CPD 30103 Plant Maintenance & Inspection UniKL MICET

MICET

Chapter 4
Installation,
Commissioning &
Testing in New Plant
Universiti Kuala Lumpur 1

Malaysian Institute of Chemical and Bioengineering Technology


CPD 30103 Plant Maintenance & Inspection SCET
MICET

Content
4.0 Installation, Commissioning &
Testing in New Process Plant
4.1 New Process Plant Set-Up
4.2 Personnel Requirement
4.3 Certificate of Commissioning

2
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Content
4.0 Installation, Commissioning &
Testing in New Process Plant
4.1 New Process Plant Set-Up
4.2 Personnel Requirement
4.3 Certificate of Commissioning

3
New Process Plant Set-up
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Any project will go through four major


phases:
a) Design.
b) Construction & Installation
c) Commissioning.
d) System Start Up, Operation &
Maintenance.
CPD 30103 Plant Maintenance & Inspection (a) Design SCET
MICET

In engineering, design used is to create new


thing or old thing is created in new way..
~ installation basically refers to fix the
new equipment for usage.
~ for new machinery or new plant

In chemical engineering, installation is a


part of plant design..
~ include of mass and energy balance
calculation, site selection, mechanical
design, piping and instrumentation, etc.
(b) Construction & Installation
CPD 30103 Plant Maintenance & Inspection SCET
MICET

The construction of chemical plant will


take from 6 month to 18 month based
on the cost of the project.
Everything that has been detail on the
specification sheet and on the various
diagram must put on place.
~ begin with preparing site, laying
foundation and ends with start up or
commissioning of plant.
Construction - Before
CPD 30103 Plant Maintenance & Inspection SCET
MICET

There are consultation among


the company with appointed
parties (Project Manager, main
contractor, sub-contractors)
Theplant is built as designed
and the contractor keep to time
schedule to complete the task
Construction - Before
CPD 30103 Plant Maintenance & Inspection SCET
MICET

The schedule will form be in form on


CPM/PERT (Critical Path Method/Program
Evaluation and Review Technique) or Gantt
Chart.

Representative (Project Manager) will


handle communication between the company
and Main Contractor for observation of
project and inspection of quality of
contractors work.
PERT/CPM Chart
CPD 30103 Plant Maintenance & Inspection SCET
MICET
Gantt Chart Template
CPD 30103 Plant Maintenance & Inspection SCET
MICET
Construction - During
CPD 30103 Plant Maintenance & Inspection SCET
MICET

many problem will arises


Representative (PM) must find
answer and resolve the problem
try to make certain laborers
are being properly used
(c) Commissioning
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Plant Commissioning is an important


phase within the project life cycle.
Upon completion of plant
installation, commissioning of plant
equipment and system functionality
test will be carried out to ensure
proper functionality of the plant
and optimize its performance.
Commissioning
CPD 30103 Plant Maintenance & Inspection SCET
MICET

a quality-assurance process for new


construction and installations - ensure
that building equipment and integrated
systems perform as company and
designers expect.
implements a systematic process to
verify and cross-check performance
from pre-design through warranty,
increasing the likelihood that a newly
constructed building will meet client
expectations
Commissioning
CPD 30103 Plant Maintenance & Inspection SCET
MICET

In return for investing in


commissioning, the building owner
can save money during construction
and throughout the operation and
maintenance of a quality building.
Designer can be an essential part
of the commissioning process,
helping to facilitate successful
commissioning, and promoting
overall client satisfaction.
Commissioning Goal
CPD 30103 Plant Maintenance & Inspection SCET
MICET

The primary goal is to provide a safe and


healthy facility for all occupants: office
staff, the public, students, faculty,
researchers, and operations and
maintenance staff.
The second goal is to improve energy
performance. Commissioning is the tune-up
that gets the most efficient performance
out of the installed equipment.
The third goal is to reduce operating costs.
Equipment operating improperly is operating
inefficiently.
Commissioning Goal
CPD 30103 Plant Maintenance & Inspection SCET
MICET

The fourth goal is to improve orientation


and training of the operations and
maintenance staff. The complicated
systems being installed will be disabled if
operations and maintenance staff do not
fully understand operation and maintenance
requirements. No matter how well the
equipment and systems are operating at the
outset, systems operation will collapse
without proper care.
Commissioning Goal
CPD 30103 Plant Maintenance & Inspection SCET
MICET

The fifth goal is improved documentation.


