You are on page 1of 36

EXTERNAL POST-TENSIONING

Contents
Preface.................................................................................................. 1
1. Introduction ............................................................................................ 2
1.1. Historical developments ....................................................................... 2
1.2. Areas of application today ..................................................................... 4
1.3. Types and components of external tendons ........................................ 5
General ................................................................................... 5
Prestressing steel ..................................................................... 5
Tendon anchorages .................................................................. 5
Corrosion protection systems ................................................... 6
Saddles at points of deviation .................................................. 7
1.4. Future developments .................................................................................. 7

2. Design Considerations for Bridges with External Tendons ................... 9


2.1. General.................................................................................................. 9
2.2. Serviceability and ultimate limit states................................................... 10
Serviceability limit state ........................................................... 10
Ultimate limit state..................................................................... 10
2.3. Particular aspects ................................................................................. 11
Saddles......................................................................................11
Minimum tendon radii .............................................................. 11
Prestress losses due to friction................................................ 11

3. VSL External Tendons .......................................................................... 12


3.1. Introduction.............................................................................................12
3.2. Types of VSL External Tendons and Technical Data ........................... 12
General .................................................................................... 12
Selection criteria ...................................................................... 12
Strands .................................................................................... 12
Characteristic breaking loads of VSL External Tendons ......... 13
Tubing ...................................................................................... 13
Anchorages ............................................................................. 13
Grouting compounds ............................................................... 13
3.3. Experimental evidence ........................................................................ 15

4. Application of the VSL External Tendons.............................................. 16


4.1. Manufacture and installation ................................................................ 16
Prefabrication .......................................................................... 16
Fabrication in the final position ............................................... 16
4.2. Stressing .............................................................................................. 16
4.3. Grouting................................................................................................ 16
4.4. Completion work................................................................................... 16

5. VSL Service Range ...............................................................................17


5.1. General.................................................................................................. 17
5.2. Tender Preparation ............................................................................... 17

6. Examples from Practice ....................................................................... 18


6.1. Introduction ........................................................................................... 18
6.2 Bridges originally designed with external tendons ............................... 18
6.3. Other structures originally designed with external tendons.................. 25
6.4. Bridges with subsequently added external tendons.............................. 26
6.5. Other structures with subsequently added external tendons ................ 28

7. Bibliography and Reference ................................................................. 30

Copyright 1992 by VSL INTERNATIONAL LTD., Switzerland - All rights reserved - Printed in Hong Kong.
EXTERNAL POST-TENSIONING

Preface
The purpose of this report is to discuss the principles and applications of external
post-tensioning and to present the VSL External Tendons. It should assist engineers in
making decisions regarding both design and construction. This document does not
represent a complete manual for detailed design and practical construction of structures
with external tendons. In this respect the reader is referred to the relevant technical
literature (see bibliography in Chapter 7). Furthermore, it must be mentioned that the
emphasis is clearly on the applications for bridges. Where appropriate, however,
reference is also made to other applications such as in buildings and circular structures.
There are many similarities between external tendons, stay tables and permanent
prestressed ground anchors. In fact, regarding many aspects there is hardly any
difference. Reference is therefore made to the report on VSL Stay Cables for Cable-
Stayed Bridges [1] and the VSL documentation on ground anchors (e.g. [2]).
The VSL Organizations will be pleased to assist and advise you on questions relating
to the use of external post-tensioning. The authors hope that the present report will help
in stimulating new and creative ideas. The VSL Representative in your country or VSL
INTERNATIONAL LTD., Berne, Switzerland, will be glad to provide you with further
information on the subject.

Authors
H.U. Aeberhard, Civil Engineer ETH

P. Buergi, Mechanical Engineer HTL

H.R. Ganz, Dr. sc. techn., Civil Engineer ETH

P. Marti, Dr. sc. techn., Civil Engineer ETH

P. Matt, Civil Engineer ETH

T. Sieber, Civil Engineer HTL.

1
EXTERNAL POST-TENSIONING

1. Introduction
1.1. Historical developments In 1934, Dischinger was granted his (25.20 - 69.00 - 23.40 m), external
patent DRP 727,429 (Fig. 1). It contains tendons consisting of smooth bars with a
The idea of actively compressing the innovative idea of post-tensioning yield strength of 520 N/mm and a diame-
structural elements with a high tensile reinforced concrete girders with external ter of 70 mm were used [6]. Due to World
material such as steel is very old. tendons. For the determination of the War II and its aftermath, the originally
Everyone is familiar with timber barrels magnitude of prestressing, he proposed planned restressing operations were not
and timber wheels stressed together by the concept of concordant prestressing, performed until 1962, together with other
steel hoops. In ancient Egypt, the same which later became known as the load- repair work [7]. In 1983, the original bar
technique was used for shipbuilding. balancing method. Dischingers main tendons were again stressed [8]. Today,
In the history of modern engineering, concern was the long-term deformation the bridge has been in service for more
Farber may first be mentioned. He was due to the time-dependent, visco-elastic than 50 years. Some years ago the
granted German patent DRP 557,331 in behaviour of the concrete. He was aware German Democratic Republic listed this
1927. In essence, this patent describes a of the pioneering work of Freyssinet and remarkable structure as one of its
prestressing system in which bond with his classical experiments, carried out in technical monuments.
the surrounding concrete structure is the years 1926 to 1929. While Freyssinet In the late thirties and early forties,
prevented by covering the prestressing clearly recognized the nature of concrete Dischinger designed other road and
steel with a bond-breaker such as with regard to creep and shrinkage [4], it railway bridges with spans of up to 150 m.
paraffin. It is not known whether Farbers was Dischinger who first proposed a valid The construction of the Warthe Bridge in
idea was actually applied in practice [3]. mathematical model in 1939 [5]. Thus, in Posen (today Posnan, Poland) with spans
the absence of a sound theory in the mid- of 55.35 - 80.50 - 55.35 m was stopped
thirties, it was quite logical for Dischinger because of the war. The external ten-
to opt for external post-tensioning. He dons, consisting of steel ropes 65 mm,
wished to retain the possibility of were already on site. They were, how-
restressing the tendons should undesir- ever, more urgently needed as external
able deflections occur. Furthermore, tendons for post-tensioning the heavy
Dischinger specifically mentioned in his reinforced concrete trusses carrying trav-
publications the longer life of such eling cranes in a large steel mill [9].
tendons resulting from the reduced Dischinger also conceived composite
influence of fatigue loadings and the bridges with external post-tensioning [10].
system-inherent possibility of replacing Based on Freyssinets ideas, Wayss &
tendons, even under traffic, should this be Freytag AG designed and constructed in
required. 1938 the bridge over the Dortmund-
In the years 1936 and 1937, these Hannover Autobahn in Oelde, FRG,
ideas were applied in practice for the now where for the first time high tensile
quite well known bridge crossing the prestressing steel arranged inside the
valley basin and the railway lines at Aue, concrete section was used for 4 simply
Saxony, now the German Democratic supported girders of 33 m span. The pre-
Republic (Fig. 2, 3). For the main spans tensioning method was applied and the

Figure 1: Dischingers patent DRP


727,429

Figure 2: Bridge at Aue; external Figure 3: First prestressed concrete bridge: Bridge over valley basin and railway at Aue,
prestressed bars of the drop-in span German Democratic Republic (designed by Dischinger)

2
EXTERNAL POST-TENSIONING

Figure 4: Bridge over River Aare at Aarwangen, Switzerland

prestressing steel was therefore bonded and stress increase up to yield strength) Also during this period, the first
to the structure [ll]. This was actually the and the free-of-charge corrosion applications of external tendons for the
first bridge in what is now called conven- protection by the surrounding concrete. strengthening of existing structures can
tional prestressed concrete. In 1949, Dischinger also was converted be found. An early example is the two-
In the same year, Finsterwalder and became an advocate of the bonded span steel truss bridge (48-48 m) over the
developed his concept of the self- concept. Despite this pronounced trend, River Aare at Aarwangen, Switzerland
stressing concrete beam, which was external post-tensioning did not disappear (Fig 4). This bridge was built in 1889 and
put to the actual test for the bridge over completely. Several externally post-ten- was no longer capable of supporting
the same Autobahn at Rheda-Wieden- sioned bridges were constructed in modern traffic foads. In 1967 the bridge
brck, FRG (a simply supported girder of France [14], Belgium [15], Great Britain was strengthened with two locked-coil
34.50 m span). The external bar tendons and a few other countries. Not all of these strands 63 mm having an ultimate
65 mm with a yield strength of 520 N/ projects were successful. In some cases strength of 1,370 N/mm [16].
mm were stressed by the self-weight of the corrosion protection system chosen A rebirth of external post-tensioning
the superstructure using a hinge at mid- did not fulfill the required purpose and can be observed from the mid-seventies
span and a precamber of 272.5 mm. The tendons had to be replaced. onward. Freeman Fox and Partners
bar tendons were later encased in
concrete [12].
In the years 1938 to 1943, Haggbohm
designed and built the Klockestrand
Bridge (Fig. 5), near Stockholm, Sweden
[13]. For the main spans (40.50 - 71.50 -
40.50 m) the Dischinger concept was ap-
plied. The main span superstructure was
prestressed with a total of 48 bars of 30
mm having a yield strength of 520 N/mm .

It is worth mentioning that these four


bridges, of which three utilize external
post-tensioning, are still in service today
after more than 50 years of use.
Why was external post-tensioning
virtually discarded in the succeeding
years?
Under the influence of Freyssinet and
other prominent engineers, the advanta-
geous characteristics of structures with
bonded tendons were emphasized. These
characteristics include the higher utiliza-
tion of the prestressing steel under
ultimate bending moment (both with
regard to achievable tendon eccentricities Figure 5: Klockestrand Bridge near Stockholm, Sweden

3
EXTERNAL POST-TENSIONING

designed the Exe and Exminster Viaducts


in England (see para. 6.2.1.) using
external tendons each consisting of a
bundle of 19 greased and plastic-
sheathed strands 13 mm. The prime
objective was to minimize the weight of
the superstructure to overcome difficult
soil conditions.
The main developments certainly came
from French engineers. In 1978/79 Muller
introduced external post-tensioning in the
United States, for the Key Bridges in
Florida [17]. His main goals were speed of
construction and economy. Many other
important structures followed [18]. Since Figure 6: Hangar at Belgrade International Airport, Yugoslavia; roof with external tendons
1980, many bridges have been designed
and built in France under the auspices of be shown, the application is by no means reinforcement etc.) and incomplete filling
Virlogeux of SETRA (State design office restricted to concrete structures. Any of the tendon ducts by cement grout etc.
of highway authority) using either external material with reasonable compression have contributed to the rapid degradation
tendons or a combination of internal and characteristics can be combined with of the prestressing steel by corrosion
external tendons [19]. At present several external tendons. Thus, applications in attack. Since no reliable, non-destructive
sizeable bridges using external post- structural steel, composite steel-concrete, inspection methods for internal tendons
tensioning are in planning and under timber and masonry structures are known. yet exist, it is very difficult to properly
construction in Switzerland and in the As mentioned earlier, the technique has assess the degree of deterioration.
Federal Republic of Germany (see para. been used for various types of structures Furthermore, internal tendons can neither
6.2.9.). such as: be detensioned nor removed.
It is true that external post-tensioning is On the other hand, external tendons
primarily applied in bridges. There are, - Bridge superstructures provide desirable features, such as the
however, applications for other types of possibility of controlling and adjusting the
structures such as large-span roofs [20] - Girders in buildings (see para. 6.5.2.)
tendon forces, inspecting the corrosion
and for the strengthening of buildings, - Roof structures (Fig. 6) protection and replacing tendons, should
silos and reservoirs [21]. this become necessary. This is, however,
- Circular structures such as silos, reser-
voirs and large masonry chimneys (see possible only if the tendon system
1.2. Areas of application together with its anchorages and saddles
today para. 6.3.1. and 6.5.1. and [21], [22])
is designed accordingly.
- Buildings with masonry walls (Fig. 7). Other advantages of external post-
External post-tensioning can be used tensioning include:
for new structures as well as for existing In the following chapters, the explana-
structures needing strengthening. As Will tions are limited to the application of - The absence of tendons inside a web
external post-tensioning to bridges, which means that pouring of concrete is made
at this stage represent the main field of easier; there is no weakening of the
activity. compression area due to ducts. In this
In designing a new bridge superstruc- way a minimum web thickness is
ture, a designer may opt for internal or achievable.
external tendons or a combination of
both. Whereas for many years internal - A polygonal tendon layout allows
tendons were selected almost exclusively, angular deviations to be concentrated
there are a number of good reasons for at carefully designed saddle locations,
deciding on external tendons. thus eliminating the influence of
It is interesting to note that some of the unintentional angular changes (wobble
arguments used previously to promote effect).
internal, bonded tendons are now The difference in mechanical behaviour
weighed differently. There is no doubt that between internal, bonded and external
most bridges with internal, cement tendons is discussed in Chapter 2.
grouted tendons behave very well. In With regard to material quantities, it
some cases, however, substandard should be mentioned that with external
concrete (exhibiting high porosity, tendons the concrete dimensions can
excessive carbonation etc.), missing or normally be reduced. However, due to
Figure 7: Strengthening of a villa deteriorated bridge deck insulation
damaged by the Friuli earthquake in Italy, reasons such as the reduction of the
(allowing free attack by de-icing available tendon eccentricity, the amount
1987 [23] chemicals), badly cracked concrete of prestressing steel generally needs to
(resulting from inadequate design, be slightly increased (Fig. 8).
insufficient provision of minimum

4
EXTERNAL POST-TENSIONING

1.3. Types and components materials is the much higher costs under which the suitability of a structure is
compared with prestressing steel. judged primarily on the basis of initial
of external tendons
construction costs, this seems to be the
1.3.3. Tendon anchorages normal choice.
1.3.1. General From a technical point of view, it
Until very recently, external tendons
A great variety of tendon types has should be remembered that the anchor-
were anchored with the same mechanical
been used and is described in the ages for external tendons must withstand
devices as those used for ordinary
technical literature. It is outside the scope the tendon force plus any potential
internal, bonded post-tensioning. Under
of this report to discuss all possibilities at subsequent force increase during the
the prevailing economic circumstances,
length.
Essentially, an external post-tensioning
tendon consists of the following elements:
- prestressing steel as tensile members,
- mechanical end anchorage devices,
- corrosion protection systems.
In the case of deflected tendons:
- saddles at points of deviation are also
required.

