3).2125 - metal loss clusters greater than 0.40 but sizing metal loss.
less than or equal to 0.60 of wall thickness.
Further discussions are sti 11 carried out with the
4) . Four meta 1 loss c lusters greater than 0.60 but contractor to clarify some points and final report
less than 0.8 of wall thickness. is still awaited.

The reports provided by this contractor included:-


2. SURVEYS OF THE 14" MAIN OIL LINE
1. Metal loss sunmary report based on automatic
CONNECTING UMM AL-DALKH FIELD TO
feature recognition and sizing process which
ZAKUM CENTRAL COMPLEX
takes into account the interaction of neighboring w
The corrosion defects which were found in the 42
metal loss indications according to interaction
MOL concluded the need to carry out an inmediate
rules based on the NG-18 formula (Figure 5).
inspect ion for the 1ines connected to it including
Fa ilure Pressure Rat io (FPR) is ca lcu lated for
MOL of UA Field.
each cluster of interacting metal loss
indications.
The line is 14w (355.6 nm) diameter of 0.688 (17.5
mm) wa 11 thickness and extends for about 65 kms.
2. Defects with high FPR and defects of depth
Five contractors were requested to submit proposa ls
exceed ing 0.5 wa 11 th ickness were subjected to
for inspecting the line.
detailed sizing. The selected defects were
reported in a format which defines the type.
orientation, dimension and location of the defect
(Figure 6).
SPE 25582 F. HERAIBA 7

The wall thickness represented a major problems for Passage of heavy instrumented pigs broke down this
MFL tools. Contractors using this system stated that scale and disturbed the debris. thereby causing
lower standards of inspection should be expected unsuccessful runs of the inspection tool.
unless major modification of their tools. financed
by ZADCO is carried out. Two contractors proposed The contractor stated that no intelligent pig.
ultrasonic tools and one of them was selected to ultrasonic or magnetic flux leakage. should be
carry out the survey. attempted until the line is subjected to extensive
scale removal and cleaning programme.
The contractor recommended a spec ia1 clean ing
programme to remove any debr is or so 1ids wh ich may The contractor recommended a long duration cleaning
exist in the line. programme wh ich was not accepted by ZADCO. ZADCO
decided to inspect the line using advanced MFL tool
Several runs were carried out using a cleaning pig after modifying it to cover the excessive wall
supplied by the same contractor and the last run was thickness of the pipeline.
performed by the contractor who confirmed that the
line is clean. The inspect ion survey was carried out in May 1991;
and 5 success i ve runs were requ i red to cover the
Caliper survey was performed early February 1990 and pipeline length. The first 4 runs recorded good
no anomalies were found. The tool brought a small quality data covering the first 58.6 kms of the
amount of debris into the receiver. Dummy inspection line. However a section of primary sensor array
pig was run followed by the ultrasonic inspection developed a fault in the fifth run which covered the
tool. distance from 58.6 km to the receiving trap at 65.6
km. This caused an impaired defect detect ion in a
The memory of the tool was filled up after only 30 186 mm spiral band throughout the last 7 kms which
kms of the line. A second run was attempted corresponds to 1.5% of the total surface area of the
ut i 1izing a de lay mode which wi 11 allow the tool to pipeline.
start recording after comp let ing the first 30 kms.
The memory of the too 1 was fi lled up after on ly 4 The analysis of the inspection data indicated an
kms and the analysis of the data demonstrated very evidence of minor internal metal loss which can be
high level of no signal information indicating that attributed to the construction of the pipe in the
the transducer signals were being scattered by a mill and this was scattered randomly throughout the
very rough inner pipe wall surface or debris in the pipe.
line. or both.
In addition to the above. there was evidence of
The contractor recommended that ZADCO should minor internal corrosion in the bottom of the last
undertake a cleaning programme consisting of part of the line.
alternating brush and magnet cleaning pigs. The
cleaning programme continued for more than one month ZADCO did not accept the completion of the job until
and both types of pigs brought very 1itt le debris repeated run was carried out in October 1992
into the receiver. The magnet pigs gathered very covering the last part of the pipeline. This run
little ferrous material. confirmed that there is evidence of minor internal
corrosion at the bottom of the last 6.5 kms of the
The fina 1 c leaning pig was witnessed by the line.
contractor's representative who confirmed that the
line was sufficiently clean and ready to launch the 3. INSPECTION SURVEY CARRIED OUT FOR
inspection instrument. 24" WATER INJECTION LINE.

