You are on page 1of 116

HOLLOW BLOCK MAKING MACHINE 2004

Ethiopian Institute of Technology-Mekelle

Department of Mechanical Engineering

Final year thesis project on

DESIGNE O HOLLOW BLOCK MAKING MACHINE

In fulfillment of the requirement of Bsc. in Mechanical Engineering

By

Dahlak Hika (FST/UR 0105/2000)

And

Zelealem Belay (FST/UR 181/1999)

Under the guidance of

ABRHA GEBREGEYORGIS (MTECH.)

JUNE 18/2012

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C


ACKNOWLEDGMENT

First of all Our deep gratitude goes to the almighty GOD for everything he did to us in all the
way we path through, then after for both my adviser Ato abrha and mechanical engineering
department staff members for their continues and progressive support, advice and guides us to do
better work and give us a reference materials and initiate us for our work and project. In addition,
we would like to thank also other local companies, which participate in this block production
sector and their employees for their respect, familiarity, their advice and support. In addition, we
would like to thank our classmates and friends for sharing their ideas and materials with us.
Finally, we would like to thank our families for understanding and helping us with all our needs.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 1


ABSTRACT

This report presents a systematic approach to enhance the current design of hollow block
machine. The design starts with data gathering from the literature review and infoBirration given
by the hollow blocks maker. Product specification is then being developed and refine to the
specific points. The weaknesses of the current design are being analyzed by looking at the
movement waste done by the machine operator and the machine limitation is being
identified. The hollow blocks are different from other noBirral blocks as it requires no
mortar or cement for masonry work. This blocks interlocked with each other by means of
positives and negative frogs on the top and bottom of the blocks which disallow the
horizontal movement of blocks. Selection of best design is chosen from the several design
concepts proposed. Finally, the drawing and detail design is produced according to standard and
ready to be built by the machine developer.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 2


TABLE OF CONTENTS
ACKNOWLEDGEMENT...... 1

ABSTRACT ....2

LIST OF TABLES ......................................................................................................................... 7

LIST OF FIGURE.......9

LIST OF ABBREVIATIONS .................................................................................................. 11

LIST OF SYMBOLS ............................................................................................................ 11

LIST OF APPENDICE ................................................................................................................. 12

PROBLEM STATEMENT....14

OBJECTIVE. 15

SCOPE...16

CHAPTER ONE INTRODUCTION ....................................................................................... 19

1.0 Introduction. .......................................................................................................................... 19

1.1 Hollow block specification....20

1.1.1 Producuction of hollow block process...20

1.2 Introduction of block product....21

1.2.1 Concrete block.......................................................................................................... 21

1.2.2 Background .............................................................................................................. 22

1.2.3. Market& demand aspect...23

1.2.4 Types of concrete block.23

1.2.5 Input material for cement block. ..25

1.2.6 Manufacturing process of blocks..26

1.3 Block making process....28

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 3


CHAPTER TWO

2. 1 LITERATURE REVIE

2.1.1 Background and justification of the H.B.P.M.......30

2.1.2 Hollow Concrete blocks......32


CHAPTER THREE
3 METHODOLOGY

3.1 Introduction....34

3.1.1 Concept development phase ..................................................................34

3.1.2 Establishing target specifications ..35

3.1.3 Concept generation ...35

3.1.4 Concept selection..35

3.1.5 Setting final specification .35

3.1.6 Concept development.37

3.1.7 Establishing target specifications ..38

3.1.8 Concept generation 43

3.1.9 prblem identification...43

3.2.0 Concept selection ..50

3.2.1 Discussion .53

CHAPTER FOUR

4.1 DESIGN ANALYSIS .......................................................................................................... 55

4.1.1 Motor selection.......56

4.1.2 Bearing selection...58

4.1.3 Design of Welded joints...62

4.1.4 Design of spring...64

4.1.5 Design of Bolt.. 70

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 4


4.1.6 Design of double acting cylinder71

4.1.7 Design of support frame............................................................ .75

4.1.8 Design of mould base..76

CHAPTER FIVE

5 RESULT AND DISCUSSION....... ........................................78

5.1 Product architecture.. 78

5.2 Components analysis .91

5.2.1 Top Structure.91

5.2.2 Table Structure....93

5.2.3 Compactor Structure ....95

5.2.2 Planar base Structure .97

5.3 Cost analysis 99

5.3.1 Guideline for Calculating Bricks selling Price .99

5.3.2 Machine component and Raw Material Cost...102

5.3.3 Material cost estimtion..104

5.3.4 Mnufacturing cost..106

5.3.5 Product design specification ....108

CHAPTER SIX

6. CONCLUSION

6.1 Introduction ..110

6.2 Conclusion.. .110

6.3 Future Development 111

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 5


RECMMENDATION.112

REFERENCES113

APPENDICES 116

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 6


LIST OF TABLES

TITLE PAGE

Table 1.1 Customer statement and interpretation24

Table 3.1 interview of hallow block producers37

Table 3.2 customer needs..42

Table 3.3 Matrix table ..42

Table 3.4 Needs-matrix table 43

Table 3.5 Concept 1 description44

Table 3.6 Concept 2 description47

Table 3.7 Concept 3 description 49

Table 3.8 Concept screening matrix .51

Table 4.1.1 life of bearing for various type of machine60

Table 4.1.2 values of service factor ..61

Table 4.1.3 stress for welded joint64

Table 4.1.4 stress concentration factor 64

Table 4.1.5 types of ends of spring .66

Table 4.1.6 stress in helical spring .66

Table 4.1.7 Material cost 104

Table 4.1.8 Screw and nuts cost 105

Table 4.1.9Mechanical system and equipment cost...107

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 7


Table 4.2. Manufacturing cost 107

Table 4.2.1 Final product design specification.109

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 8


LIST OF FIGURES

TITLE page

Figure A Flow chart represents the scope of work...18

Figure 1.1 manufacturing process of block...20

Figure 1.2 Type of Hollow Block..22

Figure 2.1 machine used for the production of H.B.32

Figure 2.2 filling in to the concrete block..33

Figure 2.3 cleaning the top and removing mould..33

Figure 2.4 method of designing hollow block ..36

Figure 3.1 Method of designing the hollow block making machine.36

Figure 3.2 Concept 1-Cantilever concept .44

Figure 3.3 Concept 2-Cantilever concept..46

Figure 3.4 Concept 3-Center cylinder concept..48

Figure 4.1.1types of bearing..59

Figure 4.1.2 ball bearing.61

Figure 4.1.3 welded lap joint .63

Figure 4.1.4 spring expression ..65

Figure 4.1.5 bolted joint..70

Figure 4.1.6 Hydraulic circuit diagram...71

Figure 4.1.7 valve representation ..74

Figure 4.1.8 mould base assembly 76

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 9


Figure 4.1.9 mould assembly design..79

Figure 4.2 Top structure displacement result 80

Figure 4.2.1 churcging system 81

Figure 4.2.2 inside control panel 82

Figure 4.2.3 top structure stress analysis91

Figure 4.2.3 top structure displacement result...92

Figure 4.2.3 table structure stress analysis93

Figure 4.2.3 Compactor structure displacement result...95

Figure 4.2.3 Compactor structure stress analysis.......96

Figure 4.2.4 Compactor structure displacement result96

Figure 4.2.5 Planar Base structure stress analysis...98

Figure 4.2.6 Planar base structure displacement result...98

Figure Cement charging/loading .

Figure Table assembly drawing

Figure Top structure assembly drawing

Figure Charging system assembly drawing

Figure Table structure assembly design

Figure Top structure assembly design

Figure Charging system assembly design

Figure Top structure stress analysis

Figure Table structure stress analysis

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 10


LIST OF ABBREVIATIONS

CAE - Computer Aided Engineering

CATIA - Computer Aided Three-Dimensional Interactive Application

D - Bore Diameter

DfX - Design for Assembly, Manufacturing, and Environment

EDM - Electrical Discharge Machine

Kg - Kilogram

KN - Kilo Newton

PDS - Product Design Specification

LIST OF SYMBOLS

- pi (3.1415)

P - Pressure

C - Degree Celsius

F - Degree Fahrenheit

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 11


LIST OF APPENDICES

TITLE page

A-1 Machine assembly drawing 116

A-2 Mold assembly drawing 117

A-3 Table assembly drawing 118

A-4 Top structure assembly drawing 119

A-5 Charging system assembly drawing 120

A-6 Block pusher drawing 121

A-7 Charger drawing 122

A-8 Compactor drawing 123

A-9 Container drawing 124

A-10 Cover drawing 125

A-11 Hinge drawing 126

A-12 Middle bar drawing 127

A-13 Mold drawing 128

A-14 Movable base drawing 129

A-15 Planar base drawing 126

A-16 Horizontal plate structure drawing 130

A-17 Pusher base drawing 131

A-18 Pusher shaft drawing 132

A-19 Rod drawing 133

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 12


A-20 Slider base drawing 134

A-21 Slider compactor drawing 135

A-22 Slider pusher drawing 136

A-23 Structure table 1 drawing 137

A-25 Structure base drawing 138

A-24 Structure table 2 drawing 139

A-26 Table structure drawing 140

A-27 Top mold drawing 141

A-28 Top structure 1 drawing 142

A-29 Top structure 2 drawing 143

B-1 Hydraulic cylinder 144

B-4 Vibration motor 145

C-1 Socket hex cap screw 146

C-2 Bolt, washer and nut 147

C-3 Bearing bush 148

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 13


PROBLEM STATEMENT
Today in our country the problems of homeless have been increasing gradually and it appear to
be continue the main reason for the cause will be higher cost of construction raw materials,
poverty, low income and lack of new technology

Since the government of Ethiopia focus to build thousands of low cost house throughout the
country, to meet the millennium development goals and achieve significant reduction in poverty
the introduction of compacted block making machine must be essential.

Nowadays providing house to our community at an affordable price is a major task being carried
out by our government and real state organizations. Hollow blocks and burnt blocks are a
colossal input for the construction of those low cost houses, but the currently in use hollow block
and burned block construction materials in our country are expensive and take long time to
manufacture and construct, which makes the selling price of those hoses expensive and take long
time to manufacture and construct, which makes the selling price of those hoses expensive and
take long time to manufacture and construct, which makes the selling price of those hoses
expensive and unaffordable for the medium income society. In addition to this those construction
materials has the following drawbacks:

high moisture penetration

low theBirral efficiency

difficulties for electric & plumbing jobs insects

cost inefficiency bad finishes

it is difficult to produce on site


higher cost & time consuming
water absorption
higher unit weight
low control over quality

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 14


OBJECTIVE OF THE PROJECT

General objective

The main objective of this project is to design a new blocks making machine with new features
and simplifying the machine for one man operation in order to reduce operational cost
and maximize the production rate. FurtheBirrore, the purpose of this is to design the
hollowblocks making machine that suitable for SME entrepreneurs.

Specific objective

To bring building construction of low cost houses effective, easier and faster using the
CBMM

To achieve superior finishes and compatible for almost all types of construction.

