# de Prdida de Cota piez.

Long. Longitud Casa Dimetro i Carga Velocidad Cota de Cota piez. de de


De A Hor. (Metros) s CAUDAL (Pulgadas) (Metros) (mts/seg) terreno Final Salida LLegada
0 26 610.00 1290 0 2.20 4 1.06 0.27 980.100 999.00 997.94
26 73 1390.00 1434 0 2.20 4 1.18 0.27 942.900 997.94 996.77
73 99 675.00 696 0 2.20 4 0.57 0.27 910.100 996.77 996.20
99 121 1286.00 1326 0 2.20 4 1.09 0.27 867.000 996.20 995.11
121 130 555.00 570 0 2.20 4 0.47 0.27 860.500 995.11 994.64
130 150 1040.00 2196 0 2.20 4 1.80 0.27 861.800 994.64 992.84
150 157 340.00 348 0 2.20 4 0.29 0.27 882.700 992.84 992.56
157 188 1890.00 1944 0 2.20 4 1.59 0.27 890.800 992.56 990.97
188 212 1350.00 1392 0 2.20 4 1.14 0.27 911.200 990.97 989.83
212 227 620.00 636 0 2.20 4 0.52 0.27 945.500 989.83 989.30
227 242 849.00 876 0 2.20 4 0.72 0.27 964.700 963.70 962.98
242 25 1610.00 1656 7 4.40 3 19.89 0.96 871.500 962.980 943.09

242 3 180.00 186 0 4.40 3 2.23 0.96 953.800 962.980 960.75


3 22 558.00 576 12 4.40 2.5 16.81 1.39 883.500 960.750 943.94

3 31 835.00 858 11 4.40 3 10.30 0.96 859.600 960.750 950.45

31 6 425.00 438 5 4.40 2.5 12.78 1.4 838.800 950.450 937.67

31 35 130.00 132 2 4.40 2.5 3.85 1.39 843.600 950.450 946.60

35 19 1752.00 1806 11 4.40 2 156.23 2.17 775.100 946.600 790.37

35 47 411.00 426 7 4.40 2.5 12.43 1.39 805.900 948.860 936.43


47 50 118.00 120 2 4.40 2.5 3.50 1.39 793.100 936.430 932.93
50 65 670.00 690 14 4.40 2.5 20.13 1.39 791.800 932.930 912.80

47 6 530.00 546 0 4.40 2.5 15.93 1.39 797.300 936.430 920.50


6 4 221.00 228 6 4.40 2.5 6.65 1.39 799.600 920.500 913.85

6 29 795.00 816 6 2.20 2.5 6.60 0.69 836.300 920.500 913.90

29 6 420.00 432 1 4.40 2 37.37 2.17 835.200 913.900 876.53


29 8 335.00 348 2 4.40 2 30.10 2.17 835.000 913.900 883.80

29 31 95.00 96 1 4.40 2.5 2.80 1.39 836.000 913.500 910.70


31 6 341.00 354 2 4.40 2 30.62 2.17 831.000 910.700 880.08

31 39 595.00 612 4 4.40 2.5 17.86 1.39 842.400 910.700 892.84


39 8 270.00 276 4 4.40 2 23.88 2.17 835.800 892.840 868.96
8 8 598.00 618 5 4.40 2.5 18.03 1.39 822.150 868.960 850.93

39 50 529.00 546 0 4.40 3 6.56 0.96 881.700 892.840 886.28

50 4 335.00 348 2 4.40 2.5 10.15 1.39 865.700 886.280 876.13


50 6 215.00 222 5 4.40 2.5 6.48 1.39 857.700 886.280 879.80
2.12 860
2076
8529
4399
###
Presin
de
Llegada
17.84
53.87
86.10
128.11
134.14
131.04
109.86
100.17
78.63
43.80
3.00
71.59

6.95
60.44

90.85

98.87

103.00

15.27

130.53
139.83 T.D.
121.00

123.20
114.25

77.60

41.33
48.80

74.70
49.08

50.44
33.16
28.78

4.58

10.43
22.10
PARAJE EL LETRERO, CASERIO LLANO GRANO, SAN GASPAR IXIL, HUEHUETENANGO
DISEO: Carlos A. Yac
Fecha: Enero 2002

