KERALA STATE NIRMITHI KENDRA

REGIONAL CENTRE, CPT CAMPUS , VATTIYOORKAVU


QUOTATION FOR THE CONSTRUCTION OF SMSMI CENTENARY BUILDING ( ANNEX ) FOR
HANDI CRAFT DEVOLOPMENT CORPORATION,THIRUVANANTHAPURAM

GROUND FLOOR
1.Substructure
Sl:
No Rate Amount
Aprox:
Particulars Unit
Quantity
Figure Words Figure Words
1 Earth work excavation for foundation
in all classes of soil ecept hard rock
and depositing on bank with intial lead
up to 50cm and lift up to 1.5m
including breaking of clods,
sectioning of spoil bank , filling in the
sides of trenches 250 m3 1 m3 294.00 73500.00
2 Cement concrete 1:4:8 using 40mm
broken stone for foundation
including all form work , watering,
curing , cost and conveyance of all
materials and labour charges etc.
complete. 30.00 m3 1 m3 5513.00 165390.00
3 Random rubble masonry in Cement
mortar 1:8 for foundation and
basement including all labour and the
cost of materials etc complete, for
foundation. 35 m3 1 m3 3822.00 133770.00
4 RCC M20 using 20mm hard granite
broken stone including all form work,
watering, curing, cost and conveyance
of all materials and labour charges
etc. complete but excluding cost and
labour of steel reinforcement
a) column footing 65.00 m3 1 m3 8820.00 573300.00
b) plinth beam 17.00 m3 1 m3 12250.00 208250.00
c) lift well 7.00 m3 1m 3 12250.00 85750.00
d) column 18.00 m3 1 m3 17150.00 308700.00
5 Supplying and fabrication of
reinforcement grill using Fe 415 steel
for RCC work, bend, tied, and placed
in postion including cost and
conveyance of all materials , hire and
labour charges etc. 17150.00 kg 1 kg 73.50 1260525.00
6 Supplying , filling and consolidation
inside basement with gravel earth
brought from out side including all
cost and conveyance of all materials ,
hire and labour charges etc 25 m3 1 m3 343.00 8575.00
7 Block masonry using concrete hollow
blocks of 8" thickness in CM 1;6 for
superstructure walls including all cost
and labour charges of scaffolding ,
watering, curing etc. complete