To have on site production to reduce transportation cost and to minimize ecological


imbalance caused due to burnt blocks.

General it aims high strength and technical superiority over conventional methods.

To achieve lighter than conventional masonry and hollow blocks save no mortar &
plaster cost.

Problem Identification
Current machine design unable to increase productivity, this is mainly due to;
i. Time wasting by doing the cement charging, loading and leveling, (Time required 50
seconds).
ii. Manually obtaining the lower mold plate as operator needs the device to turn the block
(Time required 45 seconds).
iii. The load applied several time on the hollow block (Time required: 15 seconds)
iv. Operator need to manually pick-up the block one by one after compaction process
before start the new process cycle (Time required: 20 seconds).
v. The mold lower plates are manually inserted one by one (Time required 45 seconds).

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 15


Expected results and Scope
From the above interview, we conclude that customers needs are
High production rate,
Minimum 3 blocks per cycle,
One-man operation,
Simple operation,
Comes with auto arrange block system,
Comes with cement charging system,
Comes with cooling system,
Fool proof operation,
Automated function,
UnifoBirr pressure distribution,
Can be easily maintainable.
Safe to handle,
Low cost machine,
Marketable machine,
Comes with alert system

And also The high aesthetic value, faster, theBirrally efficient, structurally durable, eco-friendly,
and low cost block will be identified for the production of low cost house in the country.
The analysis of this project is limited to the manufacturing of compacted block making machine
for producing blocks with dimensions (21*10*15cm) by applying 4.5 Mpa of compressing
pressure between the compressing mould of the machine at low cost.

N:B the compressive strength of both hollow blocks and hollow clay burned blocks range from
2Mpa up to 7Mpa it is acceptable in the Ethiopian standards for load bearing walls
.(ESC.D4.026),(ESC D3 301).

With system pressure of compacting 9-10 Mpa, cement content of 5-8% clay silt content of
10&50% a typical block can be made with a compression strength ranging from 4-7 Mpa this
compression strength for load bearing walls in the Ethiopian standard will be acceptable.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 16


With over all dimension of the machine (120*150*147cm) and

Motor driven two hydraulic units with 7.5 Mpa.

Capacity 1500 blocks/12 hours

Power 4 kw

Net weight 300 kg

The main task to be done on the design of hollow block making machine

Is to design machine that can produce

1. Three block wit


L=400mm, W=200mm, t=20mm
2. Four block with
L=400mm, W=150mm, t=20mm
3. Five block with
L=400mm, W=100mm, t=20mm

1.2 Scope of project

The scope of project is clearly define the specific field of the research and ensure that the entire
content of this thesis is confined the scope. This project is start with the literature review
on product specification in order to satisfy the project objectives. After obtaining the product
specification, this project is done base on the scope Project will focus on hollow block making
machine Designing the inter-locking block making machine that fulfill the project objective.
Machine design to suit the regular hollow blocks (Figure 1.1).

The project goes until detail design of hollow block making machine. The major output of this
project is to produce the detail drawing for the machine design. Fabrication of machine is
excluded in this project.

The scope of work can be described in teBirrs of flowchart as per the following.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 17


Literature Review on Hollow Blocks
MakingMachine Specification
Machine

Machine Specification

Conceptual Design

Selection of Best Concept

Detail Design for Selected Concept Design

Materials Selection

Component
Detail Drawing analysis (Software)

Detail Drawing

Assembly design(CATIA)

Figure A: Flow chart represents the scope of work

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 18


CHAPTER ONE

INTRODUCTION

1.0 Introduction

No construction is possible without blocks. Since many centuries block making has been
practiced by human beings. Presently, blocks are easily made by using machines using
new technologies. Generally two types of blocks are manufactured by using machines that
are concrete block machines and clay block machines. Different types of automatic
machines use different techniques to make blocks. The raw materials used by the machines for
making hollow blocks are fly ash, sand lime, iron oxide, lime sludge, quarry wastes etc.

The focus of this project is on the production of concrete blocks, specifically hollow blocks
which offer a speedier, cost effective, environmentally sound alternative to conventional
walling materials. It is based on the principle of densification of a lean concrete mix to
make a regular shape, unifoBirr, high perfoBirrance masonry unit. Concrete Block
Technology can be easily adapted to suit special needs of users by modifying some design
parameters such as mix proportion, water to cement ratio and type of production system. It is
an effective means of utilizing wastes generated by stone crushers, quarrying and stone
processing units. The technology has high potential in areas where raw materials are
easily available. The new technique in producing this interlock block can generate a highly
profitable business for micro and small scale building material producers and construction
companies. The market for this type of block in Malaysia is not yet growing at a rapid
rate, even though there are demands in construction industries due to low production rate
which reflect the cost of block itself.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 19


1.1 Hollow Block Specification

The hollow blocks are different from other noBirral blocks as it requires no mortar or
cement for masonry work. This blocks interlocked with each other by means of positives and
negative frogs on the top and bottom of the blocks which disallow the horizontal
movement of blocks. There are various application of this blocks namely; load bearing wall,
lintels, sills, wall corners etc. The specifications and the characteristics of this block depend on
the machine used to manufacture it. The most common size of block is 300x150x120mm. The
basic raw material is cement, fine aggregate and coarse aggregate. Very little water is used.
This is possible only with mechanized compaction and vibration and gives the block high
quality in spite of the lean mix, which uses very little cement. Weight of this block is about 2 - 3
Kg.

1.1.1 Production of Hollow Block Process

Current process of producing the hollow block is produced using a semi-mechanized


stationary type machine. The other production systems are - manual moulds that require hand
tamping, a mobile semi-mechanized egg-laying machine and fully mechanized system that
combines compression and manual concrete filling in mould. The machine also compacts
and consolidates the mix so that the blocks are unifoBirr in size and attain desired physical
properties. The blocks are cured for a minimum period of 14 days, before they are ready to use.
On an average 600-800 blocks can be in 8 hours by 1 skilled and 6-8 semi-skilled workers. In
this project, a high quality machines in which optimize from the current machine design
is going to propose according to the feedback and the need from the hollow block maker.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 20


1.2 Introduction of The block product

1.2.1 Concrete blocks


Concrete blocks are a basic commodity of the building industry. If you are looking for a great
business with a solid foundation this may be the one for you. Concrete products are used
everywhere for building. There is a constant strong demand. They are always in style unlike here
today gone tomorrow products. They are used to build large buildings. There is a market for
cement blocks around the world and particularly in North America. If you are looking for a good
business, which you can start from home at low cost, making concrete blocks and other concrete
products is a great opportunity. Starting with a part time business, using handmade molds, you
can get going with as little as a few hundred dollars for supplies and materials. You can operate
out of your garage then as business grows and you need more room you can expand to rented
premises. The secret is to keep your costs as low as possible to start with. Too many businesses
fail in the first year because they spend too much money unnecessarily on tents and equipment.
Start with the necessities and add more as you grow in profitability.

Concrete products of all kinds are obviously heavy and bulky. To transport them for long
distances is costly. As a local manufacturer you can supply these products t customers in your
area for a lot less than a distant manufacturer can. Your overhead cost. no rent, no staff wages
mean low production cost, again these allows you to price very competitively and still make an
excellent profit.

The only things needed to start up are sheet metal and plywood to make the molds. You can
obtain plans with instructions on how to do this. To manufacture concrete blocks you will need
port land cement, gravel, sand and water. Your local building supply store or lumberyard can
supply these items. With handmade molds one person can make 100 cement blocks in a days
work. You simply fill the molds with the appropriate concrete mix then turn the blocks out to
dry. This is pretty simple. Then as your business expands you will want to acquire a concrete
block making machine which can turn out many more blocks per day than you can with hand
molds.

You can buy concrete block making machines from various sources. They are very expensive
and do a very good job. If you can afford it go ahead and buy one. It will greatly increase your

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 21


productivity and will pay for itself. You can do it for much less however. You can build your
own machine used auto parts and a few available and it is not a difficult project. If you have
welding skills you can do these part of the work yourself, otherwise a local welding shop can do
it for you at fairly low cost.

Making your own machine is not really difficult if you have some mechanical skills. Your home
built machine will make 800 cement blocks per day. A smaller, very simple hand operated
machine can make 200 blocks per day and is quite easy to build. Operating these machines
efficiently is a two person job. One worker runs the machine and the other takes the blocks from
it and stacks them on racks to dry. Obviously you will also need sufficient space to stack
hundreds of blocks.

1.2.2 Background
today in our country the problems of homeless have been increasing gradually and it appear to be
continue the main reason for the cause will be higher cost of construction raw materials,
poverty, low income and lack of new technology

Since the government of Ethiopia focus to build thousands of low cost house throughout the
country, to meet the millennium development goals and achieve significant reduction in poverty
the introduction of compacted block making machine must be essential.

The production of compacted block making machine established in 1988 in south Africa with
joint free India expertise .the CBMM building system replaces conventional blocks and mortar
through the use of compacted blocks, which are hollow and can be dry stacked. The other
components of the conventional building system remain unchanged. These blocks can be made
on construction site or at block yard using hollow block making machines. Today the CBMM
building system and the machines are used in over 50 countries worldwide. This block-block can
be made with lo al soil and cement or fly ash (brunt coal ash) and cement.

These eco-friendly blocks are made with combinations of soil-cement, sand cement which are
durable, but cost effective because they are made using local soil and require low cement content
(about 5%) and fly ash.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 22


Cement concrete hollow blocks have an important place in modern building industry. They are
cost effective and better alternative to burnt clay blocks by virtue of their good durability, fire
resistance, partial resistance to sound, theBirral insulation, small dead load and high speed of
construction. Concrete hollow blocks being usually larger in size than the noBirral clay building
blocks and less mortar is required, faster of construction is achieved. Also building construction
with cement concrete hollow blocks provides facility for concealing electrical conduit, water and
sewer pipes wherever so desired and requires less plastering.

1.2.3 Market & demand aspects


Cement concrete hollow blocks are modern construction materials and as such are used in all the
constructions viz. residential, commercial and industrial building constructions. Construction
industry is a growing a sector. The demand for this product is always high in all cities and other
urban centers due to construction of residential apartments, commercial buildings and industrial
buildings. Growing public awareness of the advantages of the product coupled with increase in
the government and financial institutions support for housing which is a basic human necessity
would ensure a healthy growth in the demand.