1.3.2. Prestressing steel


At present, most material standards for
prestressing steel distinguish between
smooth and ribbed bars, wires and
strands. No official worldwide statistics of
the market shares are available. Unofficial
figures, however, suggest that today the
total built-in tonnage of steel consists of
75% strands, 15% wires and 10% bars.
Whereas strands and wires can be
applied more or less universally, bars are Figure 8: Comparison of box girder geometry with internal and external tendons
normally limited to short, preferably
Bar 36 mm Wire 7mm Strand
straight tendons of up to 20 m length.
hot-rolled, cold-drawn 13 mm
Table I compares the various
cold-worked stabilized cold-drawn
characteristics of the most commonly
and tempered, stabilized
used prestressing steels (based on official
ribbed
approval documents from the Federal
Republic of Germany [24]). The figures Ultimate tensile strength N/mm2 1,230 1,670 1,770
are self-explanatory. Furthermore, the
excellent groutability and the favourable Yield strength N/mm2 1,080 1,470 1,570
ton per force price of the strands may be
emphasized. It therefore becomes clear Min. elongation at rupture % 6 6 6
why strands have taken such a large
share. This trend is continuing. Usually Relaxation from 0.7 fpkt after 3.3 2 2
seven-wire strands of 13 mm (0.5) or 1,000 at 20C %
15 mm (0.6) with low relaxation
properties (stabilized material) are used. Modulus of elasticity N/mm2 2.05 . 105 2.05 . 105 1.95 . 105
The question arises whether one day
prestressing steel will be replaced by Fatigue amplitude (N/mm2) :
other materials, such as glass, aramide or 2 . 106 load cyclesat max. 210 430 250
carbon fibres. Despite the fact that in upper stress of 0.9 fpy min. 210 265 205
recent years engineers and researchers
have made serious efforts [25], [26], the Min. diameter of curvature at
authors believe that for many years to max. allowable stress of fpy m 6.83 0.98 0.85
come the application of such materials will
be limited to demonstration research Friction coefficient P 0.50 0.17 0.19
projects and applications with special
conditions. One of the major reasons Table I : Characteristics of prestressing steels (according to German approval documents)
preventing a rapid transition to other

5
EXTERNAL POST-TENSIONING

lifetime of a structure. For anchorages post-tensioning anchorages of bonded protection are required. However, as for
meeting the requirements of approval systems. Specially designed devices are internal tendons, it seems advisable to
regulations such as those published by therefore required and have been apply a corrosion protection strategy
FIP [27], the effectiveness is normally developed accordingly (see Chapter 3). which is based primarily on environmental
given. conditions and also safety considerations
As mentioned earlier, external tendons 1.3.4. Corrosion protection (e.g. with regard to fire, strand failure,
can provide additional features such as systems etc.).
the possibilities of monitoring, adjustment, It is known that prestressing steel Many different solutions have been
replacement etc. These are increasingly needs careful protection against the adopted in the past [14]:
attracting the interest of maintenance- various types of corrosion attack. For
conscious bridge authorities. Such internal, bonded prestressing this a) Z inc coating: Its corrosion resistance
operations are not possible with typical protection is provided by the alkaline depends upon the type of galvanization
environment of the cement grout and the and the applied thickness. Z inc coated
surrounding concrete. Experience has prestressing steel has been used in
Evironmental Environmental shown, however, that there are several France on several occasions. There is
class conditions aspects to which attention must be paid, doubt, however, as to whether zinc
in both design and construction, to make coating provides a permanent corrosion
the protection really effective. protection. It seems to be durable only
1 Modest Structural elements always In [28] a corrosion protecting strategy under very favourable environmental
dry or under water is proposed, which is summarized in conditions. As reported in [14], coatings
Table II. It is in line with more recent have been damaged during handling
2 Moderate Structural elements sub- recommendations in various national and installation. Another problem arose
ject to moist conditions standards. In addition to the given design when zinc accumulated in the stressing
anchorage inside the wedges.
3 Severe Structural elements sub- measures, adequate materials and good
ject to permanent humid b) Polymer coating: This technology, in
workmanship are needed. From compari-
conditions and / or sons with the practice of the past and which polymers are bonded to the steel
changing wetting and experience gained with existing struc- by fusion, has been developed in the
drying conditions tures, it has been recognized for some United States primarily for the protec-
time that improvements are necessary tion of reinforcing steel. Polymer coated
4 Aggressive Structural elements sub- with regard to concrete quality, detailing strands have also been available for
ject to aggressive condi- and the amount of reinforcement. some time [29] and a number of appli-
tions For external tendons, other means of cations are reported (see para. 6.5.2.).
It remains to be seen whether this

Environ- Prestressing steel in Special protection Allowable design crack width (mm) Concrete cover (nominal values in mm)
mental tension zone under measures necessary under sustained loads
class (see sustained loads
above) Reinforced
Prestressed concrete Reinforced Prestressed concrete
concrete
concrete Post- Pre-
tensioning tensioning
Post- Pre- Post- Pre- Post- Pre-
Sheathing Steel
tensioning tensioning tensioning tensioning tensioning tensioning

1
Yes No 0.2 0.1 0.4 40*) 35 25

2 Yes No 0.2 0.1 0.4 50*) 45 35

Yes Yes
**) **)
3 Yes No 0.2 0.25 50 45
No No 0.1 55

Yes Yes * *) * *)
* *) * *)
4
No No 0.2* * * ) 0.1* * * ) 0.25 60 65 55

*) Corrosion protection not relevant for cover of sheathing * * ) Not relevant for corrosion protection * * *) Under rare load combinations

Table II: Corrosion protection strategy for internai, bonded post-tensioning tendons, pre-tensioning and reinforcing steel
(as proposed in [28])
6
EXTERNAL POST-TENSIONING

system will prove to be a viable solution - Saddle arrangements: Various solutions Further innovation may be expected or
for prestressing steel. Problems could have been used in practice (see Fig. 9). indeed can already be seen on the
occur due to the fact that only the outer In most cases saddles consist of a pre- horizon. This will include progress in
strand surface is protected, the king bent steel tube cast into the surround- materials (e.g. corrosion protection
wire and inner surfaces of the six ing concrete or attached to a steel systems), in design proedures, in
surrounding wires having no coating. At structure by stiffening plates. The structural concepts and in construction
the anchorages, the coating is locally connection between the free tendon technology.
interrupted by the indentations of the length and the saddle must be carefully The following few examples Will
wedge teeth. It is also possible that, as detailed in order not to harm the highlight what could be expected:
with zinc coated strands, problems may prestressing steel by sharp angular - Bridge superstructures with underlying
occur in the anchorages. Special care deviations during stressing and in external tendons: It is not an entirely
must be taken to prevent damage to service; also, the protective sheathing novel idea to arrange external tendons
the coating during handling and must be jointed properly. underneath the bridge girder. For
installation. example, this concept has been used
If tendon replacement is a design
c) Protective sheathing: The protective requirement, the saddle arrangement for steel bridges, such as the Neckar
sheathing represents an envelope must be chosen accordingly (e.g. Valley Bridge at Weitingen, Federal Re-
around the prestressing steel. Suitable double sheathing; see Alt. 3, Fig. 9). public of Germany [31], (Fig. 10), and
materials are steel or plastic tubes for the Bridge Obere Argen, Federal
- Minimum radii: L imits must be respect- Republic of Germany [32], [33]. In both
(polypropylene [PP] or polyethylene
ed because otherwise either the cases, the extremely difficult local soil
[PE]). In order to achieve an effective
prestressing steel or the protective conditions led to such a design. In [34]
protection system, proper solutions are
sheathing could suffer. Although some Wittfoht proposes underlying external
required for coupling these tubes with
tests exist indicating reasonable values, tendons as a standard solution for box
each other, with the anchorages and
which may be used for preliminary girder bridges for road or rail traffic.
with the saddles.
designs, more research work is Menn describes a similar system for
Injection of the remaining voids inside required in this respect. It is therefore slab bridges, by which the feasible
the sheathing with cernent grout has advisable to verify the feasibility of a span range can be extended up to
proven to be economical and reliable. In particular practical solution by tests. about 40 m [35], (Fig. 11). A compre-
the case of restressable anchorages, hensive test programme for determining
cernent grout must be replaced at least 1.4. Future developments the structural behaviour has been
focally by grease or similar soft plastic carried out at the Swiss Federal
material. Particularly in France, grease Institute of Technology (ETH), Z urich,
The revival of external post-tensio-
and wax products have been applied, Switzerland [36] (Fig. 12).
ning has been a stimulus for engineers.
instead of cement grout, on the entire
tendon length [14], [30]. Besides being
rather expensive, these products are
difficult to inject (e.g. preheating up to
100 C required) and special measures
are needed to prevent leakages (see also
para. 6.2.5.).
In this category, individually greased
and plastic-sheathed monostrands offer
many advantages. They are manufac-
tured under factory conditions. The
prestressing steel is therefore effectively
protected against corrosion during
transportation, storage on site and
installation, provided that proper care is
taken not to damage the sheathing.
Monostrands can be used either indivi-
dually or in bundles as multistrand
tendons. In the latter configuration they
are usually placed inside a plastic or steel
tube. The remaining voids are filled with
cernent grout.

1.3.5. Saddles at points of


deviation
When designing saddles it is important
to consider the following: Figure 9: Various saddle arrangements

7
EXTERNAL POST-TENSIONING

New corrosion protection systems: In


related fields of application, new
concepts have already been imple-
mented. It is known that corrosion does
not occur in a dry environment (relative
humidity d 40%). This fact has been
utilized in steel construction. The
designers of the suspension bridge
over the L ittle Belt (1970) and later on
of the Far Bridges (1985), both in
Denmark, introduced a dehumidification
and ventilation system for the interior of
the large steel box sections, thus
protecting the inside surfaces against
corrosion [37]. In Sweden, the Swedish
State Power Board used a specially
designed dehumidification and ventila-
tion system for all containment tendons
of Forsmark 1-3 Nuclear Power Sta-
tions. It is obvious that the conditions in
a well-attended power station are more
favourable than in an ordinary bridge
structure. In the future, however, further
developments in this direction may be
expected.
figure 10: Neckar Valley Bridge at Weitingen, Federal Republic of Germany
Monitoring of tendons: External
tendons make possible monitoring of
the tendon force and of the soundness
of the tendons. Refined techniques for
monitoring the integrity of the corrosion
protection systems and for inspecting
the tendons are being developed.

Figure 11: Details of slab bridge with underlying external tendons Figure 12: Scale model

8
EXTERNAL POST-TENSIONING

2. Design Considerations for Bridges


with External Tendons

2.1.General
The purpose of this chapter is to
highlight some special aspects that
should be considered in the design of
externally post-tensioned bridge super-
structures.
As for any design, it is normally at the
conceptual stage that the fate of a
structure with regard to economy and
durability is determined. A straightforward
structural system, good detailing, and the
early integration of the construction proc-
ess are the major elements of a success-
ful design. In this respect, bridges with
external tendons are no exception.
To obtain a satisfactory behaviour of a
structure both under serviceability and
ultimate limit state conditions, it is
essential to recognize the peculiarities of
girders with external tendons. Fig. 13
shows moment-curvature curves for a
typical bridge cross-section with either
bonded or unbonded prestressing. For Figure 13: Moment-curvature curves for a typical bridge cross-section with bonded and
comparison, a curve for non-prestressed with unbonded prestressing
bonded reinforcement is also shown. The
cross-sections of the reinforcement and Good crack distribution can only be
- Girder with unbonded tendons: obtained if the flexural resistance at a
prestressing were chosen such that all
three sections would reach the same Because relative longitudinal displace- section exceeds the cracking moment.
ultimate moment. As can be seen from ments between concrete and steel are This principle is well known from minimum
Fig. 13, there is no fundamental differ- not prevented by bond, the tendon reinforcement requirements. For case a)
ence between girders with bonded or with force increases only due to deformation of Fig. 13 this principle is only barely met
unbonded tendons below decompression of the entire structural system. Similar and hence deformations may take place
moment. The section with unbonded to slabs with unbonded tendons [38], in just one or a few cracked sections.
tendons has a larger initial prestressing the tendon force increase depends This may lead to an undesirable strain
force and, therefore, a higher decompres- primarily on the geometry and the localization with a subsequent premature
sion moment than the section with overall deformation of the structure as failure.
bonded tendons. With regard to the well as the tendon profile.
fatigue behaviour, Dischinger [10] already For long tendons and slender struc- As a consequence of the described
mentioned the advantage that for behaviour, externally post-tensioned
tures this increase will be relatively
unbonded tendons only negligible stress structures are inherently more sensitive to
small, even for large overall deforma-
fluctuations occur in the prestressing secondary effects since, unlike bonded
steel under live load. tions of the system. Therefore in Fig.
13, the tendon force increase has been systems, they do not have the capability
A closer look at the behaviour of the neglected and hence the decompres- to adapt to local overloads by local
sections is required following decompres- sion moment is equal to the ultimate yielding. Hence, while a realistic assess-
sion: moment. Of course, friction at deviation ment of secondary effects is not of
- Girder with bonded tendons: After points would somewhat improve the be- primary importance for bonded systems,
decompression, the tendon force this is quite different for externally post-
haviour, but unless intermediate an-
increases up to the yield strength. The tensioned systems.
tendon force increase and the associ- chorages or partial bond at sufficiently
ated increase of the internal lever arm closely spaced locations along the In practice, continuous bonded
of the section provide a yield strength tendons and/or additional bonded reinforcement and partial bond of external
considerably larger than the decom- reinforcement are provided, it shoutd be tendons, at tendon deviations due to
pression moment of the section. Owing recognized that decompression friction or cernent grout will contribute to
to the bond between concrete and essentially means ultimate. increasing the ratio of flexural resistance
steef, the flexural behaviour at a section At any rate, the strength of an exter- to cracking moment and thus result in a
is more or less independent of adjacent nally post-tensioned girder at one par- more forgiving behaviour of the structure.
girder zones. ticular section depends on the behavi- Finally, it should be mentioned that
our of the entire structural system, or at prior to grouting of the tendons a structure
least parts of the system if intermediate with bonded tendons behaves similarly to
anchorages are used.
9
EXTERNAL POST-TENSIONING