CRITERIOS DE DISEO

Fuente: 1 Manantiales
Viviendas actuales: 109
Densidad de Poblacin: 6.00 Habitantes por vivienda
Poblacin actual: 654 Habitantes
% de crecimiento geomtrico: 3 %
Perodo de Diseo: 21 aos
Viviendas futuras: 203
Poblacin de diseo: 1217 Habitantes
Conexiones Domiciliares para el futuro: 65 Conexiones
Dotacin: 120 Lts / Hab / Da
Caudal medio diario: 1.69 Lts / seg
Factor de da mximo: 1.3
Factor de hora mximo: 2.8
Caudal de da mximo: 2.19 Lts / seg
Caudal de hora mximo: 4.73 Lts / seg
Almacenamiento diario: 40 M3
% de Almacenamiento: 38 % del caudal medio diario

Caudales de Distribucin
5
4.5
4
Caudales (Lts/seg)

3.5
3
2.5 Column J
2 Column K
1.5
1
0.5
0
0 20 40 60 80 100
# de Casas
PRESUPUESTO
CONSTRUCCION SALONES DE ESCUELA (5 SALONES)
COMUNIDAD AGRARIA NUEVO MONTECRISTO CHAMPERICO
RETALHULEU

1. TRABAJOS PRELIMINARES

1.1 GENERALES

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
1 Limpieza M.L. 82.94 20.00 1,658.80
2 Estaqueado M.L. 82.94 50.00 4,147.00
3 Excavacion M3 41 40.00 1,640.00
4 Nivelacion M2 315.77 10.00 3,157.70
TOTAL 10,603.50

2. LEVANTADO DE PARED

2.1 MATERIALES NO LOCALES

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
1 Block 0.15 x 0.20 x 0.40 M (BLOTECA) U 3720 3.50 13,020.00
2 Cemento gris Sacos 26 42.00 1,092.00
3 Material Selecto para relleno M3 31.42 150.00 4,713.00
TOTAL 18,825.00

2.2 MANO DE OBRA

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
4 Mano de obra M2 286 60.00 17160.00
TOTAL 17160.00

3. CIMENTACION

3.1 MATERIALES NO LOCALES

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
1 Block 0.15 x 0.20 x 0.40 M (BLOTECA) U 451 3.50 1,578.50
2 Cemento gris Sacos 90 42.00 3,780.00
TOTAL 1,578.50

3.2 MATERIALES LOCALES

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
3 Piedrin M3 4 150.00 600.00
4 Arena de rio M3 7 150.00 1,050.00
TOTAL 1,650.00

3.3 MANO DE OBRA

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
5 Mano de obra M3 7.5 300.00 2250.00
TOTAL 2250.00

4. TECHADO (LAMINA)

4.1 MATERIALES NO LOCALES

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
1 Lamina de zinc de 6' calibre 28 U 45 40.00 1,800.00
2 Lamina de zinc de 8' calibre 28 U 45 50.00 2,250.00
3 Lamina de zinc de 12' calibre 28 U 90 70.00 6,300.00
4 Costanera metalica de 2'' x 7'' x 1/16'' U 42 160.00 6,720.00
5 Capota para lamina calibre 28 U 6 120.00 720.00
6 Tensor para costanera varilla 3/8'' Varilla 8 15.00 120.00
7 Pernos de 3/8'' x 5'' U 384 7.00 2,688.00
8 Platina metalica 3/16'' x 4'' x 5'' x 5'' U 126 20.00 2,520.00
TOTAL 23,118.00

4.2 MATERIALES LOCALES

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
9 Madera pie/tabla de 10 pies 1'' x 12'' x 10' (para andam Docenas 2 300.00 600.00
10 Parales para soporte de entarimado 3'' x 5'' x 10'' Docenas 4 300.00 1,200.00
TOTAL 1,800.00

4.3 MANO DE OBRA

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
11 Mano de obra M2 363.21 60.00 21792.60
TOTAL 21792.60