1.2.4 Types of concrete block

1) According to production
Hollow concrete block
Solid concrete block
2) According to its size
100mm
150mm
200mm

Advantage or benefits of concrete block

UnifoBirr shape and size


High compressive strength
Fire resistant

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 23


Economical
Negligible maintenance cost
Speed in construction
Due to negligible thickness it will save cement.
Energy Efficient
Sound Resistant
Strong
Durable
Will not Warp, Twist or Rot

Benefits of hollow block V/S blocks

Hollow blocks Blocks


1. The size and shape of hollow blocks are There is a variation in size and shape i.e. one
unifoBirr and there is no variation. We side of the wall is in line. Plastering on both
can avoid plastering to have even look. sides is essential. Excessive plaster is done on
one side to have even look.
2. Less number of hollow blocks are More number of blocks are used. i.e.(1100 for
required for the given area e.g. (130 100sq.ft wall)
blocks for 100sq.ft walls).
3. Work is speedy in about 30% more. Work is slower so it needs expensive labor cost
4. Less number of joints are found. More number of joints
5. If it is room temperature is less due to Inside a room temperature is high
cavity in blocks.
6. The structure is purely concrete. The structure is purely mud
7. 7% extra floor space available without No extra space is available
compromising on strength of wall.
8. Fixing of fencing angle is easy. Wall has to be cut for fixing angle of fencing.
Table 1.1 Benefits of hollow block V/S block

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 24


1.2.5 Input materials for a cement block or block
Aggregate

Aggregate is the stone, sand and ash you want to vibrate and compact down and bind together
with the cement. A good aggregate is an aggregate that is free from chemicals, clay and organic
material. A good aggregate will bond well with the cement paste and not react with it.
As a rule of thumb the denser youre finished block or block the stronger the block or block will
be. You must choose your aggregates according to your needs. To achieve a dense block with an
aggregate that can be vibrated and compacted down easily you need to have an aggregate with
evenly graded particles ranging from fine dust up to larger stone of around 9mm.Blending
different aggregates often produces the best results

Cement

Cement is your most costly material and by doing trials with different aggregates you will be
able to minimize on cement content and so decrease your costs. Cement should always be stored
in dry place, off the floor and should be use within three months of the date of manufacture.
Never use cement that has lumps in it and only use cement from a well known brand that has an
SABS mark of approval on it.

Water
Only clean clear potable water should be used in the manufacture of the blocks and blocks. Any
organic material in water will prevent the cement from setting. Chemicals and impurities could
also affect the strength of the end product. Never use salty or break water. It is advisable to get
your water tested for impurities.

1. Cement
2. Sand
3. Water
4. Fly ash
5. Grit (Gravel)

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 25


1.2.6 Manufacturing process of blocks
The process of manufacture of cement concrete hollow blocks involves the following 5 stages;
(1) Proportioning
(2) Mixing
(3) Compacting
(4) Curing
(5) Drying
And on the machine, we divided manufacturing process

Feeding process leveling process

Ready for pressing pressing process

Fig 1.2 manufacturing process of block

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 26


(1) Proportioning:

The deteBirrination of suitable amounts of raw materials needed to produce concrete of desired
quality under given conditions of mixing, placing and curing is known as proportioning.

(2) Mixing

The objective of thorough mixing of aggregates, cement and water is to ensure that the cement-
water paste completely covers the surface of the aggregates. All the raw materials including
water are collected in a concrete mixer, which is rotated for about 1 minutes. The prepared
mix is discharged from the mixer and consumed within 30 minutes.

(3) Compacting

The purpose of compacting is to fill all air pockets with concrete as a whole without movement
of free water through the concrete. Excessive compaction would result in foBirration of water
pockets or layers with higher water content and poor quality of the product. Semi-automatic
vibrating table type machines are widely used for making cement concrete hollow blocks. The
machine consists of an automatic vibrating unit, a lever operated up and down metallic mould
box and a stripper head contained in a frame work.

(4) Curing

Hollow blocks removed from the mould are protected until they are sufficiently hardened to
peBirrit handling without damage. This may take about 24 hours in a shelter away from sun and
winds. The greatest strength benefits occur during the first three days and valuable effects are
secured up to 10 or 14 days. The longer the curing time peBirritted the better the product.

(5) Drying

Concrete shrinks slightly with loss of moisture. It is therefore essential that after curing is over,
the blocks should be allowed to dry out gradually in shade so that the initial drying shrinkage of
the blocks is completed before they are used in the construction work. Hollow blocks are stacked
with their cavities horizontal to facilitate thorough passage of air.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 27


1.3 Block Making process

Batch mixing

For high quality blocks and blocks a pan mixer should be used. For low quality blocks and
blocks hand mixing on the ground can be used. Always run a series of trials with different mix
proportions. By evaluating your results you can adapt your mix to be more cost effective. Start
you trial mixes with 1 part cement to 6 parts aggregate. This translates to one bag of cement to 3
level wheelbarrows of aggregate. Test your block or block strengths at 28 days.

Mixing process

Pan mixer

Place half of your aggregate into the pan mixer then add the cement followed by the remaining
aggregate. Allow the cement and aggregate to mix dry until a consistent even color is produced.
Then start adding in water until the correct moisture content is reached. By hand spread youre
aggregate out over a concrete surface. Then add your cement by spreading it over your aggregate
evenly. Shovel your aggregate up into a pile. Spread the pile out again and build it up into a
second pile. Spread the second pile out again and add water by sprinkling it evenly over the
spread out aggregate. Mix water into aggregate and
Then pile the mixture up for a third time. This method usually adequately mixes your batch.
Hand mixing is labor intensive and time consuming. It also tends to be more wasteful.

Water content

The moisture content within you mix is crucial. It is important for the following reasons:-
The correct water content allows for good dense compaction by lubricating the aggregate. Too
much water will lubricate the aggregate to such an extent that the block/block will fall apart or
sag
When removed from the mould.
With the correct water content the block/block will release easily from the mould. No suction
between the mould and block will be created.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 28


A very slight water rippling effect can be seen on the sides of the green blocks/blocks when the
correct moisture content is reached. Do not allow your mixed batch to stand for more than half
an hour. This will prevent strength loss in your cement and the lubricating water will not
Dry off. Your mix and aggregate may need to be adjusted to get a quality looking block.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 29


CHAPTER TWO
2.1 LITERATURE REVIEW

2.1.1 Background and justification of hollow block producing machine

An artificial foBirr called Portland cement was innovated during the industrial revolution in
England, but the national foBirrula continued to be marketable until 1890s. UN improved
version of Portland cement was produced in Great Britain though 19th century and held share of
import to the United States until 1871. The Construction of the first American company in
Pennsylvania, The American cement industry had organize into professional group by 1900, one
of which was Portland cement association. The obvious function of this group was to advance
the use of Portland cement, which was accomplished though workshop, advertising, catalogs and
pattern books. Concrete block was highly recommended by the association in 1905.

Early production of concrete block in the 19th century was achieved by filling cast iron or
wooden box molds called side-face machines with a dry mix of concrete mixed with the
minimum amount of water for hardening. the concrete was added in layers and hand-tamped.
The block was removed via the hinged sides of the mold box and laid out to dry for seven to ten
days in an upright position.

Mass production of concrete block buildings did not develop until HaBirron palmer patented a
cast-iron hollow block machine in 1900.with this invention, it was claimed that two men could
produce between eighty to one hundred blocks in a machines that rotated up 90 degrees for
release of the block. hollow blocks were considered superior as they were lighter, insulated better
and were more moisture-resistant. once the popularity of the concrete block as a building
material was established, competing companies began marketing their own machines. all
followed palmers pattern of metal frame and mold box with hand release lever for opening the
sides and removing the finished product. in the year sprier to standardization of the concrete
industry the size of some early block was 24 or 32 long. Blocks where also thicker, sometimes
weighing as much as 180 pounds. With the organization of manufacturing associations the
however,1/2 or size block attachments were accessible, as well as gable, bay window, circular
and corner block attachments.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 30


The foBirrula for the blocks was composed of Portland cement, water, sand and stone or gravel
aggregate. it was advocated that the stones for the aggregate be no larger than inch and that the
concrete should be wet but not over-moist, which would cause the block to adhere to the metal to
sag upon removal from the mold. the most common specifications called for one part cement to
two or three parts sand to four or six parts aggregate. when embossing a design on the face of the
block, a fine mix using highly ground sand or aggregate would be placed on the design plate and
then topped with a coarse mix for strength. the face design came in variety of patterns ,some
providing a delicate refined look such as egg and dart, rope face, wreath face and scroll face.
these designs were more commonly used as trim in water tables, belt courses, copings, cornices
and sills. other designs were imitative of cut stone like rock face and panel face which were most
often utilized for contraction of entire house.

The production of compacted block making machine established in 1988 in south Africa with
joint free India expertise .the CBMM building system replaces conventional blocks and mortar
through the use of compacted blocks, which are hollow and can be dry stacked. The other
components of the conventional building system remain unchanged. These blocks can be made
on construction site or at block yard using hollow block making machines. Today the CBMM
building system and the machines are used in over 50 countries worldwide. This block-block can
be made with lo al soil and cement or fly ash (brunt coal ash) and cement.

These eco-friendly blocks are made with combinations of soil-cement, sand cement which are
durable, but cost effective because they are made using local soil and require low cement content
(about 5%) and fly ash.

Cement concrete hollow blocks have an important place in modern building industry. They are
cost effective and better alternative to burnt clay blocks by virtue of their good durability, fire
resistance, partial resistance to sound, theBirral insulation, small dead load and high speed of
construction. Concrete hollow blocks being usually larger in size than the noBirral clay building
blocks and less mortar is required, faster of construction is achieved. Also building construction
with cement concrete hollow blocks provides facility for concealing electrical conduit, water and
sewer pipes wherever so desired and requires less plastering.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 31


2.1.2 Hollow concrete block (H.C.B) production
The machines used to produce HCBs are electrical vibrating machines which have 1.5 HP
motor to make sure, that the vibration is strong enough to compact the concrete sufficiently in
the moulds and to achieve the required strength. Before starting production the different
materials used to produce the HCB will be dry-mixed thoroughly on a clean and dry ground by
hand. Then the mixture will be put in the mixer with the appropriate am-mount of water required
(water to cement ratio of 0.49 0.55). The mixture is insert -ed into the mould and vibrated for
about 60 seconds before extruded as HCBs. Except for the slab-HCB, the machines can produce
three pieces at a time. The HCB is a transported by two people on a wooden pallet. The HCB
remains on the wooden pallet for 24 hrs. Then it is be cured covered by a plastic sheet to
enhance the curing process and preventing the water from evaporation. Curing-time is at least 10
days before using the HCBs for construction. It is important to write the date of production on
the HCB so that the mason can easily identify the HCBs, ready for construction. The materials
required for the production of HCBs and their mixing ratio differs from site to site depending on
the availability of the building materials and the ratio that fulfils the required strength. This holds
true for all types of HCBs production. The average overall production is 1200 HCBs per day
per machine.

Fig 2.1 The machine used for the production of HCBs

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 32


Concrete block technology offers a speedier, cost effective, environmentally sound alternative to
conventional walling materials. Concrete block technology can be easily adapted to suit special
needs of users by modifying design parameters such as mix proportion, water to cement ratio and
types of production system. The technology has high potential in areas where raw materials are
easily available

Fig 2.2 Filling in concrete while the machine Concrete is filled up during compacting until the
molde isfilled is already vibrating

Fig 2.3. Clearing the top Removing the mould upwards

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 33


CHAPTER THREE

METHODOLOGY

3.1 Introduction

This chapter consists of methods for completing product development activities.The applied
methods, which are well-structured, provide a step-by-step approach to complete the task
of this project. Based on these methodologies, there are three advantages expected.
Firstly, the decision processes is completely made, reducing the possibility of moving
forward with unsupported decisions. Secondly, by acting as

check list of the key steps in a development activity and ensure that the important issues are
not forgotten. Third, these structured methods are largely self-documenting; in the process of
executing the method, the record of the decision-making process can be used for future
reference.