an externally post-tensioned system. In A reasonable prestressing force may after all losses in order to get an estimate
one case a bridge failed during construc- be estimated using the load balancing of the ultimate resistance. Alternatively, a
tion [39] primarily because the special method. If a substantial part of the dead rigorous analysis can be performed by in-
conditions of the construction stage were load is balanced by the prestressing, a tegrating the strain increments in the
overlooked. This failure clearly exhibited satisfactory behaviour of the structure structure along the tendon axis (Fig. 15a),
the effects of strain localization and points may be expected regarding both deflec- or an estimate of the tendon elongation
to the need for a careful evaluation of all tions and cracking. can be obtained from the consideration of
possible effects of loads and imposed de- As soon as the tendons and their a rigid body mechanism (Fig. 15b).
formations when designing externally profiles are selected, the tendon force Integration of the strain increments
post-tensioned systems. diagram can be determined. As external along the tendon axis requires an iterative
tendons are generally arranged in a non-linear analysis [14], [40]. For a given
2.2. Serviceability and polygonal shape, the force diagram will load increment and an assumed tendon
ultimate limit states have steps at the deviation points. Fig. 14 force the strain increments at each
shows the forces applied to a deviation section and the associated tendon force
2.2.1. Serviceability limit state point. increase can be computed. Repeating the
Usually, the amount of prestressing is Long-term losses due to relaxation of calculations with the new value of the
selected at a relatively early stage in a the prestressing steel, as well as creep tendon force will result in an improved
project. This selection is influenced by and shrinkage of the concrete, cause a estimate and after a few iterations a
considerations regarding serviceability decrease in the tendon force. As long as reasonable approximation will be ob-
and economy of the structure: no relative displacements between tained. Similar computations can then be
tendon and concrete occur at the devia- made for the next load increment and so
- Under dead load only, the structure tion points, either because of the pres- on.
shall remain substantially uncracked or ence of high friction coefficients or
existing cracks shall be closed. On the because of partial bond, these losses
other hand, the requirement of an may be estimated section by section as
uncracked structure for dead and live for bonded tendons. However, for low
load inctuding secondary effects might friction coefficients there will be some
lead to undesirable long-term hogging slippage between tendon and concrete
deflections under dead load only. and the losses may be estimated from
However, under such loading condi- mean axial deformations due to creep
tions cracked sections can normally be and shrinkage of the entire structure.
accepted if the stresses in the rein- As mentioned in Section 2.1. structures
forcement are limited such that the with external tendons may be sensitive to
cracks close again after removal of the secondary effects. Therefore, it is
load. essential to assess tendon forces and
- From an economic point of view, one secondary effects due to temperature,
should ideally provide just enough creep, shrinkage and other effects as
non-prestressed reinforcement and re- realistically as possible when performing
stressing steel as necessary to obtain checks at serviceability limit states. The
the required resistance. effects of prestressing may be considered
either by the primary and secondary
moment method or by the load balancing
method. The first method is generally
used for the final design of a structure
because it allows for an easy considera-
tion of friction losses. On the other hand,
the second method is prlmarily suited for
preliminary designs if friction losses are
neglected. Figure 15: Tendon elongation +L

2.2.2. Ultimate Iimit state Tendon size Minimum radius


(VSL tendon unit) (m)
As mentioned in Section 2.1. the
tendon force increase in externally post- up to 5-19 or 6-12 2.50
tensioned structures will generally be up to 5-31 or 6-19 3.00
rather small unless intermediate anchor- up to 5-55 or 6-37 5.00
ages or partial bond at sufficiently closely
spaced locations are provided. Hence, for
ultimate timit state considerations one Table III: Recommended minimum tendon
Figure 14: Forces at deviation points may opt to neglect any possible tendon radii
force increase and use the tendon force

10
EXTERNAL POST-TENSIONING

ment of secondary effects is usually However, the wobble factor k can


Rigid body mechanism considerations
essentiat for externatly post-tensioned normally be neglected since the tendons
have been successfully applied in
designing post-tensioned slabs with systems because of their inherent are straight between the points of
unbonded tendons [41], [42], [43], [44]. sensitivity to such effects (see Section deviation.
Typically, a nominal failure characterized 2.1.). Hence, while a liberal attitude to- Based on test results, site experience
by a maximum deftection of about two wards secondary effects due to imposed and the technical literature, the friction
percent of the stab span is assumed and deformations of any sort may be assumed coefficient Pvaries as follows:
the resulting elongation of the tendon is when designing a bonded structure, a P
determined from geometry. Knowing the more cautious approach is necessary for - bare, dry strands over steel
elongation and the stress-strain relation- externally post-tensioned structures. saddle 0.25-0.30
ship of the tendon, the tendon stress
increase and the tendon force can be - bare, greased strands over
determined. While this procedure is well 2.3. Particular aspects steel saddle 0.20-0.25
estabtished for slabs, some caution is - bare strands inside plastic
recommended for the application to 2.3.1. Saddles tube running over saddle 0.12-0.15
bridge girders until more information The design and detailing of saddles at
on maximum deflection values is avai- - greased and plastic-sheathed
points of tendon deviations is a delicate monostrands inside plastic
lable.
task. An early coordination between the tube over saddle 0.05-0.07
If the tendon force increase is taken
into account, second order effects as designer and the tendon supplier is
exemplified by Fig. 16 have to be advisable. It is of utmost importance that
considered as well. However, if an the forces transferred at the saddle
appropriate number of deviation points is locations are carefully evaluated. It is
provided, the influence of such second recommended to use higher safety
order effects may be kept small. factors as the proper functioning of these
Knowing the tendon force, the ultimate elements is essential for the entire
resistance of an externally post-tensioned structure. Typical examples of saddles
structure can be determined using are shown in Fig. 9 and 18.
conventional methods. Similar to bonded
structures, an external tendon can either 2.3.2. Minimum tendon radii
be treated as part of the integral load
resisting system (Fig. 17a) or it may be Minimum tendon radii as recom-
considered to be separated from the mended in Table Ill must be respected in
concrete and its action can be modelled order to avoid damage of the prestressing
by applying the equivalent anchorage, steel and the plastic sheathings as well as
deviation and friction forces onto the the outer tubing. It is also known that
concrete (Fig 17b). However, in contrast friction problems may occur if the tendon
to bonded structures, a realistic assess- radii are too small.

2.3.3. Prestress losses due to


friction
Similarly to conventional prestressing,
the force -friction retationship can be
described with the following formula:

P(X) = P 0 e - ( P+kx)
where

P(X) = Post-tensioning force at a distance x


Figure 16: Influence of girder deflection from the stressing anchorage
on tendon eccentricity P 0= Post-tensioning force at the stressing
anchorage
e = Base of Napierian logarithms
P = Coefficient of friction
= Sum of angular deviations (in radians)
of the tendon in ail planes over the
distance x
k = Wobble factor (inaccuracies in
Figure 17: Ultimate resistance placing) per unit length Figure 18: Examples of deviation points

11
EXTERNAL POST-TENSIONING

3. VSL External Tendons


3.1. Introduction 1.3.2., strands have a relatively high 3.2.2. Selection criteria
breaking strength, which results in a The main technical criteria for selecting
The VSL External Tendons are in reduced consumption of steel. Another the tendon type are:
essence an adaptation of the well-proven main advantage of VSL External Tendons
VSL Post-Tensioning System [45] to the is the modular principle, which enables - Environmental conditions and tendon
requirements for external tendons. Thus, any desired tendon size and tendon exposure: as for internal, bonded
they do not represent a completely new anchorage to be made up from standard prestressing, for external tendons it
technology, but simply a further develop- units. Thus, the construction principle is seems logical to select the degree of
ment of a technology relying on many always the same. On the other hand, the corrosion protection according to the
years of practical experience. system is sufficiently flexible to allow for environmental conditions and the
The main characteristic of VSL adaptation to any requirement. This exposure of the tendons. Based on the
External Tendons is the use of strands for means, therefore, that the information classes given in Table II (p. 6), it is
the tensile members. As shown in para. presented in Chapters 3 and 4 is merely recommended to Use Type 1 for
representative and does not constitute classes 1, 2 and 3 and Type 2 for class
any limitation to the possible range. 4.

3.2. Types of VSL External - Need for tendon force adjustment


Tendons and Technical Data during lifetime of the structure: in this
case Type 2 is recommended.
3.2.1. General - Tendon friction during stressing opera-
The VSL External Tendons consist of tion: as shown in para. 2.3.3., the
the following main elements (Fig. 19): friction with tendon Type 2 is much
smaller than with Type 1. In the case of
- a bundle of prestressing strands (either
long tendons running over several
bare or individually greased and plastic-
spans with sizeable angular changes,
sheathed) as the tensile member,
Type 2 offers technical and economical
- a plastic or steel tubing for the strand advantages.
bundle,
Table IV summarizes the selection
- end and intermediate anchorages, and criteria. It should be mentioned that other
couplers, factors may influence the decision such
- a grouting compound. as price, availability of materials, local
practice, etc.
VSL offers two main types of external
tendons (Fig. 20) which can be character- 3.2.3. Strands
ized as follows: For VSL External Tendons, cold-drawn
Type 1: Bundle of strands inside a 7-wire prestressing strands of 13 mm
steel or plastic tube; the grouting com- (0.5) and 15 mm (0.6) normally of low
pound normally consists of cement grout. relaxation quality are used. The
Type 2: Bundle of greased and plastic- geometrical and mechanical properties
sheathed monostrands inside a steel or are given in Table V.
plastic tube; the grouting compound Whereas for tendon Type 1 bare
consists of cement grout, except in the strands are envisaged, greased and
anchorage zones, where especially suited plastic-sheathed strands (monostrands)
corrosion preventive compounds are are used for Type 2. The grease has
used. favourable characteristics with regard to
Figure 20: Cross-sections of VSL External
Tendons Type 1 and Type 2

Figure 19: Composition of the VSL External Tendon (schematical)


12
EXTERNAL POST-TENSIONING

its long-term stability and its suitability in 3.2.6. Anchorages Type 1 Type 2
providing corrosion protection of the The anchorage principle of VSL
prestressing steel. The sheathing is of Externat Tendons corresponds in
polyethylene (or alternatively polypro- Environmental con-
essence to the VSL Post-Tensioning ditions (see Table II):
pylene) and has a minimum thickness of
1 mm for straight tables and 1.5 to 2 mm
System. Figures 21 to 29 represent a class 1 n
for curved tables.
variety of possible anchorages. Different class 2 n
parameters, such as required adjustabil- class 3
n
ity, replaceability, load monitoring,
class 4 n
3.2.4. Characteristic breaking loads installation procedure, access to the end
of VSL External Tendons
Table VI gives the nominal breaking anchorages (e.g. for the strengthening of Need for tendon force
structures), static considerations and adjustement:
loads for the VSL External Tendons
environmental conditions as per para.
no n
according to the four strand types as
3.2.2., influence the selection of the
yes n
detailed in Table V. The characteristics of
the strand may, however, slightly deviate particular anchorage type.
Tendon friction
from these values, depending on the The exposed surfaces of the anchor- shorter tendon and
manufacturer and applicable standard. ages are properly coated for corrosion small n
protection. longer tendon and
3.2.5 Tubing high n
The strand bundle (consisting of either 3.2.7. Grouting compounds
bare or greased and plastic-coated Table IV: Main technical criteria for
The tubing around the strand bundle selection of tendon type
strands) is usually encased in a plastic
tube. Alternatively, steel tubes may be constitutes its primary corrosion protec-
used. In certain areas, such as deviation
saddles or parts of the tendon embedded
in concrete, regular corrugated steel duct
as normally used for post-tensioning 13 mm (0.5) 15 mm (0.6)
Strand type
tables may be chosen. The latter,
(A) (B) (C) (D)
however, is only applicable when the
Euronorm ASTM Euronorm ASTM
tendon does not need to be replaceable
138-79 A 416-85 138-79 A 416-85
(see also para. 3.2.6.), and tendons Type
Super Grade 270 Super Grade 270
1 are used.
Nominal diameter (mm) 12.9 12.7 15.7 15.2
In general, the plastic material is 140
Nominal steel area (mm ) 2
100 98.7 150
polyethylene and meets the requirements
of appropriate standards such as DIN Nominal mass per m (kg) 0.785 0.775 1.18 1.10
8074 and 8075, ASTM D 1248 and 3035
or equivalent. Alternatively, polypropylene Yield strength (N/mm2) 1,580   1,670
     1,500      
1,670   
may be used. The ratio of internal 1,770
Ultimate strength (N/mm2) 1,860 1,860 1,860
diameter to wall thickness is approxi-
mately 16:1. In general carbon black is 186.0 183.7 265.0 260.7
Min. breaking load (kN)
added as ultraviolet stabilizer. This
material is chemically inert against 1) 0.1 % proof load method 2) 1 % extension method

practically any foreseeable agent (see


e.g. DIN 16934). It has shown excellent Table V: Strand types
durability behaviour in structural applica-
tions.
In the case of steel tubes, a higher
internal diameter/wall thickness ratio can 13 mm (0.5) Strand 15 mm (0.6) Strand
be used (approx. 30:1 to 50:1). The Breaking load (kN) Breaking load (kN)
dimensions used are primarily dictated by Max. Max.
the availability of standardized tubes. The Cable number of Strand Strand Cable number of Strand Strand
outer surface of the tubing is normally type strands type A type B type strands type C type D
provided with a paint giving sufficient
corrosion protection. 5-3 3 558 551 6-3 3 795 782
The plastic or steel tubing represents 5-4 4 744 735 6-4 4 1,060 1,043
5-6 6 1,116 1,102 6-6 6 1,590 1,564
the prime barrier against corrosive attack. 5-7 7 1,302 1,286 6-7 7 1,855 1,825
It is connected to the anchorages and the 5-12 12 2,232 2,204 6-12 12 3,180 3,128
saddles, thus providing an effective and 5-19 19 3,534 3,490 6-19 19 5,035 4,953
continuous envelope around the 5-22 22 4,092 4,041 6-22 22 5,830 5,735
prestressing steel. 5-31 31 5,766 5,695 6-31 31 8,215 8,082
5-37 37 6,882 6,797 6-37 37 9,805 9,646
5-43 43 7,998 7,899 6-43 43 11,395 11,210
5-55 55 10,230 10,104 6-55 55 14,575 14,339

Table VI: Characteristic breaking loads


13
EXTERNAL POST-TENSIONING

tion. In addition, the tendon is completely and fulfills the same requirements
filled with a grouting compound. As as the one used in traditional post- Due to the fact that the envelope
mentioned under 3.2.1.. normally cement tensioning. With its alkaline properties, reduces or eliminates the diffusion of
grout is used. it provides active corrosion protection. gases and liquids, carbonation of the
The grout is made from Portland cement The grout completely fills the interstices cement grout is inhibited.
between the strand bundle and the outer
Notes: *Bursting steel not shown for clarity. tubing.
*Figures 26 to 29 have been omitted.

