Professional Documents
Culture Documents
Lesson 07
Chapter 7 Approach Roadway Deformations
Testing Theory
Experience
Topics
Lesson 07 - Topic 1
Approach Roadway Deformations
Section 7.0 7.6
Learning Outcomes
g Shallow
Embankment Fill
translational
failure (Infinite Firm Soil
Slope)
g Circular
Failure
Stability Problems
g Sliding
block
failure
g Lateral
squeeze
- Lesson 7
Approach Roadway Deformations
g Internal
- Within the embankment fill
Due to compression of the fill materials
Poor drainage
g External
- In the native soils below the embankment fill
Vertical and lateral deformation of native soils
Vertical: Immediate and consolidation settlements
Lateral: Squeeze (cause tilting of structures)
Internal Deformations
Avoiding Internal Deformations
90% T180 3
5 100% T99
1
1
11
6 Topsize
Heel Projection + 3 ft
Select Material Specifications
0.2p
Do you think there is a settlement
problem for the case shown below?
Granular Fill
24
= 120 pcf
Sandy Gravel
23
= 120 pcf ( = 60 pcf)
6 Soft Clay
Sand
Combined Plot of Stresses
Figure 2-13
Pressure
p pf
Legend:
zw zw = depth to groundwater
po = effective overburden pressure
pt = total overburden pressure
p = pressure due to external loads
pf = p0 + p
po pt
Depth, z
Fundamental Principles
60 100
1.0
0.38b
0.7 Centerline
0.5
0.8bf = 64 ft
Depth
0
Below
Mid Point of Surface
Side Slope
Computation of Immediate
Settlement (Vertical Deformation)
g Many methods for estimating immediate
settlement are available
g All
methods are based on some form of
estimate of soil compressibility
- Bearing Capacity Index, Compression Index,
Elastic Modulus, Constrained Modulus, etc.
Computation of Immediate
Settlement (Vertical Deformation)
g For embankments use Houghs method
- Simple to use
- Settlement estimates are conservative by a
factor of 2 (FHWA 1987)
1 p 0 + p
H = H log 10
C p0
Houghs Chart
g Inorganic SILT
curve should
not be used for
soils exhibiting
plasticity
g Determine
immediate settlement of a wide
embankment placed on silty sand
t = 120 pcf
20 ft
10 ft Silty Sand
t = 120 pcf, N160 = 20
Example 7-2 Draw po diagram
g Assume no dissipation of stress under the
centerline of a wide embankment
Pressure (psf)
pf
po
3000
5 600 p = 2400
Depth (ft)
10
Example 7-2 Draw po diagram
g Find settlement
1 p 0 + p
H = H log 10
C p0
1 600psf + 2400psf
H = 10 ft log 10
58 600psf
H = 0.12 ft = 1.44 in
Vertical p = th h
0.2p
Implications of Embankment
Settlement
g At end of embankment construction,
additional fill is required to reach final grade
g 1 inch of settlement over 1 mile of 60-ft wide
embankment will need approximately 1000
cubic yards of additional fill
g This is sometimes referred to as
Compaction Factor and is included in bid
documents
Student Exercise 3
g GIVEN: povalues at the depths where SPTs
were taken; Soil is fine to coarse sand
Depth, ft SPT N60-values po (psf)
5 6 550
10 10 1100
15 15 1650
20 17 2200
25 16 2438
g FIND: (a) N160 value
(b) C (bearing capacity index) value
Student Exercise
g Solution
Consolidation (Long-term) Deformation
to External 0.6p
Loadings 0.4p
Soft
0.2p Layer
g NoteLateral
Stresses
Beyond
Loaded
Area
Consolidation (Long-term) Deformation
'v
p n Cc pf
eo = e p Sc = H o log10
i 1 + eo po
VOID RATIO, e
Cc
ef
0.42e o
eo '
ppc
1
C n Ho pc pf
ep S= ( C r log10 + Cc log10 )
1 1 + eo po pc
VOID RATIO, e
1
ef
Cc
0.42e o
pcp pov 0
pf v f
e0
pov0
p v
1
ep Cr
n Ho p0 pf
S= ( Cc log10 + Cc log10 )
VOID RATIO
1 1 1 + eo pc p0
ef
Cc
1.0
2.0
3.0
4.0
5.0
6.0
7.0
1 2 3 4 5 6 7 8 9
Time (Months)
Example 7-3
t = 120 pcf
20
pf
po
3000
5 600 p = 2400
Depth (ft)
10
Example 7-3
(0.848)(10 ft ) 2
t 90 = = 424 days
2
0.2 ft / day
Student Soil Profile
Exercise 4 Granular Fill
= 120 pcf
24'
Compute:
(a) Primary