Figure 3.1 show the flow chart for completing this project.

3.1.1 Concept Development Phase

Development process demands the coordination among functions of the integrative


development methods, which is called as the front-end process. The front end process
generally contains many interrelated activities such as;

3.1.1 Identifying customer needs

The goal of this activity is to understand customers needs (users need) and To effectively
communicate them for the optimization job of current machine used. The output of this step is
a set of carefully constructed customer need statement, organized in a hierarchical list, with
importance weightings for many or all of the needs. The data are obtained mainly by
interviewing the user of hollow block making machine and also from the observation of the
current machine design. The identification of the current machine design weaknesses is really
helpful in providing the target specification.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 34


3.1.2 Establishing target specifications

Specifications provide a precise description of what a product has to do. is the translation of the
customer needs into technical teBirrs. Targets for the specifications are set early in the process
and represent the guide for generating the idea of machine modification. Later these
specifications are refined to be consistent with the product concept. The output of this stage
is a list of target specifications.

3.1.3 Concept generation

The goal of concept generation is to thoroughly explore the space of the product concepts that
may address the customer needs. Concept generation includes a mix of external search,
creative problem solving, and systematic exploration of the various solution fragments. The
result of this activity is three generative concepts, each typically represented by a sketch and
brief descriptive text.

3.1.4 Concept selection

Concept selection is the activity in which the generated concepts are analyzed and
sequentially eliminated to identify the most promising concept(s). The process is using the
weight age value and a given marks. The highest score can be considered as a chosen concept.
Several iterations may initiate additional concept generation and refinement, After
evaluating three generated concepts in previous.

3.1.5 Setting final specification

The target specifications set earlier in the process are revisited after a concept has been selected
and tested. At this point, the specific values of the metrics reflecting the constraints
inherent in the product concept, limitations identified through technical modeling, and
trade-offs between cost and perfoBirrance.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 35


Figure 3.1 Method of designing the hollow block making machine

Start

Identifying customer
needs

Establishing target
specifications

Concept generation

Concept selection
Detail
Design

Setting final specification


Material
selection

Product Architecture
Process

Hydraulic
Detail schmatic
Finish Drawing diagram

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 36


3.1.6 Concept development

This subtopic shows the preliminary result obtained for completing product development
activities.

Table 3.1 shows the finding data from the interviewing of hollow block producers

Question/ Customer Statement Interpretation


Prompt
Director -Increase production rate from 700 -Increase productivity
block per day to 5000 block per day
-Reduce manpower -One man operation
-Short ROI time period -Low machine cost
Engineer -It all automatic, only by single touch! -Simple operation.
-No waiting time. -Non-stop machining cycle
-Minimum 4 mould cavities per -Minimum 4 mold cavity
compaction -High compaction rigidity
-UnifoBirr pressure distribution, Cooling -Machine with
system, No messy maintenance. complete system
-Easy maintenance
Labor -I dont like to press the compactor -Fool proof operation
several times just to make sure the block -Automated operation
meet it dimension.
-The block is push to the conveyor and
have to turn to obtain the below mould
plate manually
Suggested -Nice rigid machine and marketable. -Marketable machine
Improvement -An alert system and a safety feature. -Effective alert system.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 37


3.1.7 Establishing target specifications

Product specifications represent an unambiguous agreement in order to satisfy the


customer needs. The teBirr product specifications are meant to describe the precise
description of what the product has to do. Where the most importance is no 5 and less
importance is no 1. After identifying the customer needs, target specifications are being set.
Customer needs are generally expressed in the language of customer. The primary
customer needs for machine improvement are listed in Table 3 as follows.

No Need Importance
1 High production rate 5
2 Minimum 4 blocks per cycle 5
3 One man operation 5
4 Simple operation. 5
5 Comes with auto arrange block system 5
6 Comes with cement charging system 5
7 Comes with cooling system 2
8 Fool proof operation 4
9 Automated function 3
10 UnifoBirr pressure distribution 2
11 Can be easily access for maintenance 2
12 Safe to handle 2
13 Low cost machine 1
14 Marketable machine 1
15 Comes with alert system 1

Table 3.2 Customer needs

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 38


a) High production rate

The machine must be able to increase the productivity of the block output. The main
reason is it can supply the highly demand of hollow block in the construction industries. This
need is very important so that it is highly rated (5) as it is the factor of the need of optimization
the current machine design.

b)Minimum 4 blocks per cycle

The machine must have minimum four (4) mold cavities as it can produce four hollow
blocks in one time. This is one of the factors that can increase productivity. More mold cavities
can rapidly increased the production rate.

c) One man operation

The machine operation must be handled by a single worker only (one man operation).

d) Simple operation process

A simple on/off button only and no complicated process in producing the hollow blocks operates
machine.

e) Complete with automatic arrangement

block system Compare with the current machine system, for producing the hollow block
there is no proper process for arrangement of block after it being produced. The main
objective of this system is to arrange the blocks on the pallet automatically.

f) Complete with concrete charging system

The raw material/concrete is automatically loaded to the mold cavities before the compression
process begins. The process of charging is repeated automatically after compaction process
cycle take place.

g) Equipped with cooling system

The cooling system or cooling unit functions to cool down the hydraulic system as heat is highly
generated by the non-stop compaction process.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 39


h) Infallible operation

The compression process compact the true value of pressure once. No need for compress
repetitio

i) Automated function

Machine can run automatically for the process of cement charging/ loading to the mold,
compression, and arrangement of block after compression.

j) Easy accessed for maintenance

Machine can be easily maintained and easily accessed for maintenance area.

k) Complete with alaBirr system

AlaBirr system sense the need of cement loading/charging and also detecting the movement of
operators body part inside the compaction area for safety precaution.

l) Safe to handle

Standard operation procedure is one of the factors that make the machine handling is safe.

m) Low cost machine

The cost to build this machine must be reasonable and within the capability of SME
entrepreneurs so that the return of investment time can be shortened.

n) Marketable machine

Machine appearance and perfoBirrance must be competitive and at affordable price so that
it benefit the SME entrepreneur. The most useful metrics are those that reflect as directly as
possible the degree to which the product satisfies the customer needs. The relationship
between needs and metrics is central to the entire concept of specifications.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 40


The working assumptions is that a translation from customer needs to a set of precise,
measurable specifications is possible and that meeting specifications will therefore lead to
satisfaction of the associated customer needs as shown in table 3.3.

Metric Need Nos. Metric Imp. Units


No.
1 1,2,4,5,6,9,11,15 Production rate 5 Cycle/Hour
2 3 Labor 5 Manpower
3 7 Cooling rate 2 kW

4 8,10 Compression pressure 5 pa


5 11 Maintenance 1 Subj.
6 12,15 Safe Standard 3 Subj.
7 13,14 Unit price(machine) 2 Subj.
8 14 Aesthetic 1 Subj.

Table 3.3 The relative importance of each metric and the units for the metric are also
shown Subj is an abbreviation indicating that a metric is subjective.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 41


Table 3.4 Needs-matrix table

Production rate

Safe standard
Maintenance
Cooling rate

Compression
No Metric

(machine)
Unit price

Aesthetic
Pressure
Labor
1 High production rate

2 Minimum 4 blocks per cycle


3 One man operation

4 Simple operation.

5 Comes with auto arrange block system

6 Comes with cement charging system

7 Comes with cooling system


8 Fool proof operation
9 Automated function
10 UnifoBirr pressure distribution
11 Can be easily access for maintenance

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 42


3.1.8 Concept generation

After identifying a set of customer needs and establishing the target product
specifications, the concept of modified hollowblock making machine can be generated by
identifying the main problem that preventing customer to get their needs and requirement.

3.1.9 Problem Identification

Current machine design unable to increase productivity, this is mainly due to;

i. Time wasting by doing the cement charging/loading and leveling the


cement.

(Time required: 50 seconds). See figure 3.2 & 3.3.

ii. Manually obtaining the lower mold plate as operator needs the device to turn
the block (Time required: 45 seconds). See figure 3.4& 3.5.

iii. The load applied several time on the hollow block

(Time required: 15 seconds). See figure 3.6 &3.7.

iv. Operator need to manually pick-up the block one by one after
compaction process before start the new process cycle (Time required: 20
seconds). See figure 3.8.

v. The mold lower plates are manually inserted one by one (Time
required: 45 seconds). See figure 3.9.

After identifying the weaknesses of the current design, literature review (chapter 2) is uses to
get the basic idea of the existing solution concepts. The propose concepts are then
generated according to the problem solution and establishment of customer needs and
specification. So the challenge is to design a hollow block making machine that fulfilling
the target product specification. The knowledge in mechanical and hydraulic systems is
crucially needed for generating the design concept.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 43


a) Concept one

Cantilever concept refer to figure 3.10 and 3.11

Figure 3.2 Concept 1-Cantilever concept (3D view)

Figure 3.11
Concept 1-Cantilever concept (Drawing view)

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 44


Table 3.5 Concept 1 description

No Requirement Description
1 Production rate Automatic charging/loading and block ejecting system
Reducing the waste identified previously.
Productivity increase as production time being reduced.
2 Labor One man operation with the simple control panel
3 Cooling rate The cooling system is inside the panel box
4 Compression Vertical compression hydraulic system
pressure The location of cylinder is beside of machine itself.
5 Maintenance Maintenance is easy due to all critical item are in the
machine control box
6 Safe Standard Machine operation is able to follow the safety standard;
as this machine concept is compact and all moving part
are inside the machine working area.
7 Unit price n.i.l.
(machine)
8 Aesthetic The machine is compact and suitable for small working area.
Machine is nice and compact.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 45


b) Concept two

Center cylinder concept refer to figure 3.12 and 3.13

Figure 3.3 Concept 2-Center cylinder concept (3D view)

Concept 2-Center cylinder concept (Drawing view)

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 46


Table 3.6 Concept 2 description

No Requirement Description
1 Production rate Automatic charging/loading and block ejecting system
Reducing the waste identified previously.
Productivity increase as production time being reduced.
2 Labor One man operation with the simple control panel
3 Cooling rate The cooling system is inside the panel box
4 Compression Vertical compression hydraulic system
pressure The location of cylinder at the center of machine itself.
5 Maintenance Maintenance is easy due to all critical item are in the
machine control box
6 Safe Standard Machine operation is able to follow the safety standard;
as this machine concept is compact and all moving part
are inside the machine working area.
7 Unit price n.i.l.
(machine)
8 Aesthetic The machine is compact and suitable for small working area.
Machine is nice and compact.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 47


c) Concept three

Horizontal compaction concept refer to figure 3.14 and 3.15

Concept 3-Horizontal compaction concept (3D view)

Figure 3.4 Concept 3-Horizontal compaction concept (Drawing view)

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 48


Table 3.7 Concept three description

No Requirement Description
1 Production rate Automatic charging/loading and block ejecting system (the
blocks are drop as the compaction cylinder retract and conveyor
will transfer the blocks) Reducing the waste identified
previously. Productivity increase as production time being
reduced.
2 Labor One man operation with the simple control panel
3 Cooling rate The cooling system is inside the panel box
4 Compression Horizontal compression hydraulic system
pressure The location of cylinder is below the charging container.
5 Maintenance Maintenance is easy due to all critical item are in the
machine control box
6 Safe Standard Machine operation is able to follow the safety standard;
as this machine concept is compact and all moving part
are inside the machine working area.
7 Unit price n.i.l.
(machine)
8 Aesthetic The machine is compact and suitable for small working area.
Machine is nice and compact.