5. ACABADOS

5.1 PLANILLA DE MATERIALES

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
1 Puerta 1 ancho=1.03, altura=3.10M, Metalica U 7 1800.00 12,600.00
2 Puerta 2 ancho=1.07, altura=3.10 M, Metalica U 2 1800.00 3,600.00
3 Ventana 1 Largo=2.32, Altura=1.37 M, Aluminio, ver Pl U 7 2500.00 17,500.00
4 Ventana 2 Largo=1.14, Altura=1.37 M, Aluminio, ver pl U 4 1500.00 6,000.00
5 Ventana 3 Largo=2.37, Altura=1.37 M, Aluminio, ver pl U 9 2700.00 24,300.00
6 Ventana 4 Largo=3.55, Altura=1.79 M, Aluminio, ver pl U 1 3500.00 3,500.00
7 Ventana 5 Largo=2.52, Altura=1.79 M, Aluminio, ver pl U 1 3000.00 3,000.00
8 Ventana 6 Largo=2.52, Altura=1.37 M, Aluminio, ver pl U 1 3000.00 3,000.00
9 Ventana 7 Largo=1.34, Altura=1.37 M, Aluminio, ver pl U 2 1700.00 3,400.00
10 Cemento para piso liso (Incluyendo materiales) M2 315 60.00 18,900.00
11 Cemento para torta cernida (Incluyendo materiales) M2 41.61 60.00 2,496.60
12 Pintura (Color variable) M2 800 15.00 12,000.00
13 Balcon 1 Largo=2.32, Altura=1.52 M U 7 1500.00 10,500.00
14 Balcon 2 Largo=1.14, Altura=1.52 M U 4 1200.00 4,800.00
15 Balcon 3 Largo=2.37, Altura=1.52 M U 9 2000.00 18,000.00
16 Balcon 4 Largo=3.55, Altura=1.94 M U 1 2500.00 2,500.00
17 Balcon 5 Largo=2.52, Altura=1.94 M U 1 2200.00 2,200.00
18 Balcon 6 Largo=2.52, Altura=1.52 M U 1 2700.00 2,700.00
19 Balcon 7 Largo=1.34, Altura=1.52 M U 2 2800.00 5,600.00
U 2 1500.00 3,000.00
TOTAL 159,596.60

5.2 MANO DE OBRA

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
20 Colocacion de puertas U 9 250.00 2,250.00
21 Colocacion de balcones U 25 300.00 7,500.00
22 Mano de obra alisado M2 32 40.00 1280.00
TOTAL 11030.00

6. COLUMNAS Y COLUMNAS INTERMEDIAS

6.1 MATERIALES NO LOCALES

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
1 Cemento gris Sacos 210 42.00 8,820.00
2 Hierro 1/4'' Varillas 398 11.00 4,378.00
3 Hierro 3/8'' Varillas 444 15.00 6,660.00
4 Alambre de amarre Libras 40 5.00 200.00
5 Clavos de 3'' a 4'' Libras 20 5.00 100.00
TOTAL 20,158.00

6.2 MATERIALES LOCALES

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
6 Arena de rio M3 10 150.00 1,500.00
7 Piedrin de 1/2" M 3
6 150.00 900.00
8 Madera de 1'' x 12'' x 12' Docenas 10 400.00 4,000.00
TOTAL 6,400.00

6.3 MANO DE OBRA

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
9 Armado y fundicion de columnas y columnas U 1 14000.00 14000.00
intermedias TOTAL 14000.00
7. INSTALACION DE AGUA POTABLE

7.1 MATERIALES NO LOCALES

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
1 Codos de 90 PVC de 1/2'' U 14 1.02 14.28
2 Codos horizontal de 90 CPVC de 1/2'' U 3 2.27 6.81
3 Tee PVC diamentro= 1/2'' U 15 1.64 24.60
4 Grifo de 1/2'' U 8 28.00 224.00
5 Tubo diametro 1/2'' PVC PSI Tubos 8 18.28 146.24
TOTAL 415.93

7.2 MANO DE OBRA

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
6 Mano de obra U 1 3000.00 3000.00
TOTAL 3000.00

