You are on page 1of 73

Traffic Management Measures for Main Carriageway Opening

PROJECT CODE : IA 12/13 C 054 ST


PROJECT TITLE : Construction of West Corridor P010 (Package 1)
CONTRACT NO. : C2013/56
BUDJET REF. CODE : 11320/1440913
TENDER NO. : MRPSC/006/2012-2013/L

ITEM DESCRIPTION ESTIMATED AMOUNT

Summary of Road Opening : Traffic Management Measures for Main Carriageway Opening

Traffic Management Measures for Main Carriageway Opening


1 Stage 1 : 304,975.51
(Initital Arrangement as per the layout approved by authorities concerned)
Removal of Traffic Management Measures for Main Carriageway Opening 42,836.82
Traffic Management Measures for Main Carriageway Opening
2 Stage 2 : (Layout has been changed as per the client's requirements and the Contractor was 302,458.98
requested to arrange cones and barriers accordingly)
Removal of Traffic Management Measures for Main Carriageway Opening 119,274.44

Traffic Management Measures for Main Carriageway Opening


3 Stage 3 : (During PWA President's visit, President requested the Contractor to re-arrange the 902,293.40
traffic management measures as per PWA requirements before road opening)

Future Road
4 Traffic Management Measures for Main Carriageway Opening 9,626,935.21
Opening :
5 Maintenance Total Maintenance Cost (From 11 March 2017 to 31 August 2017) 1,183,632.91

Sub-total 12,482,407.27
6 Future Road Saving by use of 6000m second hand Precast Concrete Barriers (TCB) available from
(1,308,780.00)
Opening : outside source

Total 11,173,627.27

Notes:
1 Stage 3: Concrete barriers are paid for installation only of second hand Precast Concrete Barrier (TCB), Source from outside
and J&P owned barriers
2 Future Road For every 1000m of second hand barrier used over and above 6000m included above a further saving of
Opening : QAR 218,130 is possible.
3 Overall Precast Concrete Barrier (TCB) = 16,012 m
Quantity Polyethylene Road Safety Barrier = 8,649 m
4 Handing over
Assumed all roads will be handed over by end August 2017

Page 1 of 73
Traffic Management Measures for Main Carriageway Opening

PROJECT CODE : IA 12/13 C 054 ST


PROJECT TITLE : Construction of West Corridor P010 (Package 1)
CONTRACT NO. : C2013/56
BUDJET REF. CODE : 11320/1440913
TENDER NO. : MRPSC/006/2012-2013/L

Period: From 11 March 2017 to 6 April 2017

UNIT ESTIMATED
S. No. ITEM DESCRIPTION UNIT QTY. REMARKS
RATE AMOUNT
Stage 1 : Traffic Management Measures for Main Carriageway Opening
Refer Stage 1 - Measurements
1 Traffic Signs ( Multiple Types) NR. 87.00 sum 178,839.73
Refer Stage 1 - Rate Build Ups - Traffic Signs Installation
Refer Stage 1 - Measurements
2 Installation of Polyethylene Road Safety Barrier M. 160.00 160.59 25,694.40
Refer Rate Analysis for Polyethylene Road Safety Barrier
Refer Stage 1 - Measurements
3 Solar Panel Lights NR. 537.00 39.74 21,340.38
Refer Rate Analysis for Solar Warning Light
Refer Stage 1 - Measurements (SC verified the Qty)
4 Supply and Installation of Cones NR. 1,614.00 27.50 44,385.00
Refer Rate Analysis for Traffic Cone
Refer Quoation from TMS: RSA 1 nr @ QAR 5000
5 Stage 3 for detailed design (Review of Shopdrawings) NR. 6.00 5,786.00 34,716.00
Total Cost = QAR 5000 + 15.72% OH&P = QAR 5786
Subtotal 304,975.51
Removal of Traffic Management Measures for Main Carriageway Opening
1 Removal Traffic Signs ( Multiple Types) NR. 115.00 sum 23,236.23
2 Removal of Polyethylene Road Safety Barrier M. 160.00 24.78 3,964.80
3 Removal Solar Panel Lights NR. 537.00 3.87 2,078.19
4 Removal of Cones NR. 1,614.00 8.40 13,557.60
-
Subtotal 42,836.82

Page 2 of 73
Traffic Management Measures for Main Carriageway Opening

PROJECT CODE : IA 12/13 C 054 ST


PROJECT TITLE : Construction of West Corridor P010 (Package 1)
CONTRACT NO. : C2013/56
BUDJET REF. CODE : 11320/1440913
TENDER NO. : MRPSC/006/2012-2013/L

Period: From 6 April 2017 to 21 April 2017

ESTIMATED
S. NO. ITEM DESCRIPTION UNIT QUANTITY UNIT RATE REMARKS
AMOUNT
Stage 2 : Traffic Management Measures for Main Carriageway Opening
1 Supply and Install Traffic Signs ( Multiple Types) NR. 94.00 sum 30,149.56 Refer Stage 2 - Measurements (SC verified the Qty)
Refer Stage 2 - Rate Build Ups - Traffic Signs Installation
2 Install Traffic Signs ( Multiple Types) NR. 63.00 sum 42,604.23 Refer Stage 2 - Measurements (SC verified the Qty)
Refer Stage 2 - Rate Build Ups - Traffic Signs Installation
3 Supply and Install Solar Panel Lights NR. 1,285.00 39.74 51,065.90 Refer Stage 2 - Measurements (SC verified the Qty)
Refer Rate Analysis for Solar Warning Light
4 Install Solar Panel Lights NR. 537.00 3.87 2,078.19 Refer Stage 2 - Measurements (SC verified the Qty)
Refer Rate Analysis for Solar Warning Light
5 Supply and Installation of Cones NR. 4,665.00 27.50 128,287.50 Refer Stage 2 - Measurements (SC verified the Qty)
Refer Rate Analysis for Traffic Cone
6 Installation of Cones NR. 1,614.00 8.40 13,557.60 Refer Stage 2 - Measurements (SC verified the Qty)
Refer Rate Analysis for Traffic Cone
7 Stage 3 for detailed design (Review of Shopdrawings) NR. 6.00 5,786.00 34,716.00 Refer Quoation from TMS: RSA 1 nr @ QAR 5000
Total Cost = QAR 5000 + 15.72% OH&P = QAR 5786
Subtotal 302,458.98

Removal of Traffic Management Measures for Main Carriageway Opening


1 Removal Traffic Signs ( Multiple Types) NR. 157.00 sum 59,479.70
2 Removal Solar Panel Lights NR. 1,822.00 3.87 7,051.14
3 Removal of Cones NR. 6,279.00 8.40 52,743.60
-
Subtotal 119,274.44

Page 3 of 73
Traffic Management Measures for Main Carriageway Opening

PROJECT CODE : IA 12/13 C 054 ST


PROJECT TITLE : Construction of West Corridor P010 (Package 1)
CONTRACT NO. : C2013/56
BUDJET REF. CODE : 11320/1440913
TENDER NO. : MRPSC/006/2012-2013/L

Period: From 22 April 2017 to 31 August 2017

ESTIMATED
S. NO. ITEM DESCRIPTION UNIT QUANTITY UNIT RATE REMARKS
AMOUNT
Stage 3 : Traffic Management Measures for Main Carriageway Opening
1 Supply and Install Traffic Signs ( Multiple Types) NR. 5.00 sum 7,100.71 Refer Stage 3 - Measurements (SC verified the Qty)
Refer Stage 3 - Rate Build Ups - Traffic Signs Installation
2 Install Traffic Signs ( Multiple Types) NR. 74.00 sum 41,184.08 Refer Stage 3 - Measurements (SC verified the Qty)
Refer Stage 3 - Rate Build Ups - Traffic Signs Installation
Total number of street lighting poles to be protected = 386 nrs
No. of barriers required (2 nrs for each pole) = 386 x 2 = 772 nrs
Installation only of second hand Precast Concrete Barrier (TCB)
3 M. 881.60 253.67 223,635.47 Available no. of barriers with J&P = 482 nrs
Source from outside source (to protect the street lighting poles)
Total length of the balance barriers required = 290 x 3.04 = 881.60m
Refer Rate Analysis for Precast Concrete Barrier

Installation only of second hand Precast Concrete Barrier (TCB) Available no. of barriers with J&P = 482 nrs
J&P owned barriers to protect the street lighting poles M. 1,465.28 18.85 27,620.53 Total length of the balance barriers required = 482 x 3.04 = 1,465.28m
= 482 nrs x 3.04m = 1,465.28m Refer Rate Analysis for Precast Concrete Barrier

4 Supply and Installation of Polyethylene Road Safety Barrier M. 2,840.00 160.59 456,075.60 Qty as given by J&P Site Engineer.
Refer Rate Analysis for Polyethylene Road Safety Barrier
5 Installation of Polyethylene Road Safety Barrier M. 160.00 24.78 3,964.80 Qty as given by J&P Site Engineer.
Refer Rate Analysis for Polyethylene Road Safety Barrier
6 Supply and Install Solar Panel Flashlights NR. 463.00 39.74 18,399.62 Refer Stage 3 - Measurements (SC verified the Qty)
Refer Rate Analysis for Solar Warning Light
7 Install Solar Panel Flashlights NR. 537.00 3.87 2,078.19 Refer Stage 3 - Measurements (SC verified the Qty)
Refer Rate Analysis for Solar Warning Light

Page 4 of 73
Traffic Management Measures for Main Carriageway Opening

PROJECT CODE : IA 12/13 C 054 ST


PROJECT TITLE : Construction of West Corridor P010 (Package 1)
CONTRACT NO. : C2013/56
BUDJET REF. CODE : 11320/1440913
TENDER NO. : MRPSC/006/2012-2013/L

Period: From 22 April 2017 to 31 August 2017

ESTIMATED
S. NO. ITEM DESCRIPTION UNIT QUANTITY UNIT RATE REMARKS
AMOUNT
Stage 3 : Traffic Management Measures for Main Carriageway Opening
8 Installation of Safety Cones NR. 500.00 8.40 4,200.00 Refer Stage 3 - Measurements (SC verified the Qty)
Refer Rate Analysis for Traffic Cone
9 Stage 3 Road Safety Audit NR. 6.00 5,786.00 34,716.00 Refer Quoation from TMS: RSA 1 nr @ QAR 5000
Total Cost = QAR 5000 + 15.72% OH&P = QAR 5786
10 Stage 4 Road Safety Audit NR. 6.00 13,886.40 83,318.40 Refer Quoation from TMS: RSA 1 nr @ QAR 12000
Total Cost = QAR 12000 + 15.72% OH&P = QAR 13886.40
Subtotal 902,293.40

Page 5 of 73
Traffic Management Measures for Main Carriageway Opening

PROJECT CODE : IA 12/13 C 054 ST


PROJECT TITLE : Construction of West Corridor P010 (Package 1)
CONTRACT NO. : C2013/56
BUDJET REF. CODE : 11320/1440913
TENDER NO. : MRPSC/006/2012-2013/L

Period: From 1 May 2017 to 31 August 2017

ESTIMATED
S. NO. ITEM DESCRIPTION UNIT QUANTITY UNIT RATE REMARKS
AMOUNT
Future Road Opening : Traffic Management Measures for Main Carriageway Opening
1 Supply and Install Traffic Signs ( Multiple Types) NR. 173.00 sum 316,874.09 Refer Stage 3 - Rate Build Ups - Traffic Signs Installation
2 Supply and Installation of Precast Concrete Barrier (TCB) M. 16,012.00 471.80 7,554,461.60 Qty taken from the Barrier Layout for Future Road Opening
Refer Rate Analysis for Precast Concrete Barrier
3 Supply and Installation of Polyethylene Road Safety Barrier M. 5,649.00 160.59 907,172.91 Qty taken from the Barrier Layout for Future Road Opening
Out 8649nr of barriers required 3000nr barriers are from Stage 3.
Refer Rate Analysis for Polyethylene Road Safety Barrier
4 Installation Only of Polyethylene Road Safety Barrier M. 3,000.00 24.78 74,340.00 3000nr barriers from Stage 3.
Refer Rate Analysis for Polyethylene Road Safety Barrier
4 Supply and Install Solar Panel Flashlights NR. 8,221.00 39.74 326,702.54 Qty given by J&P Site Engineer (SC verified the Qty)
Refer Rate Analysis for Solar Warning Light
5 Supply and Installation of Safety Cones NR. 5,000.00 27.50 137,500.00 Qty given by J&P Site Engineer (SC verified the Qty)
Refer Rate Analysis for Traffic Cone
6 Stage 3 Road Safety Audit NR. 12.00 5,786.00 69,432.00 Refer Quoation from TMS: RSA 1 nr @ QAR 5000
Total Cost = QAR 5000 + 15.72% OH&P = QAR 5786
7 Stage 4 Road Safety Audit NR. 12.00 13,886.40 166,636.80 Refer Quoation from TMS: RSA 1 nr @ QAR 12000
Total Cost = QAR 12000 + 15.72% OH&P = QAR 13886.40
8 Double Handling sum 1.00 73,815.27 73,815.27
Subtotal 9,626,935.21

Page 6 of 73
Traffic Management Measures for Main Carriageway Opening

PROJECT CODE : IA 12/13 C 054 ST


PROJECT TITLE : Construction of West Corridor P010 (Package 1)
CONTRACT NO. : C2013/56
BUDJET REF. CODE : 11320/1440913
TENDER NO. : MRPSC/006/2012-2013/L