3.2.0 Concept selection

The first step in using Concept Screening is to identify the criteria that will be use and
can generate significant debate itself. Each concept is then being examines and compares it
against each criterion to give it a relative score. The scoring scheme for this are +1, 0 and -1 to
show better, same, worse or may have values to indicate how much better or worse it is.
Each option then has its score totaled to show its overall score relative to the base option.
If one option scores much higher, then this is clearly likely to be the best choice.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 49


a) Concept screening

The purpose of concept screening is to narrow down the concept selection. In addition,
the concepts are analyzed for improvement possibilities. The reference concept for the analysis
has been identified, which is the existing hollowblock making machine which is currently
used. The machine is used as reference because it is currently represents the high
production rate block making machine available in Malaysia. FurtheBirrore, it is a
straightforward and familiar concept which can easily access. There are 3 concepts which
are going to be compared against the reference concept. The comparison will be done with
related to all customer needs.

From the evaluation of the concept screening, concept 1 and concept 2 having the same
rank (table 3.8). This mean Concept 1 in which having a cantilever type of hydraulic
cylinder attachment and Concept 2 in which having cylinder at the center is fulfilling the
customer requirement is rank as the most preferable concept; the second most preferable
concept is concept 3 which used the horizontal compaction system.

Concept 3 is eliminated from the concept selection which means that the concept is below
the standard customer expectation.

Table 3.8 Concept screening matrix

Selection Criteria Current Concept1 Concept2 Concept


3
(Horizon
tal)

High production rate - + + -

Minimum 4 blocks per cycle - + + +


One man operation - + + +
Simple operation - + + +
Comes with auto arrange block system - + + +
Comes with cement charging system - + + +

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 50


Comes with cooling system 0 0 0 0
Automated function - + + -
UnifoBirr pressure distribution -
Can be easily access for maintenance 0 0 0 0
Safe to handle - + + -
Low cost machine 0 - - -
Marketable machine 0 + + +
Comes with alert system - + + +

SUM + 0 12 12 8
SUM 0 4 2 2 2
SUM - 11 1 1 5
Net Score -11 11 11 3
Rank 4 3 2 6
Continue? No yes yes No

Rate the concept:

Relative PerfoBirrance Rating

Much worse than reference 1

Worse than reference 2

Same as reference 3

Better than reference 4

Much better than reference 5

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 51


b) Concept scoring

A concept-scoring matrix (Table 3.9) relates the concepts chosen from the screening
matrix to customer needs using weights to show the importance of needs. The reference in the
scoring matrix is not only one concept as it is in the screening matrix.

The reference is spread out among concepts for each need, giving better results since one concept
would not be average in all categories. The score rating from one to five is given to each concept
according to their need depending on the importance to the

overall design with five being the most important and one being the least important. Thisway of
scoring makes the concept-scoring matrix more accurate than the concept screening
importance to the overall design with five being the most important and one

being the least important. After all categories and concepts are scored, the score is
multiplied by the weight and added down a column. The weight percentage is based on the
customer requirements priority. From the listed customer needs, several important needs
are valued with high percentage of weight age.

Concept 2 scored higher than concepts 1. This concept has a vertical compression system
that has a bridge to support the hydraulic cylinder. Even though both of concept using the
hydraulic system to compact the block, the structure of how the cylinder being attached to the
structure affecting the process of machine operation. FurtheBirrore, concept 2 has a
compact shape in which having more aesthetic value compare to concept 1. Comparing the
safety features between both concepts, concept 2 due to having a compact shape, moving
machine part is minimize and became more safety to the machine operator, while concept
1 has a moving part expose to area working area. From the concept selection activities,
the hollow block making machine that bas bridge support cylinder has proved to satisfy
most of the customer requirements. From this selection, Concept 2 has been chosen as the
selected concept. However, it is not a mandatory to follow exactly this concept. This
process is just a guideline in designing the modification that need to improve in order to
fulfill the customer requirements and needs.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 52


3.2.1 Discussions

This type of projects involves a major modification effort to enhance the current design become
automated and high production rate. The new optimized machine must have an excellent
working principle compared to current machine used.

This phase begins with the needs of customer thru interviews (site visit), and observing the
product in use. From customer, the statements are interpreted in teBirrs of customer needs. These
interpret data are organize into a hierarchical list where consist of a set of primary needs and
a set of secondary needs. The relative importance of the needs are established in teBirr of
numerical importance weighting for a subset of the needs. Scale of 1 to 5 (1 not important
and 5 highly importance) are used to summarize the importance data.

The target specifications for hollow block making machine are established after the customer
needs have been identified. A good way to generate the list of metric is to contemplate each
need in turn and to consider what precise, measurable characteristic of the product will
reflect the degree to which the product satisfied the need. The units of measurement are
most commonly conventional engineering units.

After identifying a set of customer needs and establishing target product specifications, the
machine modification concept is being generated. Three concepts generated for proposed
modification, which are hollow block making machine that

have cantilever structure holding compaction cylinder (Concept 1), block making machine
that have cantilever structure holding compaction cylinder (Concept 2), and block making
machine that have horizontal compression system (Concept 3).

In concept selection, the concepts being evaluated with respect to customer needs and other
criteria, comparing the relative strengths and weakness of the concepts, for further
investigation. To narrow the number of concepts quickly and to improve the concepts, the
screening matrix is used. The current machine design used has been chosen to become
reference concept, against which all other concepts are rated. In concept

scoring, the concepts are weighted relative to the importance of the selection criteria and focuses
on more refined comparisons with respect to each criterion. The concept scores are deteBirrined

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 53


by the weighted sum of the rating. Concept 2 is selected as it obtain higher score compare
to the concept 1. Final product specification then being refine according to the chosen
concept before developing the detail design of the hollow block making machine with bridge
supporting compaction cylinder system.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 54


CHAPTER FOUR

4. DESIGN ANALYSIS

4.1 Introduction

The designed hollow block making machine consist of four major sub-assemblies in which
having several components or parts that can be classify to standard parts and custom part. Figure
4.1 show the overall machine assembly design. The main feature of this designed machine is
that it is purposely design in a compact size with a fully automatic function in order to produce
blocks in four mold cavities.

The parallel acting actuators or cylinders at the top structure assembly applying 80 tone of
force for pressing the blocks in mold cavities. The next process, the bottom cylinder will
push the compacted blocks up in which ready to be push out on to conveyor (unavailable in this
design) by the charger then the bottom cylinder will retract and concrete charging into
mold take place simultaneously as the bottom cylinder retract.

The process continue with charger retraction under the container for concrete refill,
vibration motor attached on the container is helping the refilling process and this work
simultaneously with the movement of top cylinder to press the concrete in mold. The
processes are continuously done automatically.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 55


4.1.1 Motor selection

Motor selection consideration


The overall motor perfoBirrance is related to the following parameters
Acceleration capabilities
Breakdown torque
Efficiency
Enclosure type
Heating
Inrush current
Insulation class
Power factor
Service factor
Sound level
Speed
Start torque
A good motor specification should define perfoBirrance requirement and describe the
environment within which the motor operates. As the purchase, you should avoid writing design-
based specification that would require modification of standard components such as the frame,
bearing, design, rotor design, or insulation.

Specification contents should include

Motor horsepower and service factors


Temperature rise and insulation class
Maximum starting current
Minimum stall time
Power factor range
Efficiency requirement and test standard to be used
Load inertia and expected number of starts
Environmental infoBirration should include
Abrasive or non abrasive

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 56


Altitude
Ambient temperature
Hazardous or non hazardous
Humidity level
We should specify special equipment requirement such as theBirral protection, space heaters (to
prevent moisture condensation), and whether standard or non-standard are required.
Due to the power output from the motor, there is rotational motion of the pulley. The pulley
drives a belt that are used to transmit power from one shaft to another by means of pulley which
rotates at the same speed or different speed it is very important to obtain all the listed
infoBirration before making selection
Source of input power
Types of driven equipment
Power to be transmitted
Speed and size of driven shaft
Drived center distance and drive arrangement
Means of center distance arrangement, if any
Available lubrication type
Spare limitations
Adverse environmental condition.

The power of the motor

By considering all the above preconditions of selecting the motor having, the power of 4kw is
selected.

The rpm of the selected motor


Depending on the selected motor, which has a power of 4kw, is a corresponding revolution per
minute of the shaft. This revolution per minutes of the shaft of this standard motor is given by
3000rpm.
The torque applied by the motor
The torque applied by the motor can be calculated by using the power equations.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 57


P=T*w, where p=the power of the motor
T=torque of the motor
W=angular velocity
W= (2*n*3000)/ (60)
w =314rad/sec
T=p/w
=4kw/314
T=12.73Nm

Diameter of motor shaft

Types of shaft: - the following two types of shafts are important from the subject point of view
1. Transmission shafts. These shafts transmit power between the source and the
machines absorbing power. The counter shaft, line shaft, over head shaft and all
factory are transmission
The shaft is made of mild steel
Material (steel with Allowable shear stress of=19.3Mpa)
We know that that torque transmitted by the shaft(T)
T= (n/16) (t) (d^3)
= [(12.73kN-mm) (16)]/ [(n) (19.3N/mm2)]
d=14.979mm
Taking standard shaft of
d=20mm

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 58


4.1.2 Bearing selection
Bearings typically have to deal with two kinds of loading, radial and thrust

Types bearing

Fig 4.1.1 types of bearing

Life of bearing.

- The life of an individual ball (or roller) bearing may be defined as the number of
revolutions (or hours at some given constant speed) which the bearing runs before the
first evidence of fatigue develops in the material of one of the rings or any of the rolling
elements.
- Rating life of a group of apparently identical ball or roller bearings is defined as the
number of revolutions (or hours at some given constant speed) that 90 % of a group of
bearings will complete or exceed before the first evidence of fatigue develops.
- Minimum life is used to denote the rating life. The average life of bearings is 5 times the
rating life (or minimum life). The longest life of a single bearing is seldom longer that the
4 time the average life and the maximum life of single bearing is about 30 to 50 times the
minimum life.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 59


Table 4.1.1 Life of bearings for various types of machine.