8. INSTALACION DE DRENAJE

8.1 MATERIALES NO LOCALES

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
1 Retrete para sanitario Incisa Standar Color hueso U 6 1200.00 7,200.00
2 Codo vertical a 90 grados PVC diam.= 2 ''para drenaje U 3 15.72 47.16
3 Sifon terminal PVC diam.= 2'' U 1 71.97 71.97
4 Tee vertical a 90 grados PVC para drenaje U 1 18.69 18.69
5 Tuberia PVC diam.= 2'' U 7 95.33 667.31
6 Codo a 90 grados PVC para drenaje U 1 9.92 9.92
7 Tuberia PVC diam.= 2'' U 11 20.00 220.00
TOTAL 8,235.05

8.2 MANO DE OBRA

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
8 Caja de registro de 0.50 x 0.50 M U 6 250.00 1,500.00
9 Construccin de Fosa Sptica L=3.30 x A=1.20 x H=2. U 1 4500.00 4,500.00
10 Construccn de Pozo de Absorcin U 1 4500.00 4,500.00
11 Instalacion de pegado de tuberia M.L. 48 8.00 384.00
12 Instalacion de retrete U 6 200.00 1,200.00
TOTAL 12084.00

9. ILUMINACION

9.1 MATERIALES NO LOCALES

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
1 Tablero de distribucion 8 cir 125 AMP TL-812 U 1 175.00 175.00
2 Lampara fluorescente de 2 tubos de 40 watts U 18 250.00 4,500.00
3 Lampara fluorescente de 1 tubo de 40 watts U 11 125.00 1,375.00
4 Cajas hexagonales de aluminio para lamparas U 33 6.50 214.50
5 Plafonera en pared U 3 300.00 900.00
6 Alambre solido color verde calibre 12 M.L. 92 1.50 138.00
7 Alambre solido color rojo calibre 12 M.L. 92 1.50 138.00
8 Alambre solido color blanco calibre 12 calibre 14 M.L. 92 1.50 138.00
9 Tubo polyducto 3/4'' M.L. 3 63.84 191.52
10 Tuber{ PVC elctrico Diam.= 3/4'') Tubos 16 150.00 2,400.00
11 Flipon THQL de 1 polo 50 AMP U 8 30.00 240.00
TOTAL 10,410.02

9.2 MANO DE OBRA

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
12 Mano de obra - 1 5000.00 5000.00
TOTAL 5000.00
10. FUERZA

10.1 MATERIALES NO LOCALES

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
1 Tomacorriente doble 110 voltios Bticino U 10 10.37 103.70
2 Cajas rectangulares para tomacorriente de aluminio U 10 4.80 48.00
3 Alambre solido calibre 12 Color verde M.L. 40 1.50 60.00
4 Alambre solido calibre 12 Color rojo M.L. 40 1.50 60.00
5 Alambre solido calibre 12 Color blanco calibre 14 M.L. 40 1.50 60.00
6 Rollo de poliducto 3/4'' 300 pies Rollo 2 63.84 127.68
TOTAL 459.38

10.2 MANO DE OBRA

PRECIO
No. DESCRIPCION UNIDAD CANTIDAD UNITARIO TOTAL
7 Mano de obra - 1 4500.00 4500.00
TOTAL 4500.00

RESUMEN DE MATERIAL Y MANO DE OBRA

No. DESCRIPCION Material No Local Material Local Mano de Obra Total


1 Trabajos preliminares 10,603.50 10603.5
2 Levantado de pared 18,825.00 17160.00 35985.00
3 Cimentacion 1,578.50 1,650.00 2250.00 5478.50
4 Techado lamina 23,118.00 1,800.00 21792.60 46710.60
5 Acabados 159,596.60 11030.00 170626.60
6 Columnas y columnas intermedias 20,158.00 6,400.00 14000.00 40558.00
7 Instalacion de agua potable 415.93 3000.00 3415.93
8 Instalacion de drenaje 8,235.05 12084.00 20319.05
9 Iluminacion 10,410.02 5000.00 15410.02
10 Fuerza 459.38 4500.00 4959.38
SUBTOTAL 242796.48 9,850.00 101420.1 354066.58

INTEGRACION FINAL DEL PRESUPUESTO

No. RENGLON Material Local


1 Materiales y Mano de obra 352,026.58
2 Transporte de materiales 10,000.00
3 Administracion de campo (6 meses) 12,000.00
4 Prestaciones laborales 35,406.66
5 Supervision 10,000.00
6 Legalizacion de documentos y fianzas 8,000.00
TOTAL 427,433.24