Period: From 1 May 2017 to 31 August 2017

Double Handling Cost


Moving the Safety Cones and Flash Lights with the
Site
5000 nrs of Safety Cones 8.40 42,000.00
8221 nrs of Flash Lights 3.87 31,815.27
Total Double Handling Cost 73,815.27

Page 7 of 73
Traffic Management Measures for Main Carriageway Opening

PROJECT CODE : IA 12/13 C 054 ST


PROJECT TITLE : Construction of West Corridor P010 (Package 1)
CONTRACT NO. : C2013/56
BUDJET REF. CODE : 11320/1440913
TENDER NO. : MRPSC/006/2012-2013/L

Period: From 11 March 2017 to 12 September 2017

1. Stage 1 (From 11 March 2017 to 6 April 2017, 25 working days)

Maintenance Cost (No Cost)

2. Stage 2 (From 6 April 2017 to 21 April 2017, 13 working days)

Maintenance Cost
Replacement Cost
30% of the total material cost for flash lights 16,944.60
30% of the total material cost for cones 31,081.05
Total Maintenance Cost for Stage 2 48,025.65 48,025.65

3. Stage 3 (From 22 April 2017 to 31 August 2017, 107 working days)

Maintenance Cost
4 labourers @ QAR 15 (G/DS/3/G),
38,520.00
for 107 days (107 x 6 hrs) = QAR (4 x 15 x 107 x 6)
1 Water Bowser @ QAR 120 (G/DS/8/C),
77,040.00
for 107 days (107 x 6 hrs) = QAR (1 x 120 x 107 x 6)
1 Truck Mounted Attenuator (TMA) @ QAR 306.25,
196,612.50
for 107 days (107 x 6 hrs) = QAR (1 x 306.25 x 107 x 6)
Sub-total 1 312,172.50
Add 15.72% of Overhead and Profit 49,073.52
Sub-total 2 361,246.02
Replacement Cost
10% of the total material cost for PE barriers 36,183.00
30% of the total material cost for flash lights 9,300.00
30% of the total material cost for cones 2,475.00
Total Maintenance Cost for Stage 3 409,204.02 409,204.02

4. Future road opening (From 1 May 2017 to 31 August 2017, 99 working days) 3.73

Maintenance Cost
4 labourers @ QAR 15 (G/DS/3/G), 59,400.00
for 99 days (99 x 10 hrs) = QAR (4 x 15 x 99 x 10)
1 Water Bowser @ QAR 120 (G/DS/8/C), 118,800.00
for 99 days (99 x 10 hrs) = QAR (1 x 120 x 99 x 10)
1 Truck Mounted Attenuator (TMA) @ QAR 306.25,
303,187.50
for 99 days (99 x 10 hrs) = QAR (1 x 306.25 x 99 x 10)
Sub-total 1 481,387.50
Add 15.72% of Overhead and Profit 75,674.12
Sub-total 2 557,061.62
Replacement Cost
10% of the total material cost for PE barriers 68,132.59
30% of the total material cost for flash lights 76,455.30
30% of the total material cost for cones 24,750.00
Total Maintenance Cost for Future Road Openings 726,399.51 726,399.51

Total Maintenance Cost 1,183,632.91

Page 8 of 73
Traffic Management Measures for Main Carriageway Opening

Rate Analysis for Pre-cast Concrete Barrier, Type M, Type M, Size 0.15/0.32m x 1.345m x 3.04m
Rate (QAR)
Item Item Description Unit Qty.
Labor Plant Materials Overhead Profit Total Rate Remarks
10.93% 4.79%
Precast Concrete Barrier (3.04m Length)
Precast concrete barrier Type M, Size 0.15/0.32m x 1.345m Refer CC's
nr 1.00 - - 1,149.12
x 3.04m LPO.
Reflective Strips m 3.04 - - 33.00
Cost of installation including transportation within the Site
sum 1.00 9.50 47.81 -
(Loading, Transporting and Unloading)

Supply and install Precast Concrete Barrier


Unit Rate / nr nr 1.00 9.50 47.81 1,182.12 135.47 59.37 1,434.27
(3.04m Length)
Supply and install Precast Concrete Barrier
Unit Rate / m m 1.00 471.80
(3.04m Length)

Install Precast Concrete Barrier


Unit Rate / nr nr 1.00 9.50 47.81 - - - 57.31
(3.04m Length)
Install Precast Concrete Barrier
Unit Rate / m m 1.00 18.85
(3.04m Length)
10.93% 4.79%
Rented Precast Concrete Barrier (3.80m Length)
Refer CC's
Precast concrete barrier 3.80m nr 1.00 - - 800.00
LPO.
Reflective Strips m 3.80 - - 33.00
Cost of installation including transportation within the Site
sum 1.00 - - -
(Loading, Transporting and Unloading)

Supply and install Precast Concrete Barrier


Unit Rate / nr nr 1.00 - - 833.00 91.05 39.90 963.95
(3.80m Length)
Supply and install Precast Concrete Barrier
Unit Rate / m m 1.00 253.67
(3.80m Length)

Page 9 of 73
Traffic Management Measures for Main Carriageway Opening

Cost Break-down for the Installation of Concrete Barrier (3.04m Length)

Labour Plant Material


S. No. Description Unit Qty Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost Remarks
(QAR) (QAR) (QAR) (QAR) (QAR) (QAR)

Installation of Concrete Barrier (3.04m Length)


Consider 20nrs Barriers

01. Loading from store (for 20nrs) m


1 Crane (upto 5 tons) hr 1.00 100.00 100.00 Ref: Daywork Shedule G/DS/9/U
1 Trailer hr 1.00 150.00 150.00 In-house cost data
1 Operator (Heavy) hr 1.00 20.00 20.00 Ref: Daywork Shedule G/DS/3/K
1 Driver (Heavy) hr 1.00 20.00 20.00 Ref: Daywork Shedule G/DS/3/G
2 Labourers @ 1 hr hr 2.00 15.00 30.00 Ref: Daywork Shedule G/DS/3/A

02. Transportation from store to site (for 20nrs) m


1 Trailer hr 1.00 150.00 150.00 In-house cost data
1 Driver (Heavy) hr 1.00 20.00 20.00 Ref: Daywork Shedule G/DS/3/G

03. Unloading on site and installatino (for 20nrs) m


1 Truck Mounted Attenuator (TMA) hr 1.00 306.25 306.25 Ref: CC's Quotation
1 Crane (upto 5 tons) hr 1.00 100.00 100.00 Ref: Daywork Shedule G/DS/9/U
1 Trailer hr 1.00 150.00 150.00 In-house cost data
1 Operator (Heavy) hr 1.00 20.00 20.00 Ref: Daywork Shedule G/DS/3/K
1 Driver (Heavy) hr 1.00 20.00 20.00 Ref: Daywork Shedule G/DS/3/G
4 Labourers @ 1 hr hr 4.00 15.00 60.00 Ref: Daywork Shedule G/DS/3/A

TOTAL COST m 20.00 190.00 956.25 -


UNIT RATE PER NUMBER m 1.00 9.50 47.81 -

Page 10 of 73
Traffic Management Measures for Main Carriageway Opening

Rate Analysis for Polyethylene Road Safety Barrier, Joint Type #WR 1027, Size: 2000mm(L)x500mm(W)x800mm(H)
Rate (QAR)
Item Item Description Unit Qty.
Labor Plant Materials Overhead Profit Total Rate Remarks

10.93% 4.79%
Polyethylene Road Safety Barrier (2.00m Length)

Polyethylene Road Safety Barrier, Joint Type #WR 1027, Refer CC's
nr 1.00 - - 195.00
Size: 2000mm(L)x500mm(W)x800mm(H), Colour RED. LPO.
Reflective Strips m 2.00 - - 33.00
Cost of installation including transportation within the Site
nr 1.00 7.20 29.13 -
(Loading, Transporting and Unloading)
Filling in the PE Barrier with dune sand and water (5% of
sum 1.00 - - 13.22
the base cost)

Supply and install Polyethylene Road Safety Barrier (2.00m


Unit Rate / nr nr 1.00 7.20 29.13 241.22 30.34 13.29 321.18
Length)
Supply and install Polyethylene Road Safety Barrier (2.00m
Unit Rate / m m 1.00 160.59
Length)

Unit Rate / nr Install Polyethylene Road Safety Barrier (2.00m Length) nr 1.00 7.20 29.13 13.22 - - 49.55

Unit Rate / m Install Polyethylene Road Safety Barrier (2.00m Length) m 1.00 24.78

Page 11 of 73
Traffic Management Measures for Main Carriageway Opening

Cost Break-down for the Installation of Polyethylene Road Safety Barrier (2.00m Length)

Labour Plant Material


S. No. Description Unit Qty Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost Remarks
(QAR) (QAR) (QAR) (QAR) (QAR) (QAR)

Installation of Polyethylene Road Safety Barrier (2.00m Length)


Consider 50nrs Barriers

01. Loading from store (for 50nrs) m


1 Crane (upto 5 tons) hr 2.00 100.00 200.00 Ref: Daywork Shedule G/DS/9/U
1 Trailer hr 2.00 150.00 300.00 In-house cost data
1 Operator (Heavy) hr 2.00 20.00 40.00 Ref: Daywork Shedule G/DS/3/K
1 Driver (Heavy) hr 2.00 20.00 40.00 Ref: Daywork Shedule G/DS/3/G
2 Labourers @ 2 hr hr 4.00 15.00 60.00 Ref: Daywork Shedule G/DS/3/A

02. Transportation from store to site (for 50nrs) m


1 Trailer hr 1.00 150.00 150.00 In-house cost data
1 Driver (Heavy) hr 1.00 20.00 20.00 Ref: Daywork Shedule G/DS/3/G

03. Unloading on site and installatino (for 50nrs) m


1 Truck Mounted Attenuator (TMA) hr 1.00 306.25 306.25 Ref: CC's Quotation
1 Crane (upto 5 tons) hr 2.00 100.00 200.00 Ref: Daywork Shedule G/DS/9/U
1 Trailer hr 2.00 150.00 300.00 In-house cost data
1 Operator (Heavy) hr 2.00 20.00 40.00 Ref: Daywork Shedule G/DS/3/K
1 Driver (Heavy) hr 2.00 20.00 40.00 Ref: Daywork Shedule G/DS/3/G
4 Labourers @ 2 hr hr 8.00 15.00 120.00 Ref: Daywork Shedule G/DS/3/A

TOTAL COST nr 50.00 360.00 1,456.25 -


UNIT RATE PER NUMBER nr 1.00 7.20 29.13 -

Page 12 of 73
Traffic Management Measures for Main Carriageway Opening

Rate Analysis for Solar Warning Light


Rate (QAR)
Item Item Description Unit Qty.
Labor Plant Materials Overhead Profit Total Rate Remarks

10.93% 4.79%
Solar Warning Light
Solar Warning Light, 2way Flashing Solar and Battery Road Refer CC's
nr 1.00 - - 31.00 3.39 1.48 35.87
Maxi Light. LPO.
Refer CC's
Installation of Solar Warning Light nr 1.00 3.34 - - 0.37 0.16 3.87
Rate

Unit Rate / nr Supply and install Solar Warning Light nr 1.00 3.34 - 31.00 3.76 1.64 39.74

Page 13 of 73
Traffic Management Measures for Main Carriageway Opening

Rate Analysis for Traffic Cone


Rate (QAR)
Item Item Description Unit Qty. Total
Labor Plant Materials Overhead Profit Remarks
Rate

10.93% 4.79%
Traffic Cone (5kg)
Supply and install Traffic Cone, Red and White, Height 1m, Refer CC's
nr 1.00 1.70 5.56 16.50
Weight 5kg LPO.

Unit Rate / nr Supply and install Traffic Cone nr 1.00 1.70 5.56 16.50 2.60 1.14 27.50

Unit Rate / nr Install Traffic Cone nr 1.00 1.70 5.56 - 0.79 0.35 8.40

Page 14 of 73
Traffic Management Measures for Main Carriageway Opening

Cost Break-down for the Installation of Trafic Cone

Labour Plant Material


S. No. Description Unit Qty Unit Cost Total Cost Unit Cost Total Cost Unit Cost Total Cost Remarks
(QAR) (QAR) (QAR) (QAR) (QAR) (QAR)

Installation of Traffic Cones (5kg)


Consider 200nrs Barriers

01. Traffic Cone, Red and White, Height 1m, Weight 5kg nr 200.00 16.50 3,300.00 Refer CC's LPO.

02. Loading from store (for 200nrs) m


1 Dump Track up to 5 tons hr 2.00 100.00 200.00 Ref: Daywork Shedule G/DS/7/R
1 Driver (Heavy) hr 2.00 20.00 40.00 Ref: Daywork Shedule G/DS/3/G
4 Labourers @ 2 hr hr 8.00 15.00 120.00 Ref: Daywork Shedule G/DS/3/A

03. Transportation from store to site (for 200nrs)


1 Dump Track up to 5 tons hr 1.00 100.00 100.00 Ref: Daywork Shedule G/DS/7/R
1 Driver (Heavy) hr 1.00 20.00 20.00 Ref: Daywork Shedule G/DS/3/G

04. Unloading on site and installatino (for 200nrs) m


1 Truck Mounted Attenuator (TMA) hr 2.00 306.25 612.50 Ref: CC's Quotation
1 Dump Track up to 5 tons hr 2.00 100.00 200.00 Ref: Daywork Shedule G/DS/7/R
1 Driver (Heavy) hr 2.00 20.00 40.00 Ref: Daywork Shedule G/DS/3/G
4 Labourers @ 2 hr hr 8.00 15.00 120.00 Ref: Daywork Shedule G/DS/3/A