The too 1 fa i led to record any data and contractor Inspection of this line was decided to evaluate the
claimed that the problem was due to damaging the condit ion of the water inject ion network after 6
tool processor by metallic debris in the line. years of operation and to evaluate the effect of the
sea water treatment and corrosion control
The contractor advised that the debris is thought to programmes.
be particles of corroded material which are normally
kept attached to the inner pipe wall by scale build
up.
8 EVALUATION OF PIPELINE INTEGRITY BY ON-LINE INSPECTION SPE 25882

The selected line connects lAKUM Central Complex The line is 24"(509.6 mm) diameter, its length is
wi th the North Sate 11 ite and the 1ine is 24" (509.6 about 13 km and its wall thickness is 0.688"(17.5
mm) diameter, of 1.125" (28.6 mm) wall thickness and mm). The gas flows under extreme low operating
extends for about 13 km. pressure.

Seven contractor were requested to submit proposa ls All contractors advised that the inspection tool
for inspecting the line and their answers indicated will stop at girth welds until pressure builds up
that all MFL too 1s cannot inspect the 1ine due to behind it and then the tool moves at very high speed
its wall thickness. Accordingly a contractor subjecting the tool to damage. Two solutions for the
proposing advanced ultrasonic tool was selected to problem were proposed:
carry out the job.
To increase the operat ing pressure of the 1ine
The contractor requested the use of special cleaning and this can not be achieved without installing
pigs to remove any dirts, solids or scale which may gas compression facilities.
cover the corrosion pits.
Or to temporarily convert the line to liquid flow
This is required to ensure that the Ultrasonic beam while running the inspection tool.
can penetrate to the bottom of the pits. Two
clean ing runs were conducted and both brought no The contractor who carried out the second and third
significant scale or debris. inspection jobs for the 42" pipeline advised that
advanced MFL too 1s can not do the job un less major
The inspection runs were carried out in May 1990 and modifications are carried out to solve the problems
three runs were conducted. The first run failed related to the excessive wall thickness. The cost of
part ia lly and no data were recorded at all in the the proposed modifications' for MFL tool rendered it
second run. The failure was attributed to ingress of to be relatively expensive. Hence contractor
air which was not completely vented while running proposing ultrasonic tool was finally selected by
the pigs. ZADCO to carry out the two inspection jobs.

The third run recorded all inspection data. The


survey indicated lamination, external and internal
4.1. INSPECTION FOR THE 14" MOL
metal loss and also recorded all subjects which are
The contractor advised that liquid batch should be
welded to the pipeline.
used to provide a couplant for the Ultrasonic
transducers. lADCO requested the contractor to be
The metal loss recorded was insignificant and
responsib le for all necessary arrangements for the
1aminat ions found are a norma 1 occurrence in the
liquid batch.
pipe which probably were enclosed in the plates from
which the pipe was made.
Several cleaning runs were carried out before
running the inspection tool; and the last run was
4. INSPECTION OF SATAH FIELD MAIN OIL attended by the contractor who accepted the degree
LINE AND ONE GAS TRUNK LINE IN of cleanliness of the line. Gauge plate pig was then
ZAKUM FIELD used to confirm free passage followed by the
inspection tool which was launched in diesel batch
Five contractor were requested to submit proposals in August 1992.
to inspect these two lines.
This run fa i led and the inspect ion . too 1 was
SATAH Main Oil line is 14"(355.6 mm) diameter, of extensively damaged. The failure was attributed to
0.75"(19 mm) wall thickness and extends for about 57 pumping the batch liquid at pressure exceeding the
kms. The 1ine transfers crude oi 1 from SATAH field allowable pressure of the inspection tool.
to lIRKU Island. The stream is two phase with
relatively high H2S content. The second run was carried out in Nov. 1992
follOWing repeated cleaning runs using special type
The gas trunk line connects North Satellite to lAKUM of pigs. Checking the recorded data after receiving
Central Complex. the inspection pig indicated successful operation
for the tool.
9 F. HERAIBA SPE 25582

