Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr M
1 ABPR3 MainCoolingWaterSystem Thu300317 Sat170617 80days 30-03
30-03 Main
Main Cooling
Cooling Water
Water System
System
6 ABPR3 AuxilairyCoolingWaterSystem Thu300317 Wed030517 35days 30-03 Auxilairy Cooling Water System
17 PipeInstallation Thu 12-01-17 Wed 03-05-17 112 days 12-01 Pipe Installation
26 ABPR3 Instrument&ServiceAirSystem Thu230317 Tue220817 153days 23-03 Instrument & Service Air System
27 PipeInstallation Thu 23-03-17 Tue 01-08-17 132 days 23-03 Pipe Installation
33 NDE (RT&PT) Fri 31-03-17 Tue 04-04-17 4 days 31-03 NDE (RT&PT)
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr M
35 Punchclear Thu 06-04-17 Sat 08-04-17 3 days 06-04 Punch clear
43 Pipe Installation Fri 09-06-17 Sat 10-06-17 1 day? 09-06 Pipe Installation
44 Line Check Sun 11-06-17 Sun 11-06-17 1 day? 11-06 Line Check
45 Punch Clear Mon 12-06-17 Tue 13-06-17 1 day 12-06 Punch Clear
46 Hyd. Test Wed 14-06-17 Fri 16-06-17 2 days 14-06 Hyd. Test
48 Pipe Installation Mon 03-04-17 Fri 09-06-17 67 days 03-04 Pipe Installation
49 NDE (RT) Thu 18-05-17 Wed 21-06-17 34 days 18-05 NDE (RT)
50 Line Check Sat 17-06-17 Wed 21-06-17 4 days 17-06 Line Check
51 Punch Clear Thu 22-06-17 Fri 30-06-17 8 days 22-06 Punch Clear
52 Hyd. Test Sat 01-07-17 Mon 03-07-17 2 days 01-07 Hyd. Test
54 Pipe Installation Mon 03-04-17 Wed 24-05-17 51 days 03-04 Pipe Installation
55 Line Check Thu 25-05-17 Fri 26-05-17 2 days 25-05 Line Check
56 Punch Clear Sat 27-05-17 Tue 13-06-17 17 days 27-05 Punch Clear
57 Hyd. Test Tue 13-06-17 Thu 15-06-17 2 days 13-06 Hyd. Test
59 Pipe Installation Mon 03-04-17 Sat 15-07-17 103 days 03-04 Pipe Installation
61 Line Check Mon 24-07-17 Wed 26-07-17 3 days 24-07 Line Check
62 Punch Clear Thu 27-07-17 Wed 16-08-17 21 days 27-07 Punch Clear
63 Hyd. Test Wed 16-08-17 Fri 18-08-17 2 days 16-08 Hyd. Test
65 Pipe Installation Mon 03-04-17 Mon 17-07-17 105 days 03-04 Pipe Installation
67 Line Check Tue 25-07-17 Thu 27-07-17 3 days 25-07 Line Check
68 Punch Clear Fri 28-07-17 Sat 12-08-17 15 days 28-07 Punch Clear
69 Hyd. Test Mon 14-08-17 Tue 15-08-17 2 days 14-08 Hyd. Test
71 Pipe Installation Wed 26-04-17 Thu 01-06-17 36 days 26-04 Pipe Installation
72 Line Check Fri 02-06-17 Fri 09-06-17 7 days 02-06 Line Check
73 Punch Clear Sat 10-06-17 Sat 17-06-17 7 days 10-06 Punch Clear
74 Hyd. Test Mon 19-06-17 Mon 26-06-17 8 days 19-06 Hyd. Test
77 Pipe Installation Tue 28-03-17 Fri 26-05-17 59 days 28-03 Pipe Installation
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr M
78 Line Check Mon 26-06-17 Wed 28-06-17 2 days 26-06 Line Check
79 Punch Clear Thu 29-06-17 Sat 01-07-17 3 days 29-06 Punch Clear
80 Hyd. Test Sun 02-07-17 Tue 04-07-17 3 days 02-07 Hyd. Test
82 Pipe Installation Tue 28-03-17 Fri 26-05-17 59 days 28-03 Pipe Installation
83 Line Check Mon 26-06-17 Wed 28-06-17 2 days 26-06 Line Check
84 Punch Clear Wed 28-06-17 Sat 01-07-17 3 days 28-06 Punch Clear
85 Hyd. Test Sun 02-07-17 Tue 04-07-17 3 days 02-07 Hyd. Test
87 Pipe Installation Thu 23-03-17 Tue 16-05-17 55 days 23-03 Pipe Installation
88 Line Check Tue 16-05-17 Wed 17-05-17 1 day 16-05 Line Check
89 Punch Clear Wed 17-05-17 Sat 27-05-17 10 days 17-05 Punch Clear
90 Preparation Temporary Pipe for Hyd. Wed 17-05-17 Sat 27-05-17 10 days 17-05 Preparation Temporary Pipe for Hyd. Test and Flushing