Features : Replaceable stressing or dead end


anchorage where no adjustability
and load monitoring is required.
Available for 0.6" diameter bare
strand tendons (Tendon Type 1).

Figure 21: Anchorage Type Ed

Features : Large-sized guide pipe enabling


push-through for trumpet/anchor
head assembly. Fully adjustable,
detensionable and replaceable
anchorage (Tendon Type 2).
Ring nut can be used instead of
split shims. Can also be used with
bare strands, if only load monitoring,
small adjustements or replaceability
is required.

Figure 22: Anchorage Type A

Features : Replaceable stressing or dead end


anchorage where no adjustability
and load monitoring is required
(Tendon Type 1)

Figure 23: Anchorage Type CSd

14
EXTERNAL POST-TENSIONING

Feature: Replaceable stressing or dead end


anchorage where no adjustability
and load monitoring is required
(Tendon Type 1)

Figure 24: AnchorageType ECd

Composition: Anchor block with wedges, retainer plate on passive side to secure
wedges, steel case. Tube for strand overlenght if detensionability or ad-
justability required.
Features: For tendons with insuficient access for stressing at end anchorages
(e.g. strenghtening of structure) or for circular tendons.

Figure 25: Centre-stressing anchorage Type Z Figure 30: Intermediate tendon supports

Figure 31: Test installation

3.3. Experimental evidence by VSL (Fig.31). The first test aimed at tendon was slightly stressed from both
Several tests have been conducted
during the development of the VSL determining the groutability of a bundle of anchorages prior to grouting. The tendon
Extemal Tendons. These tests have monostrands, especially in the saddle was then stressed to 70% of the breaking
provided valuable data for material area. The second test involved stressing load, again applying a 600 mm relative
selection and procedures, anchorage the tendon in stages up to 70% of the displacement. The fourth test was similar
design, and friction losses in saddles. For breaking load. To simulate actual to the third, but incorporated the improve-
the Bois de Rosset Viaduct project conditions, a relative displacement of ments obtained through the earlier tests.
(para.6.2.9.), four tests were performed 600 mm was applied. In the third test, the
15
EXTERNAL POST-TENSIONING

4. Application of the VSL External Tendons


4.1. Manufacture and The strands are inserted by pushing the Type 2 Tendons (greased and plastic-
installation tube over the prepared strand bundle or coated monostrands) are stressed in two
by pushing individual strands through the stages. In the first stage, an initial force is
Basically there are two different tube. applied which removes the slack in the
methods used for the installation of VSL tendon. Then the tendon is grouted. After
External Tendons The bearing plates or anchorage the grout has attained the required
bodies and the supports at the deviation strength, the stressing operation is
- Installation of completely prefabricated points are fixed to the structure. The continued. In the second stage, the
tendons. prefabricated tendon is then placed into stressing force is raised in uniform fashion
its final position either manually or by to its final value.
- Installation of the empty tube in the final mechanical means using hoists or Depending upon the anchorage type
position followed by insertion of the winches. Intermediate temporary fixings chosen, the tendon force can be checked,
strands. along the straight lengths are provided to adjusted or released using the same
keep the tendon in its correct position. multtstrand stressing jack.
4.1.1. Prefabrication
The method of complete tendon 4.3. Grouting
prefabrication is usually applied for short, 4.1.2. Fabrication in the final
light tendons where easy access on site position The VSL anchorages incorporate a
allows the placing of the entire tendon. Besides the fixing of bearing plates and grout connection which can be used as
Prefabrication may be carried out deviation points, it is necessary to provide inlet or as outlet. Further grout connec-
either in a factory or in a prefabrication temporary intermediate tendon supports tions are provided at the deviation points.
area on site depending on the means of along the straight length of the tendon Grouting commences at the lower end
transport, the time between manufacture prior to the placing of the tubes (Fig. 30). of the tendon and proceeds at a steady
and installation, and the availability of The tube (steel or PE) is prepared in rate until grout of the same consistency is
adequate space on site. The standard suitable sections and placed in its final ejected at the deviation points and finaly
lengths of tube are connected to position by attaching it to the previously at the other end of the tendon. For long
achieve the required total length. PE fixed supports. The tube sections are tendons, the grout is injected at subse-
tubes are connected by butt-welding, connected by welding or by using quent inlets along the tendon. When
steel tubes by welding or with couplers. couplers. At the ends the tube is tightly using greased and plastic-sheathed
connected to the anchorages. strands inside a steel or PE tube (tendon
When the tube is securely fixed in the Type 2), the tendon is grouted after initial
final position it is ready to receive the tensioning by injecting cement grout into
strands. The strands are inserted by the tubing only. The anchorage zones are
pulling the prepared strand bundle (as filled with a non-hardening corrosion
one unit or in groups) through the tube by preventive compound.
a winch. If the tendon consists of bare
strands, the VSL push-through machine 4.4. Completion Work
can be used by taking the strands directly
from the coil and pushing them through The exposed surfaces of the anchor-
the tube one by one (Fig. 32). ages are properly coated for corrosion
protection.
4.2. Stressing As a result of the simplicity of the
construction principle, the high quality of
The VSL External Tendons are the materials used and the excellent
stressed with the appropriate VSL corrosion protection, VSL External
multistrand jack. All the strands are Tendons are virtually maintenance-free.
Figure 32: Pushing strand The use of anchorages type Am,
stressed simultaneously but individually
locked off (Fig. 33). The stressing (anchor head with thread) enables the
operation normally follows the procedures attachment of a VSL Load Cell (Fig. 34),
established by the specifications, by local allowing the monitoring, checking and
codes of practice or by the FIP recom- small adjustments of the tendon force
mendations. during the whole life of the structure.
Type 1 Tendons (bare strands) are Anchorages type As, and Ar, provide for
stressed at a steady rate in one or several adjusting and detensioning of the tendon
increments until the required stressing force and, if required, replacing of the
force is reached. Grouting is carried out entire tendon.
after completion of the stressing opera-
tion.

Figure 33: Stressing a VSL tendon

16
EXTERNAL POST-TENSIONING

5. VSL Service Range


5.1. General
The VSL Organizations provide a
comprehensive range of services in
connection with externally post-tensioned
structures, including:
- Consulting services to owners, engi-
neers and contractors
- Preliminary design studies
- Assistance with the design of externally
post-tensioned structures
- Detaifed design of external tendons
- Supply and installation of external
tendons
- Supply of materials, equipment, and
supervisory personnel
- The use of other VSL Systems, such as
slipforming, soil and rock anchors,
heavy lifting, bearings, expansion joints
etc.
The extent of VSLs services will
usually be clarified in discussions
between the owner, engineer, contracter,
and the VSL Organization.
In many cases the application of
several VSL Systems is possible on a Figure 34 : Stressing of an external tendon equipped with a VSL Load Cell
single project. This enables the use of
labour and material to be rationalized
with consequent cost savings. - Pamphlet Life Extension and Strength-
At this point, reference may be made to ening of Structures The first solution, in most cases, will
other VSL publications which are of - Various Job Reports prove to be the better one and therefore
importance in the construction of exter- should be selected as a rule. The
nally post-tensioned structures: - VSL Newsletters.
foremost reason is quality assurance. The
durability over the lifetime of a structure
- Pamphlet VSL Post-tensioning [45] 5.2. Tender Preparation mainly depends on quality of materials
- Technical report Concrete Storage and on quality of workmanship. The
The basic requirements for a tender for experience available with VSL, whose
Structures [21]
one or more of the above services, in so personnel is engaged exclusively on post-
- Technical report The Incremental far as they concern the carrying out of tensioning, is the most suitable for the
Launching Method in Prestressed detailed design, supply, installation and effective manufacture and installation of
Concrete Bridge Construction execution, are detailed drawings and tendons. Another reason is economy. A
specification documents. This applies specialist worker can achieve a better rate
- Technical report The Free Cantilever- both for structures which are about to be of progress both by his experience and by
ing Method in Prestressed Concrete constructed and also for Clients propos- the advanced type of equipment he has at
Bridge Construction. als which require further technical his disposal. He will require less time to
development, or to which alternative solve unforeseen problems on site.
In addition, the following VSL publica- proposals are to be prepared. In addition, considerable savings are
tions are available that may also be of A VSL tender for external post- possible if a Main Contractor investigates
interest in connection with externally post-
tensioning may consist of: jointly with VSL how best to use the
tensioned structures:
available material, plant, equipment and
- Pamphlet VSL Slipforming - Supply of material plus manufacture methods for a specific project. VSL has,
and complete installation of the cables, for this purpose, built up its own design
- Pamphlet VSL Soil and Rock
Anchors [2] including provision of personnel and engineering staff. The combination of
equipment, or engineering skill with detailed knowledge
- Pamphlet VSL Heavy Lifting of the possibilities and special features of
- Pamphlet VSL Messtechnik/Measuring - Supply of material, provision of supervi- the VSL Systems has proved to be an
Technique/Technique de mesure sory personnel and provision of attractive service to Main Contractors for
equipment. optimizing their construction work.
17
EXTERNAL POST-TENSIONING

6. Examples from practice


6.1. Introduction
The purpose of this chapter is to give
the reader information about a number of
structures in which VSL External Tendons
have been used, and at the same time to
illustrate in what structures external
tendons are applicable. The descriptions
include concrete and steel bridges,
buildings, silos and other structures. The
chapter is split into a first part presenting
structures that have been designed for
the use of external tendons from the
beginning, while the second part com-
prises structures which had to be
strengthened by means of external
tendons.
The job reports show that external
post-tensioning is applied in various
countries; a certain predominance of Figure 35: Exe and Exminster Viaducts
France and the USA cari,, however, be
observed because these countries are at 6.2. Bridges originally separated from each other by an embank-
the forefront of the development of this designed with external ment approx. 380 m long, cross the Exe
technique. Wherever available, details tendons Valley. The Exe Viaduct spans the river
regarding the design of the structures and Exe and the Exeter Canal, while the
the reasons for the selection of external 6.2.1. Exe and Exminster Viaducts Exminster Viaduc$ carries the motorway
post-tensioning are also presented. near Exeter, Great Britain across a double-track railway line (Fig.
In both parts, the projects are listed Owner Department of Transport, 35).
chronologically. The designs of the older South Western Road The Exe Viaduct has a length of 692 m
structures may differ from what is outlined Construction Unit and comprises eleven spans (53.50 - 9 x
in the previous chapters, but at the same Engineer Freeman Fox and Partners, 65.00 - 53.50 m). The Exminster is 302 m
time they may make evident the improve- London long and has five spans (53.50 - 3 x 65.00
ments in the state of the art achieved over Contractor Cementation Construction - 53.50 m). The superstructures of both
the past years. Ltd., Croydon bridges consist of two parallel, twin-cell
Post- Losinger Systems Ltd., box girders of 7.00 m width and 2.80 m
tensioning Thame depth, having 5.00 m cantilever wings on
Construction each side. Diaphragms are provided in the
Span 1 Span 2 Span 3 Period 1974-1976 boxes at 7.50 m and 10.00 m distances.
The viaducts were designed with the
These two viaducts are part of the objective of obtaining the lightest possible
motorway M5 linking Birmingham in the structure, as soil conditions were found to
Midlands to Plymouth in the south. Not far be poor. Therefore, the dimensions of the
from Exeter the two structures, which are superstructure were minimized and the
Stage 1 post-tensioning tables placed inside the

Stage 2

Stage 3

Figure 36: Construction procedure Figure 37: Tendon layout scheme

18
EXTERNAL POST-TENSIONING

boxes. The construction procedure was 6.2.2. Seven Mile Bridge, Florida,
chosen accordingly. Construction of the USA
superstructure was split into two phases. Owner Florida Department of
First the boxes were constructed on Transportation, Tallahassee,
falsework, while the cantilever slabs were Florida
added later, using movable shuttering. Engineer Figg and Muller Engineers,
The technique applied in the construc- Inc., Tallahassee, Florida
tion of the boxes was as follows (Fig. 36): Contractor Misener Marine Construc-
- Stage 1: Construction of span 1 plus tion, St. Petersburg Beach,
115th of span 2 by successively Florida
concreting diaphragms, base slab and Erection of
webs, soffit slab. superstruc-
- Stage 2: Installation and stressing of ture and
the first half of the span 1 tables, con- post- VSL Corporation,
creting of the remainder of span 2. tensioning Los Gatos, California Figure 38: Saddle detail
- Stage 3: Moving of scaffolding and Construction
from span 1 to span 3 formwork, Period 1979-1982
installation and stressing of tendons
covering spans 1 and 2, concreting of The Seven Mile Bridge, which leads
span 3. from south of Marathon to Little Duck
- repetition of cycle. Key, is the longest in the chain of road
structures connecting the mainland of
The tendons were made up from Florida to Key West. With a total length of
monostrands and are not encased in any 10,931 m (35,863) it is also the longest
additional sheathing between the dia- concrete box girder bridge in the world. It
phragms. In each span, there are 16 VSL consists of 266 spans, most of them
tendons type 6-19 dyform (breaking load having the standard 41 .15 m (135) span
approx. 5,700 kN each) having normal length. The superstructure with its single-
VSL anchorages type E at both ends. The cell box section has a total width of
tendons caver two spans and overlap at 11.89 m (39) and a constant depth of
the piers. Thus the maximum tendon 2.13 m (7).
length is approx. 170 m (Fig. 37). Profiling The design especially aimed at speed
was achieved by means of saddles cast of construction, in addition to economy.
into the diaphragms. The saddles Thus some structural details are quite
consist of mild steel tubes of 110 mm unusual, even somewhat bold, with
outside diameter welded into a steel box regard to concept and durability. These
(Fig. 38). details are:
The tendons were prefabricated in the - No gluing material to bond or seal the
Figure 39: Construction phase
workshop and introduced into the box joints of the match-cast segments.
through a hole in the deck slab. Tendons Multiple keys only were provided to
near the top of the box or inclined transfer shear forces. temporary prestressing strands. The pier
tendons showed a considerable sag - Segments stressed together with segment, accompanying the assembled
between diaphragms, due to their dead external tendons running inside the box spart, was also transferred to the shuttle
load. As this would have created prob- and connected to pier diaphragms and barge, which then moved beneath the
lems during stressing, intermediate props deflector blocks. erection truss (Fig. 39).
were temporarily placed between The truss was a very sophisticated
- No overlay or wearing surface on the gantry combining innovative engineering
neighbouring diaphragms.
segments; the traffic runs directly on with proven techniques and practical
Originally, stressing at both tendon
the precast concrete. experience. VSL proposed to use such a
ends was required to compensate for the
friction losses, as in the design a friction The segments of the superstructure truss as a variant to the construction
coefficient u = 0.30 was adopted. Tests were cast in a yard in Tampa, Florida, scheme given in the contract documents.
on site, however, showed an effective of approx. 400 km (250 miles) north of the The following are the main factors that led
between 0.05 and 0.10. A revised bridge site. The five sets of forms allowed VSL to alter that scheme:
calculation with these values proved that for an average production rate of three - The segment alignment is taken off the
unilateral stressing was therefore accept- spans (i.e. 24 segments) per week. After critical path. thus increasing speed of
able for obtaining the required forces. proper curing, the segments were barged construction and adding flexibility to the
Post-tensioning work started in June to site. There, the segments of a span operation.
1975, and was completed in Cctober were placed aboard a shuttle barge, then - A cleaner division is achieved between
1976. The total quantity of strand incorpo- winched together, aligned to the required the work performed by the general
rated in both viaducts is 1,100 tonnes. alignment and connected with four contracter and by VSL.

