1. Bored excavation for 300mm diameter piers, depth of 2.50 meters.
The total number of piers are 44 spread out of maximum 1800mm, as per below
drawing.

Item Particulars Unit Quantity Rate $ C

1 Bored excavation for 300 mm piers, m 110


Depth of piers 2.50 m

44 x 2.50 = 110 linear meters

2. Bulk excavation to prepare site generally

Item Particulars Unit Quantity Rate $ C

2 Bulk excavation m3 73

16.91 + 2.00 =18.91


11.87 + 2.00 = 13.87
RL 0.325 RL 0.050 = 0.275
72.12

Page 1 of 6
3. N25 concrete to the slab on ground
Slab: 12,830 x 5,760 x 100 = 7.39 m3
Garage set down: 5,640 x 5,500 x 75 = 2.32 m3
Patio Slab: 1,670 x 6,350 x 100 =1.06 m3
Family Room: 5,510 x 4,080 x 100 = 2.24 m3

450 12,830

4,080
11,870
5,510

100 mm beams on slab ground


12,830 450 = 12,380 11,870 900 = 10,970
11,870 450 = 11,420 12,830 900 = 11,930
12,830 450 = 12,380
11,870 450 = 11,420
4,080 450 = 3,630
5,510 450 = 5,060
4,080 = 4,080
83,270

Page 2 of 6
Pad footings
1200 x 900 x 2 = 2.16
350 x 240 = 0.84

Item Particulars Unit Quantity Rate $ C

3 N25 Concrete slab on ground m3

Slab on ground m3 8
12.83 x 5.76 x 0.100 = 7.39

Garage set down m3 3


5.64 x 5.50 x 0.075 = 2.32

Patio Slab m3 2
1.67 x 6.35 x 0.100 = 1.06

Family Room m3 3
5,510 x 4,080 x 100 = 2.24

100 mm beams on slab on ground m3 4


83.27 x 0.100 x 0.450 = 3.74

Pad footing m3 2
2.16 + 0.84 x 0.350 = 1.05

Total m3 22

4. SL72 reinforcing mesh to ground slabs.


a) Nett measure in m2 (when costed, the $ rate per m2 will include an amount
for wastage)
b) The number of sheets required to complete the slab. Note: reinforcing mesh
is sold in 6.0m x 2.4m sheets. 2 bar overlaps are typically required resulting in
an effective cover of 5.8m x 2.2m with 400mm lap.

Item Particulars Unit Quantity Rate $ C

4 (a) SL72 reinforcing mesh m2 175


12.73 x 11.77 = 149.83
5.41 x 4.48 = 24.23
174.06

4 (b) Mesh Sheets 2.4 x 6m, 400 mm lap lengths 12


12.73: 2.20 = 5.78 (6 lengths)
11.77 5.8: 2.20 = 2.68 (3 lengths)
4.48: 2.2 = 2.03 (3 lengths)

5. The lengths of SL12TM required to complete the construction of the slab on ground.

Page 3 of 6
Item Particulars Unit Quantity Rate $ C

5 SL12TM Trench mesh 300mm m 89

3 x 12.73 =38.19
3 x 11.77 = 35.31
1 x 5.41 =5.41
2 x 4.98 = 9.96
88.87

SL 12TM lengths of 6 metres lengths 15


89:6 = 14.83

6. The structural steel in tonnes. Measure to 2 decimal places.

Item Particulars Unit Quantity Rate $ C

6 Structural Steel tonnes 0.60


SL 12 TM 6meter length 6.8 kg
15 x 6.8 = 102 kg
SL 72 reinforcing mesh: 2.4 x 6 41 kg
12 x 41 = 492
Total: 102 + 492 = 594 (0.59 tonnes)

7. The plasterboard required to complete the lining of first floor rooms excluding the wet
areas.
a) Nett measure in m2. The rate per m2 will include a wastage factor.
b) The number of sheets of plasterboard required to complete the lining of the
rooms.