Specifications and drawings do not provide
all of the information needed for operation,
troubleshooting, and renovation of the
facility.
Fully documented testing procedures and
results verify the capacity and operating
parameters of the facility and systems, and
facilitate re-commissioning as needed in the
future.
Commissioning Goal
CPD 30103 Plant Maintenance & Inspection SCET
MICET

The final and most important goal


is to meet the clients needs.
When the design and construction
is subjected to systematic
inspection and verification, the
design intent and customer
satisfaction will be achieved.
Commissioning Process
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Commissioning is a strategy that:


Begins early in the design process
Requires special bidding
requirements during contractor
selection
Controls the static and dynamic
testing that acceptance is based
on
Finishes with staff training and
warranty monitoring.
Commissioning Process
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Building systems to be commissioned


include:
Building enclosure and interior
finish materials
HVAC*/mechanical
Electrical
Lighting
Life safety
Plumbing

*HVAC ~heating, ventilating, and air conditioning


Building Commissioning
CPD 30103 Plant Maintenance & Inspection SCET
MICET

isa systematic process of


ensuring that building systems
are designed, installed,
functionally tested, and capable
of being operated and
maintained according to the
owners operational needs.
Building Commissioning
CPD 30103 Plant Maintenance & Inspection SCET
MICET

The key elements in building commissioning


include:
Thorough documentation of system design
intent, operating sequences, and test
procedures.
Verification of system performance based
on extensive functional testing and
measurement.
Training of building operations staff on
system operation and maintenance
procedures.
Ongoing monitoring of system performance
Building Commissioning
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Ensure that building systems operate


efficiently, meet the needs of the end
user, function as designed, and
maintain occupant comfort.

The initial costs of commissioning are


recovered many times over through
operating savings, improved staff
performance, and avoidance of costly
construction problems.
Commissioning Phase
CPD 30103 Plant Maintenance & Inspection SCET
MICET

There are three major stages during the


commissioning phases. Each phase
consists of a logical progression of steps
necessary to verify that installed plant
is fully functional and fit for its design
and operational purposes:
a) Pre-Commissioning.
b) Actual Commissioning.
c) Plant Trial Run.
(a) Pre-Commissioning
CPD 30103 Plant Maintenance & Inspection SCET
MICET

System Configuration Check

Verify all pipe work and connections


within the entire system are as per
the approved P & ID and relevant
design drawings.

Perform visual inspections on


equipment and pipe works to ensure
they are clean, properly installed and
with professional finishing.
Pre-Commissioning
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Instrumentation System Check

Verify all alarms settings and signals on


instrumentation are function as
intended.
Verify relevant signals from the field
instrumentation are displayed locally,
and on their corresponding control
panels.
Verify all instrumentation devices are
properly calibrated.
Pre-Commissioning
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Flushing & Cleaning of Lines & Vessels

Do internally clean up all pipe works


and pressure vessels, ensuring no
obstructions, blockages or any
potential contaminants in the process
lines or vessels as a result of poor
house keeping during the construction
phase.
Pre-Commissioning
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Flushing & Cleaning of Lines & Vessels

After flushing, it is important to


ensure all pipelines and equipment are
thoroughly dried off, especially if any
water incompatible chemicals are being
introduced to them during
commissioning.
(This is normally prevented by using
dry air to clean the pipes or vessels,
instead of water).
Pre-Commissioning
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Start-up & Shut-down Protocol

To provide a guide line and


concept for system
isolations, commissioning
sequences, testing period,
etc, prior to actual
commissioning.
(b) Actual Commissioning
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Equipment Testing Energization & Dynamic Testing

Thisinvolves the test of equipment


performances. Equipment such as
pumps, heat exchangers, cooling
towers, etc will be run individually
for certain period of time, and its
performances will be checked
against design specifications.
(b) Actual Commissioning
CPD 30103 Plant Maintenance & Inspection SCET
MICET