19
EXTERNAL POST-TENSIONING

- VSL can control all its operations Additional details about the Seven Mile type EE 5-12 are installed, providing
overhead. Bridge and its construction can be found forces from 600 to 1,200 kN. The tendons
in [ 46] . are encased in PE tubes and were
The truss, designed and operated by grouted after stressing (Fig. 42).
VSL, in a typical operation lifted the pier 6.2.3. Chtelet Viaduct, Charleroi, As the Belgian standard in force at that
segment into place, then cantilevered Belgium time did not contain any prescriptions for
itself forward to position its centre on that Owner I.A.C. (Intercommunale this type of construction, full size model
newly placed pier segment and finally Autoroute Charleroi), tests were performed with tendons of the
raised the lifting frame bearing the Charleroi above-mentioned unit in order to assess
preassembled span from the barge. Engineer Office J. Rondas, Brussels the fatigue behaviour of the tendon itself
Concrete blocks were then inserted into Contractor Joint Venture Socol S.A., and especially of the anchorages. In this
the gap and the post-tensioning tendons Brussels/ Ateliers de Con- way an anchorage design fulfilling the re-
stressed to 15% of the ultimate force. struction Jambes-Namur; quirements was found. Another detail
After the closure concrete had reached a later Ateliers de Construc- checked was the tightness of the tendon
strength of 17.5 N/ mm (2,500 psi) tion Jambes-Namur/ Socit system at every point, in particular at the
overnight, the tendons were fully Pieux Franki S.A., Lige anchorages and the saddles.
stressed. Post- Civielco B.V., Leiden, The tables being practically straight,
VSL started erection of the first span of tensioning Netherlands saddles were required only near the
the bridge on May 30, 1980. On average, Construction anchorages, for reasons of space. These
three spans were installed per week, with Period 1981-1982 saddles consist of thick-walled steel tubes
a maximum of six spans in a six day In order to take the transit traffic off the welded to the web of the steel girder. The
single shift period. The structure was city centre and to connect the industry PE tubes of the tendons are fitted into the
completed in May 1982. zones at the periphery, an outer ring road saddles and the joints tightly sealed.
Each span contains 4 VSL tendons was built around Charleroi, an industrial
5-27 (breaking load approx. 4,960 kN centre in southern Belgium. In the suburb
each) and 2 of the unit 5-19 (Fig. 40). The of Chtelet the ring road crosses the
tendons are anchored in the pier dia- valley of the river Sambre, which is
phragms by VSL stressing anchorages densely built-up and through which the
type EC. In the five central segments of a railway line Paris-Cologne also passes.
span, the tendons are deflected in To cross the valley a 1,097 m long
deviation saddles. In the pier segment, viaduct had to be constructed.
semi-rigid duct was embedded to bring The design adopted was put forward in
the tendon to the anchorage, while a the tender stage as an alternative to the
short piece of galvanized pipe guides the tender design. It comprises two independ-
tendons through the deviation saddles. ent superstructures, each made up of two
Between these, the tendons are encased 3.00 m deep steel girders carrying a
in plastic pipes. Plastic pipe and duct or 16.00 m wide light-weight concrete deck.
pipe are connected with rubber boots and Most of the 25 spans, the lengths of
hose clamps (Fig. 41). All tendons were which vary between 34.98 and 58.60 m Figure 41: Detail of deviation saddle
prefabricated and pulled in by hydraulic (except the main span which measures
winch; they were cement-grouted for 68.40 m), are simply supported beams.
corrosion protection. In view of the bad soil conditions, the
Transverse post-tensioning was lightest possible structure was sought. For
also applied, in the deck slab of the pier this reason the steel girders are post-
segments only. The tables used are tensioned with external tables. At the
internal, consist of four strands 13 mm base of each girder, up to 6 VSL tendons
(0.5) and are provided with VSL anch-
orages.

Figure 42: Cross-section and detail with


Figure 40: Tendon layout tendons

20
EXTERNAL POST-TENSIONING

designed for twin-track operation, is


2.13 m (7) deep and has a deck width of
9.22 m (30 -3).
Both structures are longitudinally post-
tensioned with external VSL tendons 5-12
to 5-27 which run in the interior of the
box. These are between 21.34 and 43.59
m (70 and 143) long and have EC an-
chorages at both ends. The strands were Figure 44: Prefabrication yard
placed in polyethylene ducts, which were
grouted with cernent mortar after stress-
ing.
Deviator blocks are provided in every
3.05 m segment. In these and in the end
blocks, the strands lie in steel pipes which
are connected to the polyethylene pipes
by means of rubber hoses clamped on
the pipes (Fig. 45).
Transversely, the deck was preten-
sioned in the casting bed. Figure 45: Detail of pipe connection at
deviator block
Figure 43: General view of one bridge 6.2.5. Loir Bridge, La Flche, France
under construction
Owner Direction Dpartementale
de IEquipement de la
6.2.4. MARTA Bridges, Atlanta, Sarthe, Le Mans
Ga., USA Engineer SETRA, Bagne/ Bureau
Owner Metropolitan Atlanta Rapid dEtudes Dragages et
Transit Authority (MARTA), Travaux Publics, Paris
Atlanta, Ga. Contractor Dragages et Travaux
Engineer Figg and Muller Engineers, Publics, Tours
Inc., Tallahassee, Fla. Post- VSL France s.a.r.l.,
Contractor J. Rich Steers Inc., tensioning Boulogne-Billancourt
New York, N.Y. Construction Figure 46: One bridge half nearly
Post- VSL Corporation, Period 1982-1983 completely rotated
tensioning Atlanta, Ga. The construction of a by-pass road in
Construction the town of La Flche made a new bridge
Period 1982-1983 over the river Loir necessary. In view of
the large areas of land liable to flooding
The two bridges described below, one and the bad soil conditions, a very low span a depth of 1.75 m was adopted. The
designated CS-360, the other one CN- road level was adopted in order to avoid deck slab width is 10.75 m.
480, are the first precast segmental embankments. This fact, of course, had Each half superstructure was con-
concrete box girder railway bridges built in also a decisive influence on the design of structed parallel to the river with two 9 m
the USA (Fig. 43,44). Originally the struc- the bridge. long form-works, which were advanced
tures should have been constructed of in- A three-span bridge with the smallest like travellers of a free cantilever bridge.
situ concrete; the successful contracter, possible depth of the superstructure Thus segments of about 5 m length were
however, took advantage of a value- obviously was the only solution corre- obtained. After completion, each half was
engineering clause and had a redesign sponding to the given conditions. The rotated to the final alignment (Fig. 46).
prepared which resulted in the least length of the centre span was fixed at Construction lasted from March 1982 to
amount of expenditure and saved time. 64 m, while the lateral spans were chosen February 1983.
Thus up to four spans were completed at 26 m each. In order to equalize the Post-tensioning consists of two families
per week. Construction of both bridges masses between the lateral span and half of tendons. For the quasi free cantilever-
fasted for 64 weeks. the centre span, lightweight concrete was ing stages, internal tendons VSL type EC/
CS-360 is 1,594-10 m (5,230) long and selected for 59 m of the centre span while EC 6-12 were chosen, one tendon was
additional concrete was required in the anchored at the top of the web at each
has spans of 21.34 to 30.48 m (70 to
last 10 m of the side spans. segment end. In the bottom slab of the
100), while CN-480 has a length of
For hydraulic reasons, the depth of the centre span 4 VSL tendons EC/ EC 6-12
579.12m (1,900) and spans between
single-cell box girder superstructure had had to be placed, within the concrete
22.86 and 43.59 m (75 and 143). The
to be limited to 2.80 m at piers; at mid- section. In addition, 8 external tendons
single-cell box girder superstructure,

21
EXTERNAL POST-TENSIONING

Figure 47: Longitudinal section with external tendons

VSL 6-19 run near each web. These are


provided with standard VSL anchorages
type EC (Fig. 47). The strands were
installed by means of the VSL Push-
through Method. The sheathing of the ex-
ternal tendons consists of steel tubes. To
allow for possible force monitoring or the
replacement of an external tendon, these
were grouted with grease. This, however,
proved to be a very expensive method
due to the cost of the grease and of the
steel tubes.
The external tendons are deviated in
diaphragms and cross-beams provided at
various sections of the superstructure.
Deviation is obtained by means of a
curved piece of rigid steel tube which is
connected to the tendon sheathing by a
connecting sleeve welded to both tubes.

6.2.6. Bridge O.A. 33, Marseille,


France
Owner Direction Dpartementale
de IEquipement des
Bouches-du-Rhne, Figure 48: Bridge O.A.33 under construction
Marseille
Engineer Bureau dEtudes Dragages This is the location of the bridge desig- 48) as this variation offered the lowest
et Travaux Publics, Paris nated O.A. 33. The bridge consists of two price. Fabrication was carried out behind
Contractor Dragages et Travaux superstructures each having three traffic the Marseille abutment which is the
Publics, Marseille lanes. The two structures have spans of lowest point of the structure. The pier
Post- VSL France s.a r.l., 23-29-43-2x40-43-38-20 m and 31.69- diaphragms and internal diaphragms for
tensioning Boulogne-Billancourt 2x40.01 -38.61-2x43.02-33.01 -27.01 m the external tables were constructed at
Construction respectively. They are curved both in the the same time as the respective incre-
Period 1983-1985 horizontal and the vertical plane. The ments.
single-cell box girders have a depth of In the tender a post-tensioning layout,
2.85 m, the width of each deck slab being partly or entirely external, could be
In Marseille, the motorway A55 leaves 14.42 m. proposed. For execution the following
the centre of the City northwards. Soon it Both superstructures were built using three groups of tables were selected (Fig.
crosses an industrial and railway area. the incremental launching method (Fig. 49):

Figure 49: Tendon scheme

22
EXTERNAL POST-TENSIONING

Engineer Figg and Muller Engineers, of 3.66 m (12) by inclined struts ending at
Inc., Tallahassee, Fla. the intersection point between web and
Contractor Paschen Contractors, Inc., bottom slab. The main structure is
Chicago, Ill. followed on each side by 18 spans of
Post- VSL Western, 41 .15 m (135) standard length twin
tensioning Campbell, Cal. single-cell box girders (Fig. 52).
Construction All box-sectional parts were made up
Period 1983-1987 from precast segments joined together
The Sunshine Skyway Bridge replaces with an adhesive, some with in-situ
a section of the bridge structure leading concrete. In the main structure, the
across Tampa Bay between St. Peters- segments were hoisted from barges and
burg and Sarasota. The replacement placed at alternate ends in the free
Figure 50: Tendons inside the box became necessary, as in May 1980 a cantilevering manner. In the 41.15 m
tanker veered out of the navigation (135) spans, however, the erection truss
channel and rammed one of the main from the Seven Mile Bridge (see para.
piers, thus sending 400 m (1,300) of 6.2.2.) was reused after adaptation and
- Permanent tendons which were bridge into the water. In October 1982, complete spans were placed by the
stressed before a new increment was the owner opened bids for a replacement contracter, who had bought the truss from
jacked forwards. These tables are bridge. VSL.
polygonal and parabolic and are within The winning design for the high-level The superstructure is post-tensioned
the concrete section. and main approach spans consisted of a longitudinally and partially transversely.
- Temporary tendons that were stressed concrete box girder structure with a The latter tables consist of VSL tendons
before jacking and afterwards were 365.76 m (1,200) table-stayed main SO/ SO 6-4 placed in the concrete section
destressed and removed. After span. It should be noted that all stays are in flat corrugated ducts of high-density
completion of the first superstructure, VSL Stay Cables System 200 with up to polyethylene. Longitudinal post-tensioning
these temporary tendons were reused 82 strands of 15 mm (0.6). The rebuilt in the free cantilevered part consists of
in the second one. All of these tendons crossing was opened to traffic in April tendons within the concrete section
were external. Some were straight, 1987 (Fig. 51).
while others followed a polygonal The table-stayed part with spans of
profile to give, in conjunction with the 164.59-365.76-164.59 m (540 -1,200 -
first group, a central prestress. 540) is adjoined on each side by three
- Permanent tendons which were spans each of 73.15 m (240) and one
stressed after the increments were span of 42.67 m (140). The superstruc-
jacked forwards. They are all external ture of this main part consists of a 4.47 m
and either straight or polygonal in (14 -8) deep single-cell box girder with
layout. steeply inclined webs. The deck slab is
Figure 52: Cross-section of twin, single
All tendons are of the VSL unit 6-12 28.78 m (94 -5) wide. Along the central
box girder structure
(breaking force 3,024 kN each) and have axis it is supported in the box at intervals
stressing anchorages type EC at both
ends. The temporary tendons and the
final external tendons were placed in
polyethylene tubes, while steel pipes
were used for the final internal tendons
(Fig. 50). All final internal tendons were
grouted with cement grout.
The external tendons are deviated in
concrete frames provided in the boxes,
into which curved steel tubes are placed.
A short piece of PE tube is placed on the
ends of the steel tubes and fixed in the
concrete. To this the PE tube of the
tendon is joined by means of a joint
welded on both ends of the PE tubes.