No. Application of bearings. Life of bearing, in


hours
1 Instruments and apparatus that are rarely used
a) Demonstration apparatus, mechanisms for sliding 500
doors.
b) Aircraft engines. 1000 2000
2 Machines used for short periods or inteBirrittently and 4000 8000
whose breakdown would not have serious consequences.
3 Machines working inteBirrittently whose breakdown 8000- 12000
would have serious consequences.
4 Machines working 8 hours per day and not always fully 12000 20000
utilized.
5 Machines working 8 hours per day and fully utilized. 20000 30000
6 Machines working 24 hours per day. 40000 60000
7 Machines required working with high degree of 100000 20000
reliability 24 hours per day.

Selection of ball bearing.

1- Basic dynamic radial load is calculated. It is then multiplying for the service factor to get
the design basic dynamic radial load capacity.
2- Selection of the bearing is made from catalogue of manufacturer, according to basic static
and dynamic capacities.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 60


Table 4.1.2 Values of service factor

No. Type of service. Service factor K S for radial ball


bearings
1 UnifoBirr and steady load 1,0
2 Light shock load 1,5
3 Moderate shock load 2,0
4 Heavy shock load 2,5
5 Extreme shock load 3,0

Standard designation of ball bearings


Fig 4.1.2 ball bearings

Lubrication of ball bearing.

They are lubricated for the following purposes:


- To reduce friction and wear between the sliding parts of the bearing.
- To prevent rusting or corrosion of the bearing surfaces.
- To protect the bearing surfaces from water, dirt, etc.
- To dissipate heat.
In general, oil and light grease are used for lubricating ball and roller bearings. Too much oil or
grease causes the rise of the temperature of the bearing. Temperatures should be kept below 90o
C and in no case, the bearing should operate above 150o C.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 61


4.1.2 Design of welded joint
Types of weld selected: - fillet

Assumption

1. The load is distributed unifoBirrly along the entire length of the weld
2. Stress is spread unifoBirrly over its effective section.
3. Static condition.

Advantages of welded joints over riveted joints.

1- Welding structures are usually lighter than riveted joints.


2- Welded joints provide maximum efficiency, which is not possible in riveted joints.
3- Alteration and additions can be easily made in the existing structures.
4- Smooth structure in appearance, therefore its look pleasing.
5- Tension member are not weakened as in the case of riveted joints.
6- Greater strength often has the strength of the parent metal itself.
7- Sometimes, the members are of such shape that the welding is easier.
8- Welding provides very rigid joints.
9- It is possible to weld any part of a structure at any point.
10- The process of welding takes less time than riveting.

Disadvantages of welded joints over rivet joints.

1- Members may be distorted or additional stresses may be developed for heating and
cooling during fabrication.
2- Requires a highly skilled labor and supervision.
3- There is a possibility of crack developing for no provision for expansion and contraction
on the frame.
4- Inspection is more difficult.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 62


Types of welded joints.
But joint - two parts in approximately in the same plane.

Corner joint: - two parts located approximately at right angle each other.

Lap joint: - between over lapping parts in parallel plates.

T- joint: - joints at approximately right angle in the foBirr of T.

Edge joint: - between the edge of two or more parallel parts.

Lap joints

1)- Single transverse, 2)- Double transverse and 3)- Parallel.

Fig 4.1.3 welded lap joint

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 63


Table 4.1.3 Stresses for welded joints.

Type of weld Bare electrode Coated electrode

Steady load Fatigue load Steady load Fatigue load


Mpa Mpa Mpa Mpa

Fillet weld 80 21 98 35

All types

Butt weld

Tension 90 35 110 55

Compression 100 35 125 55

Shear 55 35 70 35

Table 4.1.4 Stress concentration factors.

Types of joints Stress concentration factor

1- Reinforcement Butt joint. 1,2

2- Toe of transverse filled weld. 1,5

3- End of parallel filled weld. 2,7

4- T - Butt joint with sharp corner. 2,0

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 64


4.1.4 Design of spring
.
Material for springs.

There are many types of springs: Helical springs (compression and tension); Conical and
volute springs; Torsion springs; Leaf springs; Disc (or Belleville) springs.Materials for
springs should have high fatigue strength, high ductility, and high resilience and should
be creep resistant. Its selection depends upon the service for which are they used. (Severe
service, average service and light service).

Selected type is helical springs: advantage of this spring is,

- Easy to manufacture.
- Available in a wide range.
- Are reliable.
- Have constant spring rate.
- Their perfoBirrance can be predicted more accurately.
- Their characteristic can be varied by changing dimensions.

Basic TeBirrs in compression springs.

Fig 4.1.4 spring expression

Solid length: When the spring is compressed until, the coils meet each other. Is the product of
numbers of coils times the diameter of the wire. [ LS = nd ], (n) number of coils, (d) diameter
of wire.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 65


Free length: Is the length of the spring in the unloaded condition. It is equal to the solid length
plus the maximum deflection or compression of the spring and the clearance between the
adjacent coils.

Table 4.1.5 Type of end

Type of end Total numbers of turns Solid Free


(n) length length

1 - Plain ends n (n + 1) d pn + d

2 - Ground ends N Nd pn

3- Square ends n+2 (n + 3) d pn + 3d

4- Square and ground ends n+2 (n + 2)d pn + 2d

Table 4.1.6 Stress in helical springs of circular cross section wire.

D Mean diameter of the D Diameter of spring wire


spring coil

N Number of active coils G Modulus of rigidity for spring


material

W Axial load on the spring Maximum shear stress induced in


the wire

C Spring index [D/d] P Pitch of the coil

Deflection of the spring as a result of an axial load

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 66


On the compression spring, the load W tends to rotate the wire due to the twisting moment (T)
D
set up in the wire. Tensional stress is induced on the wire. Twisting moment [ T W ] and [
2
8WD
1 ]
d 3

In addition to tensional shear stress ( 1 ) induced on the wire, also the following stresses are
present: Direct shear stress due to the load W and Stress due to the curvature of the wire Direct
W 4W
shear stress:[ 2 = Load/ Cross sectional area of the wire]. 2 2
d 2
d
4

Analysis of spring design

= p= maximum allowable load

Where F=noBirral spring load

S=allowable stress

D=mean coil diameter

d= wire size

K=stress factor

Deflection per coil

G=modulus of elasticity

The force exerted by the unbalance force F=200N and the value of c ranges from 4 20 for
standard spring The material selected for spring is steel with

K= subtracting c=4 in to the equation

K=1.4

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 67


To find diameter of the spring

from this

=2.159 taking 3mm

And from the equation

D=43=12mm

Find outer diameter

=12mm+3mm

=15mm take standard=20mm

To find the number of turns of the spring(n). the number of active turn of the spring we know
that compression of the spring=40mm

40mm=

40mm=

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 68


Solid length

=13

From standard we know that (maximum deflection)=10mm, so to find free length

(nd)+ +(n-1)=51mm take standard =50mm

Finding pitch of the coil

P=[ ]+d

=[ ]+3

=3.846 take 4mm

Stress on the spring is only the direct noBirral stress and direct shear stress

Check for direct shear stress

=28mpa

= +

=254.46mpa

=612mpa > .safe

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 69


4.1.5 Design of bolt
Assumption:-

1. The shear loads are carried by friction.


2. The attached members are rigid and do not deflect with loads.

Fig 4.1.5 Bolted joint.

Material selection

So the material we chose for bolt has to have high wear resistance and good machine
ability
The material is ASTM A47, A338 with
Ultimate tensile stress 345Mpa and yield stress of 224Mpa

; ;
;

From standard diameter of the bolt is 2mm

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 70


4.1.7 Design of double acting piston
Purposes of major hydraulic components

Pump:-changing mechanical energy to fluid energy in the foBirr of flow


Tanker :-store oil, allow air to be separated and sediment the dirties in the oil by using
baffle plate
Control valves:-allow the fluid to the desired direction they
1. Direction control valves
2. Flow control valves
3. Presser control valves
Actuator:-by acting linier motion, changes hydraulic motion to mechanical motion.

The overall line circuit of double acting cylinder will be (the selected one)

Extract cylinder Retract cylinder

Fig 4.1.6 hydraulic circuit

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 71


Basic calculation of hydraulic power needed

Hydraulic power is defined as Flow x Pressure. The hydraulic power supp a pump: P in [bar] and
Q in [lit/min] => (P x Q) 600 [kW].

The machine needs to apply the forces of 800kN (Maju Dinamik Sdn. Bhd.) on the concrete
particle inside the mold in order to foBirr the hollow block. Therefore;

From top structure designed, bore diameter = 112mm, after compensate fo10mm wall cylinder.

Area for hydraulic bore = (D/2)2

= (0.112m) 2

= 0.04m

Required force = 800kN

Pressure = Force / Area = 800kN / 0.04m2

= 20 Mpa (200 bar)

According to standard hydraulic part in catalog in Appendix, the most suitable cylinder with
required stroke is PMC21020 with 5bore diameter, shaft diameter 2.5, and 20 stroke (required
stroke 18 or 460mm).

Due to high pressure system required the power unit also should carefully selected in order to
make sure that the system is under power which mean the blocks are not well compress and may
rise a quality issue to the end user. However if the high power of power unit is chosen the system
can be say as under utilize as the power required is less than supplied by power pack unit and
furtheBirrore, the cost is higher than the middle power of power pack unit.

According to standard power unit in catalog in Appendix, the most power unit with required
200bar of pressure is 255617 part number with 3000psi and 5 gallon of reservoir tank capacity in
which sufficient enough to supply the hydraulic oil for both cylinders during operation and hold
the oil during machine shut down.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 72


Flow Regulating Valve

Restriction depending
Restriction depending on the viscosity

Spring

Manual - lever
Muscular control - lever

Double - single piston


Double-acting cylinder - single-ended piston

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 73


Restrictor
Restrictor valve - simplified symbol

Constant, 1 direction
Constant hydraulic motor with one direction of flow

Pressure reducing
Pressure reducing valve

Basic
Valve noBirrally closed in un activated position \

Fig 4.1.7 valve representation

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 74


4.1.7 Design of support frame

Material selection for the support frame


steel
Assumption
consider the support as columns with one end free and the other end fixed the critical
load is given as

( )

And

Where
A=ranking constant
L=equivalent length of the column
K=last radius of gyration
=crushing or yield stress In compression

And the above consideration of one end free and the other end fixed will case for buckling and
the weight applied on the support frame is about ( ) =200N
And the factor of safety for steady load is given by F.s (5-6) there for the critical load will be

=5
=250

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 75


Assuming the length of the frame 400mm and from Euler foBirrula of crippling load the 4 polar
moment of inertia is given by

=0.00966

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 76


4.1.8 Design of shear mould base

This shear plate is a part of the main components of the machine, which are basically used as a
mould to get the exact shape of the compacted block. And also, the maximum bending moment
is created at the center.

Fig 4.1.8 mold base.

