HOJA DE METRADOS

PROYECTO: CERCO PERIMETRICO UNIVERSIDAD PERUANA UNION


CURSO: GESTION DE EMPRESAS CONSTRUCTORAS
ELABORADO: TRAFASA S.A.C
Dimensiones
Partida Descripcin Und N Veces Parcial
L A H
01 CERCO PERIMETRICO
01.01 MOVIMIENTO DE TIERRAS
EXCAVACION MANUAL PARA
01.01.01 CIMIENTOS m3 1 15.00 1.50 1.00 22.50
ELIMINACION DE MATERIAL
01.01.02 EXCEDENTE m3 1 15.00 1.50 28.13
01.02 OBRAS DE CONCRETO SIMPLE

01.02.01 CIMIENTO CORRIDO (Fc=100 kg/cm2) m3 1 15.00 1.00 1.00 15.00

01.02.02 SOBRECIMIENTO (Fc=100 kg/cm2) m3 1 14.00 0.15 0.50 1.05


01.03 CONCRETO ARMADO
CONCRETO EN COLUMNAS fc=210
01.03.01 kg/cm2 m3 3 12.80 0.30 0.15 1.73

02.02 CONCRETO EN VIGAS fc=210 kg/cm2 m3 4 0.30 0.15 5.00 0.90


01.04 ALBAILERA
MURO DE SOGA LADRILLO KK 18
01.04.01 HUECOS CEMENTO- ARENA m2 2,200.00