6.2.7. Sunshine Skyway Bridge


across Tampa Bay, Florida, USA
Owner Florida Department of
Transportation, Tallahassee,
Fla.
Figure 51: Sunshine Skyway Bridge
23
EXTERNAL POST-TENSIONING

installed during free cantilevering while has two river piers. The height above the stresses desired by the engineer.
the continuity cables run inside the box. river varies from 24.38 m (80) at the north All tendons were cement-grouted for
These are VSL units 5-17 and 5-27, up to end to 58.22 m (191) at the south end, corrosion protection. A special detail was
238 m (781) long. In the 41.15 m (135) making it one of the worlds steepest required for the trumpet to allow for
spans, VSL tendons 5-19 to 5-27 are bridges (Fig. 53). structure movement during stressing
arranged inside the box similarly to the The new bridge makes use of some while maintaining a seal capable of
cables of Seven Mile Bridge (see para. innovative structural techniques. Although withstanding the high grouting pressure.
6.2.2.). Anchorages used were standard the main river span appears to be a
EC type. After stressing (double end traditional arch, it does not function as 6.2.9. Bois de Rosset Viaduct near
stressing for longer tendons) the cables such. The structural loads are distributed Faoug (VD), Switzerland
were cement-grouted. in cantilevered action through the use of Owner Dpartement des Travaux
the half arches on either side of the main Publics du Canton de Vaud,
6.2.8. High Bridge, St. Paul, Mn., span and the tensioned tables beneath Lausanne
USA the deck. This unique structural system Engineer CETP Ingnieurs-Conseils
allows steel members to be lighter than SA, Lausanne/DIC
Owner State of Minnesota, conventional arches and this contributes Ingnieur Conseil, Aigle
St. Paul, Mn. to the graceful aesthetic qualities of the Contractor Joint Venture of
Engineer Strgar-Roscoe, Inc., structure. Frutiger SA, Yvonand/
Wayzata, Mn./ Eight VSL tendons 5-27, 166.12 m Ramella + Bernasconi SA/
T.Y. Lin International, (545) long, tie the cantilevered arches Reymond SA
San Francisco, Cal. together at the south pier. Similarly eight Post-
Contractor Lunda Construction, black tendons of the same unit, 146.61 m (481) tensioning VSL International SA
River Falls, Wi. long, were used at the north pier. The Crissier
Post- VSL Corporation, tendons, which are straight, were Construction
tensioning Burnsville, Mn. anchored at both ends by means of period 1988-1990
Construction normal E type stressing anchorages
Period 1985-1987 provided with a special cover cap. Each The Bois de Rosset Viaduct consists of
tendon was pulled from ground into a two parallel structures with 15 spans each
The new High Bridge, which replaces a galvanized steel pipe of 101.6 mm (4). (23.00-34.20-11x42.75-51.30-38.50 m). It
structure that was built in 1889, is the first Stressing was carried out in three stages: has a total length of 617.25 m, a width of
bridge in the USA to use a combination Stage I stressing closed the gaps in the 2x13.0 m, and crosses a railway line at a
of table and steel tension-tie design for a slotted connections at the ends of the height of approx. 10 m. The composite
deck-tied arch bridge. It is 839.72 m wide flanges, Stage II took place after the superstructures consist of steel trough
(2,755) in length with a width varying concrete deck was cast and Stage Ill fine- girder sections connected to a transverse-
from 20.02 to 27.13 m (65 -8 to 89). It tuned the arch to the camber and ly post-tensioned concrete deck slab.
The structures are longitudinally post-
tensioned with four VSL External Ten-
dons in each span. Each tendon consists
of 12 individually greased and plastic-
sheathed VSL Monostrands which are
grouted inside a thick-walled polyethylene
tube. Tendon lengths range from 196 m
to 216 m, and are located inside the steel
troughs, routed over a maximum of five
upper deviation saddles and ten lower
saddles.

Figure 54: Cross-section of


superstructure of Bois de Rosset Viaduct
project
Figure 53: High Bridge, St. Paul, Minnesota

24
EXTERNAL POST-TENSIONING

This project represents the first use of b) Surrounding the masonry with stressed entirely surrounds the flue gas pipe and is
monostrand external tendons in Switzer- steel bands. The installation of these anchored in a steel buttress. To minimize
land, and the installation is monitored as bands and the disc springs required be- the effect of friction losses, successive
part of a long-term observation program. tween band segments are expensive as pairs of tendons are alternately anchored
Four tendons are equipped with perma- exterior scaffolding is needed around at buttresses on opposite sides. Each
nent VSL load cells, and all tendons are the chimney. The same is also true for tendon is stressed to 100 kN. Tendon
adjustable and replaceable. additional stressing of the bands at a spacing is 1 m. Before reaching the
As mentioned in para. 3.3, extensive later date, which is necessary as the buttress, one table end undergoes a
testing was performed for the develop- springs do not provide long-term com- deviation in a special construction, so that
ment of this tendon system with regaid to pensation for creep of the gap-filling
materials, procedures, anchorage design, compound. it can be anchored in the buttress. The
and friction losses in the saddles. For two chimneys a new method was deflection device and the anchor buttress
applied in 1986/87, in particular to avoid are coated with an anti-corrosive paint
6.3. Other structures the above-mentioned disadvantages. This (Fig. 56).
originally designed with method consists of surrounding the flue The installation of the special bricks,
external tendons gas pipe at regular intervals with external, the PE protective pipes containing the
individual post-tensioning tendons. These monostrands, and the buttresses was
6.3.1. Flue gas chimneys, Federal must fulfill the following requirements: carried out as part of the brickwork of the
Republic of Germany - easy installation, flue gas pipe. Thus, no special outside
For environmental reasons, coal-fired scaffolding was required. For stressing,
- easy stressing operation, however, a scaffold was used, which
power plants in the Federal Republic of
Germany are equipped with flue gas - possibility of additional stressing, could be displaced vertically in front of the
sulphur removal systems. The purified - possibility of monitoring the tendon
flue gases are normally expelled through force,
the cooling tower, together with the - easy replacement.
cooling steam. In the case of a break-
down, however, the flue gases are The tendons used are VSL Monos-
diverted past the desulphurization system trands 15 mm. They rest on special
and fed into the chimney. bricks containing a groove into which the
The shaft of the chimney ( approx. 10 tendon is fitted. These bricks are thermal-
to 17 m) is made of reinforced concrete; ly insulated from the flue gas pipe so that
the tendons are subject to a maximum
inside is the flue gas pipe made of acid-
temperature of 40C which both grease
resistant ceramic masonry. The flue gas
and PE coating are able to withstand
pipe is surrounded by thermal insulation
without problems. Nevertheless each
made of foam glass (Fig. 55). Upon
monostrand is additionally inserted into a
breakdown of the desulphurization
protective pipe of PE in order to prevent
system, the temperature of the flue gas Figure 55: Cross-section of the flue gas
the coating of the tendon from bearing
rises quickly by 90C to 180C. The shock chimney
directly onto the bricks. Each tendon
of the sudden change in temperature
leads to high compressive and tensile
stresses in the heat-resistant ceramic
masonry. The tensile stress exceeds the
stress limit allowed in the standard DIN
1056. To ensure the serviceability of the
flue gas pipe, special methods must
therefore be taken.
Up to now the following methods have
been used:
a) Reinforcing steel with anti-corrosive
coating. The disadvantages of this
solution are that the reinforcing steel
does not prevent cracks and that
bonding problems can occur as a result
of the differing thermal expansion
coefficients of reinforcing steel and
ceramic brick.

Figure 56: Deflection device with anchorages

25
EXTERNAL POST-TENSIONING

row of buttresses. The post-tensioning after checking of the design, it was found and because of the length and the weight
force cari be checked at a later date, if that no temperature gradient had been of the tendons. Thus only the push-
required, the anchor heads being considered and that the cover of the through method was applicable. Tests
externally threaded for this purpose. prestressing tendons was insufficient. The made by VSL enabled the best way of
Before the system was actually applied structure therefore had to be repaired in operating to be found. They showed that
on site, tests were carried out in order to: the shortest possible period. A complete two intermediate pushing posts were
- verify that the edge of the bricks would interruption of the highway being unac- required. According to the access
not cause any long-term damage to the ceptable, the owner had to allow for the possibilities, pushing sections of 135, 160
PE coating of the monostrands repair work to be done under light traffic. and 135 m were selected. Two pushing
- test and practise proper installation, Therefore, the consultant proposed to machines had to be placed at the first
stressing and replacing of the tendons apply external longitudinal prestressing intermediate post in order to obtain the
after the cracks had been grouted with required pushing force (Fig. 58).
The tests gave fully satisfactory results resin. In addition, the following measures When a certain number of strands had
which were confirmed during application. had to be taken: been introduced, the pushing force
available was no longer sufficient for
6.4. Bridges with - Construction at either end of the bridge overcoming the friction in the steel tubes
subsequently added external of a prestressed concrete cross-beam, and an auxiliary strand running between
tendons incorporating the anchorages of the the first two posts was used, to which the
new tendons and transmitting the strands to be installed were coupled. The
6.4.1. Roquemaure Bridge near additional forces to the superstructure first machine pushed the auxiliary strand
Avignon, France of the bridge. while the second machine pulled it. After
- Construction of a working chamber pulling, the auxiliary strand was pushed
Owner Autoroutes du Sud de la behind each cross-beam, from which back to the first post and the operation
France, Vdne the strands would be fed into the ducts then repeated. When the pushing
Engineer Etudes Ouvrages dArt and where the cables could be operation was finished, the openings in
(Bouygues), St. Quentin en stressed. the tubes were closed by previously
Yvelines - Installation of hangers beneath the mounted coupling sleeves.
Additional bridge deck carrying the cable ducts. Before the tables were stressed each
Post- VSL France s.a. r.l., individual strand was pretensioned to
tensioning Boulogne-Billancourt The longitudinal prestressing force
required amounted to 54,000 kN after 1 N/mm by means of a monojack to bring
Execution 1975-1976 all strands to the same length.
losses. VSL thus proposed to use 8
This bridge is part of Motorway A9 tendons of the unit 5-55 (ultimate force
Orange-Narbonne in Southern France, 9,169 kN) running from one end of the
which it carries across the river Rhne bridge to the other without any coupler
near Avignon. The structure is 420 m long (table length thus 430 m!). Four spare
and has spans of 50-4x80-50 m. The ducts were also installed in case addi-
21.60 m wide superstructure consists of a tional prestressing should be needed.
double-T section with a depth between VSL was awarded the post-tensioning
5.40 m at piers and 1.80 m at mid-spans contract because, besides a reasonable
(Fig. 57). It was built in 1971 to 1974 by price, VSL could prove its experience, in
the free cantilevering method, with cast- pushing through strands and it had
in-place segments up to 6.12 m in length. available equipment for this method,
In 1975 a surveillance campaign revealed including several high capacity jacks.
the presence of major cracks (as wide as Placing of the tendons was the most de-
8 to 10 mm) at the mid-span sections. manding part of the job. Placing preas-
After examination of the damage and sembled strand bundles was excluded
from the beginning because of the limited
space available in the working chambers Figure 58: Pushing trough strands

Figure 59: Stressing of additional tendons


Figure 57: Cross-section of Roquemaure Bridge with added external tendons in the stressing chamber