Test and Flushing
91 Hyd. Test Sun 28-05-17 Thu 01-06-17 4 days 28-05 Hyd. Test
93 Pipe Installation Mon 29-05-17 Wed 31-05-17 3 days 29-05 Pipe Installation
94 Line Check Thu 01-06-17 Thu 01-06-17 1 day 01-06 Line Check
95 Punch Clear Fri 02-06-17 Sat 03-06-17 1 day 02-06 Punch Clear
97 Pipe Installation Mon 20-03-17 Thu 04-05-17 46 days 20-03 Pipe Installation
98 Line Check Fri 05-05-17 Fri 05-05-17 1 day 05-05 Line Check
99 Punch Clear Sat 06-05-17 Wed 10-05-17 5 days 06-05 Punch Clear
100 Hyd. Test Wed 10-05-17 Thu 11-05-17 2 days 10-05 Hyd. Test
102 Pipe Installation Mon 17-04-17 Sat 01-07-17 75 days 17-04 Pipe Installation
103 Line Check Mon 03-07-17 Tue 04-07-17 2 days 03-07 Line Check
104 Punch Clear Wed 05-07-17 Sat 08-07-17 4 days 05-07 Punch Clear
105 Hyd. Test Sun 09-07-17 Wed 12-07-17 3 days 09-07 Hyd. Test
108 UAT- Oil seperator Tue 07-02-17 Sat 18-03-17 7 days 07-02 UAT- Oil seperator
109 AUT- Oil seperator Mon 13-03-17 Thu 30-03-17 17 days 13-03 AUT- Oil seperator
110 GTG- Oil seperator Thu 23-03-17 Wed 26-04-17 34 days 23-03 GTG- Oil seperator
111 CEP- Oil seperator Thu 20-04-17 Wed 17-05-17 27 days 20-04 CEP- Oil seperator
112 EDG- Oil seperator Fri 07-04-17 Fri 12-05-17 35 days? 07-04 EDG- Oil seperator
113 Oil seperator - Retention pit Thu 02-02-17 Wed 01-03-17 27 days 02-02 Oil seperator - Retention pit
114 Line check Fri 12-05-17 Thu 18-05-17 6 days? 12-05 Line check
115 Punch clear Thu 18-05-17 Thu 25-05-17 7 days 18-05 Punch clear
117 Pipe installation Sat 25-03-17 Mon 01-05-17 37 days? 25-03 Pipe installation
118 Line check Tue 02-05-17 Wed 03-05-17 2 days 02-05 Line check
119 Punch clear Wed 03-05-17 Fri 05-05-17 2 days 03-05 Punch clear
121 Pipe installation Wed 01-02-17 Mon 13-03-17 40 days? 01-02 Pipe installation
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr M
122 Line check Mon 13-03-17 Thu 16-03-17 3 days 13-03 Line check
123 Punch clear Thu 16-03-17 Sat 18-03-17 2 days 16-03 Punch clear
124 Retention Basin Pit pipe Installation Sun 19-02-17 Wed 22-03-17 31 days
125 Pipe installation Sun 19-02-17 Wed 22-03-17 31 days 19-02 Pipe installation
126
127
155 NDE (RT&PT) Wed 13-09-17 Wed 20-09-17 7 days 13-09 NDE (RT&PT)
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr M
158 Pig cleaning Sun 24-09-17 Fri 29-09-17 5 days 24-09 Pig cleaning
161 Pipe Installation Tue 27-06-17 Tue 25-07-17 28 days 27-06 Pipe Installation
162 Line Check Tue 25-07-17 Thu 27-07-17 2 days 25-07 Line Check
163 Punch Clear Wed 26-07-17 Sun 30-07-17 4 days 26-07 Punch Clear
164 Hyd. Test Sat 29-07-17 Wed 02-08-17 4 days 29-07 Hyd. Test
166 Pipe Installation Mon 15-05-17 Fri 21-07-17 67 days 15-05 Pipe Installation
167 NDE (RT) Thu 29-06-17 Fri 28-07-17 29 days 29-06 NDE (RT)
168 Line Check Sat 29-07-17 Wed 02-08-17 4 days 29-07 Line Check
169 Punch Clear Thu 03-08-17 Fri 11-08-17 8 days 03-08 Punch Clear
170 Hyd. Test Fri 11-08-17 Mon 14-08-17 3 days 11-08 Hyd. Test
172 Pipe Installation Mon 07-08-17 Wed 27-09-17 51 days 07-08 Pipe Installation
173 Line Check Thu 28-09-17 Wed 04-10-17 6 days 28-09 Line Check
174 Punch Clear Wed 04-10-17 Wed 18-10-17 14 days 04-10 Punch Clear
175 Hyd. Test Wed 18-10-17 Thu 19-10-17 1 day 18-10 Hyd. Test
177 Pipe Installation Sun 14-05-17 Fri 25-08-17 103 days 14-05 Pipe Installation