TOTAL COST nr 200.00 340.00 1,112.50 3,300.00


UNIT RATE PER NUMBER nr 1.00 1.70 5.56 16.50

Page 15 of 73
Traffic Management Measures for Main Carriageway Opening

Rate Analysis for F-Shape Regid Concrete Barrier (3.04m Length), SGM 100b
Rate (QAR)
Item Item Description Unit Qty.
Labor Plant Materials Overhead Profit Total Rate

G35A/4/B Provision of concrete: Class 30/20, OPC m - - 291.40


G35A/5/B Placing of concrete: Class 30/20, OPC m 12.97 8.63 4.21
Formwork: Class F2; Vertical sides of leveling pad; width:
G32/4/A m 19.51 1.74 12.94
0.2 0.4m
G32/4/B Reinforcement t 424.08 64.49 2,664.98
Waterproofing; footing, 2 coats of approved bituminous
G4/4/B m 6.97 - 1.27
paint

10.93% 4.79%
F-Shape Regid Concrete Barrier (3.04m Length)
Precast concrete barrier Type M, Size 0.15/0.32m x 1.345m
nr 1.00 - - 1,149.12 Refer CC's LPO.
x 3.04m
Transportation Cost with the Site (Loading, Transporting
sum 1.00 17.68 24.67 -
and Unloading)
Reflective Strips m 3.00 - - 33.00

Supply and install F-Shape Regid Concrete Barrier (3.04m


Base Rate nr 1.00 17.68 24.67 1,182.12 133.83 58.65 1,416.95
Length)
Supply and install F-Shape Regid Concrete Barrier (3.04m
Base Rate m 1.00 466.10
Length)

Page 16 of 73
Contract No.: C2013/56
Project ID: IA 12/13 C/054 ST
Description: Construction of West Corridor P010 (Package 1)
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV

Subject :Traffic Management Measures for Main carriageway Opening

Stage 1 - Rate Build Ups - Traffic Signs Installation

ITEM ITEM DESCRIPTION CESMM3 UNIT QTY RATE AMOUNT Remark


Ref. (QAR) (QAR)

Traffic Management Measures for Main carriageway Opening

Traffic Signs
Supply and install temporary traffic signs including all necessary
fittings complete as detailed on Drawings and described in Qatar
Traffic Manual.

Sign Ref. R108-R


1 nr 22.00 1,230.81 27,077.83
(Size: 1200mm)

Sign Ref. R108-L


2 nr 4.00 1,230.81 4,923.24
(Size: 1200mm)

Sign Ref. T200


3 nr 9.00 1,115.09 10,035.82
(Size: 1200mm)

Sign Ref. T224 (600m)


4 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm nr 4.00 2,376.44 9,505.75
Alum. Plank)

Sign Ref. T224 (400m)


5 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. nr 3.00 2,376.44 7,129.32
Plank)

Sign Ref. T300


6 nr 13.00 970.44 12,615.73
(Size WxH: 1200 x 400mm)

Sign Ref. T223 (200m)


7 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm nr 3.00 2,376.44 7,129.32
Alum. Plank)

Sign Ref. T223 (100m)


8 nr - 1,577.97 -
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


9 nr 1 1,334.96 1,334.96
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T223 (100m)


10 nr 1 1,334.96 1,334.96
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T224 (300m)


11 Nr 2 1,577.97 3,155.94
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


12 nr 1 2,098.71 2,098.71
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (200m)


13 1 2,098.71 2,098.71
(Proposed Size WxH: 2000 x 1500mm, as per standard)
Sign Ref. T223 (100m)
14 nr 1 2,098.71 2,098.71
(Proposed Size WxH: 2000 x 1500mm, as per standard)
-
Sign Ref. T223 (100m)
15 nr 3 1,577.97 4,733.91
(Proposed Size WxH: 1200 x 1500mm, as per standard)
-
Sign Ref. T223 (200m)
16 Nr 4 1,855.70 7,422.79
(Proposed Size WxH: 1650 x 1500mm, as per standard)
-
Sign Ref. T224 (400m)
17 Nr 2 1,855.70 3,711.40
(Proposed Size WxH: 1650x 1500mm, as per standard)
-
18 Electronic Arrow Board T302 Nr 13 5,571.74 72,432.63
Sign Ref. T224 (400m)
19 Nr - -
(Proposed Size WxH: 1650x 1500mm, as per standard)

QAR. 178,839.73

Page 17 of 73
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV

Subject :Traffic Management Measures for Main carriageway Opening

Stage 1 - Rate Build Ups - Traffic Signs Installation

ITEM ITEM DESCRIPTION CESMM3 UNIT QTY RATE AMOUNT Remark


Ref. (QAR) (QAR)

Traffic Management Measures for Main carriageway Opening

Sign Ref. T223 (200m)


20 nr - -
(Proposed Size WxH: 1650 x 1500mm, as per standard)
Sign Ref. T223 (200m)
21 nr 1,577.97 -
(Proposed Size WxH: 1650 x 1500mm, as per standard)

QAR. -

Traffic Management Measures for Main carriageway Opening

Collection

Page 1 178,839.73

Page 2 -

Total Carried to Summary QAR. 178,839.73

Page 18 of 73
Temporary Traffic Signs

Contract No.: C2013/56


Project ID: IA 12/13 C/054 ST
Description: Construction of West Corridor P010 (Package 1)
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV

Subject :Traffic Management Measures for Main carriageway Opening

Stage 1 - Rate Build Ups - Traffic Signs Installation

Cost of Installation including


Sign Actual cost OH&P
Description Qty Unit ,frames,Loading & Rate (QAR)
No. (QAR) 15.72%
Supply Rate Unloading Amount
(QR) (QR)

Supply of Required Temporary Traffic Signs as per attached


Drawings, BOQ and Work Zone Traffic Management Guide
Rev.1.1:
-Sign face: 2mm / 3mm Aluminum Sheet/ 2mm Aluminum Plank
-Reflective: Type XI as per WZTMG Rev. 1.1 and with stainless steel
fasteners and extruded aluminum clamps.

Sign Ref. R108-R


1 no 450.00 613.61 1,063.61 167.20 1,230.81 -
(Size: 1200mm)

Sign Ref. R108-L


2 no 450.00 613.61 1,063.61 167.20 1,230.81 -
(Size: 1200mm)

Sign Ref. T200


3 no 350.00 613.61 963.61 151.48 1,115.09 -
(Size: 1200mm)

Sign Ref. T224 (600m)


4 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. no 1,440.00 613.61 2,053.61 322.83 2,376.44 -
Plank)

Sign Ref. T224 (400m)


5 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. no 1,440.00 613.61 2,053.61 322.83 2,376.44 -
Plank)

Sign Ref. T300


6 no 225.00 613.61 838.61 131.83 970.44 -
(Size WxH: 1200 x 400mm)

Sign Ref. T223 (200m)


7 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. no 1,440.00 613.61 2,053.61 322.83 2,376.44 -
Plank)

Sign Ref. T223 (100m)


8 no 750.00 613.61 1,363.61 214.36 1,577.97 -
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


9 no 540.00 613.61 1,153.61 181.35 1,334.96 -
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T223 (100m)


10 no 540.00 613.61 1,153.61 181.35 1,334.96 -
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T224 (300m)


11 no 750.00 613.61 1,363.61 214.36 1,577.97 -
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


12 no 1,200.00 613.61 1,813.61 285.10 2,098.71 -
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (200m)


13 no 1,200.00 613.61 1,813.61 285.10 2,098.71 -
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (100m)


14 no 1,200.00 613.61 1,813.61 285.10 2,098.71 -
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (100m)


15 no 750.00 613.61 1,363.61 214.36 1,577.97 -
(Proposed Size WxH: 1200 x 1500mm, as per standard)

Sign Ref. T223 (200m)


16 no 990.00 613.61 1,603.61 252.09 1,855.70 -
(Proposed Size WxH: 1650 x 1500mm, as per standard)

Sign Ref. T224 (400m)


17 no 990.00 613.61 1,603.61 252.09 1,855.70 -
(Proposed Size WxH: 1650x 1500mm, as per standard)

18 Electronic Arrow Board T302 no 4,201.24 613.61 4,814.85 756.89 5,571.74 -

Sign Ref. T223 (200m)


21 no 750.00 613.61 1,363.61 214.36 1,577.97 -
(Proposed Size WxH: 1250 x 1500mm, as per standard)

6/1/2017
Page 19 of 73 3/5
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign installation
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 16.00 No/day
2.00 No/hr.

A. Material Cost B. Manpower cost C. Equipment cost


Rate Total
Material Unit Qty Cost/ Unit Title Qty UF Equipment Qty UF Rate
(QR) hrly cost hrly coste
Type (QR) type hrly Total Cost

Sand bag m 4.00 0.65 2.60 Labourer 12.00 1.00 11.50 138.00 Hiab Crane 1.00 0.75 134.95 101.21
Track Mounted
Bolt & nut No. 4.00 0.40 1.60 Skilled Labour 6.00 1.00 13.00 78.00 1.00 1.00 306.25 306.25
Attenuator
Safty cone (10 Times used) No. 6.00 16.50 9.90 Hiab Crane operator 1.00 0.75 15.00 11.25
Frame No. 1.00 272.12 272.12 Driver 1.00 1.00 15.00 15.00
Micsilanious Hand tools 5.0% 5.06

Total 286.22 Total 242.25 Total 412.52

A = Material Unit Cost 286.22 QAR/No.


B = Manpower Unit Cost 242.3QR / 2.00 m2 121.13 QAR/No.
C = Equipment Unit Cost 412.5QR / 2.00 m2 206.26 QAR/No.

Direct cost of work item =


613.61 QAR/No.
A+B+C =

Total cost = 613.61 QAR/No.

UF : Utilization Factor

Page 20 of 73
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign frame production
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 4.00 No/day
0.50 No/hr.

A. Material Cost B. Manpower cost C. Equipment cost


Rate Total
Material Unit Qty Cost/ Unit Title Qty UF Equipment Qty UF Rate
(QR) hrly cost hrly coste
Type (QR) type hrly Total Cost

Hollow Section 20mm X 20mm Steel m 15.60 3.33 52.00 Welder 2.00 1.00 14.00 28.00 Portable Generator 5kv 1.00 1.00 12.38 12.38
10mm dia reinforcment Kg 0.62 3.94 2.43 Labourer 4.00 1.00 11.50 46.00 Welding Machine 1.00 1.00 20.81 20.81

Micsilanious Hand tools 5% 1.66

Total 54.43 Total 74.00 Total 34.85

A = Material Unit Cost 54.43 QAR/No.


B = Manpower Unit Cost 74QR / 0.50 Nr 148.00 QAR/No.
C = Equipment Unit Cost 35QR / 0.50 Nr 69.70 QAR/No.

Direct cost of work item = A+B+C


272.12 QAR/No.
=

Total cost = 272.12 QAR/No.

UF : Utilization Factor

Page 21 of 73
Traffic Management Measures for Main Carriageway Opening

PROJECT CODE : IA 12/13 C 054 ST


PROJECT TITLE : Construction of West Corridor P010 (Package 1)
CONTRACT NO. : C2013/56
BUDJET REF. CODE : 11320/1440913
TENDER NO. : MRPSC/006/2012-2013/L

Stage 1 : Measuremets Verified by SC


Period: From 11 March 2017 to 6 April 2017

00032 CA

00026 CA

00023 CA

00030 CA

00025 CA

00031 CA

TOTAL

NO OF
LANES
QTY.
Unit
STAGE 1 DESCRIPTION REMARKS

CC
Supply and install temporary traffice signs including all necessary fitings complete and as detailed on Drawings and describe in Qatar traffice Manual
Sign Ref. R108-R
1 (Size: 1200mm) nr 26 4.00 2.00 14.00 2.00 22.00
Sign Ref. R108-L
2 (Size: 1200mm) nr 4 - 4.00 4.00
Sign Ref. T200
3 (Size: 1200mm) nr 12 2.00 1.00 4.00 1.00 1.00 9.00

similar drawing to 00025 CA


Sign Ref. T224 (600m)
(Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm
4 Alum. Plank) nr 10 - 1.00 1.00 1.00 3.00 6 lanes
Sign Ref. T224 (600m)
(Proposed Size WxH: 1650 x 1500mm, as per standard- 2mm
5 Alum. Plank) nr 1.00 1.00 4 lanes
Sign Ref. T224 (400m)
(Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm
5 Alum. Plank) nr 6 1.00 1.00 1.00 3.00 6 lanes
Sign Ref. T300
6 (Size WxH: 1200 x 400mm) nr 15 2.00 1.00 7.00 1.00 2.00 13.00
Sign Ref. T223 (200m)
(Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm
7 Alum. Plank) nr 6 - 1.00 1.00 1.00 3.00 6 lanes
Sign Ref. T223 (100m)
8 (Proposed Size WxH: 1250 x 1500mm, as per standard) nr 2 - 3 lanes
Sign Ref. T224 (300m)
9 (Proposed Size WxH: 900 x 1500mm, as per standard) nr 1 - 1.00 1.00 2 lanes
Sign Ref. T223 (100m)
10 (Proposed Size WxH: 900 x 1500mm, as per standard) nr 2 - 1.00 1.00 2 lanes
Sign Ref. T224 (300m)
11 (Proposed Size WxH: 1250 x 1500mm, as per standard) Nr 2 - 2.00 2.00 3 lanes
Sign Ref. T224 (300m)
12 (Proposed Size WxH: 2000 x 1500mm, as per standard) nr 1 - 1.00 1.00 5 lanes
Sign Ref. T223 (200m)
13 (Proposed Size WxH: 2000 x 1500mm, as per standard) nr 2 1.00 1.00 5 lanes
Sign Ref. T223 (100m)
14 (Proposed Size WxH: 2000 x 1500mm, as per standard) nr 1 1.00 1.00 5 lanes
Sign Ref. T223 (100m)
15 (Proposed Size WxH: 1250 x 1500mm, as per standard) nr 3 2.00 1.00 3.00 3 lanes
Sign Ref. T223 (200m)
16 (Proposed Size WxH: 1650 x 1500mm, as per standard) Nr 4 2.00 2.00 4.00 4 lanes
Sign Ref. T224 (400m)
17 (Proposed Size WxH: 1650x 1500mm, as per standard) Nr 3 1.00 1.00 2.00 4 lanes
18 Electronic Arrow Board T302 Nr 15 2.00 1.00 7.00 1.00 2.00 13.00
Sign Ref. T223 (200m)
20 (Proposed Size WxH: 1650 x 1500mm, as per standard) nr - 4 lanes