Item Particulars Unit Quantity Rate $ C

7 (a) Plasterboard m2

Bedroom 1: 5.27 x 4.06 = 21.39 m2 22

Bedroom 2: 3.54 x 3.49 = 12.35 m2 13

Bedroom 3: 3.54 x 3.23 = 11.43 m2 12

Bedroom 4: 3.34 x 3.29 = 10.98 m2 11

Rumpus Room: 4.00 + 7.26 + 1.99 + 4.16 + m2 27


3.03 + 6.06 = 26.50

Total m2 85

7 (b) Plasterboard sheets sheets


Bedroom 1: 5.27 x 4.06 = 21.39
8
2.7 2 sheets

Page 4 of 6
4.2 4 sheets
5.4 2 sheets
Bedroom 2: 3.54 x 3.49 = 12.35 8
2.7 4 sheets
3.6 4 sheets
Bedroom 3: 3.54 x 3.23 = 11.43 8
2.7 4 sheets
3.3 4 sheets
Bedroom 4: 3.34 x 3.29 = 10.98 8
2.4 2 sheets
3.3 4 sheets
3.6 2 sheets
Rumpus Room:
14
4.00 + 7.26 + 1.99 + 4.16 + 3.03 + 6.06 =
26.50
2.4 4 sheets
3.3 2 sheets
3.6 4 sheets
4.2 4 sheets
Total Sheets:
46
2.4 6 sheets
2.7 10 sheets
3.3 10 sheets
3.6 10 sheets
4.2 8 sheets
5.4 2 sheets

8. 66 x 18mm finished DAR primed pine skirting to the first-floor rooms.


Bedroom 1: 5,270 x 4,060 = 5.4m (1 length), 4.2m (2 lenghts), 2.7 (1 length)
Bedroom 2: 3,540 x 3,490 = 3.6m (2 lenghts), 2.7m (1 length), 2.4m (1 length)
Bedroom 3: 3,540 x 3,230 = 2.7m (2 lengths), 3.3m (2 lengths),
Bedroom 4: 3,340 x 3,290 = 3.3m (2 lengths), 3.6m ( 1 length), 2.1m (1 length)
Rumpus Room: 4.00 + 7.26 + 1.99 + 4.16 + 3.03 + 6.06 2.4m (1 length), 2.7m (2
lengths), 3.3m (3 lengths), 4.2m (1 length)

Item Particulars Unit Quantity Rate $ C

8 Skiting primed pine length

Bedroom 1: 5.27 x 4.06


4
5.4m (1 lengths)
4.2m (2 lengths)
2.7m (1 length)
Bedroom 2: 3.54 x 3.49
4
3.6m (2 lengths)
2.7m (1 length)
2.4m (1 length)
Bedroom 3: 3.54 x 3.23
4
2.7m (2 lengths)
3.3m (2 lengths)
Bedroom 4: 3.34 x 3.29
4
3.3m (2 lengths)
3.6m (1 length)
2.1m (1 length)

Page 5 of 6
Rumpus Room: 7
4.00 + 7.26 + 1.99 + 4.16 + 3.03 + 6.06
2.4m (1 length)
2.7m (2 lengths)
3.3m (3 lengths)
4.2m (1 length)
Total:
23
2.1m 1 length
2.4m 2 length
2.7m 6 lengths
3.3m 7 lengths
3.6m 3 lengths
4.2m 3 lengths
5.4m 1 length

9. Ceramic floor tiles to the following ground floor rooms:


Family room: 4,080 x 5,030 =20.52m + 10% = 23m
Meals room: 2,430 x 4,680 = 11.37m + 10% = 13m
Kitchen allow tile to go under the cupboards: 4,590 x 6,110 = 28.05m +
10% = 31m
Foyer/stair area: 1,710 x 1,090 = 1.87m + 10% = 3m

Item Particulars Unit Quantity Rate $ C

9 Family room + 10% wastage m2 23


4.08 x 5.03 =20.52m + 10% = 22.57m

Meals room + 10% wastage m2 13


2.43 x 4.68 = 11.37m + 10% = 12.50m

Kitchen + 10% wastage m2 31


4.59 x 6.11 = 28.05m + 10% = 30.85m

Foyer/stair area + 10% wastage m2 3


1.71 x 1.09 = 1.87m + 10% = 2.05m

Total m 70