Where C=t/2

The maximum allowable stress for the mould

where F.S is taken 2

from this

Since the shear plate are the most important part of the machine, we decided the thickness of
material to be 4mm

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 77


CHAPTER FIVE

5. RESULT AND DISCUSSION

5.1 Product Architecture

The architecture of a product can influence many aspects of its life-cycle perfoBirrance
from the design phase through to the recycling of a product and the reuse of fragments of its
design. Product architecture choice therefore deserves careful consideration, which would
be facilitated by the ability to represent and assess alternatives at an early stage.

In this context, product architecture refers to the conceptual structure of a design.

It has been defined by Ulrich [1] as the arrangement of functional elements, the mapping from
functional elements to physical components, and the specification of the interfaces among
interacting physical components. Others extend this definition to include the division of a
product into functional modules and component-sharing relationships within a family of
products.

Product architecture may be represented using a product modeling language. There are
many such languages, which vary in the types of infoBirration they represent and the way
in which they do so.

Models of a products architecture constructed in such languages may be used for various
purposes, including communication between the client and a design team or within a
design team, or (the focus of this paper) for assessing the product against life-cycle
objectives. These objectives may be classified into perfoBirrance-related objectives and those
related to other aspects of the products existence. Many objectives in the second class, also
teBirred non-functional requirements, are addressed by Design for X (DfX) methods (where
X may be Assembly, Manufacture, Environment etc.) [1].

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 78


5.1.1 Mold

Mold assembly (figure 4.2) consists of six different parts and each of it can be produce
by conventional machine process except for mold itself which require the modern
machining process namely Wire EDM. One of the six parts is M10 Hex cap screw.
Details can refer to figure 4.15. The mold isattached on the table structure by bolt M20.

Fig 4.1.9 Mold assembly design

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 79


5.1.2 Top Structure

Top Structure assembly (figure 4.4) consists of thirteen different parts and each of it can be
produce by conventional machine process except for top mold itself which require the modern
machining process namely Wire EDM and join by using welding process for the structure
(hinge and compactor, and top structure 2) component. Beside M24, M20 and M10 bolt, nut,
and hex cap screw, this sub-assembly consists of two hydraulic cylinders. Details can
refer to figure 4.17. This structure is attached on the mold structure by M20 bolt.

Fig 4.2 Top structure assembly design

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 80


5.1.3 Charging System

Charging system assembly (figure 4.5) consists of sixteen different parts and each of it
can be produce by conventional machine process (except for charger, container and cover
suitable process is laser cutting).and join by using welding process for the structure (block
pusher, slider base, structure base, and charging structure) component. Beside M20, M12,
and M4 bolt, nut, and hex cap screw, this sub-assembly consists of one hydraulic cylinder and
also a vibration motor. Details can refer to figure 4.18. This structure is attached on the mold
structure by M16 bolt and table structure by M12.

Fig 4.2.1 Charging System assembly design

In this sub-assembly lays the heart of the machine whereby the control system devices are place
inside the control panel. The control panel consists of on/off knob, two hand control as a point of
operation safeguarding device. The palm button must be depressed concurrently and maintained
during the hazardous down stroke of the ram. Release of palm button reverses or stops the action
of ram. The controls offered also include a light curtain interface. All the electronics parts are
placed inside the control panel box (figure 4.6).

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 81


Fig 4.2.2 Inside control panel

5.1.4 PerfoBirrance of the safety related function

When a component, device or system failure occurs, such that it or a subsequent failure of
another component, device or system would lead to the inability of the safety related function to
respond to a noBirral stop command or an immediate stop command, the safety related function
shall;

Prevent initiation of hazardous machine motion until the failure is corrected or until the
control system is manually reset; or
Initiate an immediate stop command and prevent re-initiation of hazardous machine
motion until the failure is corrected or until the control system is manually reset; or
Prevent re-initiation of hazardous machine motion at the next noBirral stop command
until the failure is corrected or until the control system is manually reset.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 82


Table 4.1.7 Material and process selection

No. Part material Manufacturing process

1 i) Steel rod -Cutting process by hacksaw


(Mild Steel)

ii) Sheet metal -Cut by shearing machine; Lasercutting,


(Mild Steel) etc.
Assemble by welding process

Block pusher assembly

2 Cutting process
i) Steel bar by hacksaw

ii) Sheet metal Cut by shearing


(Mild Steel) machine; Laser
cutting, etc.
charger Assemble by welding process

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 83


No. Part material Manufacturing process

3 i) Metal plate Milling, drilling,


(Mild Steel) counterboring.

compactor
4 i) Sheet metal Laser cutting, Turret punching, and
(Mild Steel) welding process for joining.

container
5 ii) Sheet metal Laser cutting, Turret punching, and
(Mild Steel) welding
process for joining.

cover
6 i) Steel bar Milling and
drilling process

Join on the top of compactor by


welding process

Hingue

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 84


7 i) Steel Bar Cut by sawing
(Mild Steel) process, drilling,
and tapping.

middle bar
8 i) Steel Block Drilling and
(Mild Steel) wire cutting

Mold
9 i) Steel Plate Milling, drilling,
(Mild Steel) counterboring
and wire cutting

movable base
10 i) Steel Plate Milling, drilling,
(Mild Steel) and
counterboring.

planar base

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 85


11 i) Angle Bar Cut by sawing,
ii) Steel Bar and drilling

Assemble by welding process

plate structure
12 i) Steel Plate Milling, drilling,
(Mild Steel) counterboring.

Pusher Base
13 i) Steel rod Cut by sawing
(Mild Steel) process, drilling
and tapping
process

Pusher Shaft
14 i) Steel rod
(Mild Steel) Cut by sawing
process, turning,
drilling, and
tapping process.

Rod

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 86


15 i) Steel Plate Steel plate cut
(Mild Steel) into several
parts, then
further with
milling and

Slider Base drilling process.


The parts then
join by welding
process.
16 i) Steel rod Cut by sawing
(Carbon steel) process drilling
and tapping.

Slider Compactor
17 i) Angle Bar Cut by sawing
(Mild Steel) process drilling.

Table Structure 1
18 i) Parallel Cut by sawing
Flange process drilling.

Table Structure 2

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 87


19 i) Steel Bar Cut by sawing
(Mild steel) process, drilling,
and welding.

Structure Base
20 i) Angle Bar Cut by sawing
ii) Parallel process, drilling,
Flange milling, and
welding.

Table
21 Drilling, tapping
i) Steel Block and wire cutting
(Mild Steel)

Top Mold
22 i) Parallel Cut by sawing
Flange process drilling,
and milling

Top Structure 1

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 88


23 i) Parallel Cut by sawing
Flange process drilling,
and milling
ii) Steel Bar Cut by sawing
(Mild Steel) process, and
drilling.

Top Structure 2
24 i) Steel rod Cut by sawing
(Carbon Steel) process drilling
and tapping.

Pusher Slider
25 Standard
- Vibration vibration motor
frequency for heavy duty
50 90 Hz
- 1400 RPM

Vibrator (PL15E-QD 1.8 HP) &


(PL20E-QD 2.4 HP)
26 Standard
- Stroke 400mm hydraulic
- BoreDiameter cylinder with
30mm side mounting
- Force 1KN
Horizontal Cylinder

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 89


(PMC42020)
27 - Stroke150mm Standard
hydraulic
- Bore cylinder with
Diameter30mm bottom
- Force 1KN mounting

Bottom Cylinder (PMC42008)


28 - Stroke450mm Custom hydraulic cylinder with
- Bore special mounting
Diameter
80mm
- Force 800KN

Top Cylinder (PMC21020)

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 90


5.2. Components Analysis

In this section, the critical parts which are top structure and the table structure are being tested by
putting the maximum force along its structure. The analysis are conducted by using the CAE
software namely CATIA V5 in order to obtain the result.

5.2.1 Top Structure

The maximum forces 800kN exerted at the cylinders mount and also distributed along top plate.
Figure below shows the result of simulation analysis, it seems that the maximum Von
Misses Stress does not exceed that Yield Strength of the structure, so that the top structure can
be considered as tough enough to work with 800kN force ces from hydraulic cylinder

Figure 5.11 Top structure stress analysis

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 91


The analysis also shows the result of displacement of the top plate after applying the 800kN
forces on it. The maximum displacement 0.138mm occurs at the center of the op plate, and it
seems this maximum displacement is still not exceeding the elastic region of the top plate
material properties.

Figure 5.12 Top structure displacement results

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 92


5.2.2 Table Structure

The maximum forces 800kN exerted at the top surface of table structure and also distributed
along top plate. Figure below shows the result of simulation analysis; it seems that the
maximum Von Mises Stress does not exceed that Yield Strength of the structure, so that
the table structure can be considered as tough enough to work with 800kN forces from
hydraulic cylinder.

Figure 5.13 Table structure stress analysis

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 93


The analysis also shows the result of displacement of the table structure after applying
the 800kN forces on it. The maximum displacement 0.319 mm occurs at the center of
the top plate, and it seems this maximum displacement is still not exceeding the elastic
region of the top plate material properties. FurtheBirrore, on top of the table surface will
be put the 30 mm planar base plate and this will change the result to a lot better.

Figure 5.14 Table structure displacement result

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 94


5.2.3 Compactor Structure

The maximum forces 800kN exerted on the planar base and distributed along it face. Figure
below shows the result of simulation analysis; it seems that the maximum Von Mises
Stress does not exceed that Yield Strength of the structure, so that the table structure can be
considered as tough enough to work with 800kN forces from hydraulic cylinder.

Figure 515 Compactor structure stress analysis

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 95


The analysis also shows the result of displacement of the compactor structure after
applying the 800kN forces on it. The maximum displacement 0.0571 mm occurs at the center of
the top plate, and it seems this maximum displacement is still not exceeding the elastic
region of the top plate material properties. FurtheBirrore, on top of the table surface will be
put the 30 mm planar base plate and this will change the result to a lot better.

Figure 4.2.4 Compactor structure displacement result

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 96


5.2.4 Planar Base Structure

The maximum forces 800kN exerted on the planar base and distributed along it face. Figure
below shows the result of simulation analysis; it seems that the maximum Von Mises
Stress does not exceed that Yield Strength of the structure, so that the table structure can be
considered as tough enough to work with 800kN forces from hydraulic cylinder.

Figure 5.2.5 Planar Base structure stress analysis

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 97


The analysis also shows the result of displacement of the compactor structure after
applying the 800kN forces on it. The maximum displacement 0.273 mm occurs at the center of
the top plate, and it seems this maximum displacement is still not exceeding the elastic
region of the top plate material properties.

Figure 5.2.6 Planar base structure displacement result

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 98


5.3 Cost Analysis
In todays competitive business environment, pricing strategy can be a critical factor that can
make the difference between success and failure. Organizations that are cost efficient
would have a clear competitive advantage, therefore accurate and timely cost infoBirration
can go a long way in helping these organizations become successful. Organizations also
need to control their cost through effective budgeting and variance analysis. This will
enable them to quickly take corrective action and steer the organization back on track.

5.3.1 Guidelines for Calculating the Block Selling Price

The data presented in this sub topic is meant to help entrepreneurs to estimate the production
cost of compressed block with a view to identifying the lowest costing technology and
size of production. A methodological framework for the estimation of production costs is
described in the following sections.