BARRIERS

Installation of Precast Concret Barrier (TCB) (from temporary


1 barrier) m

2 Installation of Precast Concret Barrier (TCB) (New barrier) m

3 Installation of Polyethylene Road Safety Barrier m 160 20.00 100.00 20.00 140.00

4 Solar Panel flash light Nr 537 -

Supply and installation of Concrete Barrier Tapes (3M EGP


Reflective Sticker 200MM) (Fixing it to the facia of the concrete
5 barriers) m -

Contractor QS on
receives verbal inst from
6 Supply & Instalation Of Cones Nr 1614 1,614.00 site engineer (Henok)

Page 22 of 73
Contract No.: C2013/56
Project ID: IA 12/13 C/054 ST
Description: Construction of West Corridor P010 (Package 1)
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV

Subject :Traffic Management Measures for Main carriageway Opening

ITEM ITEM DESCRIPTION CESMM3 UNIT QTY RATE AMOUNT Remark


Ref. (QAR) (QAR)

Traffic Management Measures for Main carriageway Opening

Traffic Signs
Supply and install temporary traffic signs including all necessary
fittings complete as detailed on Drawings and described in Qatar
Traffic Manual.
Sign Ref. R108-R Only Installation
1 nr 23 710.07 16,331.62
(Size: 1200mm)

Sign Ref. R108-L Only Installation


2 nr 7.00 710.07 4,970.49
(Size: 1200mm)

Sign Ref. T200


3 nr 7.00 1,115.09 7,805.63
(Size: 1200mm)

Sign Ref. T224 (600m) Only Installation


4 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm nr 3.00 710.07 2,130.21
Alum. Plank)

Sign Ref. T224 (400m)


5 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. nr 1.00 2,376.44 2,376.44
Plank)

Sign Ref. T300


6 nr 14.00 970.44 13,586.17
(Size WxH: 1200 x 400mm)

Sign Ref. T223 (200m) Only Installation


7 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm nr 1.00 710.07 710.07
Alum. Plank)

Sign Ref. T223 (100m)


8 nr - 1,577.97 0.00
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T223 (100m) Only installation


nr - 710.07 0.00
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


9 nr 0 1,334.96 0.00
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T224 (300m) Only installation


nr 1 710.07 710.07
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T223 (100m)


10 nr 2 1,334.96 2,669.92
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T223 (100m) Only installation


nr 1 710.07 710.07
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T224 (300m)


11 Nr 710.07 0.00
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


12 nr 710.07 0.00
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (200m)


13 710.07 0.00
(Proposed Size WxH: 2000 x 1500mm, as per standard)
Sign Ref. T223 (100m) Only installation
14 nr 1 710.07 710.07
(Proposed Size WxH: 2000 x 1500mm, as per standard)
-
Sign Ref. T223 (100m) Only installation
15 nr 3 710.07 2,130.21
(Proposed Size WxH: 1200 x 1500mm, as per standard)
-
Sign Ref. T223 (200m) Only installation
16 Nr 3 710.07 2,130.21
(Proposed Size WxH: 1650 x 1500mm, as per standard)
-
Sign Ref. T224 (400m) Only installation
17 Nr 3 710.07 2,130.21
(Proposed Size WxH: 1650x 1500mm, as per standard)
QAR. 59,101.41

Page 23 of 73
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV

Subject :Traffic Management Measures for Main carriageway Opening

ITEM ITEM DESCRIPTION CESMM3 UNIT QTY RATE AMOUNT Remark


Ref. (QAR) (QAR)

Traffic Management Measures for Main carriageway Opening

-
18 Electronic Arrow Board T302 Only installation Nr 14 710.07 9,940.99
Sign Ref. PR0.001 (Proposed Size WxH: 1650x 1500mm, as per
19 Nr 1 1,855.70 1,855.70
standard)
Sign Ref. PR0.002 (Proposed Size WxH: 1650x 1500mm, as per
20 nr 1 1,855.70 1,855.70
standard)
Sign Ref. (100m)
21 nr - 710.07 0.00
(Proposed Size WxH: 1200 x 1500mm, as per standard)
Sign Ref. "NEW ROAD LAYOUT AHEAD"
22 nr - 710.07 0.00
(Proposed Size WxH: 1200 x 1500mm, as per standard)
Sign Ref. 100
23 nr - 710.07 0.00
(Size: 1200mm)
Sign Ref. Give Way
24 nr - 710.07 0.00
(Size: 1200mm)

QAR. 13,652.39

Traffic Management Measures for Main carriageway Opening

Collection

Supply and Installation


Page 1 26,438.16
Page 2 3,711.40
30,149.56
Installation Only
Page 1 32,663.25
Page 2 9,940.98
42,604.23

Page 24 of 73
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV

Subject :Traffic Management Measures for Main carriageway Opening

ITEM ITEM DESCRIPTION CESMM3 UNIT QTY RATE AMOUNT Remark


Ref. (QAR) (QAR)

Total Carried to Summary QAR. 145,507.56

Page 25 of 73
Temporary Traffic Signs

Cost of Installation including


Sign Actual cost OH&P
Description Qty Unit ,frames,Loading & Rate (QAR)
No. (QAR) 15.72%
Supply Rate Unloading Amount
(QR) (QR)

Supply of Required Temporary Traffic Signs as per attached


Drawings, BOQ and Work Zone Traffic Management Guide
Rev.1.1:
-Sign face: 2mm / 3mm Aluminum Sheet/ 2mm Aluminum Plank
-Reflective: Type XI as per WZTMG Rev. 1.1 and with stainless steel
fasteners and extruded aluminum clamps.

Sign Ref. R108-R


1 no 613.61 613.61 96.46 710.07 -
(Size: 1200mm)

Sign Ref. R108-L


2 no 613.61 613.61 96.46 710.07 -
(Size: 1200mm)

Sign Ref. T200


3 no 350.00 613.61 963.61 151.48 1,115.09 -
(Size: 1200mm)

Sign Ref. T224 (600m)


4 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. no 613.61 613.61 96.46 710.07 -
Plank)

Sign Ref. T224 (400m)


5 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. no 1,440.00 613.61 2,053.61 322.83 2,376.44 -
Plank)

Sign Ref. T300


6 no 225.00 613.61 838.61 131.83 970.44 -
(Size WxH: 1200 x 400mm)

Sign Ref. T223 (200m)


7 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. no 613.61 613.61 96.46 710.07 -
Plank)

Sign Ref. T223 (100m)


8 no 750.00 613.61 1,363.61 214.36 1,577.97 -
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T223 (100m) Only installation


613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


9 no 540.00 613.61 1,153.61 181.35 1,334.96 -
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T224 (300m) Only installation


613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T223 (100m)


10 no 540.00 613.61 1,153.61 181.35 1,334.96 -
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T223 (100m) Only installation


no 613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T224 (300m)


11 no 613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


12 no 613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (200m)


13 no 613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (100m) Only installation


14 no 613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (100m) Only installation


15 no 613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 1200 x 1500mm, as per standard)

Sign Ref. T223 (200m) Only installation


16 no 613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 1650 x 1500mm, as per standard)

Sign Ref. T224 (400m) Only installation


17 no 613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 1650x 1500mm, as per standard)

18 Electronic Arrow Board T302 Only installation no 613.61 613.61 96.46 710.07 -

Sign Ref. T224 (400m)


19 no 613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 1650x 1500mm, as per standard)

Sign Ref. T223 (200m)


20 no 990.00 613.61 1,603.61 252.09 1,855.70 -
(Proposed Size WxH: 1650 x 1500mm, as per standard)

Sign Ref. T223 (200m)


21 no 750.00 613.61 1,363.61 214.36 1,577.97 -
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Barriers

6/1/2017
Page 26 of 73 4/7
Temporary Traffic Signs

Cost of Installation including


Sign Actual cost OH&P
Description Qty Unit ,frames,Loading & Rate (QAR)
No. (QAR) 15.72%
Supply Rate Unloading Amount
(QR) (QR)

Installation of Precast Concret Barrier (0.15/0.32m X 1.345 X 3.04) m

Installation of Polyethylene Road Safety Barrier 2M Long m

2 way flashing Solar and Battery road maxi light 1285 nr 42.29

2 way flashing Solar and Battery road maxi light Only installation 537 3.87

Supply & Installation of Safty Cones 4665 nr 31.77 4.99 36.76

Safty Cones Only installation 1614 14.10 2.22 16.32

Traffic study for the proposed work sum

Rumble strips sum 55.00 8.65 63.65

3M EGP Reflective Sticker nr 11.52 1.81 13.33

LED Solar Powered Variable Message Signs (VMS) Signs (VMS) nr 64,000.00 10,060.80 74,060.80

Road Safety Audits at Two Stages

Stage 3 for detailed design (Review of Shop Drawings) nr 5,000.00 786.00 5,786.00

Stage 4 for pre-opening (Actual Road Inspection) nr 12,000.00 1,886.40 13,886.40

6/1/2017
Page 27 of 73 5/7
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign installation
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 16.00 No/day
2.00 No/hr.

A. Material Cost B. Manpower cost C. Equipment cost


Rate Total
Material Unit Qty Cost/ Unit Title Qty UF Equipment Qty UF Rate
(QR) hrly cost hrly coste
Type (QR) type hrly Total Cost

Sand bag m 4.00 0.65 2.60 Labourer 12.00 1.00 11.50 138.00 Hiab Crane 1.00 0.75 134.95 101.21
Track Mounted
Bolt & nut No. 4.00 0.40 1.60 Skilled Labour 6.00 1.00 13.00 78.00 1.00 1.00 306.25 306.25
Attenuator
Safty cone (10 Times used) No. 6.00 16.50 9.90 Hiab Crane operator 1.00 0.75 15.00 11.25
Frame No. 1.00 272.12 272.12 Driver 1.00 1.00 15.00 15.00
Micsilanious Hand tools 5.0% 5.06

Total 286.22 Total 242.25 Total 412.52

A = Material Unit Cost 286.22 QAR/No.


B = Manpower Unit Cost 242.3QR / 2.00 m2 121.13 QAR/No.
C = Equipment Unit Cost 412.5QR / 2.00 m2 206.26 QAR/No.

Direct cost of work item =


613.61 QAR/No.
A+B+C =

Total cost = 613.61 QAR/No.

UF : Utilization Factor

Page 28 of 73
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign frame production
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 4.00 No/day
0.50 No/hr.

A. Material Cost B. Manpower cost C. Equipment cost


Rate Total
Material Unit Qty Cost/ Unit Title Qty UF Equipment Qty UF Rate
(QR) hrly cost hrly coste
Type (QR) type hrly Total Cost

Hollow Section 20mm X 20mm Steel m 15.60 3.33 52.00 Welder 2.00 1.00 14.00 28.00 Portable Generator 5kv 1.00 1.00 12.38 12.38
10mm dia reinforcment Kg 0.62 3.94 2.43 Labourer 4.00 1.00 11.50 46.00 Welding Machine 1.00 1.00 20.81 20.81

Micsilanious Hand tools 5% 1.66

Total 54.43 Total 74.00 Total 34.85

A = Material Unit Cost 54.43 QAR/No.


B = Manpower Unit Cost 74QR / 0.50 Nr 148.00 QAR/No.
C = Equipment Unit Cost 35QR / 0.50 Nr 69.70 QAR/No.

Direct cost of work item = A+B+C


272.12 QAR/No.
=

Total cost = 272.12 QAR/No.

UF : Utilization Factor

Page 29 of 73
Contract No.: C2013/56
Project ID: IA 12/13 C/054 ST
Description: Construction of West Corridor P010 (Package 1)
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV

Subject :Traffic Management Measures for Main carriageway Opening

ITEM ITEM DESCRIPTION CESMM3 UNIT QTY RATE AMOUNT Remark


Ref. (QAR) (QAR)

Traffic Management Measures for Main carriageway Opening

Traffic Signs
Removal temporary traffic signs including all necessary fittings
complete as detailed on Drawings and described in Qatar Traffic
Manual.