85 m3 1 m3 4469.00 379865.00
8 Brick masonry using country burned
brick in CM 1:6 for steps including
all cost and labour charges of
scaffolding , watering, curing etc.
complete 3 m3 1 m3 6860.00 20580.00
9 Providing and fixing shutter for front
door made with shutter frames of 1st
class teak wood 125x 35mm size
vertically top and bottom rail of
240mmx35mm and central lock rail
of 320mmx35mm and panels with
5.5mm thick etched glass in required
shape with frames of 125x75mm size
and fixed glazed portion on top as per
design and drawing including all
jointing and fixing all fitting and
fixtures etc . compete with locking
arrangement and with polishing 8.5 m2 1 m2 12500.00 106250.00
10 Supplying and fabricating and fixing
in position wooden outer frames for
doors and panelled door shutter with
suitable sections for frames and
shutter as specified in the drawing
using voilet/ pigoda of approved
patten and design including cost and
conveyance of all materials , hire and
labour charges etc. 2.50 m3 1 m3 132800.00 332000.00
11 Fabricating, supplying andand fixing
in position of openable wooden glazed
windows with fixed portion on top
whereever necessary as per design
made up voilet/ pigoda wood and
4mm thick plain or pin headed glass
as inserts of approved pattern with
grill including cost and conveyance of
all materials , hire and labour charges
and appling a coat of primer etc
complete. 42.00 m2 1 m2 8330.00 349860.00
12 Jally work in brick masonry in cm 1:6
using contry burnt bricks of nominal
size including centering , scaffolding ,
curing , material and labour charges
etc. complete 2.00 m3 1 m3 4802.00 9604.00
13 Supplying and fixing sintex colour
matt finish PVC doors with 3nos
stainless steel hinges, 2nos tower bolt
and 2nos handle, scews, joining
cleats, and gum etc complete
including all cost and labour charges
etc complete as per specifications and
as directed by the Engineer in -chare 8.5 m2 1 m2 1872.00 15192.00
14 RCC M20 using 20mm hard granite
broken stone including all form work,
watering, curing, cost and conveyance
of all materials and labour charges
etc. complete but excluding cost and
labour of steel reinforcement
a) Lintel beam 23.50 m3 1 m3 15500.00 364250.00
b) sunshade 6.50 m3 1 m3 14455.00 93957.50
c) slab sloping 1.50 m3 1 m3 15435.00 23152.50
d) slab flat 40.50 m3 1 m3 13270.00 555660.00
15 Supplying and fabrication of
reinforcement grill using Fe 415 steel
for RCC work, bend, tied, and placed
in postion including cost and
conveyance of all materials , hire and
labour charges etc. 8800.00 kg 1 kg 73.50 646800.00
16 Ceiling plastering 1:3 CM 9mm thick
floated hard and trowelled smooth
including scaffolding, watering
curing cost and conveyance of all
materials , hire and labour charges etc.
complete. 510.00 m2 1 m2 221.00 112710.00
17 Plastering inside walls 1:4 12mm
thick floated hard and trowelled
smooth including scaffolding,
watering, curing cost and conveyance
of all materials , hire and labour
charges etc. complete. 490 m2 1 m2 245.00 120050.00
18 Plastering outside walls 1:4 12mm
thick floated hard and trowelled
smooth including scaffolding,
watering, curing cost and conveyance
of all materials , hire and labour
charges etc. complete. 300 m2 1 m2 245.00 73500.00
19 Providing boardering /water cutting to
bottom of sunshade and roof
projection also sides and bottom of
windows and doors in the external/
internal sides whereever it is required
including cost and labour charges etc.
complete.
100.00 m 1m 40.00 4000.00
20 Flooring with cement concrete 1:4:8
using 40mm coarse aggregate and laid
to an average thickness or not less
than 10cm including ramming,
consolidating , watering, curing cost
and conveyance of all materials , hire
and labour charges etc. complete. 40.00 m2 1 m2 5243.00 209720.00
21 Vertified tile laying
Eliminated as per the
discussion with KDCK
Officials
22 Supplying and laying ceramic tiles of
any branded make , shade and colour
and of minimum size 300mmx300mm
laid in 15mm thick CM 1:3 to correct
line and level, cutting neatly and
pointing with matching coloured
cement including cost and conveyance
of all materials , hire and labour
charges etc. complete for floor 15.00 m2 1 m2 980.00 14700.00
23 Supplying and laying coloured glazed
ceramic tiles of any branded make ,
shade and colour and of minimum
size 300mmx200mm laid in 15mm
thick CM 1:3 to correct line and level,
cutting neatly and pointing with
matching coloured cement including
cost and conveyance of all materials ,
hire and labour charges etc. complete 35.00 m2 1 m2 1250.00 43750.00
24 Supplying and fixing of coloured
cement tiles of any branded make ,
over a base of cement mortar 1:3
15mm thick to correct line and level,
cutting neatly and pointing with
matching coloured cement including
all cost and abour charges etc.
complete for steps. 35.00 m2 1 m2 1078.00 37730.00
25
White washing two coats with
lovelicemor equivalent to the
plastered surface including all cost
and abour charges etc. complete 510.00 m2 1 m2 19.00 9690.00
26
Colour washing to the inner side of
wall using distemper of any branded
make two coat over a coat of white
cement after cleaning the newly
plastered surface using carborandum
stones including all cost and abour
charges etc. complete 490 m2 1 m2 68.00 33320.00
27 Painting two coats to the out side of
the walls using exterior emulsion of
any branded make over a coat of
cement primer including cost and
conveyance of all materials , hire and
labour charges etc. complete. 300 m2 1 m2 130.00 39000.00
28 Painting the wooden doors and
windows with two coats of ready
mixed enamel paint over a coat of
wood primer after cleaning the surface
with sand papers including cost and
conveyance of all materials , hire and 105 m2 1 m2 150.00 15750.00
labour charges
29 Supplying and etc.
fixingcomplete.
hand rail using
GI pipes and MS flats as per design
and drawing including all cost and
abour charges etc. complete with a
coat of iron primer 30.00 m2 1 m2 750.00 22500.00
30 Roof plastering in cm 1:3 15mm thick
floated hard and trowelled smooth
including watering, curing cost and
conveyance of all materials , hire and
labour charges etc. complete. with
water proofing 15.00 m2 1 m2 290.00 4350.00
31
Providing and laying MP tiles over
sloping roof over cement reaper
including all cost and abour charges
etc. complete 10.00 m2 1 m2 750.00 7500.00

