QATAR BUILDING ENGINEERING COMPANY

SITE WORK PROCEDURE Doc. No. SWP.CS.04


Department QA/QC Rev. 1
Title Steel Reinforcement for concrete Works Date 05.12.01

SITE WORK PROCEDURE


SWP.CS.04
STEEL REINFORCEMENT FOR
CONCRETE WORKS

REVISION HISTORY

1 Revision-1 05.12.01

0 Original Issue 11.11.01

Rev. Revision information Date

Originated by Reviewed by Approved by

Owner: QBEC Page 1 of 3


QATAR BUILDING ENGINEERING COMPANY
SITE WORK PROCEDURE Doc. No. SWP.CS.04
Department QA/QC Rev. 1
Title Steel Reinforcement for concrete Works Date 05.12.01

Swaminathan Ganesan K.Kunjappan Hassan Sahli

-Signed-: -Signed-: -Signed-:

Owner: QBEC Page 2 of 3


QATAR BUILDING ENGINEERING COMPANY
SITE WORK PROCEDURE Doc. No. SWP.CS.04
Department QA/QC Rev. 1
Title Steel Reinforcement for concrete Works Date 05.12.01

STEEL REINFORCEMENTS FOR CONCRETE WORKS

1.0 OBJECTIVE

1.1 Is to define the requirements for the supply and execution g Reinforcement works
for the constructions under the contract no GTC.101/ED/01 Engineering,
Procurement, Installation and Commissioning (EPIC) of Ras Laffan Utilization Project
Buildings and utilities and support service Phase 1-Utilities.

2.0 SCOPE

2.1 For foundation, substructure and superstructure of buildings and utilities at Base
Area, New Service Berth in Berth Area, FSO Marine and Telecom building.

3.0 REFERENCE

3.1 Project Approved Drawings


3.2 Qatar Petroleum Standard Specification for Civil Works Clause 3.27&3.28

4.0 PROCEDURE

4.1 Approval shall be taken for Steel reinforcements of various sizes before the
commencement of concrete works.

4.2 Steel Reinforcement shall be bent accurately to the shapes and dimensions
shown on the drawings and approved bar bending schedules. Bars must not be re-
bent or straightened after bending. Special care must be taken that the depth of
the bend is correct and that the bar when bent is not in winding. All reinforcement
shall be bent cold.

4.3 All loose rust must be carefully and thoroughly removed from all bars before they
are placed in position and bars must not be painted or oiled .All bars must be
placed in the exact position shown on the drawings. Stirrups and binding wire shall
be in contact with the bars , the latter being wedged out so as tighter the binding or
stirrups, but no wedges must be left in. All bars must be bound together in their
correct position with iron wires, so that they cannot be displaced during concreting.
Great care must be taken that all bars are given their correct cover.

4.4 All the reinforcement placed in position and ready for concreting shall be taken
approval from QP engineer before closing the form work/concreting.

4.5 A competent steel fixer shall be present during the whole time that the concreting
is in progress.

Owner: QBEC Page 3 of 3


QATAR BUILDING ENGINEERING COMPANY
SITE WORK PROCEDURE Doc. No. SWP.CS.04
Department QA/QC Rev. 1
Title Steel Reinforcement for concrete Works Date 05.12.01

5.0 RECORDS

5.1 Mill certificate

5.2 Inspection reports

5.3 Checklist

5.4 Approved Bar -bending schedules

Owner: QBEC Page 4 of 3