Sign Ref. R108-R


1 nr 26 378.85 9,850.14
(Size: 1200mm)

Sign Ref. R108-L


2 nr 4.00 378.85 1,515.41
(Size: 1200mm)

Sign Ref. T200


3 nr 13.00 378.85 4,925.07
(Size: 1200mm)

Sign Ref. T224 (600m)


4 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm nr 2.00 378.85 757.70
Alum. Plank)

Sign Ref. T224 (400m)


5 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. nr 2.00 378.85 757.70
Plank)

Sign Ref. T300


6 nr 14.00 378.85 5,303.92
(Size WxH: 1200 x 400mm)

Sign Ref. T223 (200m)


7 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm nr 2.00 378.85 757.70
Alum. Plank)

Sign Ref. T223 (100m)


8 nr 2.00 378.85 757.70
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T223 (100m)


nr 4.00 378.85 1,515.41
(Proposed Size WxH: 1250 x 1500mm, as per standard)
Sign Ref. T224 (300m)
9 nr 2 378.85 757.70
(Proposed Size WxH: 900 x 1500mm, as per standard)
Sign Ref. T224 (300m)
nr 1 378.85 378.85
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T223 (100m)


10 nr 3 378.85 1,136.56
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T223 (100m)


nr 2 378.85 757.70
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T224 (300m)


11 Nr 378.85 0.00
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


12 nr 378.85 0.00
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (200m)


13 378.85 0.00
(Proposed Size WxH: 2000 x 1500mm, as per standard)
Sign Ref. T223 (100m)
14 nr 1 378.85 378.85
(Proposed Size WxH: 2000 x 1500mm, as per standard)
-
Sign Ref. T223 (100m)
15 nr 1 378.85 378.85
(Proposed Size WxH: 1200 x 1500mm, as per standard)
-
Sign Ref. T223 (200m)
16 Nr 3 378.85 1,136.56
(Proposed Size WxH: 1650 x 1500mm, as per standard)
-
Sign Ref. T224 (400m)
17 Nr 3 378.85 1,136.56
(Proposed Size WxH: 1650x 1500mm, as per standard)
QAR. 32,202.40

Page 30 of 73
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV

Subject :Traffic Management Measures for Main carriageway Opening

ITEM ITEM DESCRIPTION CESMM3 UNIT QTY RATE AMOUNT Remark


Ref. (QAR) (QAR)

Traffic Management Measures for Main carriageway Opening

-
18 Electronic Arrow Board T302 Nr 14 378.85 5,303.92
Sign Ref. PR0.001 (Proposed Size WxH: 1650x 1500mm, as per
19 Nr 2 378.85 757.70
standard)
Sign Ref. PR0.002 (Proposed Size WxH: 1650x 1500mm, as per
20 nr 4 378.85 1,515.41
standard)
Sign Ref. (100m)
21 nr 4.00 378.85 1,515.41
(Proposed Size WxH: 1200 x 1500mm, as per standard)
Sign Ref. "NEW ROAD LAYOUT AHEAD"
22 nr 4.00 378.85 1,515.41
(Proposed Size WxH: 1200 x 1500mm, as per standard)
Sign Ref. 100
23 nr 36.00 378.85 13,638.66
(Size: 1200mm)
Sign Ref. Give Way
24 nr 8.00 378.85 3,030.81
(Size: 1200mm)

QAR. 27,277.32

Traffic Management Measures for Main carriageway Opening

Collection

Page 1 32,202.40

Page 2 27,277.32

Total Carried to Summary QAR. 59,479.72

Page 31 of 73
Contract No.: C2013/56
Project ID: IA 12/13 C/054 ST
Description: Construction of West Corridor P010 (Package 1)
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV

Subject :Traffic Management Measures for Main carriageway Opening

ITEM ITEM DESCRIPTION CESMM3 UNIT QTY RATE AMOUNT Remark


Ref. (QAR) (QAR)

Traffic Management Measures for Main carriageway Opening

BARRIERS

1 Solar Panel flash light Nr 1,285.00 3.87 4,972.95

2 Solar Panel flash light Nr 537.00 3.87 2,078.19

#REF! QAR. 7,051.14

Traffic Management Measures for Main carriageway Opening

Collection

Page 1 7,051.14

Total Carried to Summary QAR. 7,051.14

Page 32 of 73
Temporary Traffic Signs

Cost of Installation including


Sign Actual cost OH&P
Description Qty Unit ,frames,Loading & Rate (QAR)
No. (QAR) 15.72%
Supply Rate Unloading Amount
(QR) (QR)

Supply of Required Temporary Traffic Signs as per attached


Drawings, BOQ and Work Zone Traffic Management Guide
Rev.1.1:
-Sign face: 2mm / 3mm Aluminum Sheet/ 2mm Aluminum Plank
-Reflective: Type XI as per WZTMG Rev. 1.1 and with stainless steel
fasteners and extruded aluminum clamps.

Sign Ref. R108-R


1 26 no 327.39 327.39 51.47 378.85 9,850.14
(Size: 1200mm)

Sign Ref. R108-L


2 4 no 327.39 327.39 51.47 378.85 1,515.41
(Size: 1200mm)

Sign Ref. T200


3 13 no 327.39 327.39 51.47 378.85 4,925.07
(Size: 1200mm)

Sign Ref. T224 (600m)


4 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. 2 no 327.39 327.39 51.47 378.85 757.70
Plank)

Sign Ref. T224 (400m)


5 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. 2 no 327.39 327.39 51.47 378.85 757.70
Plank)

Sign Ref. T300


6 14 no 327.39 327.39 51.47 378.85 5,303.92
(Size WxH: 1200 x 400mm)

Sign Ref. T223 (200m)


7 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. 2 no 327.39 327.39 51.47 378.85 757.70
Plank)

Sign Ref. T223 (100m)


8 2 no 327.39 327.39 51.47 378.85 757.70
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T223 (100m) Only installation


4 327.39 327.39 51.47 378.85 1,515.41
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


9 1 no 327.39 327.39 51.47 378.85 378.85
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T224 (300m) Only installation


1 327.39 327.39 51.47 378.85 378.85
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T223 (100m)


10 3 no 327.39 327.39 51.47 378.85 1,136.56
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T223 (100m) Only installation


2 no 327.39 327.39 51.47 378.85 757.70
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T224 (300m)


11 no 327.39 327.39 51.47 378.85 -
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


12 no 327.39 327.39 51.47 378.85 -
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (200m)


13 no 327.39 327.39 51.47 378.85 -
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (100m) Only installation


14 1 no 327.39 327.39 51.47 378.85 378.85
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (100m) Only installation


15 1 no 327.39 327.39 51.47 378.85 378.85
(Proposed Size WxH: 1200 x 1500mm, as per standard)

Sign Ref. T223 (200m) Only installation


16 3 no 327.39 327.39 51.47 378.85 1,136.56
(Proposed Size WxH: 1650 x 1500mm, as per standard)

Sign Ref. T224 (400m) Only installation


17 3 no 327.39 327.39 51.47 378.85 1,136.56
(Proposed Size WxH: 1650x 1500mm, as per standard)

18 Electronic Arrow Board T302 Only installation 14 no 327.39 327.39 51.47 378.85 5,303.92

Sign Ref. T224 (400m)


19 no 327.39 327.39 51.47 378.85 -
(Proposed Size WxH: 1650x 1500mm, as per standard)

Sign Ref. T223 (200m)


20 no 327.39 327.39 51.47 378.85 -
(Proposed Size WxH: 1650 x 1500mm, as per standard)

Sign Ref. T223 (200m)


21 no 327.39 327.39 51.47 378.85 -
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Barriers

6/1/2017
Page 33 of 73 4/8
Temporary Traffic Signs

Cost of Installation including


Sign Actual cost OH&P
Description Qty Unit ,frames,Loading & Rate (QAR)
No. (QAR) 15.72%
Supply Rate Unloading Amount
(QR) (QR)

Installation of Precast Concret Barrier (0.15/0.32m X 1.345 X 3.04) m

Installation of Polyethylene Road Safety Barrier 2M Long m

2 way flashing Solar and Battery road maxi light 1285 nr 3.87

2 way flashing Solar and Battery road maxi light Only installation 537 3.87

Supply & Installation of Safty Cones 4665 nr 14.10 2.22 16.31

Safty Cones Only installation 1614 14.10 2.22 16.31

Traffic study for the proposed work sum

Rumble strips sum 55.00 8.65 63.65

3M EGP Reflective Sticker nr 11.52 1.81 13.33

LED Solar Powered Variable Message Signs (VMS) Signs (VMS) nr 64,000.00 10,060.80 74,060.80

Road Safety Audits at Two Stages

Stage 3 for detailed design (Review of Shop Drawings) nr 5,000.00 786.00 5,786.00

Stage 4 for pre-opening (Actual Road Inspection) nr 12,000.00 1,886.40 13,886.40

6/1/2017
Page 34 of 73 5/8
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign Removal
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 16.00 No/day
2.00 No/hr.

A. Material Cost B. Manpower cost C. Equipment cost


Rate Total
Material Unit Qty Cost/ Unit Title Qty UF Equipment Qty UF Rate
(QR) hrly cost hrly coste
Type (QR) type hrly Total Cost

Sand bag m - Labourer 12.00 1.00 11.50 138.00 Hiab Crane 1.00 0.75 134.95 101.21
Track Mounted
Bolt & nut No. - Skilled Labour 6.00 1.00 13.00 78.00 1.00 1.00 306.25 306.25
Attenuator
Safty cone (10 Times used) No. - Hiab Crane operator 1.00 0.75 15.00 11.25
Frame No. - Driver 1.00 1.00 15.00 15.00
Micsilanious Hand tools 5.0% 5.06

Total 0.00 Total 242.25 Total 412.52

A = Material Unit Cost 0.00 QAR/No.


B = Manpower Unit Cost 242.3QR / 2.00 m2 121.13 QAR/No.
C = Equipment Unit Cost 412.5QR / 2.00 m2 206.26 QAR/No.

Direct cost of work item =


327.39 QAR/No.
A+B+C =

Total cost = 327.39 QAR/No.

UF : Utilization Factor

Page 35 of 73
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign frame production
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 4.00 No/day
0.50 No/hr.

A. Material Cost B. Manpower cost C. Equipment cost


Rate Total
Material Unit Qty Cost/ Unit Title Qty UF Equipment Qty UF Rate
(QR) hrly cost hrly coste
Type (QR) type hrly Total Cost

Hollow Section 20mm X 20mm Steel m 15.60 3.33 52.00 Welder 2.00 1.00 14.00 28.00 Portable Generator 5kv 1.00 1.00 12.38 12.38
10mm dia reinforcment Kg 0.62 3.94 2.43 Labourer 4.00 1.00 11.50 46.00 Welding Machine 1.00 1.00 20.81 20.81

Micsilanious Hand tools 5% 1.66

Total 54.43 Total 74.00 Total 34.85

A = Material Unit Cost 54.43 QAR/No.


B = Manpower Unit Cost 74QR / 0.50 Nr 148.00 QAR/No.
C = Equipment Unit Cost 35QR / 0.50 Nr 69.70 QAR/No.

Direct cost of work item = A+B+C


272.12 QAR/No.
=

Total cost = 272.12 QAR/No.

UF : Utilization Factor

Page 36 of 73
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Removal 2 way flashing Solar and Battery road maxi light
- Traffic Management Measures
BOQ Qty: 1,822.00 No
Performance rate : 55.00 No/day
6.88 No/hr.

A. Material Cost B. Manpower cost C. Equipment cost


Rate Total
Material Unit Qty Cost/ Unit Title Qty UF Equipment Qty UF Rate
(QR) hrly cost hrly coste
Type (QR) type hrly Total Cost

2 way flashing Solar and


No 1.00 - Labourer 2.00 1.00 11.50 23.00
Battery road maxi light

loading and unloading 2% 0.00

Micsilanious Hand tools 5% 0.00

Total 0.00 Total 23.00 Total 0.00

A = Material Unit Cost 0.00 QAR/No.


B = Manpower Unit Cost 23QR / 6.88 Nr 3.35 QAR/No.
C = Equipment Unit Cost .0QR / 6.88 Nr 0.00 QAR/No.

Direct cost of work item =


3.35 QAR/No.
A+B+C =

OH&P 15.72% 0.53 QAR

Total cost = 3.87 QAR/No.