179 Line Check Sat 02-09-17 Wed 06-09-17 4 days 02-09 Line Check
180 Punch Clear Wed 06-09-17 Wed 27-09-17 21 days 06-09 Punch Clear
181 Hyd. Test Wed 27-09-17 Fri 29-09-17 2 days 27-09 Hyd. Test
183 Pipe Installation Wed 12-07-17 Sat 07-10-17 87 days 12-07 Pipe Installation
185 Line Check Fri 13-10-17 Wed 18-10-17 5 days 13-10 Line Check
186 Punch Clear Tue 17-10-17 Sat 04-11-17 18 days 17-10 Punch Clear
187 Hyd. Test Fri 03-11-17 Wed 08-11-17 5 days 03-11 Hyd. Test
189 Pipe Installation Wed 19-07-17 Fri 08-09-17 51 days 19-07 Pipe Installation
190 Line Check Thu 07-09-17 Sun 10-09-17 3 days 07-09 Line Check
191 Punch Clear Sat 09-09-17 Sat 16-09-17 7 days 09-09 Punch Clear
192 Hyd. Test Fri 15-09-17 Mon 25-09-17 10 days 15-09 Hyd. Test
194 Pipe Installation Sun 11-06-17 Sat 05-08-17 55 days 11-06 Pipe Installation
195 Line Check Fri 04-08-17 Mon 07-08-17 3 days 04-08 Line Check
196 Punch Clear Sun 06-08-17 Wed 09-08-17 3 days 06-08 Punch Clear
197 Hyd. Test Tue 08-08-17 Sat 12-08-17 4 days 08-08 Hyd. Test
199 Pipe Installation Tue 27-06-17 Thu 27-07-17 30 days 27-06 Pipe Installation
200 Line Check Thu 27-07-17 Sat 29-07-17 2 days 27-07 Line Check
201 Punch Clear Fri 28-07-17 Mon 31-07-17 3 days 28-07 Punch Clear
202 Hyd. Test Mon 31-07-17 Fri 04-08-17 4 days 31-07 Hyd. Test
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr M
203 ABPR4 CCCWSystem Mon080517 Wed270917 142days
204 Pipe Installation Wed 02-08-17 Wed 27-09-17 56 days 02-08 Pipe Installation
205 Line Check Mon 08-05-17 Wed 10-05-17 2 days 08-05 Line Check
206 Punch Clear Wed 10-05-17 Sat 13-05-17 3 days 10-05 Punch Clear
207 Preparation Temporary Pipe for Hyd. Sat 16-09-17 Thu 21-09-17 5 days 16-09 Preparation Temporary Pipe for Hyd. T
Test and Flushing
208 Hyd. Test Thu 11-05-17 Wed 24-05-17 13 days 11-05 Hyd. Test
210 Pipe Installation Mon 19-06-17 Sat 24-06-17 5 days 19-06 Pipe Installation
211 Line Check Fri 23-06-17 Sun 25-06-17 2 days 23-06 Line Check
212 Punch Clear Sat 24-06-17 Mon 26-06-17 2 days 24-06 Punch Clear
214 Pipe Installation Wed 05-07-17 Thu 03-08-17 29 days 05-07 Pipe Installation
215 Line Check Thu 03-08-17 Sat 05-08-17 2 days 03-08 Line Check
216 Punch Clear Sat 05-08-17 Mon 07-08-17 2 days 05-08 Punch Clear
217 Hyd. Test Mon 07-08-17 Sat 12-08-17 5 days 07-08 Hyd. Test
219 Pipe Installation Fri 12-05-17 Fri 28-07-17 77 days 12-05 Pipe Installation
220 Line Check Fri 28-07-17 Sun 30-07-17 2 days 28-07 Line Check
221 Punch Clear Sun 30-07-17 Thu 03-08-17 4 days 30-07 Punch Clear
222 Hyd. Test Thu 03-08-17 Tue 08-08-17 5 days 03-08 Hyd. Test
225 Pipe installation Mon 08-05-17 Wed 16-08-17 100 days 08-05 Pipe installation
226 Line check Tue 15-08-17 Thu 17-08-17 2 days 15-08 Line check
227 Punch clear Thu 17-08-17 Thu 24-08-17 7 days 17-08 Punch clear
229 Pipe installation Thu 27-07-17 Sat 02-09-17 37 days 27-07 Pipe installation
230 Line check Sat 02-09-17 Tue 05-09-17 3 days 02-09 Line check
231 Punch clear Mon 04-09-17 Sat 09-09-17 5 days 04-09 Punch clear
233 Pipe installation Mon 08-05-17 Fri 07-07-17 60 days? 08-05 Pipe installation
234 Line check Fri 07-07-17 Sun 09-07-17 2 days 07-07 Line check
235 Punch clear Sat 08-07-17 Tue 11-07-17 3 days 08-07 Punch clear
236 Retention Basin Pit pipe Installation Wed 21-06-17 Sat 22-07-17 31 days
237 Pipe installation Wed 21-06-17 Sat 22-07-17 31 days 21-06 Pipe installation