26
EXTERNAL POST-TENSIONING

Stressing had to be done on two cables grouted cracks. Furthermore, it was stressed at the anchorages behind the
simultaneously and at both ends for established that the stress variation in the pier diaphragm. Elongations measured
symmetry reasons. The time available for post-tensioning steel considerably 440 mm on average. Post-tensioning
stressing 4 x (of the 8) tendons was fixed exceeded the allowed value. work lasted for seven days. All cracks
at 6 hours and therefore great mobility of Thus a static strengthening was closed after stressing.
the equipment was required. Five VSL required, not only corrosion protection The rehabilitation work overall took five
jacks ZPE-1000 (one as spare) and corre- measures. In view of the limited space months.
sponding accessories, as well as five available inside the box cells, which did
pumps were engaged (Fig. 59). The not allow for adding reinforcement, 6.4.3. Bridge over Wangauer Ache
jacks, each weighing 2.5 tonnes, were strengthening the larger span by means near Mondsee, Austria
mounted on specially constructed of post-tensioning tables offered the best Owner Republic of Austria, Federal
hydraulic carriages. Stressing was done solution. Straight unbonded tendons were Road Administration, Vienna
in steps of 5 N/mm. The cable extension selected, the number of which had to be Engineer
amounted to 3,150 mm. The cables of the the smallest possible. (Repair) Kirsch-Muchitsch, Linz
end cross-beams (16 No. EE 5-12 on A total of 24 tendons VSL type 5-16 Contractor Hofman u. Maculan,
each side) were stressed in groups of two (breaking force 2,833 kN each) with (Repair) Salzburg
at the same time as the longitudinal threaded anchor heads and an average Additional
tendons. length of 75 m were required. At the post-
In view of the quantity of material to be abutment side these were anchored in tensioning Sonderbau GesmbH, Vienna
injected and of the length of the cables, anchor blocks added to the web prolonga- Execution 1987-1988
the use of a special grout mix with tions, while buttresses were provided
retarded hardening and consisting of behind the pier diaphragm, which itself This bridge is part of the highway
clinker and resin was required by the also had to be post-tensioned to take the Vienna-Salzburg. It was built in 1962-
client. Grouting was executed in sections, additional forces. 1964. In recent years improvements have
which made movable equipment neces- The monostrands were placed in PE been made several times, but a thorough
sary. The grout mix was injected over a ducts which were provided with two inspection revealed a large number of
distance of 180 m before the installation movable joints to absorb temperature deficiencies, making a general rehabilita-
had to be moved. Two tables were movements. As strand deviations could tion necessary. In particular, a lack of
grouted per day, requiring 12 m3 of not be avoided and inaccuracies in the longitudinal prestressing force was
boring had to be expected and in view of detected, which had become obvious in
grouting material.
the large elongations, the likelihood of opened construction joints. Thus, rehabili-
damage on the strand coating due to tation had to include also the installation
6.4.2. Ruhr Bridge Essen-Werden,
transverse pressures caused by strand of additional tendons. Since a closure of
Federal Republic of Germany
deviations was evaluated in tests. The the motorway was not acceptable, one
Owner City of Essen
coating remained safe in these tests. structure was strengthened first, followed
Engineer
Borings had to be carried out with high by the other.
(Repair) Prof. Dr. G. Ivanyi, Essen
accuracy. Boring distances were 10 to
Contractor Polensky & Zollner AG, The twin bridge has spans of 25-6x28-
12 m (in pier diaphragm). Oblique boring
(Repair) Bochum 2x41.25-3x28-25 m, i.e. a total length of
(in plan view) was also required through a
Additional span diaphragm and subsequently 384.50 m. Each superstructure has a
post- SUSPA Spannbeton GmbH, through a web. double-T cross-section, 13.05 m wide and
tensioning Langenfeld The strand bundles were prepared in 2.20 m deep. Since the existing longitudi-
Execution 1985-1986 the workshop. The diaphragm tables nal post-tensioning was bonded, and no
were placed by means of a movable spare ducts were available, the additional
This two-span post-tensioned concrete crane. The longitudinal tendons were post-tensioning had to be placed on the
bridge (spans 66.40-47.00 m) has a multi-
cell box superstructure with a deck width
over the intermediate pier of 34.41 m.
This width increases on both sides
towards the abutments (Fig. 60).
In the bottom slab and in the web of
the larger span, numerous cracks due to
bending had developed making rehabilita-
tien measures necessary especially in
view of the corrosion protection of the
post-tensioning tables in the cracked
area. Grouting the cracks (which were up
to 0.4 mm wide) was disregarded since it
was established that the cracks originated
from temperature gradients; thus new
Figure 60: Plan view of Ruhr Bridge Figure 61: Anchorages inside the box
cracks would have appeared near the
(showing cracks) prior to concreting

27
EXTERNAL POST-TENSIONING

distances of 40 to 50 m. Two grouting


pumps were required.

6.5. Other structures with


subsequently added external
tendons
6.5.1. Clinker Silo, Jakarta,
Indonesia
Owner PT Perkasa lndonesia
Cement Enterprise (Indoce-
figure 62: View of added tendons ment), Jakarta
Engineer VSL INTERNATIONAL LTD.
outside of the webs. However, the total (Repair) Berne, Switzerland
length of 386 m was considered to be a Contractor PT John Holland Construc-
problem. (Repair) tions Indonesia, Jakarta
Four VSL tendons EE 5-12 per web Additional
were selected as the additional post- post-
tensioning. Polyethylene tubes of 90 mm tensioning PT VSL Indonesia, Jakarta
diameter and 4 mm wall thickness were Execution 1985
chosen as sheathings (Fig. 62). At the
ends of the superstructures, end dia- The silo, which is located at Tanjung
phragms, each post-tensioned by 3 VSL Priok, Jakartas harbour, is used for the
tendons EP 5-7, were provided. storage of clinker awaiting export. The
The ducts were fixed to the webs at the structure has an internal diameter of
quarter points of the spans by means of Figure 63: View of rehabilitated clinker
19.80 m and a height of 30 m. Its wall is
clamps. In between, additional cable silo
400 mm thick. It was built of reinforced
supports were provided in order to avoid concrete in the early seventies. Because tendons comprising four strands. Since
wobble. These supports were hung from the reinforcement was inadequate, it had there were no buttresses, VSL anchor-
the deck slab. In order to prevent the to be repaired. ages type Z 5-4 were used (two on every
strands from abrading the polyethylene The repair consisted of placing external tendon). In total 60 hoop tendons were
duct at clamping points, steel tubes were tendons around the silo. In view of the required. The tables were assembled by
placed inside the polyethylene ducts at high ambient temperature and the hand and temporarily hung from steel
those points. These steel tubes also act aggressive environment, it was decided to supports. The anchorages were placed
as stiffeners at the joints of the polyethy- use greased and PE-coated strands on concrete pads. After stressing, the
lene ducts. (monostrands) 13 mm bundled to anchorages were covered with concrete
The strands were installed by the VSL
Push-through Technique. Two pushing
machines were placed one behind the
other and driven by a hydraulic pump of
corresponding power. The strands had to
be cut to length by hand before they
could be pushed through. However, only
the first 3 to 4 strands could be fully
pushed through without squeezing.
Therefore, strand installation was com-
pleted by hand from a joint opened in the
duct about 250 m from the push-through
machines.
Before stressing all joints were
checked for tightness. Stressing was
done from both ends. A friction coefficient
of only 5% was observed. Grouting was
provided for corrosion protection, not
bond. It was performed from the lowest
point in the middle of the table, towards
both ends. Vent hoses were provided at

Figure 64: View of Pier 39 parking structure

28
EXTERNAL POST-TENSIONING

so that now the repaired structure out. Top-of-slab cracking adjacent and Approx. 10% of the tendons were
appears to have four buttresses (Fig. 63). parallel to many beams, and beam replaced. Most stressing work was carried
deflections of up to 38 mm (1 1/2) in out from the outside of the building (Fig.
6.5.2. Pier 39 Parking Structure, many instances were found. Also several 66). The repair job started in August 1986
San Francisco, USA strands popped out of beam ends. All and was substantially complete by April
Owner Pier 39 Associates, strands were subsequently examined; 1987.
San Francisco, Cal. they all showed some signs of corrosion. It should be emphasized that short-
Engineer Bijan, Florian & Associates Several strands had even failed. comings encountered in early application
(Repair) Inc., Mountain View, Cal. The central issue to the rehabilitation of of unbonded strands in commercial
Contractor the structure, besides economy, was that buildings and parking structures have
(Repair) and a new system had to be built around or long been recognized and fully rectified.
Additional added to the existing structural members Today, post-tensioning of such structures
post- VSL Corporation, while the parking garage remained is commonly the most economical and
tensioning Los Gatos, Cal. essentially operational. The beams, and performance-healthy mode of design and
Execution 1986-1987 to a lesser degree the slabs, were the construction.
primary targets of rehabilitation.
This structure, which is part of a Two major options of rehabilitation
shopping centre, was originally con- were reviewed in detail, one using steel
structed in 1978/79 in the Fishermans members (trusses or channels) and the
Wharf area; it has space for 1,000 cars other post-tensioned tendons. The latter
(Fig. 64). It has five parking levels was adopted.
including the roof, and a rectangular plan The structural design followed UBC
with overall dimensions of 118.90 x 63.00 1982. Two tendons per beam, each
m (370 x 196); at one corner there is a consisting of six strands 13 mm (0.5)
square recess of 20.90 x 54.60 m (65 x were added, one on each side of the web.
170). At mid-spans and over columns the
The original structural system con- tendons are deviated by means of
sisted of post-tensioned beams, 914 mm deflectors. These were made of 114
(36) deep and spanning 21.00 m mm (4 1/2) extra-heavy pipe. In order to
(65 1/2), which frame into columns to obtain the best possible corrosion protec-
form a parallel plane frame in the trans- tion, the strands were coated with epoxy.
verse direction. One-way post-tensioned The 51 mm (2) corrugated PVC pipe
slabs, 114 mm (4 1/2) thick, span the was used as tendon sheathing (Fig. 65).
longitudinal direction with spans of 5.80 m The work was carried out to allow
continuous use of the garage by the
(18). The beams contained seven public. Deflectors, end brackets and
15 mm (0.6) monostrands while the slab precast members were erected on a night
had 13 mm (0.5) monostrands at shift, tendons in a day shift. The slab
660 mm (26) centres. When in 1985 tendons were inspected and replaced by
severe slab cracking at the roof level and removing 1.22 m (4) closure strips
substantial water leakage from the roof located at approximately one-third points
were noted, further inspection was carried along the longer side of the structure.

Figure 65: Scheme of added beam tendons Figure 66: Stressing added tendons

29
EXTERNAL POST-TENSIONING

7. Bibliography and References


[1] VSL Stay Cables for Cable-Stayed [12] Schambeck H.: ber das Langzeitverhal- [24] Verzeichnis der allgemain bauaufsicht-
Bridges, January 1984. VSL INTERNA- ten einer 50 Jahre alten Spannbe- lich zugeiassenen Spann-sthle (List of
TIONAL LTD., Berne, Switzerland. tonbrcke (On the iong-term behaviour the generally officially approved
of a 50-year old post-tensioned concrete prestressing steels). Mitteilungen Institut
[2 ]VSL Soil and Rock Anchors. Pamphlet bridge). Bauingenieur, 1987, pp. 557- fr Bautechnik (IfBt), Berlin, 1/1988, pp.
issued by VSL INTERNATIONAL LTD., 559. 12-15.
Berne, Switzerland, 1987.
[13] Broar ver Angermanalven vid Sand [25] Heavy Duty Composite Bar HLV made of
[3]Specht M. et al.: Spannweite der (Bridge across Anger-Manlven to Polystal for Prestressing Tendons and
Gedanken, zur 100. Wiederkehr des Sand). Kungl. Vg-och Vat- Soil Anchors. Pamphlet by joint venture
Geburtstages von Franz Dischinger (The tenbyggnadsstyrelsen, Sweden, 1949. Strabag Bau-oAG, Cologne/Bayer AG,
span of ideas, on the centenary of the Leverkusen.
birth of Franz Dischinger). Springer- [14] Virlogeux M.; La prcontrainte extrieure
Verlag, Berlin, 1987. (External Post-tensioning). Annales de [26] Gerritse A., Schrhoff H.J.: Prestressing
IInstitut Technique du Batiment et des with Aramid Tendons. 10th International
[4] Freyssinet E.: Une rvolution dans les Travaux Publics (ITBTP), No. 420, Congress of the FIP, New Delhi, In dia,
techniques des btons (A revolution in December 1983. 1986, Proceedings Vol. 2, pp. 35-44.
concrete techniques). Librairie de
lEnseignement Technique, Editeur Lon [15] Storrer E: Le pont de Sclayn sur la [27] Recommendations for acceptance and
Eyrolles, Paris, 1936. Meuse (The Scfayn bridge across river application of post-tensioning systems.
Meuse). Annales des Travaux Publics de Fdration Internationale de la Prcon-
[5] Dischinger F.: Elastische und plastische Belgique, 1959, No. 2, pp. 179-196 and trainte (FIP), London, UK, 1981.
Verformungen der Eisenbetontragwerke No. 4, pp. 603-618.
und insebesondere der Bogenbrcken [28] Thielen G., Jungwirth D.: Corrosion
(Elastic and plastic deformations of [16] Mller Th.: Umbau der Strassenbrcke Protection of Prestressing Tendons.
structures in reinforced concrete and ber die Aare in Aarwangen (Recon- IABSE Symposium Paris-Versailles
especially of arch bridges). Der Bauin- struction of the road bridge across the 1987. IABSE Report Vol. 55, pp. 73-78.
genieur, 1939, pp. 53/286/426/563 and river Aare at Aarwangen). Schweizeris- International Association for Bridge and
following. che Bauzeitung, 1969, No. 11, pp. 199- Structural Engineering (IABSE), Zurich,
203. Switzerland.
[6] Schonberg M., Fichtner F.: Die Adolf-
Hitler-Brcke in Aue (Sa.). (The Adolf [17] Mu//er J.: Construction of the Long Key [29] Dorsten V., Hunt F.F..Preston H.K.:
Hitler Bridge in Aue [Sa.]). Die Bautech- Bridge. Journal of the Prestressed Epoxy Coated Seven-Wire Strand for
nik, 1939, No. 8, pp. 97-104. Concrete Institute, November-December Prestressed Concrete. Journal of the
1980, pp. 97-111. Prestressed Concrete Institute, July-
[7] Lippold P., Spaethe G.: Rekonstruktion August 1948, kpp. 120-129.
der Bahnhofsbrcke in Aue (Reconstruc- [18] Podolny W., Muller J.: Prestressed
tion of the railway station bridge in Aue). Concrete Segmental Bridges. John Wiley
Bauplanung - Bautechnik, 1965, No. 9, & Sons, New York, 1982. [30] Chabert A. et al.: Injection la cire
pp. 435-438, No. 10, pp. 505-512 and ptrolire de cables de prcontrainte
No. 11, pp. 542-547. [19] Virlogeux M.: Bilan de la politique (mise en oeuvre en premire mondiale
dinnovation dans le domaine des au viaduc de la Boivre). (Grouting of
[8] Hofmann G.,: Thrmer E.: Erfahrung bei ouvrages dart (Evaluation of innovation post-tensioning tendons by means of
der Sanierung der Bahnhofsbrcke Aue policy in civil engineering works). petroleum wax [worlds first application at
(Experience with the rehabilitation of the Travaux, March 1985, pp. 20-34. the Boivre Viaduct]). Travaux, March
railway station bridge Aue). Die Strasse, 1985, pp. 41-44.
1986, NO. 6, pp. 174-180. [20] Ivkovic M. et a/.: New Prestressed
Concrete Hangar at the Belgrade [31] Wssner K. et al.: Die NeckartalbrUucke
[9] Dischinger F.: Weitgespannte Tragwerke International Airport in Yugoslavia. 10th, Weitingen (Neckar Valley Bridge Weitin-
(Large-span structures). Der Bauin- International Congress of the FIP, New gen). Der Stahlbau, 1983, No. 3, pp. 65-
genieur, 1949, No. 7, pp. 193-199, NO. Delhi, India, 1986, Proceedings Vol. 1, 77 and No. 4, pp. 113-124.
9, pp. 275-280 and No. 10, pp. 308-314. pp. 239-244.
[32] Hofmann E. Becker A.: Talbrcke
[10] Dischinger F.: Stahlbrcken im Verbund [21] Concrete Storage Structures - Use of the <<Obere Argen>> - Entwurfs-varianten
mit Stahlbetondruck-platten bei gle- VSL Special Construction Methods, May aus Ideen- und Angebotswettbewerb
ichzeitiger Vorspannung durch hochwer- 1983. VSL INTERNATIONAL LTD., (Valley Bridge <<Obere Argen>> -
tige Seile (Steel bridges combined with Berne, Switzerland. Design variants from idea proposing and
reinforced compression slabs and post- tender competition). Bauingenieur, 1987,
tensioned with high-strength cables). Der [22] Pelle K., Schtt K.: Post-Tensioning pp. 219-229.
Bauingenieur, 1949, No. 11, pp. 321-322 System for Flue Gas Pipes of Power
and No. 12, pp. 364-376. Plant Chimneys. FIP Symposium Israel [33] Talbrcke Obere Argen (Valley Bridge
1988. Obere Argen). Pamphlet issued by the
[11] Mller P.: Brcken der Reichsautobahn joint venture TalbrUucke Obere
aus Spannbeton (Bridges of the Reich [23] Adeguamenti antisismici (Antiseismic Argen>>.
motorway in post-tensioned concrete). equalizers). Pamphlet by ICOS S.p.A.,
Die Bautechnik, 1939. No. 10, pp. 128- Milan, Italy, September 1978.
135.
30
EXTERNAL POST-TENSIONING