UF : Utilization Factor

Page 37 of 73
Traffic Management Measures for Main Carriageway Opening

PROJECT CODE : IA 12/13 C 054 ST


PROJECT TITLE : Construction of West Corridor P010 (Package 1)
CONTRACT NO. : C2013/56
BUDJET REF. CODE : 11320/1440913
TENDER NO. : MRPSC/006/2012-2013/L

Stage 2 : Measuremets Verified by SC


Period: From 6 April 2017 to 21 April 2017

00032 CA

00026 CA

00023 CA

00030 CA

00025 CA

00031 CA

TOTAL

NO OF
LANES
QTY.
Unit
STAGE 2 DESCRIPTION REMARKS

CC
Supply and install temporary traffic signs including all necessary fittings complete as detailed on Drawings and described in Qatar Traffic Manual.
-
Sign Ref. R108-R Only Installation
1 (Size: 1200mm) nr 26 2.00 1.00 12.00 2.00 6.00 23.00
Sign Ref. R108-L Only Installation
2 (Size: 1200mm) nr 4 4.00 2.00 1.00 7.00
Sign Ref. T200
3 (Size: 1200mm) nr 13 2.00 1.00 2.00 1.00 1.00 7.00
Sign Ref. T224 (600m) Only Installation
(Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum.
4 Plank) nr 2 1.00 1.00 6 lanes

Sign Ref. T224 (600m)


(Proposed Size WxH: 1650 x 1500mm, as per standard- 2mm Alum.
Plank) nr 2.00 2.00 4 lanes
Sign Ref. T224 (400m) Only installation
(Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum.
5 Plank) nr 2 1.00 1.00 6 lanes
Sign Ref. T300
6 (Size WxH: 1200 x 400mm) nr 14 3.00 1.00 6.00 1.00 3.00 14.00
Sign Ref. T223 (200m) Only Installation
(Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum.
7 Plank) nr 2 1.00 1.00 6 lanes
Sign Ref. T223 (100m)
8 (Proposed Size WxH: 1250 x 1500mm, as per standard) nr 2 - 3 lanes
Sign Ref. T223 (100m) Only installation
(Proposed Size WxH: 1250 x 1500mm, as per standard) nr 4 - 3 lanes
Sign Ref. T224 (300m)
9 (Proposed Size WxH: 900 x 1500mm, as per standard) nr 2 - 2 lanes
Sign Ref. T224 (300m) Only installation
(Proposed Size WxH: 900 x 1500mm, as per standard) nr 1 1.00 1.00 2 lanes
Sign Ref. T223 (100m)
10 (Proposed Size WxH: 900 x 1500mm, as per standard) nr 3 1.00 1.00 2.00 2 lanes
Sign Ref. T223 (100m) Only installation
(Proposed Size WxH: 900 x 1500mm, as per standard) nr 2 1.00 1.00 2 lanes
Sign Ref. T224 (300m)
11 (Proposed Size WxH: 1250 x 1500mm, as per standard) nr 2.00 2.00 3 lanes
Sign Ref. T224 (300m)
12 (Proposed Size WxH: 2000 x 1500mm, as per standard) nr - 5 lanes
Sign Ref. T223 (200m)
13 (Proposed Size WxH: 2000 x 1500mm, as per standard) - 5 lanes
Sign Ref. T223 (100m) Only installation
14 (Proposed Size WxH: 2000 x 1500mm, as per standard) nr 1 1.00 1.00 5 lanes
Sign Ref. T223 (100m) Only installation
15 (Proposed Size WxH: 1250 x 1500mm, as per standard) nr 1 1.00 2.00 3.00 3 lanes
Sign Ref. T223 (200m) Only installation
16 (Proposed Size WxH: 1650 x 1500mm, as per standard) nr 3 1.00 1.00 1.00 3.00 4 lanes
Sign Ref. T224 (400m) Only installation
17 (Proposed Size WxH: 1650x 1500mm, as per standard) nr 3 3.00 3.00 4 lanes
18 Electronic Arrow Board T302 Only installation nr 14 3.00 1.00 6.00 1.00 3.00 14.00
Sign Ref. PR0.001 (Proposed Size WxH: 1650x 1500mm, as per
19 standard) nr 2 1.00 1.00
Sign Ref. PR0.002 (Proposed Size WxH: 1650x 1500mm, as per
20 standard) nr 4 1.00 1.00
Sign Ref. (100m)
21 (Proposed Size WxH: 1200 x 1500mm, as per standard) nr 4 -
Sign Ref. "NEW ROAD LAYOUT AHEAD"
22 (Proposed Size WxH: 1200 x 1500mm, as per standard) nr 4 -
Sign Ref. 100
23 (Size: 1200mm) nr 36 -
Sign Ref. Give Way
24 (Size: 1200mm) nr 8 -

Page 38 of 73
Traffic Management Measures for Main Carriageway Opening

PROJECT CODE : IA 12/13 C 054 ST


PROJECT TITLE : Construction of West Corridor P010 (Package 1)
CONTRACT NO. : C2013/56
BUDJET REF. CODE : 11320/1440913
TENDER NO. : MRPSC/006/2012-2013/L

Stage 2 : Measuremets Verified by SC


Period: From 6 April 2017 to 21 April 2017

00032 CA

00026 CA

00023 CA

00030 CA

00025 CA

00031 CA

TOTAL

NO OF
LANES
QTY.
Unit
STAGE 2 DESCRIPTION REMARKS

CC
BARRIERS

1 Installation of Precast Concret Barrier (TCB) (from temporary barrier) m -


2 Installation of Precast Concret Barrier (TCB) (New barrier) m -
3 Installation of Polyethylene Road Safety Barrier m -
4 Solar Panel flash light nr 1285 -
5 Solar Panel flash light Only installation 537 -
6 Supply and installation of Concrete Barrier Tapes (3M EGP Reflective
Sticker 200MM) (Fixing it to the facia of the concrete barriers)
m -
Contractor QS on
receives verbal inst
from site engineer
7 Supply & Instalation Of Cones nr 4665 4,665.00 (Henok)
-
Contractor QS on
receives verbal inst
from site engineer
8 Safty Cones Only installation nr 1614 1,614.00 (Henok)
-

Page 39 of 73
Contract No.: C2013/56
Project ID: IA 12/13 C/054 ST
Description: Construction of West Corridor P010 (Package 1)
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV

Subject :Traffic Management Measures for Future Opening

ITEM ITEM DESCRIPTION CESMM3 UNIT QTY Rate AMOUNT Remark


Ref. (QAR) (QAR)

Traffic Management Measures for Main carriageway


Opening
Traffic Signs
Supply and install temporary traffic signs including all necessary
fittings complete as detailed on Drawings and described in Qatar
Traffic Manual.
Sign Ref. R108-R Only Installation
1 nr 10.00 1,420.14 14,201.41
(Size: 1200mm)
Sign Ref. R108-L Only Installation
2 nr 4.00 710.07 2,840.28
(Size: 1200mm)
Sign Ref. T200 Only Installation
3 nr 5.00 710.07 3,550.35
(Size: 1200mm)
Sign Ref. T224 (600m) Only Installation
4 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm nr 2.00 710.07 1,420.14
Alum. Plank)

Sign Ref. T224 (400m)


5 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. nr - 710.07 0.00
Plank)

Sign Ref. T300 Only Installation


6 nr 7.00 710.07 4,970.49
(Size WxH: 1200 x 400mm)

Sign Ref. T223 (200m) Only Installation


7 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm nr 710.07 0.00
Alum. Plank)
Sign Ref. T223 (100m)
8 nr 5.00 1,420.14 7,100.71
(Proposed Size WxH: 1250 x 1500mm, as per standard)
Sign Ref. T223 (100m) Only installation nr 710.07 0.00
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


9 nr 710.07 0.00
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T224 (300m) Only installation


nr 1 710.07 710.07
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T223 (100m)


10 nr 710.07 0.00
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T223 (100m) Only installation


nr 1 710.07 710.07
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T224 (300m) Only installation


11 nr 2 710.07 1,420.14
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


12 nr 710.07 0.00
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (200m)


13 710.07 0.00
(Proposed Size WxH: 2000 x 1500mm, as per standard)
Sign Ref. T223 (100m) Only installation
14 nr 710.07 0.00
(Proposed Size WxH: 2000 x 1500mm, as per standard)
-
Sign Ref. T223 (100m) Only installation
15 nr 3 710.07 2,130.21
(Proposed Size WxH: 1200 x 1500mm, as per standard)
-
Sign Ref. T223 (200m) Only installation
16 nr 2 710.07 1,420.14
(Proposed Size WxH: 1650 x 1500mm, as per standard)
-
Sign Ref. T224 (400m) Only installation
17 nr 3 710.07 2,130.21
(Proposed Size WxH: 1650x 1500mm, as per standard)
QAR. 42,604.24

Page 40 of 73
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV

Subject :Traffic Management Measures for Future Opening

ITEM ITEM DESCRIPTION CESMM3 UNIT QTY Rate AMOUNT Remark


Ref. (QAR) (QAR)

Traffic Management Measures for Main carriageway Opening

18 Electronic Arrow Board T302 Only installation Nr 8 710.07 5,680.56


Sign Ref. PR0.001 (Proposed Size WxH: 1650x 1500mm, as per
19 Nr 710.07 0.00
standard)
Sign Ref. PR0.002 (Proposed Size WxH: 1650x 1500mm, as per
20 nr 710.07 0.00
standard)
Sign Ref. (100m)
21 nr 710.07 0.00
(Proposed Size WxH: 1200 x 1500mm, as per standard)
Sign Ref. "NEW ROAD LAYOUT AHEAD"
22 nr 710.07 0.00
(Proposed Size WxH: 1200 x 1500mm, as per standard)
Sign Ref. 80km/hr
23 nr - 1,420.14 0.00
(Size: 1200mm)
Sign Ref. Give Way
24 nr 1,420.14 0.00
(Size: 1200mm)

QAR. 5,680.56

Page 41 of 73
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV

Subject :Traffic Management Measures for Future Opening

ITEM ITEM DESCRIPTION CESMM3 UNIT QTY Rate AMOUNT Remark


Ref. (QAR) (QAR)

Traffic Management Measures for Main carriageway Opening

Collection

Page 1 42,604.24

Page 2 5,680.56

Supply and Installation


Page 1 7,100.71
Page 2 0.00
7,100.71
Installation Only
Page 1 35,503.53
Page 2 5,680.55
41,184.08

Total Carried to Summary QAR. 144,854.38

Page 42 of 73
Temporary Traffic Signs

Cost of Installation including


Sign Actual cost OH&P
Description Qty Unit ,frames,Loading & Rate (QAR)
No. (QAR) 15.72%
Supply Rate Unloading Amount
(QR) (QR)

Supply of Required Temporary Traffic Signs as per attached


Drawings, BOQ and Work Zone Traffic Management Guide
Rev.1.1:
-Sign face: 2mm / 3mm Aluminum Sheet/ 2mm Aluminum Plank
-Reflective: Type XI as per WZTMG Rev. 1.1 and with stainless steel
fasteners and extruded aluminum clamps.

Sign Ref. R108-R


1 10 no 613.61 613.61 1,227.22 192.92 1,420.14 14,201.41
(Size: 1200mm)

Sign Ref. R108-L


2 4 no 613.61 613.61 96.46 710.07 2,840.28
(Size: 1200mm)

Sign Ref. T200


3 13 no 613.61 613.61 96.46 710.07 9,230.92
(Size: 1200mm)

Sign Ref. T224 (600m)


4 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. 2 no 613.61 613.61 96.46 710.07 1,420.14
Plank)

Sign Ref. T224 (400m)


5 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. 2 no 613.61 613.61 96.46 710.07 1,420.14
Plank)

Sign Ref. T300 Only installation


6 14 no 613.61 613.61 96.46 710.07 9,940.99
(Size WxH: 1200 x 400mm)

Sign Ref. T223 (200m)


7 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. 2 no 613.61 613.61 96.46 710.07 1,420.14
Plank)

Sign Ref. T223 (100m)


8 2 no 613.61 613.61 96.46 710.07 1,420.14
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T223 (100m) Only installation


4 613.61 613.61 96.46 710.07 2,840.28
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


9 1 no 613.61 613.61 96.46 710.07 710.07
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T224 (300m) Only installation


1 613.61 613.61 96.46 710.07 710.07
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T223 (100m)


10 3 no 613.61 613.61 96.46 710.07 2,130.21
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T223 (100m) Only installation


2 no 613.61 613.61 96.46 710.07 1,420.14
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T224 (300m)


11 no 613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


12 no 613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (200m)


13 no 613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (100m) Only installation


14 1 no 613.61 613.61 96.46 710.07 710.07
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (100m) Only installation


15 1 no 613.61 613.61 96.46 710.07 710.07
(Proposed Size WxH: 1200 x 1500mm, as per standard)

Sign Ref. T223 (200m) Only installation


16 3 no 613.61 613.61 96.46 710.07 2,130.21
(Proposed Size WxH: 1650 x 1500mm, as per standard)

Sign Ref. T224 (400m) Only installation


17 3 no 613.61 613.61 96.46 710.07 2,130.21
(Proposed Size WxH: 1650x 1500mm, as per standard)

18 Electronic Arrow Board T302 Only installation 14 no 613.61 613.61 96.46 710.07 9,940.99

Sign Ref. T224 (400m)


19 no 613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 1650x 1500mm, as per standard)

Sign Ref. T223 (200m)


20 no 613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 1650 x 1500mm, as per standard)

Sign Ref. T223 (200m)


21 no 613.61 613.61 96.46 710.07 -
(Proposed Size WxH: 1250 x 1500mm, as per standard)

6/1/2017
Page 43 of 73 4/6
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign installation
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 16.00 No/day
2.00 No/hr.

A. Material Cost B. Manpower cost C. Equipment cost


Rate Total
Material Unit Qty Cost/ Unit Title Qty UF Equipment Qty UF Rate
(QR) hrly cost hrly coste
Type (QR) type hrly Total Cost

Sand bag m 4.00 0.65 2.60 Labourer 12.00 1.00 11.50 138.00 Hiab Crane 1.00 0.75 134.95 101.21
Track Mounted
Bolt & nut No. 4.00 0.40 1.60 Skilled Labour 6.00 1.00 13.00 78.00 1.00 1.00 306.25 306.25
Attenuator
Safty cone (10 Times used) No. 6.00 16.50 9.90 Hiab Crane operator 1.00 0.75 15.00 11.25
Frame No. 1.00 272.12 272.12 Driver 1.00 1.00 15.00 15.00
Micsilanious Hand tools 5.0% 5.06

Total 286.22 Total 242.25 Total 412.52

A = Material Unit Cost 286.22 QAR/No.


B = Manpower Unit Cost 242.3QR / 2.00 m2 121.13 QAR/No.
C = Equipment Unit Cost 412.5QR / 2.00 m2 206.26 QAR/No.

Direct cost of work item =


613.61 QAR/No.
A+B+C =

Total cost = 613.61 QAR/No.

UF : Utilization Factor

Page 44 of 73
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign frame production
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 4.00 No/day
0.50 No/hr.