System Functional Testing

Individual plant system will be


run and all mechanical &
electrical items within that
particular system will be
checked to ensure the entire
system is function as per its
design concept.
(c) Plant Trial Run
CPD 30103 Plant Maintenance & Inspection SCET
MICET

The entire plant will be put into


operation.
All system involves will be run
concurrently to simulate actual
plant operation condition.
Plant final output will be verified.
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Content
4.0 Installation, Commissioning &
Testing in New Process Plant
4.1 New Process Plant Set-Up
4.2 Personnel Requirement
4.3 Certificate of Commissioning

37
Personnel Requirement
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Plant Commissioning is a specialized


area which shall be handled by
qualified personnel.
This is especially so when comes to
commissioning certain specialized
equipment such as gas and steam
turbines, compressors and boilers.
Personnel Requirement
CPD 30103 Plant Maintenance & Inspection SCET
MICET

The following personnel shall participate and


witness the commissioning of plant equipment
and system :

a) The Final Plant Operator (Client).


b) The Main Contractor.
c) The Original Equipment Manufacturer.
d) Local Authority ( Such as BOMBA).
e) Third Party Consultants (Normally
Engaged by Client).
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Content
4.0 Installation, Commissioning &
Testing in New Process Plant
4.1 New Process Plant Set-Up
4.2 Personnel Requirement
4.3 Certificate of Commissioning

40
Project Organizational Chart
CPD 30103 Plant Maintenance & Inspection SCET
MICET

41
Contract Document Requirements
CPD 30103 Plant Maintenance & Inspection SCET
MICET

There are three contract documents


required to appropriately incorporate
and coordinate the commissioning
process:
i. the design professional agreement,

ii. the commissioning authority


agreement,
iii. and the construction contract.
Design Professional Agreement
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Design professionals may include the


architect, mechanical design engineer,
electrical design engineer, or other
specialty sub-consultants.
The design professionals scope of
services should include their
assistance in development of the scope
of commissioning services and
participation in the selection of a
commissioning authority.
Design Professional Agreement
CPD 30103 Plant Maintenance & Inspection SCET
MICET

The design professional agreement


must address communication with the
commissioning authority (CA) during
design and construction.
The design professionals must
participate in resolution of problems
and conflicts during construction.
Commissioning Authority Agreement
CPD 30103 Plant Maintenance & Inspection SCET
MICET

The owner must have the full


commitment of the commissioning
authority (CA) during the project.
The scope of services includes:
i. responsibilities during the design and
construction.
ii. a quality-assurance role relative to the
contractors commissioning activities.
iii. witnessing and verifying the results of
systems functional performance tests
Commissioning Authority Agreement
CPD 30103 Plant Maintenance & Inspection SCET
MICET

The commissioning authoritys


agreement should also include:
i. analysis of the functional performance
test results,
ii. review of the contractors proposed
corrective measures when test results
are not acceptable, and
iii. recommendation of alternate or
additional corrective measures, as
appropriate in the commissioning
authoritys scope.
Construction Contract
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Contractors and manufacturers


representatives construct the facility.
They provide, install, start-up, and often
test the buildings systems and their
components.

They are also responsible for providing


system documentation and training building
staff.
Commissioning Lead Qualifications
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Technical knowledge
In all commissioning projects, the
commissioning lead should have experience and
up-to-date technical knowledge in the related
fields of design, construction and building
operations.
Relevant experience
The commissioning lead must have experience
troubleshooting commissioned systems. The
lead should have served in a similar capacity on
at least two other projects with similar needs.
Commissioning Lead Qualifications
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Communication and organizational skills


Diplomacy and an ability to resolve
conflicts are also essential.
References and sample work products
The commissioning lead should provide
references and work products from
other, similar commissioning projects.
Testing & Commissioning Work Objectives
CPD 30103 Plant Maintenance & Inspection SCET
MICET

i. to verify proper functioning of the


equipment/system after installation.
ii. to verify that the performance of the
installed equipment/systems meet with the
specified design intent through a series of
tests and adjustments.
iii. to capture and record performance data of
the whole installation as the baseline for
future operation and maintenance.
Testing & Commissioning Work Scope
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Tests and Inspections during Construction