The inspection report is not received yet. However Our experience with the ultrason ic too ls confi rmed
in order to provide liquid couplant for the that the tool is extremely sensitive to any
ultrasonic transducers, several batches of diesel contaminants in the pipeline like wax, corrosive
were pumped in the line which caused repeated solids attached to the pipe wall or any other type
production shutdowns. The estimated indirect of debris.
additional cost to carry out the job was $ 300,000.
This value in addition to the cost of the inspection Extensive cleaning of the pipeline is essential to
job revealed that inspecting the line by ultrasonic achieve reliable ultrasonic inspection data. The
tool might not be the cost effective selection. cost of the necessary arrangements for an effective
cleaning can be very expensive and should be
considered in the overall cost.
4.2. INSPECTION FOR THE 24" GAS TRUNK
LINE Liquid interface is a must to ensure proper transfer
of ultrasonic energy into and out of the pipe wall.
Piping modifications were made to allow pumping
Gas or air bubbles shou ld be totally avoided while
water in the pipeline prior to and during the
running ultrasonic tool.
inspection run. In addition very high standards of
clean 1iness were set by the contractor to ensure
MFL tools of the second generation type satisfied
reliable inspection data.
most of ZADCD Inspection requirements except for
lines whose wall thickness exceed the MFL limits.
Accordingly lADCD increased the frequency of routine
cleaning. This was followed by running special
Selection of MFL tools should take into
cleaning pigs which removed about 200 kgs of foreign
consideration the design of magnetizing system,
materials in each run. More cleaning pigs were
number and arrangement of the sensors, the
launched for about 10 days and the amount of foreign
experience of other operators with the tool and
materia 1s decreased to about 30 kg. The materials
contractor who is running it. The reporting format
changed from soft wax to hard res idue. The
should provide information about pipeline defects,
contractor then advised that mechanical cleaning
how much they affect the pipeline integrity and what
operations by pigs wi 11 not achieve the required
areas require immediate repair. It should also
degree of clean 1iness and that a more aggress ive
provide means to assess corrosion growth which took
chemical solvent should be considered.
place during the period between two successive
inspection runs.
It was then decided to suspend the operations until
the nature of the residue is analysed and the
arrangements required to clean the line are ACKNOWLEDGEMENT
implemented.
We thank the management of ABU DHABI NATIONAL OIL
The indirect additional cost for the inspection job COMPANY (ADNDC) and the management of lAKUM
(which had not yet been completed) is about $ DEVELOPMENT COMPANY (lADCO) for their permission to
400,000. It is expected that similar cost will be pub 1ish th is paper. Thanks is given to Product ion
spent to meet the cleanliness standards required for Department staff and thanks and appreciation for our
the Ultrasonic tool. secretaries for their great effort and help.

CONCLUSIONS AND RECOMMENDATIONS REFERENCE


1. W.K. Holm., "Magnetic inspection pigging is an
Utilization of in line inspection tools proved to be
aid to pipeline maintenance" Pipeline Industry -
valuable and cost effective means to detect
July 1985.
defective areas in the pipeline.
2. G. Avrin and R.I. Coote "On-Line Inspection and
The internal condition of the pipeline and the
Analysis for Integrity" Report published by NOVA,
degree of clean 1iness shou ld be assessed accurate ly
an Alberta Corporation.
by the pipeline operator. This should be considered
in the selection process of the inspection tool.
10 EVALUATION OF PIPELINE INTEGRITY BY ON-LINE INSPECTION SPE 25582

3. G.A. Nespeca and K.B. Hveding "Intelligent


Pigging of Ekofisk-Emden 36 "Gas Pipeline" SPE
18232 Presented in the Annual Techn ica 1
Conference and Exhibition of the SPE held in
Houston. TX Dctober 2-5. 1998.

4. Magnetic Flux Pig Run successful on TAPS Dil &


Gas Journal - Oct . 1988.

5. "Alyeska maps big corrosion repair program on


Tran-Alaska Crude Line" - Dil & Gas Journal April
3D. 1990 Page 23 - 26.
SPE25582

-~----
III1II
....;.;;..--.;;;..;..-.----~--- ~~
.111__-
....
HAGNFTIC FLUX LINES SHOWN SCHEMATICALLY AROUND A PIPE DEFECT.

Figure -1

III REPORTED DEPTH "10


100 1:1
/
/
/
90 //
/
'" '"
80

70 /
,/
/
. . '"
/
'"
",'" '" '"'"
/'
'"
60
/ '" '"'" ",'" '"'"
/
'"
50
A / '" '" '"
.'" ",'" '"'"
'"
40
/
J,.
",.
'" '"

",'" '"'"
30 y '"'" '"'"
20
/
/
A.",
/ '". . ",'" '"
/
/ J,. SPIRAL CORROSION
GENERAL CORROSION
1:1 line
'" '" == 10% ERROR ALLOWANCE
10
/ '" '"
( '"
Oa:...-......,t.:.-__-~-~--...-'""'T"-_r-..,...-""'T""___,
10 20 30 40 50 60 70 80 90 100

ACTUAL DEPTH %
Figure-2

INSPECTION SURVEY REPORTED DEPTH VS.