A. Material Cost B. Manpower cost C. Equipment cost


Rate Total
Material Unit Qty Cost/ Unit Title Qty UF Equipment Qty UF Rate
(QR) hrly cost hrly coste
Type (QR) type hrly Total Cost

Hollow Section 20mm X 20mm Steel m 15.60 3.33 52.00 Welder 2.00 1.00 14.00 28.00 Portable Generator 5kv 1.00 1.00 12.38 12.38
10mm dia reinforcment Kg 0.62 3.94 2.43 Labourer 4.00 1.00 11.50 46.00 Welding Machine 1.00 1.00 20.81 20.81

Micsilanious Hand tools 5% 1.66

Total 54.43 Total 74.00 Total 34.85

A = Material Unit Cost 54.43 QAR/No.


B = Manpower Unit Cost 74QR / 0.50 Nr 148.00 QAR/No.
C = Equipment Unit Cost 35QR / 0.50 Nr 69.70 QAR/No.

Direct cost of work item = A+B+C


272.12 QAR/No.
=

Total cost = 272.12 QAR/No.

UF : Utilization Factor

Page 45 of 73
Traffic Management Measures for Main Carriageway Opening

PROJECT CODE : IA 12/13 C 054 ST


PROJECT TITLE : Construction of West Corridor P010 (Package 1)
CONTRACT NO. : C2013/56
BUDJET REF. CODE : 11320/1440913
TENDER NO. : MRPSC/006/2012-2013/L

Stage 3 : Measuremets Verified by SC


Period: From 22 April 2017 to 31 August 2017

SUPPLY/INST

SUPPLY/INST

SUPPLY/INST

SUPPLY/INST

SUPPLY/INST

SUPPLY/INST
REMOVED

REMOVED

REMOVED

REMOVED

REMOVED

REMOVED

NO OF LANES
RE INST.

RE INST.

RE INST.

RE INST.

RE INST.

RE INST.
CC Stage 2
TOTAL QUANTITY

UNIT
STAGE 2 DESCRIPTION REMARKS

00023 CB 00025 CB 00026 CB 00030 CB 00031 CB 00032 CB REMOVED RE-INSTALLED SUPPLY/INST

Supply and install temporary traffic signs including all necessary fittings complete as detailed on Drawings and described in Qatar Traffic Manual. - - -
- - -
Sign Ref. R108-R Only Installation
1 (Size: 1200mm) nr 26 2 - 1.00 4.00 8.00 2.00 6.00 13.00 10.00 -
Sign Ref. R108-L Only Installation
2 (Size: 1200mm) nr 4 4.00 2.00 1.00 3.00 4.00 -
Sign Ref. T200
3 (Size: 1200mm) nr 13 2.00 1.00 2.00 1.00 1.00 2.00 5.00 -
Sign Ref. T224 (600m) Only Installation
(Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum.
4 Plank) nr 2 1.00 1.00 - - 6 lanes

Sign Ref. T224 (600m)


(Proposed Size WxH: 1650 x 1500mm, as per standard- 2mm Alum.
5 Plank) nr 2.00 - 2.00 - 4 lanes
Sign Ref. T224 (400m) Only installation
(Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum.
6 Plank) nr 2 1.00 1.00 - - 6 lanes
Sign Ref. T300
7 (Size WxH: 1200 x 400mm) nr 14 1 2.00 1.00 2.00 4.00 1.00 3.00 7.00 7.00 -
Sign Ref. T223 note: not found in
temporary traffic sign
8 nr 2.00 1.00 1.00 1.00 - - 5.00 4 lanes drawings.
Sign Ref. T223 (200m) Only Installation
(Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum.
9 Plank) nr 2 1.00 1.00 - - 6 lanes
Sign Ref. T223 (100m)
10 (Proposed Size WxH: 1250 x 1500mm, as per standard) nr 2 - - - 3 lanes
Sign Ref. T223 (100m) Only installation
11 (Proposed Size WxH: 1250 x 1500mm, as per standard) nr 4 - - - 3 lanes
Sign Ref. T224 (300m)
12 (Proposed Size WxH: 900 x 1500mm, as per standard) nr 2 - - - 2 lanes
Sign Ref. T224 (300m) Only installation
13 (Proposed Size WxH: 900 x 1500mm, as per standard) nr 1 1.00 - 1.00 - 2 lanes
Sign Ref. T223 (100m)
14 (Proposed Size WxH: 900 x 1500mm, as per standard) nr 3 1.00 1.00 - - 2 lanes
Sign Ref. T223 (100m) Only installation
15 (Proposed Size WxH: 900 x 1500mm, as per standard) nr 2 1.00 1.00 1.00 1.00 - 2 lanes
Sign Ref. T224 (300m)
16 (Proposed Size WxH: 1250 x 1500mm, as per standard) Nr 2.00 - 2.00 - 3 lanes

Page 46 of 73
Traffic Management Measures for Main Carriageway Opening

PROJECT CODE : IA 12/13 C 054 ST


PROJECT TITLE : Construction of West Corridor P010 (Package 1)
CONTRACT NO. : C2013/56
BUDJET REF. CODE : 11320/1440913
TENDER NO. : MRPSC/006/2012-2013/L

Stage 3 : Measuremets Verified by SC


Period: From 22 April 2017 to 31 August 2017

SUPPLY/INST

SUPPLY/INST

SUPPLY/INST

SUPPLY/INST

SUPPLY/INST

SUPPLY/INST
REMOVED

REMOVED

REMOVED

REMOVED

REMOVED

REMOVED

NO OF LANES
RE INST.

RE INST.

RE INST.

RE INST.

RE INST.

RE INST.
CC Stage 2
TOTAL QUANTITY

UNIT
STAGE 2 DESCRIPTION REMARKS

00023 CB 00025 CB 00026 CB 00030 CB 00031 CB 00032 CB REMOVED RE-INSTALLED SUPPLY/INST

Sign Ref. T224 (300m)


17 (Proposed Size WxH: 2000 x 1500mm, as per standard) nr - - - 5 lanes
Sign Ref. T223 (200m)
18 (Proposed Size WxH: 2000 x 1500mm, as per standard) - - - 5 lanes
Sign Ref. T223 (100m) Only installation
19 (Proposed Size WxH: 2000 x 1500mm, as per standard) nr 1 1.00 1.00 - - 5 lanes
Sign Ref. T223 (100m) Only installation
20 (Proposed Size WxH: 1250 x 1500mm, as per standard) nr 1 1.00 2.00 - 3.00 - 3 lanes
Sign Ref. T223 (200m) Only installation
21 (Proposed Size WxH: 1650 x 1500mm, as per standard) Nr 3 1.00 1.00 - 1.00 2.00 1.00 - 4 lanes
Sign Ref. T224 (400m) Only installation
22 (Proposed Size WxH: 1650x 1500mm, as per standard) Nr 3 3.00 - 3.00 - 4 lanes
23 Electronic Arrow Board T302 Only installation Nr 14 3.00 1.00 2.00 4.00 1.00 3.00 6.00 8.00 -
Sign Ref. PR0.001 (Proposed Size WxH: 1650x 1500mm, as per
24 standard) Nr 2 1.00 1.00 - -
Sign Ref. PR0.002 (Proposed Size WxH: 1650x 1500mm, as per
25 standard) nr 4 1.00 1.00 - -
Sign Ref. (100m)
26 (Proposed Size WxH: 1200 x 1500mm, as per standard) nr 4 - - -
Sign Ref. "NEW ROAD LAYOUT AHEAD"
27 (Proposed Size WxH: 1200 x 1500mm, as per standard) nr 4 - - -
Sign Ref. 100
28 (Size: 1200mm) nr 36 - - -
Sign Ref. Give Way
29 (Size: 1200mm) nr 8 - - -

BARRIERS

1 Installation of Precast Concret Barrier (TCB) (from temporary barrier) m - - -


2 Installation of Precast Concret Barrier (TCB) (New barrier) m - - -
3 Installation of Polyethylene Road Safety Barrier m - - -
4 Solar Panel flash light Nr 1285 - 463.00 -
5 Solar Panel flash light Only installation 537 - 537.00 -
6 Supply and installation of Concrete Barrier Tapes (3M EGP Reflective
Sticker 200MM) (Fixing it to the facia of the concrete barriers)
m - - -
7 Supply & Instalation Of Cones Nr 4665 500.00 500.00
8 Safty Cones Only installation 1614 1,614.00

Page 47 of 73
Contract No.: C2013/56
Project ID: IA 12/13 C/054 ST
Description: Construction of West Corridor P010 (Package 1)
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV

Subject :Traffic Management Measures for Future Road Opening

ITEM ITEM DESCRIPTION CESMM3 UNIT QTY AMOUNT Remark


Ref. (QAR) (QAR)

Traffic Management Measures for Main carriageway


Opening

Traffic Signs
Supply and install temporary traffic signs including all necessary
fittings complete as detailed on Drawings and described in Qatar
Traffic Manual.

Sign Ref. R108-R


1 nr 26.00 1,230.81 32,001.08
(Size: 1200mm)

Sign Ref. R108-L


2 nr 4.00 1,230.81 4,923.24
(Size: 1200mm)

Sign Ref. T200


3 nr 12.00 1,115.09 13,381.09
(Size: 1200mm)

Sign Ref. T224 (600m)


4 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm nr 10.00 2,376.44 23,764.39
Alum. Plank)

Sign Ref. T224 (400m)


5 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. nr 6.00 2,376.44 14,258.63
Plank)

Sign Ref. T300


6 nr 15.00 970.44 14,556.61
(Size WxH: 1200 x 400mm)

Sign Ref. T223 (200m)


7 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm nr 6.00 2,330.15 13,980.90
Alum. Plank)

Sign Ref. T223 (100m)


8 nr 2.00 1,577.97 3,155.94
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


9 nr 1.00 1,334.96 1,334.96
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T223 (100m)


10 nr 2.00 1,334.96 2,669.92
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T224 (300m)


11 Nr 2.00 1,577.97 3,155.94
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


12 nr 1.00 2,098.71 2,098.71
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (200m)


13 2.00 2,098.71 4,197.42
(Proposed Size WxH: 2000 x 1500mm, as per standard)
Sign Ref. T223 (100m)
14 nr 1.00 2,098.71 2,098.71
(Proposed Size WxH: 2000 x 1500mm, as per standard)
-
Sign Ref. T223 (100m)
15 nr 3.00 1,577.97 4,733.91
(Proposed Size WxH: 1200 x 1500mm, as per standard)
-
Sign Ref. T223 (200m)
16 Nr 4.00 1,855.70 7,422.79
(Proposed Size WxH: 1650 x 1500mm, as per standard)
-
Sign Ref. T224 (400m)
17 Nr 3.00 1,855.70 5,567.10
(Proposed Size WxH: 1650x 1500mm, as per standard)
-
18 Electronic Arrow Board T302 Nr 15.00 5,571.75 83,576.18
Sign Ref. PR0.001 (Proposed Size WxH: 1650x 1500mm, as per
19 Nr 2.00 1,855.70 3,711.40
standard)
Sign Ref. PR0.002 (Proposed Size WxH: 1650x 1500mm, as per
20 nr 4.00 1,855.70 7,422.79
standard)

QAR. 248,011.71

Page 48 of 73
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV

Subject :Traffic Management Measures for Future Road Opening

ITEM ITEM DESCRIPTION CESMM3 UNIT QTY AMOUNT Remark


Ref. (QAR) (QAR)

Traffic Management Measures for Future Road Opening

Sign Ref. (100m)


21 nr 4.00 1,577.97 6,311.88
(Proposed Size WxH: 1200 x 1500mm, as per standard)
Sign Ref. "NEW ROAD LAYOUT AHEAD"
22 nr 4.00 2,098.71 8,394.84
(Proposed Size WxH: 1200 x 1500mm, as per standard)
Sign Ref. 80km/hr
23 nr 36.00 1,230.81 44,309.18
(Size: 1200mm)
Sign Ref. Give Way
24 nr 8.00 1,230.81 9,846.48
(Size: 1200mm)

#REF! QAR. 68,862.39

Page 49 of 73
Employer: Public Works Authority (Ashghal)
PMC: Kellogg Brown & Root Services Inc.
Consultant: Halcrow (Consulting Engineers & Architects) Ltd.
Contractor:Joannou & Paraskevaides (Overseas) Ltd / J&P-Avax S.A-JV

Subject :Traffic Management Measures for Future Road Opening

ITEM ITEM DESCRIPTION CESMM3 UNIT QTY AMOUNT Remark


Ref. (QAR) (QAR)

Traffic Management Measures for Future Road Opening

Collection

Page 1 248,011.71

Page 2 68,862.39

Total Carried to Summary QAR. 316,874.10

Page 50 of 73
Temporary Traffic Signs

Cost of Installation including


Sign Actual cost OH&P
Description Qty Unit ,frames,Loading & Rate (QAR)
No. (QAR) 15.72%
Supply Rate Unloading Amount
(QR) (QR)

Supply of Required Temporary Traffic Signs as per attached


Drawings, BOQ and Work Zone Traffic Management Guide
Rev.1.1:
-Sign face: 2mm / 3mm Aluminum Sheet/ 2mm Aluminum Plank
-Reflective: Type XI as per WZTMG Rev. 1.1 and with stainless steel
fasteners and extruded aluminum clamps.