First Floor
1 RCC M20 using 20mm hard granite
broken stone including all form work,
watering, curing, cost and conveyance
of all materials and labour charges
etc. complete but excluding cost and
labour of steel reinforcement for
column 18.00 m3 1 m3 18100.00 325800.00
2 Supplying and fabrication of
reinforcement grill using Fe 415 steel
for RCC work, bend, tied, and placed
in postion including cost and
conveyance of all materials , hire and
labour charges etc. 4500.00 kg 1 kg 73.50 330750.00
3 Block masonry using concrete hollow
blocks of 8" thickness in CM 1;6 for
superstructure walls including all cost
and labour charges of scaffolding ,
watering, curing etc. complete

106 m3 1 m3 4522.00 479332.00


4 Brick masonry using country burned
brick in CM 1:6 for steps including
all cost and labour charges of
scaffolding , watering, curing etc.
complete 3 m3 1 m3 7203.00 21609.00
5 Supplying and fabricating and fixing
in position wooden outer frames for
doors and panelled door shutter with
suitable sections for frames and
shutter as specified in the drawing
using voilet/ pigoda of approved
patten and design including cost and
conveyance of all materials , hire and
labour charges etc. 4.50 m3 1 m3 132800.00 597600.00
6 Fabricating, supplying andand fixing
in position of openable wooden glazed
windows with fixed portion on top
whereever necessary as per design
made up voilet/ pigoda wood and
4mm thick plain or pin headed glass
as inserts of approved pattern with
grill including cost and conveyance of
all materials , hire and labour charges
and appling a coat of primer etc
complete. 29.00 m2 1 m2 8330.00 241570.00
7 Jally work in brick masonry in cm 1:6
using contry burnt bricks of nominal
size including centering , scaffolding ,
curing , material and labour charges
etc. complete 2.00 m3 1 m3 4900.00 9800.00
8 Supplying and fixing sintex colour
matt finish PVC doors with 3nos
stainless steel hinges, 2nos tower bolt
and 2nos handle, scews, joining
cleats, and gum etc complete
including all cost and labour charges
etc complete as per specifications and
as directed by the Engineer in -chare 8.5 m2 1 m2 1872.00 15912.00
9 RCC M20 using 20mm hard granite
broken stone including all form work,
watering, curing, cost and conveyance
of all materials and labour charges
etc. complete but excluding cost and
labour of steel reinforcement
a) Lintel beam 21.00 m3 1 m3 15950.00 334950.00
b) sunshade 6.50 m3 1 m3 15380.00 99970.00
c) slab 40.50 m3 1 m3 14150.00 566000.00
10 Supplying and fabrication of
reinforcement grill using Fe 415 steel
for RCC work, bend, tied, and placed
in postion including cost and
conveyance of all materials , hire and
labour charges etc. 7550.00 kg 1 kg 73.50 554925.00
11 Ceiling plastering 1:3 CM 9mm thick
floated hard and trowelled smooth
including scaffolding, watering
curing cost and conveyance of all
materials , hire and labour charges etc.
complete. 500.00 m2 1 m2 235.00 117500.00
12 Plastering inside walls 1:4 12mm
thick floated hard and trowelled
smooth including scaffolding,
watering, curing cost and conveyance
of all materials , hire and labour
charges etc. complete. 535 m2 1 m2 255.00 136425.00
13 Plastering outside walls 1:4 12mm
thick floated hard and trowelled
smooth including scaffolding,
watering, curing cost and conveyance
of all materials , hire and labour
charges etc. complete. 315 m2 1 m2 255.00 80325.00
14 Providing boardering /water cutting to