[34] Wittfoht H.: Outstanding and Innovative [45] VSL Post-tensioning. Pamphlet issued [57] Aalami B.O., Swanson D.T.: Innovative
Construction Methods in Concrete by VSL INTERNATIONAL LTD., Berne, Rehabilitation of a Parking Structure.
Structures - Recent and Future Trends Switzerland, 1980/1986. CONSTRUCTION INTERNATIONAL,
(from the Viewpoint of the Main Contrac- February 1988, PP. 30-35.
tor). 10th international Congress of the [46] Closing the gaps with assembly line
FIP, New Delhi, India, 1986, Proceed- span placement. Engineering News [58] Post-tensioning turns inside out.
ings Vol. 1, pp. 349-357. Record, Mc Graw-Hill, New York, Engineering New Record, Mc Graw-Hill;
September 3, 1981. New York, March 12, 1987, p. 32FC.
[35] Menn Ch.: Brckentrager mit Unterspan-
nung (Bridge girder with underlying [47] FIP 9th Congress Stockholm 1982 June
tendons). Schweizer Ingenieur und 6-10 (Extract from Annales des Travaux
Architekt, 1987, pp. 200-204. Publics de Belgique No. 2 - 1982).
Ministry of Public Works/Belgian Con-
[36] Menn Ch., Gauvreau P.: Scale model crete Society, pp. 6/7.
study of an externalty prestressed
concrete slab bridge. International [48] MARTA Rapid Transit Bridges Going Up
Conference on Cable-Stayed Bridges, Full Speed. Journal of the Prestressed
Bangkok, Thailand, 1987, Proceedings, Concrete Institute, July-August 1983, pp.
pp. 919-926. 184/185.

[37] Haas G. et al.: Die Stahlberbauten der [49] MARTA Rapid Transit Bridges. Journal
Far-Brcken, Dane-mark (The steel of the Prestressed Concrete Institute,
superstructures of the Far Bridges, March-April 1985, pp. 188-194.
Denmark). Der Stahlbau, 1985, No. 12,
pp. 353-363. [50] US rapid transit bridge built span-by-
span with precast elements. VSL News
[38] Ritz P.: Beigeverhalten von Platten mit Letter August 1985, pp. 20/21. VSL
Vorspannung ohne Verbund (Flexural INTERNATIONAL LTD., Berne, Switzer-
behaviour of slabs prestressed with un- land.
bonded tendons). Institut fr Baustatik
und Konstruktion ETH Zrich, Bericht Nr. [51]Virlogeux M., Placidi M., Hirsch D.,
80, Birkhauser Verlag Basel und Lacoste G., Mossot J., Fesnais P., Colas
Stuttgart, Mai 1978. M.: Le nouveau pont sur le Loir a la
Flche (Sarthe). (The new bridge across
[39] Wittfoht H.: Betrachtungen zur Theorie river Loir at La Flche [Sarthe]). Travaux,
und Anwendung der Vor-spannung im July-August 1983, pp. 3-23.
Massivbrckenbau (Considerations on
the theory and application of post- [52] Bridge halves constructed parallel to the
tensioning in concrete bridge construc- river and connected together after
tion). Beton-und Stahlbetonbau, 1981, rotating. VSL News Letter May 1983, pp.
No. 4, pu. 78-86. 21/22. VSL INTERNATIONAL LTD.,
Berne, Switzerland.
[40] Zimmermann J.: Tragverhalten und
Systemtragfhigkeit von Trgern mit [53] Autoroute A.55, Ouvrage dart 33
Vorspannung ohne Verbund (Behaviour (Motorway A.55, Structure No. 33).
ai-id ultimate strength of beams with Brochure issued by Dragages et Travaux
unbonded prestressing). Thesis, Publics.
Technische Hochschule Aachen, 1985.
[54] Unconventional table layout for
[41] Post-tensioned Slabs, January 1981/ incrementally launched bridge with
1985. VSL INTERNATIONAL LTD., varying spans. VSL News Letter August
Berne, Switzerland. 1985, pp. 7/8. VSL INTERNATIONAL
LTD., Berne, Switzerland.
[42] DIN 4227, Teil 6: Spannbeton, Bauteile
mit Vorspannung ohne Verbund [55] Skyway bridge boasts a record and
(Prestressed Concrete, Structural parts innovations. Engineering News Record,
with unbonded prestressing). Vornorm Mc Graw-Hill, New York, September 11,
Mai 1982, Beuth-Verlag, Berlin und kln. 1986.

[43] SlA E 162: Betonbauten (Concrete [56] Ivanyi G., Fastabend M., Lardi R., Pelle
Structures). Draft March 1987. K.: Statisch-konstruktive Verstarkung
Schweizer lngenieur- und Architekten durch zusatzliche Vorspannung (Static-
Verein, Zrich, pp. 13 and 29. constructive reinforcement by means of
additional post-tensioning). Bautechnik
[44] CAN 3 - A 23.3 - M 84: Oesign of 1987, No. 6, pp. 181-187.
Concrete Structures for Buildings.
Canadian Standards Association,
Toronto, 1984, p. 170. 31
PUBLISHED BY VSL International Ltd., Bernstrasse 9, 3421 LYSSACH, Switzerland

Representative Office, VSL International Ltd., 41 Avenue du Centre, 78067 ST QUENTIN YVELINES, France
Tel 33 - 1 - 30 12 09 30, Fax 33 - 1 - 30 48 94 94

REGIONAL HEADQUARTERS

SOUTH. EAST ASIA / NORTH EAST ASlA USA - AMERICA EASTERN EUROPE WESTERN EUPOPE
AUSTRALIA MIDDLE EAST SOUTH AMERICA,
AFRICA* AFRICA* *
* (English speaking dart) (French speaking)

VSL Prestressing (Aust.) VSL North East Asia VSL Corporation VSL (Switzerland) Ltd. VSL France S.A.
Pty. Ltd. Regional Office 1508 Bernstrasse 9 3421 110, Avenue Verdun
Crosspointe II Plaza 91520 EGLY
6 Pioneer Avenue Devon House 979 King's LYSSACH Switzerland
2840 Plaza Place
THORNLEIGH, NSW 2120 Road QUARRY BAY Tel 41-34-479911 France
Suite 200
Australia Hong Kong Fax 41 - 34 - 45 43 22 Tel 33 - 1 - 69 26 14 00
RALEIGH, NC 27612
Tel 61 - 2 - 484 59 44 Tel 852 - 590 22 22 USA Fax 33 - 1 - 60 83 89 95
Fax 61 - 2 - 875 38 94 Fax 852 - 590 95 93 Tel 1 - 919 - 781 6272

VSL COMPANIES AND LICENSEES

AUSTRALIA CZECH REPUBLIC INDIA PERU USA


VSL Prestressing (Aust.) VSL Systemy (CZ) s. r. o., Killick Prestressing Ltd., Pretensado VSL del Peru VSL Corporation
Pty. Ltd. PRAHA BOMBAY SA, ATLANTA, GA
THORNLEIGH, NSW 2120 Tel 42 - 2 - 242 252 96 Tel 91 -22-5784481 Fax 91 - LIMA Tel 1 - 404 - 446 - 3000
Tel 61 -2-4845944 Fax 42 - 2 - 242 254 31 22 - 578 47 19 Tel 51 -14-760423, Fax 1 - 404 - 242 - 7493
Fax 61 - 2 - 875 38 94 - 76 04 26
INDONESIA VSL Corporation DALLAS, TX
FRANCE Fax 51 - 14 - 76 04 77
PT VSL Indonesia, Tel 1 - 214 - 647 - 0200
VSL Prestressing (Aust.) VSL France S.A.
JAKARTA Tel 62 - 21 - 570
Pty. Ltd. EGLY Fax 1 - 214 - 641 - 1192
07 86 Fax 62 - 21 - 573 12 PORTUGAL
VIRGINIA, OLD Tel 33-1 -69261400 17 VSL Prequipe SA, LISBOA
Tel 61 - 7 - 265 64 00 Fax 33 - 1 - 60 83 89 95 Tel 351 - 1 - 793 85 30 VSL Corporation DENVER,
Fax 61 - 7 - 265 75 34 ITALY Fax 351 - 1 - 793 09 01 CO
GERMANY VSL Italia S. r. I. Tel 1 - 303 - 239 - 6655
VSL Prestressing (Aust.) VSL Vorspanntechnik (D) MONTESE SINGAPORE Fax 1 - 303 - 239 - 6623
Pty. Ltd. GmbH Tel 39-59-981413 VSL Singapore Pte. Ltd.,
NOBLE PARK, VIC ELSTAL Fax 39 - 59 - 98 14 12 SINGAPORE VSL Corporation
Tel 61 -3-7950366 Tel 49 - 33234 - 8340 Tel 65 - 235 70 77/9 HONOLULU, HI
Fax 61 - 3 -795 05 47 Fax 49 - 33234 - 83416 JAPAN Fax 65 - 733 86 42 Tel 1 - 808 - 682 - 2811
VSL Japan Corporation, Fax 1 - 808 - 682 - 2814
AUSTRIA GREAT BRITAIN TOKYO SOUTH AFRICA
Sonderbau GesmbH, WIEN Balvac Whitley Moran Ltd. Tel 81 - 33 - 346 89 13 Fax Steeledale Systems (Pty.) VSL Corporation MIAMI, FL
81 - 33 - 345 91 53 Tel 1 - 305 - 592 - 5075
Tel 43 - 222 - 892 02 80 DERBYSHIRE DE55 4PY Ltd.
Fax 43 - 222 - 892 02 80 33 Tel 44 - 773 54 16 00 JOHANNESBURG Fax 1 - 305 - 592 - 5629
KOREA
Fax 44 - 773 54 17 00 VSL Korea Co., Ltd., Tel 27-11 -6137741/9
BOLIVIA Fax 27 - 11 - 613 74 04 VSL Corporation
SEOUL
Prestress VSL of GREECE Tel 82-2-5748200 MINNEAPOLIS, MN
Bolivia Jauregui Ltd., LA VSL Systems S.A., ATHENS Fax 82 - 2 - 577 00 98 SPAIN Tel 1 - 612 - 456 - 0985
PAZ Tel 30 - 1 - 363 84 53 VSL Iberica S.A., MADRID Fax 1 - 612 - 456 - 9281
Tel 591 - 2 - 321 874 Fax 30 - 1 - 360 95 43 MALAYSIA Tel 34 - 1 - 556 18 18
Fax 591 - 2 - 371 493 VSL Engineers (M) Sdn. Fax 34 - 1 - 597 27 01 VSL Corporation
GUAM Bhd. PHILADELPHIA, PA
BRAZIL VSL Prestressing (Guam), KUALA LUMPUR SWEDEN Tel 1 - 215 - 750 - 6609
Rudloff-VSL Industrial Ltda. TUMON Tel 60 - 3 - 242 47 11 Internordisk Spannarmering Fax 1 - 215 - 757 - 0381
SAO PAULO Tel 67-1-6468061 Fax 60 - 3 - 242 93 97 AB, DANDERYD
Tel 55 - 11 - 826 04 55 Fax 67 - 1 - 649 08 50 Tel 46-8-7530250 VSL Corporation
Fax 55 - 11 - 826 62 66 NETHERLANDS Fax 46 - 8 - 753 49 73 SAN JOSE, CA
Civielco B.V, AT LEIDEN Tel Tel 1 - 408 - 866 - 5000
HONG KONG
31 -71 -768900 Fax 1 - 408 - 374 - 4113
BRUNEI DARUSSALAM VSL Hong Kong Ltd. SWITZERLAND
Fax 31 - 71 - 72 08 86
VSL Systems (B) Sdn. Bhd. Quarry Bay, HONG KONG VSL (Switzerland) Ltd.
BANDAR SERI BEGAWAN Tel 852 - 590 22 88 LYSSACH VSL Corporation
NEW ZEALAND
Tel 673 - 2 - 22 91 53, Fax 852 - 590 02 90 Precision Precasting Tel 41 - 34 - 47 99 11 WASHINGTON, DC
-221827 (Wgtn.) Ltd., OTAKI Fax 41 - 34 - 45 43 22 Tel 1 - 703 - 451 - 4300
Fax 673 - 2 - 22 19 54 VSL Redland Concr. Prod. Tel 64 - 694 81 26 Fax 1 - 703 - 451 - 0862
Fax 64 - 694 83 44 THAILAND
CHILE Ltd. VSL (Thailand) Co., Ltd., VIETNAM
Sistemas Especiales de Quarry Bay, HONG KONG NORWAY BANGKOK VSL North East Asia
Construccion SA, VSL Norge A/S, Tel 66-2-237 32 88/89/90 HONG KONG
SANTIAGO Tel 852 - 590 03 28 STAVANGER Fax 66-2-238 24 48 Tel 852 - 590 22 22
Tel 56 - 2 - 233 10 57 Fax 852 - 562 94 28 Tel 47-4-563701 Fax 852 - 590 95 93
Fax 56 - 2 - 231 12 05 Fax 47-4-562721

You might also like