Sandy Gravel
23' T = 122 pcf
settlement 6' Soft Clay T= 104 pcf, e o = 2.1, Cc = 1.1 Cv = 0.0175 ft2 /day
of NC clay Sand
Pressure Diagram
(b) Time in
months for Sandy po pF
90% Gravel
primary
Middle of clay layer
23
Clay
settlement 29 p
Secondary Compression
Fill
Lateral Zone of Tensile
Stresses
Squeeze p = t h
h
0.6p
g Short-term 0.4p
undrained Soft
0.2p Layer
bearing
capacity
failure
g Long-term
drained 3-D
creep
Abutment Tilting Due to Lateral
Squeeze
Rotation of Rockers
Threshold Condition for Lateral
Squeeze
2c u 4.14c u
FSSQ = +
D S tan H
Lateral Squeeze:
How to Prevent Abutment Rotation
THE ROAD TO
UNDERSTANDING
SOILS
AND
FOUNDATIONS
APPROACH ROADWAY
DEFORMATIONS
Lesson 07 - Topic 2
Mitigation of Approach Roadway Deformations
Construction Monitoring and Quality Assurance
Section 7.7, 7.8, 7.9
Learning Outcomes
g Surcharge treatment
g Vertical drains
Embankment on Clay Foundation
Effect of Surcharge Treatment
Surcharge
Surcharge
Fill
Fill
Without
Without
Settlement
Settlement
Surcharge
Surcharge Clay
Clay
With
With Surcharge
Surcharge
Time Time
Time for
for Equivalent
Equivalent Settlement
Settlement Time
Time for
for Total
Total Settlement
Settlement
Time With Surcharge Remove
With Surcharge Remove Without Surcharge
Without Surcharge
Surcharge
Surcharge at
at This
This Time
Time
Acceleration of Consolidation
Using Vertical Drainage
Sand
Clay
Vertical Drains
Surcharge
Settlement Platform
Drainage Blanket
Permanent Fill
Soft Clay
Vertical
Drain
Firm Soil
Fill
S.I. Original Ground S.I.
H
H
4 3
2 H
Soft Clay 4
H
Firm Soil
Piezometers
Settlement Plate
S.I.
Slope Inclinometer
Settlement Platform Schematic
Vertical Inclinometer
Embankment
Compressible
Soil
Firm Soil
Principle of Inclinometer Operation
L Sin
L Sin
Embankment
Compressible
Soil
Learning Outcomes
THE ROAD TO
UNDERSTANDING
SOILS
AND
FOUNDATIONS
Interstate 0 Apple Freeway
Note: Scale shown in Station Form
S.B. N.B.
Apple Apple
Frwy Frwy
Baseline
Baseline 90
90 91
91 92
92 93
93
Stationing
Stationing
Interstate
Interstate 00
Proposed
Proposed Toe
Toe
of
of Slope
Slope
Proposed
Proposed Final
Final Grade
Grade
2 Proposed
Proposed
1 Abutment
Abutment
Existing
Existing
Ground
Ground Surface
Surface
9
Subsurface Terrain reconnaissance
Apple Freeway
Explorations Site inspection
Subsurface borings
9
Basic Soil Properties Visual description
Exercise
Classification tests
Soil profile
9
Laboratory Testing Po diagram
Test request
Consolidation results
- Section A.6 9
Slope Design soil profile
Stability Circular arc analysis
Sliding block analysis
Lateral squeeze analysis
Fill
2:1 = 130 pcf
= 400 30'
c=0
Clay
= 65 pcf
Cc = 0.35
Cr = 0.035 35'
Cv = 0.6 ft 2 /day
w = 35%
s.g. = 2.78
Incompressible
Po Diagram
Pressure (psf)
0 1000 2000 3000 4000 5000 6000
x 135 Organic x 4100
x 570 Sand x 4460
10
x 1020 x 4950
20
x 1630
Clay pc 4450
x 5300
x
30
po
2460
x x 3600 pF x 5800
40
Compute Total Settlement
Total Settlement
12.66" (max. H)
15
Assume:
10 high compacted surcharge ( = 130 pcf)
P of emb. (PF) + surch. (Ps) = 5200 psf
Time - Settlement Plot
180
Days
30 Fill + 10 Surcharge
Recheck stability of 30 Fill With 10' Surcharge
F.S. Bishop= 1.33
2:1
33' Fill
Dense
Gravel
30' Fill
10
12.66"
30' Fill + 10' Surcharge
15 30' Fill w/Drains
Fill only 14 -
Fill w/10' surcharge 6 $120,000
fill w/ wick drain 2 $172,000
Summary Design Soil Profile
Soil layer consolidation
properties selected
Settlement
32" settlement predicted
Recommend organic excavation
Rec. waiting period @ abut.
Time-Rate
433 days for t90
Surcharge
10' surcharge improves t90 to 190 days
Cost $120,000, F.S. = 1.33 O.K.
Vertical Drains
60 days for t90
Cost $172,000 -> $385,000
Any Questions?
THE ROAD TO
UNDERSTANDING
SOILS
AND
FOUNDATIONS