bottom of sunshade and roof
projection also sides and bottom of
windows and doors in the external/
internal sides whereever it is required
including cost and labour charges etc.
complete.
75.00 m 10 m 40.00 3000.00
15 Supplying and laying ceramic tiles of
any branded make , shade and colour
and of minimum size 300mmx300mm
laid in 15mm thick CM 1:3 to correct
line and level, cutting neatly and
pointing with matching coloured
cement including cost and conveyance
Eliminated as per the
of all materials , hire and labour
discussion with KDCK
charges etc. complete for floor 390.00 m2 1 m2 Officials
16 Supplying and laying coloured glazed
ceramic tiles of any branded make ,
shade and colour and of minimum
size 300mmx200mm laid in 15mm
thick CM 1:3 to correct line and level,
cutting neatly and pointing with
matching coloured cement including
cost and conveyance of all materials ,
hire and labour charges etc. complete 60.00 m2 1 m2 1250.00 75000.00
17 Supplying and fixing of coloured
cement tiles over a base of cement
mortar including all cost and abour
charges etc. complete for steps. 35.00 m2 1 m2 1078.00 37730.00
18
White washing two coats with
lovelicemor equivalent to the under
side of all RCC slabs including all
cost and abour charges etc. complete 500.00 m2 1 m2 18.00 9000.00
19
Colour washing to the inner side of
wall using distemper of any branded
make two coat over a coat of white
cement after cleaning the newly
plastered surface using carborandum
stones including all cost and abour
charges etc. complete 535 m2 1 m2 68.00 36380.00
20 Painting two coats to the out side of
the walls using exterior emulsion of
any branded make over a coat of
cement primer including cost and
conveyance of all materials , hire and
labour charges etc. complete. 315 m2 1 m2 130.00 40950.00
21 Painting the wooden doors with two
coats of ready mixed enamel paint
over a coat of wood primer after
cleaning the surface with sand papers
including cost and conveyance of all
materials , hire and labour charges etc. 15 m2 1 m2 150.00 2250.00
complete.the windows with two coats
22 Painting
of ready mixed synthetic enamel paint
over a coat of wood primer after
cleaning the surface with sand papers
including cost and conveyance of all
materials , hire and labour charges etc. 55 m2 1 m2 150.00 8250.00
complete. and fixing hand rail using
23 Supplying
GI pipes and MS flats as per design
and drawing including all cost and
abour charges etc. complete with a
coat of iron primer 32.00 m2 1 m2 750.00 24000.00
24 Painting the hand rail with two coats
of ready mixed enamel paint over a
coat of wood primer after cleaning the
surface with sand papers including
cost and conveyance of all materials ,
hire and labour charges etc. complete. 62.00 m2 1 m2 150.00 9300.00
25 Roof plastering in cm 1:3 15mm thick
floated hard and trowelled smooth
including watering, curing cost and
conveyance of all materials , hire and
labour charges etc. complete. with
water proofing 310.00 m2 1 m2 294.00 91140.00
10712669.00
Terrace Floor
Eliminated as per the
discussion with KDCK
Officials
Grand Total (civil work) : 10712669.00
Plumbing : 315000.00
Electrification : 275000.00
Total 11302669.00
unforseen : 720.00
Grand Total (civil work) : 11,303,389.00
( Rupees one crore thirteen three thousand three hundred and eighty nine)
TENDER SCHEDULE FOR THE CONSTRUCTION OF SMSMI CENTENARY BUILDING
( ANNEX BUILDING ) FOR HANDICRAFTS DEVELOPMENTCORPORATION OF
KERALA Ltd