ACTUAL DEPTH
SPE25582

i
~4

!
I
I
I
[2] - channel ( 3] - c ire urn of er.;:.e:.:.;nc=-=~~(m.:.:;:rn.;.:.]__....:[--'.4.:!..]-=-=--=.'=~1o::..::c~k:::..w.:...;,s::.:::!"1

Figure - 3

Figure - 4
ADVANCED MFL TOOL
SPE255 82
CRITERIA FOR INTERACTIoN

CIRCUMFERENTIAL
IIIOTH

... __ .....~
..
_ _ - lI
~
, .~~.:-:~.:-:.::-:.:.;.::;:

7e
~~~:::::::-31
I :.. ..- I
I I
I
I
I
I
PROJECTED AXIAL LENGTH

AXIAL INTERACTION HAY OCCUR IF L3 IS LESS THAN L1 AND L2


CIRCUl1FERENTIAL INTERACTION HAY OCCUR IF \/3 IS LESS THAN III AND liz

Figure- 5

Figure- 6
DEFECT DETAILED SHEET
PIPEliNE INSPECTION SHEET NO: ~3

Qil:!N!'A.'::l;iK: . &.. :;0


r~':::lQCic\
!!.1!"J?..!: NTJlf8t!l: 48/1

lU1'tlU Q!1!.!:ISIOHS:
?U.CW-II No. 43/1

A.x1.al lOt. .
Cl:,c:::afllrent1al liS6. .
Cei'c.~ - ..veu1e 36: .-r
- ,el.:ic. 53: .-r .

St=lp lI.ap NWlber .'0.8029

uru.!NC!:
1. a..-'ODt
(C:' 49810 6.111)

2. NODE
(C7 49930 + 6.0la)

it.fDlEYCE Gri.'IH qttD:


~. r:eference ,11:0 veld ~c t..'1. z.u::nc CE:NI1U.L (Upu.tUIl.) enci 0: ::..
fucun ,pool 15 aUlaoftC' 49900.

n. locacoa of u1s veld 1.s 103.91:1: dovnsceu f'r=m rafue=lC1t 1 and


42.&1. u:pct:n.g ft'OlI r:e!ereo.ce 1.

FEAnra& t..oeA':"ION:
:he fucuu 1s locaced 2.... dOfoo"DSCeaci =011 a. reference S:.:-....:r. ve!'d.

G1ro ;.lcl !.EF!lWfCt 1 f!.AF a.u~ Z i


:i'umbflr _4_58.,..8_3 49...,8.,..9_0 4_9.,.90_0 4_'.,."_0 0'.,..9.,..2_0 '9..,9_30_1
1"1'1=. L.&n~Q L2.2:& 12.:::::. L2.4111 12.1:1 ::.. ~ I
ZA.J:UK a:m.u. no~) :::?J::1 :Su.:O

C:;M.V:S~
~e fu.r.ure is e:tarac:~!!nsi:.:c. ot' i:lce:na.l :eol :'05S &.:Ia :'.s :.::.-t =osr.
:oc.&ol. in .l s?ool c.ant.11nln~ nWllerous DC-at' :llIu.l ion u.::l:"~:'ocs.

:e:a:i.h of :.":esc oIre s1'l'e:n in the selScence4 .:.II loss l~~~~ :..:.
Se~::.on '?l.
SPE25582

SEfJIENCEO METAL LOSS HISTOGRAM


~~~~~~,~~~~~,~~~"-----,------

lakum CenLral Complex Lo Z,rku Island


1
I

Oll 5P E21n
Figure - 7 20-r1AR-91
30 ..
10 ..
30. F.P.R >0.30

r-r--+--',---r-,-r,~,---r-,or,-r,.....",..-+-,'A,-, ,---r-.,....... ~1-L,


.L.,.'

20. 10. 50. 60.

SCA TTER fiRAPl1 or: CLUSTER AVERAGE DEPTH vs CLUSTER LENGTH


ZAK1Jn CENTRAL conpu,x 10 Z iRKU ISLAND

100.

V1
MAO? "lI,a psi
."
c., UO.
z
'"
w
....:c
.....
.....
-(
3:
60.
~ ,',,

~ ':.

..
'Y. I
'LJ

~ r)
1-
VI
;:)
.....
'-J

'1. '0.
0
:r:
.... 1250 psi
u.a
n.

~
'LJ
L:J

...>
<{
c-.: 711.
-(

I
(), 1 - - - -
II. 1.10. ]'0. 3&0. 'so. bOO.

LENGTH OF CLUSTER 1m",!

Fi~ure -8
SCATTER GR~PH OF CLUSTER

You might also like