The purpose of these tests is to ensure that all
components and systems are in a satisfactory
and safe condition before start up.
Functional Performance Tests
The purpose of functional performance tests is
to demonstrate that the equipment/installation
can meet the functional and performance
requirements as specified in the
General/Particular Specifications.
Testing & Commissioning Work Scope
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Commissioning and Statutory Inspections


Commissioning is the advancement of an
installation from the stage of static
completion to full working conditions and
to meet the performance requirements as
specified in the General/Particular
Specification.
Documentation and Deliverables
All inspection and T & C results shall be
recorded in the data record forms
CPD 30103 Plant Maintenance & Inspection SCET
MICET
CPD 30103 Plant Maintenance & Inspection SCET
MICET
CPD 30103 Plant Maintenance & Inspection SCET
MICET
CPD 30103 Plant Maintenance & Inspection SCET
MICET
CPD 30103 Plant Maintenance & Inspection SCET
MICET
Understanding Insulation Resistance Testing
CPD 30103 Plant Maintenance & Inspection SCET
MICET

Why have an insulation testing


program?
A regular program of testing insulation
resistance is strongly recommended to
prevent electrical shocks, assure safety
of personnel and to reduce or eliminate
down time.
primarily to test motor, generator and
transformer insulation
Understanding Insulation Resistance Testing
CPD 30103 Plant Maintenance & Inspection SCET
MICET

What causes insulation failure?


Some of the more common causes of
insulation failure include:
excessive heat or cold,
moisture, dirt, corrosive vapors,
oil, vibration, aging and
nicked wiring.
Testing & Commissioning Work Scope
CPD 30103 Plant Maintenance & Inspection SCET
MICET

CLASSIFICATION OF TESTS
Pump tests should be classified as
follows:
Shop tests are also called laboratory,
manufacturers, or factory acceptance
tests.
They are conducted in the pump
manufacturers plant under geometrically
similar, ideal, and controlled conditions
and are usually assumed to be the most
accurate tests.
Testing & Commissioning Work Scope
CPD 30103 Plant Maintenance & Inspection SCET
MICET

CLASSIFICATION OF TESTS
Pump tests should be classified as follows:
Field tests are made with the pumping unit
installed in its exact environment and
operating under existing field or ultimate
conditions.
The accuracy and reliability of field testing
depend on the instrumentation used,
installation, and advance planning during the
design stages of the installation.
By mutual agreement, field tests can be used as
acceptance tests.
CPD 30103 Plant Maintenance & Inspection SCET
MICET
Commissioning Certificate
CPD 30103 Plant Maintenance & Inspection SCET
MICET

When equipment or a system is


commissioned successfully, a
certificate will be issued to justify its
functionality and performances.

This certificate is normally issued by


the Client ( Final Plant Operator) to
the contractor.

This certificate is referred as


Commissioning Certificate
Commissioning Certificate
CPD 30103 Plant Maintenance & Inspection SCET
MICET

If local authorities are involve in


the approval process, such as the
plant fire fighting system where
BOMBA will have the final
jurisdiction on the system, this
certificate has to be approved by
them as well.
Provisional Acceptance Certificate (PAC)
CPD 30103 Plant Maintenance & Inspection SCET
MICET

This document is issued by the


clients to the contractor once trial
run is completed successfully.

This certificate is an indication of


accepting the plant temporarily based
on the positive outcomes from the
trial run.
Warranty Period
CPD 30103 Plant Maintenance & Inspection SCET
MICET

For any project, the contractor is


normally contractually obligated to
give warranty on plant equipment and
system performances to its clients, at
a period mutually agreed by both
parties.

The time frame normally ranges from


1 to 3 years, and is referred as
Warranty Period.
Warranty Period
CPD 30103 Plant Maintenance & Inspection SCET
MICET

It is the responsibilities of the


contractor to repair the equipment
and resolve any issues affecting the
plant performances without any cost
to its client, if such occurrences
happen during the warranty period.
CPD 30103 Plant Maintenance & Inspection Hand Over SCET
MICET

Upon completion of the warranty


period, and if there is no issues arise
on the plant operations and
performances, Final Acceptance
Certificate ( FAC) will be issued to
the contractor.

The plant is considered handover


officially to the client.
CPD 30103 Plant Maintenance & Inspection SCET