GROUND FLOOR
Sl: No Aprox:
Particulars Unit Rate Amount
Quantity
1 Earth work excavation for
foundation in all classes of soil
ecept hard rock and depositing on
bank with intial lead up to 50m
and lift up to 1.5m including
breaking of clods, sectioning of
spoil bank , filling in the sides of
trenches 250 m3 1 m3 276.27 69067.50
2 Cement concrete 1:4:8 using
40mm broken stone for
foundation including all form
work , watering, curing , cost and
conveyance of all materials and
labour charges etc. complete. 30.00 m3 1 m3 5180.57 155417.10
3 RR masonry in Cement mortar 1:8
for foundation and basement
including all labour and the cost
of materials etc complete 35 m3 1 m3 3591.53 125703.55
4 RCC M20 using 20mm size hard
granite broken stone including all
form work, watering, curing,
including cost and conveyance of
all materials and labour charges
etc. complete but excluding cost
and labour of steel reinforcement
a) column footing 65.00 m3 1 m3 8288.15 538729.75
b) plinth beam 17.00 m 3
1m 3
11511.33 195692.61
c) lift well 7.00 m3 1m 3 11511.33 80579.31
d) column 18.00 m 3
1m 3
16115.86 290085.48
5 Supplying and fabrication of
reinforcement grill using Fe 415
steel for RCC work, bend, tied,
and placed in postion including
cost and conveyance of all
materials , hire and labour charges
etc. 17150.00 kg 1 kg 69.07 1184550.50
6 Supplying , filling and
consolidating inside basement
with gravel earth brought from out
side including all cost and
conveyance of all materials , hire
and labour charges 25 m3 1 m3 322.32 8058.00
7 Block masonry using concrete
hollow blocks of 8" thickness in
CM 1;6 for superstructure walls
including all cost and labour
charges of scaffolding , watering,
curing etc. complete
85 m3 1 m3 4199.52 356959.20
8 Brick masonry using country
burned brick in CM 1:6 for steps
including all cost and labour
charges of scaffolding , watering,
curing etc. complete 3 m3 1 m3 6446.34 19339.02
9 Providing and fixing shutters for
front door made with shutter
frames of 1st class teak wood
125x 35mm size vertically top and
bottom rail of 240mmx35mm and
central lock rail of
320mmx35mm and panels with
5.5mm thick etched glass in
required shape with frames of
125x75mm size and fixed glazed
portion on top as per design and
drawing including all jointing and
fixing all fitting and fixtures etc .
compete with locking arrangement
and with polishing 8.5 m2 1 m2 11746.25 99843.13
10 Supplying , fabricating and fixing
in position wooden outer frames
for doors and panelled door
shutter with suitable sections for
frames and shutter as specified in
the drawing using voilet/ pigoda
of approved patten and design
including cost and conveyance of
all materials , hire and labour
charges etc. 2.50 m3 1 m3 124792.16 311980.40
11 Fabricating, supplying and fixing
in position of openable wooden
glazed windows with fixed
portion on top whereever
necessary as per design made up
voilet/ pigoda wood and 4mm
thick plain or pin headed glass as
inserts of approved pattern with
grill including cost and
conveyance of all materials , hire
and labour charges and applying a
coat of primer etc complete. 42.00 m2 1 m2 7827.70 328763.40
12 Jally work in brick masonry in
CM 1:6 using contry burnt bricks
of nominal size including
centering , scaffolding , curing ,
material and labour charges etc.
complete 2.00 m3 1 m3 4512.44 9024.88
13 Supplying and fixing sintex colour
matt finish PVC doors with 3nos
stainless steel hinges, 2nos tower
bolt and 2nos handle, screws,
joining cleats, and gum etc
complete including all cost and
labour charges etc complete as per
specifications and as directed by
the Engineer in -charge 8.5 m2 1 m2 1759.12 14952.52
14 RCC M20 mix using 20mm size
hard granite broken stone
including all form work, watering,
curing, cost and conveyance of all
materials and labour charges etc.
complete but excluding cost and
labour of steel reinforcement
a) Lintel beam 23.50 m3 1 m3 14565.35 342285.73
b) sunshade 6.50 m3 1 m3 13583.36 88291.84
c) slab sloping 1.50 m3 1 m3 14504.27 21756.41
d) slab flat 40.50 m3 1 m3 12469.82 505027.71
15 Supplying and fabrication of
reinforcement grill using Fe 415
steel for RCC work, bend, tied,
and placed in postion including
cost and conveyance of all
materials , hire and labour charges
etc. 8800.00 kg 1 kg 69.07 607816.00
16 Ceiling plastering 1:3 CM 9mm
thick floated hard and trowelled
smooth including scaffolding,
watering curing cost and
conveyance of all materials , hire
and labour charges etc. complete. 510.00 m2 1 m2 207.67 105911.70
17 Plastering inside walls 1:4 12mm
thick floated hard and trowelled
smooth including scaffolding,
watering, curing cost and
conveyance of all materials , hire
and labour charges etc. complete. 490 m2 1 m2 230.23 112812.70
18 Plastering outside walls 1:4 12mm
thick floated hard and trowelled
smooth including scaffolding,
watering, curing cost and
conveyance of all materials , hire
and labour charges etc. complete. 300 m2 1 m2 230.23 69069.00
19 Providing boardering /water
cutting to bottom of sunshade and
roof projection also sides and
bottom of windows and doors in
the external/ internal sides
whereever it is required including
cost and labour charges etc.
complete.
100.00 m 1m 37.59 3759.00
20 Flooring with cement concrete
1:4:8 using 40mm coarse
aggregate and laid to an average
thickness or not less than 10cm
including ramming,
consolidating , watering, curing
cost and conveyance of all
materials , hire and labour charges
etc. complete. 40.00 m2 1 m2 4926.85 197074.00
21 Supplying and laying ceramic
tiles of any branded make , shade
and colour and of minimum size
300mmx300mm laid in 15mm
thick CM 1:3 to correct line and
level, cutting neatly and pointing
with matching coloured cement
including cost and conveyance of
all materials , hire and labour
charges etc. complete for the
floors 15.00 m2 1 m2 920.91 13813.65
22 Supplying and laying coloured
glazed ceramic tiles of any
branded make , shade and colour
and of minimum size
300mmx200mm laid in 15mm
thick CM 1:3 to correct line and
level, cutting neatly and pointing
with matching coloured cement
including cost and conveyance of
all materials , hire and labour
charges etc. complete 35.00 m2 1 m2 1174.63 41112.05
23 Supplying and fixing of coloured
cement tiles of any branded
make , over a base of cement
mortar 1:3 15mm thick to correct
line and level, cutting neatly and
pointing with matching coloured
cement including all cost and
abour charges etc. complete for
steps. 35.00 m2 1 m2 1013.00 35455.00
24