Sign Ref. R108-R


1 no 450.00 613.61 1,063.61 167.20 1,230.81 -
(Size: 1200mm)

Sign Ref. R108-L


2 no 450.00 613.61 1,063.61 167.20 1,230.81 -
(Size: 1200mm)

Sign Ref. T200


3 no 350.00 613.61 963.61 151.48 1,115.09 -
(Size: 1200mm)

Sign Ref. T224 (600m)


4 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. no 1,440.00 613.61 2,053.61 322.83 2,376.44 -
Plank)

Sign Ref. T224 (400m)


5 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. no 1,440.00 613.61 2,053.61 322.83 2,376.44 -
Plank)

Sign Ref. T300


6 no 225.00 613.61 838.61 131.83 970.44 -
(Size WxH: 1200 x 400mm)

Sign Ref. T223 (200m)


7 (Proposed Size WxH: 2400 x 1500mm, as per standard- 2mm Alum. no 1,400.00 613.61 2,013.61 316.54 2,330.15 -
Plank)

Sign Ref. T223 (100m)


8 no 750.00 613.61 1,363.61 214.36 1,577.97 -
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


9 no 540.00 613.61 1,153.61 181.35 1,334.96 -
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T223 (100m)


10 no 540.00 613.61 1,153.61 181.35 1,334.96 -
(Proposed Size WxH: 900 x 1500mm, as per standard)

Sign Ref. T224 (300m)


11 no 750.00 613.61 1,363.61 214.36 1,577.97 -
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Sign Ref. T224 (300m)


12 no 1,200.00 613.61 1,813.61 285.10 2,098.71 -
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (200m)


13 no 1,200.00 613.61 1,813.61 285.10 2,098.71 -
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (100m)


14 no 1,200.00 613.61 1,813.61 285.10 2,098.71 -
(Proposed Size WxH: 2000 x 1500mm, as per standard)

Sign Ref. T223 (100m)


15 no 750.00 613.61 1,363.61 214.36 1,577.97 -
(Proposed Size WxH: 1200 x 1500mm, as per standard)

Sign Ref. T223 (200m)


16 no 990.00 613.61 1,603.61 252.09 1,855.70 -
(Proposed Size WxH: 1650 x 1500mm, as per standard)

Sign Ref. T224 (400m)


17 no 990.00 613.61 1,603.61 252.09 1,855.70 -
(Proposed Size WxH: 1650x 1500mm, as per standard)

18 Electronic Arrow Board T302 no 4,201.24 613.61 4,814.85 756.89 5,571.75 -

Sign Ref. T224 (400m)


19 no 990.00 613.61 1,603.61 252.09 1,855.70 -
(Proposed Size WxH: 1650x 1500mm, as per standard)

Sign Ref. T223 (200m)


20 no 990.00 613.61 1,603.61 252.09 1,855.70 -
(Proposed Size WxH: 1650 x 1500mm, as per standard)

Sign Ref. T223 (200m)


21 no 750.00 613.61 1,363.61 214.36 1,577.97 -
(Proposed Size WxH: 1250 x 1500mm, as per standard)

Barriers

Installation of Precast Concret Barrier (0.15/0.32m X 1.345 X 3.04) m 600.00

Installation of Polyethylene Road Safety Barrier 2M Long m 225.00

2 way flashing Solar and Battery road maxi light nr 42.29

Supply & Installation of Safty Cones nr 31.77 4.99 36.76

6/1/2017
Page 51 of 73 4/7
Temporary Traffic Signs

Cost of Installation including


Sign Actual cost OH&P
Description Qty Unit ,frames,Loading & Rate (QAR)
No. (QAR) 15.72%
Supply Rate Unloading Amount
(QR) (QR)

Safty Cones Only installation nr 14.10 2.22 16.32

Traffic study for the proposed work sum #REF!

Rumble strips sum 55.00 8.65 63.65

3M EGP Reflective Sticker nr 11.52 1.81 13.33

LED Solar Powered Variable Message Signs (VMS) Signs (VMS) nr 64,000.00 10,060.80 74,060.80

Road Safety Audits at Two Stages

Stage 3 for detailed design (Review of Shop Drawings) nr 5,000.00 786.00 5,786.00

Stage 4 for pre-opening (Actual Road Inspection) nr 12,000.00 1,886.40 13,886.40

6/1/2017
Page 52 of 73 5/7
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign installation
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 16.00 No/day
2.00 No/hr.

A. Material Cost B. Manpower cost C. Equipment cost


Rate Total
Material Unit Qty Cost/ Unit Title Qty UF Equipment Qty UF Rate
(QR) hrly cost hrly coste
Type (QR) type hrly Total Cost

Sand bag m 4.00 0.65 2.60 Labourer 12.00 1.00 11.50 138.00 Hiab Crane 1.00 0.75 134.95 101.21
Track Mounted
Bolt & nut No. 4.00 0.40 1.60 Skilled Labour 6.00 1.00 13.00 78.00 1.00 1.00 306.25 306.25
Attenuator
Safty cone (10 Times used) No. 6.00 16.50 9.90 Hiab Crane operator 1.00 0.75 15.00 11.25
Frame No. 1.00 272.12 272.12 Driver 1.00 1.00 15.00 15.00
Micsilanious Hand tools 5.0% 5.06

Total 286.22 Total 242.25 Total 412.52

A = Material Unit Cost 286.22 QAR/No.


B = Manpower Unit Cost 242.3QR / 2.00 m2 121.13 QAR/No.
C = Equipment Unit Cost 412.5QR / 2.00 m2 206.26 QAR/No.

Direct cost of work item =


613.61 QAR/No.
A+B+C =

Total cost = 613.61 QAR/No.

UF : Utilization Factor

Page 53 of 73
Detailed Cost Breakdown
Project: CONSTRUCTION OF WEST CORRIDOR P010 (PACKAGE 1)
Activity: Traffic sign frame production
- Traffic Management Measures
BOQ Qty: 144.00 No
Performance rate : 4.00 No/day
0.50 No/hr.

A. Material Cost B. Manpower cost C. Equipment cost


Rate Total
Material Unit Qty Cost/ Unit Title Qty UF Equipment Qty UF Rate
(QR) hrly cost hrly coste
Type (QR) type hrly Total Cost

Hollow Section 20mm X 20mm Steel m 15.60 3.33 52.00 Welder 2.00 1.00 14.00 28.00 Portable Generator 5kv 1.00 1.00 12.38 12.38
10mm dia reinforcment Kg 0.62 3.94 2.43 Labourer 4.00 1.00 11.50 46.00 Welding Machine 1.00 1.00 20.81 20.81

Micsilanious Hand tools 5% 1.66

Total 54.43 Total 74.00 Total 34.85

A = Material Unit Cost 54.43 QAR/No.


B = Manpower Unit Cost 74QR / 0.50 Nr 148.00 QAR/No.
C = Equipment Unit Cost 35QR / 0.50 Nr 69.70 QAR/No.

Direct cost of work item = A+B+C


272.12 QAR/No.
=

Total cost = 272.12 QAR/No.

UF : Utilization Factor

Page 54 of 73
1149.12

Page 55 of 73
Page 56 of 73
Page 57 of 73
Page 58 of 73
Page 59 of 73
Page 60 of 73
Page 61 of 73
Page 62 of 73
Page 63 of 73
Page 64 of 73
Page 65 of 73
J&P (OVERSEAS) LTD 09 MAY - 2017
P.O. Box 19389
Doha, State of Qatar

Project: Ashghal Doha Expressway West Corridor (P010) Project

Quotation 1374/09-05

Unit Price Total Amount


Description Qty Unit
(QAR) (QAR)

Supply of Concrete Barriers

Supply of Concrete Barriers (Oregon


Department of Transport F-Shape 3-Pin and 1,200 Nos 800 960,000
Loop system)
TOTAL FOR ALL THE ABOVE MENTIONED SERVICES 960,000

All Rates are subject to the attached standard terms and conditions
Validity: Our prices will remain valid for 30 days

Regards,

SHEBIN M. A.
Accounting Department, TMS

Traffic Management Solutions WLL


P.O. Box: 22997, Zone 37, Building 241, Suite# 14
Mohammed Bin Thani Street, Doha, Qatar
T: +974 4450 2146 F: +974 4479 3420
Page 66 of 73
www.tmsqatar.com

TMSQatar
Terms and Conditions of Contract

1. These terms and conditions constitute a contract between Traffic Management Solutions (TMS) and, (The
Client) for the supply of services as per the attached quotation / pricing schedule.
2. The Client is deemed to accept these conditions by virtue of your written or verbal instruction, interview
or engagement of TMS, its workforce, associated companies or nominated sub-contractors.
3. All conditions are deemed accepted and no variations will be valid or accepted unless agreed in writing
with a Senior Manager of TMS.
4. Prior to engagement or assignment, TMS will confirm the details of the contract including rates, service to
be provided etc. in writing for the Clients approval.
5. The client should issue an official purchase order to formally accept and engage TMS but where this
process is not in operation or is not practicable, TMS will accept and confirm a verbal instruction.
6. The client agrees to pay in full the rates quoted and charged by TMS as notified prior to or at
commencement of the engagement/assignment.
7. No deduction for retention will be made in any circumstance.
8. To be agreed but generally a minimum 10% advanced payment will be required.

Service Agreements

Traffic Management Operations


Our Rates are based on the contract information supplied at the time of tender and not any subsequently
issued programme unless specifically referred to.
All TM equipment will remain the property of TMS unless specifically agreed in writing with a senior manager.
Where a part shift is worked the full agreed daily rate will be charged.
All layouts will typically be as per the WZTMG and/or approved TDP unless specifically agreed otherwise.
TMS have not allowed for any sweeping or cleaning of the carriageway in any instance.
All signs will be free standing or fixed to street furniture unless otherwise specified.
TMS have not allowed for any temporary overhead lighting in any situation.
Where specifically referred to, temporary road markings will be provided in locations as per the approved TDP
only.
Any changes or alterations from the approved TM Drawing / TDP will be subject to re-measurement and
possibly additional charges.
Any cancellation inside 12 hrs from the scheduled start time will incur 100% of the fee charged.
Any cancellation within 12-24 hrs of a scheduled check will be subject to 50% of the agreed fee.
Any re-scheduling out with 24hrs notice will not be subject to any charge.

Traffic Management Solutions WLL


P.O. Box: 22997, Zone 37, Building 241, Suite# 14
Mohammed Bin Thani Street, Doha, Qatar
T: +974 4450 2146 F: +974 4479 3420
Page 67 of 73
www.tmsqatar.com

TMSQatar
J&P (OVERSEAS) LTD 01-FEBRUARY-2017
P.O. Box 19389
Doha, State of Qatar

Quotation 1271/01-02

Unit Price Total Amount


Description Qty Unit
(QAR) (QAR)
TRUCK MOUNTED ATTENUATOR (TMA) RENTAL

1. Truck Mounted Attenuator (TMA) rental


for 8 hrs shift/day
Option 1. Daily Rental 1 Day 2,450 Rate Only
Option 2. Weekly Rental (6 Days) 1 Week 12,300 Rate Only
Option 3. Monthly Rental (26 Days) 1 Month 40,300 Rate Only

TOTAL FOR ALL THE ABOVE MENTIONED SERVICES Rate Only

All Rates are subject to the attached standard terms and conditions
Validity: Our prices will remain valid for 30 days

Regards,

SHEBIN M. A.
Accounting Department, TMS

Traffic Management Solutions WLL


P.O. Box: 22997, Zone 37, Building 241, Suite# 14
Mohammed Bin Thani Street, Doha, Qatar
T: +974 4450 2146 F: +974 4479 3420
Page 68 of 73
www.tmsqatar.com

TMSQatar
Terms and Conditions of Contract

1. These terms and conditions constitute a contract between Traffic Management Solutions (TMS) and, (The
Client) for the supply of services as per the attached quotation / pricing schedule.
2. The Client is deemed to accept these conditions by virtue of your written or verbal instruction, interview
or engagement of TMS, its workforce, associated companies or nominated sub-contractors.
3. All conditions are deemed accepted and no variations will be valid or accepted unless agreed in writing
with a Senior Manager of TMS.
4. Prior to engagement or assignment, TMS will confirm the details of the contract including rates, service to
be provided etc. in writing for the Clients approval.
5. The client should issue an official purchase order to formally accept and engage TMS but where this
process is not in operation or is not practicable, TMS will accept and confirm a verbal instruction.
6. The client agrees to pay in full the rates quoted and charged by TMS as notified prior to or at
commencement of the engagement/assignment.
7. No deduction for retention will be made in any circumstance.
8. To be agreed but generally a minimum 10% advanced payment will be required.

Service Agreements

Traffic Management Operations


Our Rates are based on the contract information supplied at the time of tender and not any subsequently
issued programme unless specifically referred to.
All TM equipment will remain the property of TMS unless specifically agreed in writing with a senior manager.
Where a part shift is worked the full agreed daily rate will be charged.
All layouts will typically be as per the WZTMG and/or approved TDP unless specifically agreed otherwise.
TMS have not allowed for any sweeping or cleaning of the carriageway in any instance.
All signs will be free standing or fixed to street furniture unless otherwise specified.
TMS have not allowed for any temporary overhead lighting in any situation.
TMS have not allowed for any work in connection to manufacturing, installing or removing concrete safety
barriers.
Where specifically referred to, temporary road markings will be provided in locations as per the approved TDP
only.
Any changes or alterations from the approved TM Drawing / TDP will be subject to re-measurement and
possibly additional charges.
TMS have not allowed for any work in relation to removal or reinstatement of cats eyes / road studs.
Any cancellation inside 12 hrs from the scheduled start time will incur 100% of the fee charged.
Any cancellation within 12-24 hrs of a scheduled check will be subject to 50% of the agreed fee.
Any re-scheduling out with 24hrs notice will not be subject to any charge.

Traffic Management Solutions WLL


P.O. Box: 22997, Zone 37, Building 241, Suite# 14
Mohammed Bin Thani Street, Doha, Qatar
T: +974 4450 2146 F: +974 4479 3420
Page 69 of 73
www.tmsqatar.com

TMSQatar
Page 70 of 73
Page 71 of 73
Page 72 of 73
Page 73 of 73

You might also like