White washing two coats with


lovelicemor equivalent to the
plastered surface including all cost
and abour charges etc. complete 510.00 m2 1 m2 17.85 9103.50
25

Colour washing to the inner side


of the wall using distemper of any
branded make two coat over a
coat of white cement after
cleaning the newly plastered
surface using carborandum stones
including all cost and abour
charges etc. complete 490 m2 1 m2 63.90 31311.00
26 Painting two coats to the out side
of the walls using exterior
emulsion of any branded make
over a coat of cement primer
including cost and conveyance of
all materials , hire and labour
charges etc. complete. 300 m2 1 m2 122.16 36648.00
27 Painting the wooden doors and
windows with two coats of ready
mixed enamel paint over a coat of
wood primer after cleaning the
surface with sand papers
including cost and conveyance of
all materials , hire and labour
charges etc. complete. 105 m2 1 m2 140.96 14800.80
28 Supplying and fixing hand rail
using GI pipes and MS flats as per
design and drawing including all
cost and abour charges etc.
complete with a coat of pf iron
primer 30.00 m2 1 m2 704.78 21143.40
29 Roof plastering in cm 1:3 15mm
thick floated hard and trowelled
smooth including watering, curing
cost and conveyance of all
materials , hire and labour charges
etc. complete. with water
proofing 15.00 m2 1 m2 272.51 4087.65
30
Providing and laying MP tiles
over sloping roof over cement
reaper including all cost and abour
charges etc. complete 10.00 m2 1 m2 704.78 7047.80

First Floor
1 RCC M20 using 20mm size hard
granite broken stone including all
form work, watering, curing, cost
and conveyance of all materials
and labour charges etc. complete,
excluding cost and labour of steel
reinforcement for column 18.00 m3 1 m3 17008.57 306154.26
2 Supplying and fabrication of
reinforcement grill using Fe 415
steel for RCC work, bend, tied,
and placed in postion including
cost and conveyance of all
materials , hire and labour charges
etc. 4500.00 kg 1 kg 69.07 310815.00
3 Block masonry using concrete
hollow blocks of 8" thickness in
CM 1;6 for superstructure walls
including all cost and labour
charges of scaffolding , watering,
curing etc. complete
106 m3 1 m3 4249.32 450427.92
4 Brick masonry using country
burned brick in CM 1:6 for steps
including all cost and labour
charges of scaffolding , watering,
curing etc. complete 3 m3 1 m3 6768.66 20305.98
5 Supplying and fabricating and
fixing in position wooden outer
frames for doors and panelled
door shutter with suitable sections
for frames and shutter as
specified in the drawing using
voilet/ pingoda of approved patten
and design including cost and
conveyance of all materials , hire
and labour charges etc. 4.50 m3 1 m3 124792.16 561564.72
6 Fabricating, supplying andand
fixing in position of openable
wooden glazed windows with
fixed portion on top whereever
necessary as per design made up
voilet/ pigoda wood and 4mm
thick plain or pin headed glass as
inserts of approved pattern with
grill including cost and
conveyance of all materials , hire
and labour charges and appling a
coat of primer etc complete. 29.00 m2 1 m2 7827.70 227003.30
7 Jally work in brick masonry in
cm 1:6 using contry burnt bricks
of nominal size including
centering , scaffolding , curing ,
material and labour charges etc.
complete 2.00 m3 1 m3 4604.53 9209.06
8 Supplying and fixing sintex colour
matt finish PVC doors with 3nos
stainless steel hinges, 2nos tower
bolt and 2nos handle, screws,
joining cleats, and gum etc
complete including all cost and
labour charges etc complete as per
specifications and as directed by
the Engineer in -chare 8.5 m2 1 m2 1759.12 14952.52
9 RCC M20 using 20mm hard
granite broken stone including all
form work, watering, curing, cost
and conveyance of all materials
and labour charges etc. complete
but excluding cost and labour of
steel reinforcement
a) Lintel beam 21.00 m3 1 m3 14988.22 314752.62
b) sunshade 6.50 m 3
1m 3
14452.59 93941.84
c) slab 40.00 m3 1 m3 13296.76 531870.40
10 Supplying and fabrication of
reinforcement grill using Fe 415
steel for RCC work, bend, tied,
and placed in postion including
cost and conveyance of all
materials , hire and labour charges
etc. 7550.00 kg 1 kg 69.07 521478.50
11 Ceiling plastering 1:3 CM 9mm
thick floated hard and trowelled
smooth including scaffolding,
watering curing cost and
conveyance of all materials , hire
and labour charges etc. complete. 500.00 m2 1 m2 220.83 110415.00
12 Plastering inside walls 1:4 12mm
thick floated hard and trowelled
smooth including scaffolding,
watering, curing cost and
conveyance of all materials , hire
and labour charges etc. complete. 535 m2 1 m2 239.62 128196.70
13 Plastering outside walls 1:4 12mm
thick floated hard and trowelled
smooth including scaffolding,
watering, curing cost and
conveyance of all materials , hire
and labour charges etc. complete. 315 m2 1 m2 239.62 75480.30
14 Providing boardering /water
cutting to bottom of sunshade and
roof projection also sides and
bottom of windows and doors in
the external/ internal sides
whereever it is required including
cost and labour charges etc.
complete.
75.00 m 1m 37.59 2819.25
15 Supplying and laying coloured
glazed ceramic tiles of any
branded make , shade and colour
and of maximum size
300mmx200mm laid in 15mm
thick CM 1:3 to correct line and
level, cutting neatly and pointing
with matching coloured cement
including cost and conveyance of
all materials , hire and labour
charges etc. complete 60.00 m2 1 m2 1174.63 70477.80
16 Supplying and fixing of coloured
cement tiles over a base of cement
mortar including all cost and
abour charges etc. complete 35.00 m2 1 m2 1013.00 35455.00
17
White washing two coats with
lovelicem/ equivalent to the under
side of all RCC slabs including all
cost and abour charges etc.
complete 500.00 m2 1 m2 16.91 8455.00
18
Colour washing to the inner side
of wall using distemper of any
branded make two coat over a
coat of white cement after
cleaning the newly plastered
surface using carborandum stones
including all cost and abour
charges etc. complete 535 m2 1 m2 63.90 34186.50
19 Painting two coats to the out side
of the walls using exterior
emulsion of any branded make
over a coat of cement primer
including cost and conveyance of
all materials , hire and labour
charges etc. complete. 315 m2 1 m2 122.16 38480.40
20 Painting the wooden doors with
two coats of ready mixed enamel
paint over a coat of wooden
primer after cleaning the surface
with sand papers including cost
and conveyance of all materials ,
hire and labour charges etc.
complete. 15 m2 1 m2 140.96 2114.40
21 Painting the windows with two
coats of ready mixed synthetic
enamel paint over a coat of wood
primer after cleaning the surfaces
with sand papers including cost
and conveyance of all materials ,
hire and labour charges etc.
complete. 55 m2 1 m2 140.96 7752.80
22 Supplying and fixing hand rail
using GI pipes and MS flats as per
design and drawing including all
cost and abour charges etc.
complete 32.00 m2 1 m2 704.78 22552.96
23 Painting the hand rail with two
coats of ready mixed enamel paint
over a coat of iron primer after
cleaning the surface with sand
papers including cost and
conveyance of all materials , hire
and labour charges etc. complete. 62.00 m2 1 m2 140.96 8739.52
24 Roof plastering in cm 1:3 15mm
thick floated hard and trowelled
smooth including watering, curing
cost and conveyance of all
materials , hire and labour charges
etc. complete. with water
proofing 310.00 m2 1 m2 276.27 85643.70
10050318.72

10050319.00
( Rupees one crore fifty thousand three hundred and nineteen only )