It should be noted that the cost of producing compressed block will vary a great deal from
country to country and even from one area to another within the same country. Unit production
costs will differ in relation to local conditions.

Causes for cost variations include:

Availability of soil, whether it is available on site or has to be transported to the site.


Suitability of the soil for stabilization, and thus the type, quality and quantity of
stabilizer needed. It may also be necessary to buy sand if the soil has an
excessively high linear shrinkage,
Current prices of materials.
Whether the blocks are to be made in rural or urban areas, size and type of
equipment used and quality required.
Current wage rates and productivity of the labor force.

It is important to note that block making can be carried out on a self-help basis, where labor
costs are eliminated. FurtheBirrore, soil is often available at no cost. The methodological
costing technique consists of 12 steps that may be sub-divided into two main parts:

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 99


(a) DeteBirrining quantities of the various inputs (Steps 1 to 6),

(b) Estimation of the cost of each input and computation of unit production costs (Steps 7 to
12). These steps are briefly described in the remaining part of this section.

Step 1 - DeteBirrine the quantity of blocks to be produced in a given period of time. The number
will be a function of market demand, availability of finance, acquired production techniques, etc.

Step 2 - Calculate amount of material inputs required for the chosen scale of production. The
basic materials are suitable soil, sand (if needed for linear shrinkage modification), stabiliser and
water. Some oil, for example used engine oil, will be needed as a mould release agent.

Step 3 - List of equipment required. This will include items for digging and moving
soil, preparing soil with a crusher or sieving screen, mixing, a device for moulding the
blocks, a covered yard for curing the blocks and an office. Provision should also be made
for soil investigation and testing equipment. Chapters 2 to 4 provide infoBirration on the type
of materials, equipment and infrastructure needed. The cost of industrial pieces of
equipment may be acquired from equipment suppliers and manufacturers, (see Appendix
III), or from local workshops in cases where the equipment is produced locally.

Step 4 - List of labor requirements. The productivity of the labor force may not only vary from
one country to another, but also from one site to another within the same country. It is
important to specify the length of the working day, the number of days worked per week
and the number of working weeks per year, taking into account an allocation of time for
leave of absence during the year. The level of skill requirements must also be deteBirrined.

Step 5 - Other local services and facilities may be required, such needs may include:

land for quarrying soil for block making,


land for production area,
land for curing area and storage of raw materials,
provision of access to working area for delivery of materials and dispatch of
products.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 100


Step 6 - Computation of working capital requirements. In addition to funds required for
purchase of equipment and land as itemized in the preceding steps, it will be necessary
to have sufficient financial resources for the purchase of raw materials and payment of
wages for a period of one month, since there can be no income from the sale of blocks until they
have been made and cured. If difficulties are anticipated in obtaining any particular commodity,
it might be necessary to maintain enough stocks for a period longer than one month. It may also
be desirable to use some of the first products in the construction of the covered area, offices, etc.,
in order to reduce the cost of items under Step 3. It will then be necessary to slightly increase the
working capital to allow for the number of blocks that will be used for this purpose, rather than
sold.

Step 7 - Annual cost of materials identified in Step 2 must be calculated. Clay, sand and water
are often extremely cheap items. The mould-releasing agent will not be needed in large
amounts so should cost very little. Reject engine oil may be acquired at a very low price or
obtained free in some cases.

Step 8 - Computation of depreciation costs of equipment and buildings. Whatever type of


equipment used, it will have a limited life-span. An estimate must be made of the annual
depreciation costs for separate equipment items. The depreciation cost of buildings must
also be estimated. These costs will depend on the original purchase cost, the life-span of
equipment and buildings and the prevailing interest rate. It should be noted that the
longer the useful life of equipment or building the lower the annual depreciation cost.

Step 9 - Reasonable value must be given for the cost of labor in the area where blocks
are to be produced. Local wage levels for different skills must be applied and fringe
benefits included in the estimation of labor costs.

Step 10 - Land has an infinite life, and the area from which soil is obtained may be restored
to its original use in some instances. Thus the annual cost of land may be assumed to
be equal to the annual rent of the same or equivalent piece of land. If the land is already
owned by the investor, a hypothetical annual rental rate should be used when estimating the
annual land cost, since this is the income the investor might have obtained by renting it
out instead of using the land themselves.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 101


Step 11 - Working capital raised on loan for the block-making project will need to be accounted
for in the annual cost for interest payments on borrowed capital.

Step 12 - The unit production cost may be calculated by summing up the separate cost
items from Steps 7 to 11 in order to get the total annual cost. The latter is then divided
by the number of blocks manufactured annually to obtain the unit production cost.
Therefore:

+ Material costs (7)

+ Depreciation (8)

+ Labor cost (9)

+ Land rental (10)

+ Interest on loan (11)

= Total annual production cost

Unit production cost = Total annual production costs annual output

(Source from: Compressed Stabilized Earth Block Manufacture in Sudan, Dr. E.A.Adam in
collaboration with Prof. A.R.A.Agib)

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 102


5.3.2 Machine component and Raw Material Cost

In order to calculate the cost of building this machine, the list of parts or component
must be clearly identify by referring to the bill of material generated upon the final stage
of design. This hollow block making machine consist of four sub-assemblies and each
component in the sub-assembly consist of several components which can be classify as
standard part and custom part. These can be clearly understood by referring to the bill of
materials figures shown.

5.3.2.1 Bill of Materials

Total assembly drawing (figure 4.19)

Mold assembly drawing (figure 4.20)

Table assembly drawing (figure 4.21)

Top structure assembly drawing (figure 4.22)

Charging system assembly drawing (figure 4.23)

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 103


4.1.9 Material Cost Estimation

a) Material cost

Table 4.1.8 Material cost

No. Parts Quantity Price(Birr) Total Price(Birr)

1 Parallel Flange 1 115.00 115.00


i) 152 X 76 X 18 1 598.00 598.00
ii) 200 X 90 X 30 1 464.00 464.00
iii) 260 X 75 X 28 1 880.00 880.00
iv) 305 X 102 X 46
2 Angle Bar
i) 60 X 70 X 522 2 30.00 60.00
ii) 60 X 70 X 740 6 57.00 342.00
iii) 102 X 102 X 480 2 79.00 158.00
iv) 100 X 73 X 748 2 244.00 488.00
3 Steel Plate
i) 530 X 780 X 30 1 1881.00 1881.00
ii) 100 X 725 X 40 1 1696.00 1696.00
iii) 160 X 44 X 23 4 196.00 784.00
iv) 125 X 300 X 15 4 82.00 328.00
v) 500 X 750 X 40 1 1881.00 1881.00
vi) 60 X 489 X 10 2 121.00 242.00
vii) 120 X 750 X 20 1 585.00 585.00
viii) 610 X 1267 X 20 1 1174.00 1174.00
ix) 1127 X 50 X 20 1 585.00 585.00

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 104


4 Round Bar
i) 15 X 120 1 6.00 6.00
ii) 20 X 190 1x8 32.00 32.00
iii) 30 X 250 2 28.00 56.00
iv) 60 X 720 4 281.00 1124.00
v) 100 X 160 4 102.00 408.00
5 Square Bar
i) 25.4 x 25.4 X 8364 1 280.00 280.00
ii) 50.8 x 50.8 X 11320 1 1529.00 1529.00
6 Sheet Metal (2mm)
i) 4x 8 2 256.00 512.00
7 Steel Block
i) 300 x 125 x 52 1 500.00 500.00
ii) 610 x 350 x 165 1 1000.00 1000.00
TOTAL 17,708.00

b) Screws and nuts

Table 4.1.9 Screw and nuts cost

No. Parts Quantity Price (BIRR) TotaPrice(BIRR)


1 M12 x 130 12 2.80 33.60
2 M12 Nut 12 2.70 32.40
3 M16 x 40 24 1.50 36.00
4 M16 Nut 24 3.20 76.80
5 M20 x 70 37 4.00 148.00
6 M20 Nut 37 3.20 118.40
7 M24 x 100 4 9.00 36.00
8 M4 x 15 34 0.30 10.20
9 M10 x 40 58 1.40 81.20
572.60

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 105


c) Mechanical System Equipment Cost Estimation

Table 4.1.9 Mechanical system and equipment cost

No. Parts Quantity Price (BIRR) TotalPrice


(BIRR)
1 Top Hydraulic System
i) Hydraulic 2 1875.00 3750.00
cylinder (PMC21020)
ii) Power pack unit (255617) 1 4470.00 4470.00
2 Horizontal Hydraulic System
i)Hydraulic cylinder 1 659.00 659.00
(PMC42020)
ii) Power pack unit (251688) 1 4224.00 4224.00
3 Bottom Hydraulic System
i)Hydraulic cylinder 1 579.00 579.00
(PMC42008)
ii)Power pack unit (share with
horizontal hydraulic system) - - -
4 Vibrator Motor
i) PL15E QD 1.8HP 2 1242.00 2484.00
ii) PL20E QD 2.4HP 1 1338.00 1338.00
5 Bearing Bush
i) LHFCWM30 2 51.00 102.00
ii) LHFCWM50 4 144.00 576.00
TOTAL 18182.00

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 106


5.3.4 Manufacturing cost

Table 4.2.Manufacturing cost

No. Machine Hour Price/Hour Total (BIRR)


1 Drilling 48 30.00 1440.00
2 Milling 12 100.00 1200.00
3 Turning 6 100.00 600.00
4 Wire EDM 48 100.00 4800.00
5 Welding 5 60.00 300.00
6 Assembly 36 50.00 1800.00
TOTAL 10140.00

Estimation of total machine cost.

+10140.00 Manufacturing Cost

+17708.00 - Material Cost

+ 572.60 - Screws and nuts

+ 18182.00 - Mechanical System Equipment

BIRR= 46,602.00

Therefore, roughly, total machine cost including the mechanical system is BIRR 46,602.00.
However, this value may change relatively as a time goes by.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 107


5.3.5 Product design specification

Product Design Specification (PDS) is the basis for all design decisions, it may serve as a
contract that must be fulfilled; PDS is dynamic rather than static; PDS must be established with
consideration of all aspects of the product and its interactions; systematic and thorough
in foBirrulating PDS; Poor PDSs lead to poor designs; good PDSs are necessary, but not
sufficient for a good design. At the first stages of design it is essential to cover ALL the
aspects of the product even if at a superficial level. The specificity of details can be
honed as more is learned about the product and the interactions of different aspects of the
PDS. From internal market research, it has been decided that this machine need to be designed
as simple as possible so that it can be sell to the hollow block making machine
construction sector. The machine should be automated so it can have a shorter lead time in
making a blocks. Below is the product design specification that has been generated
according to the development of the final design. However, as long as this design become
a real product, it still can be considered as not yet a final PDS as it can be change parallel with
the fabrication of this machine.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 108


Table 4.2.1 Final product design specification

NO. METRIC METRIC VALUE


1 PerfoBirrance

i. Production rate
ii. Maximum force Cycle/Hour 60>
iii. Charging container capacity kN 800
iv. Operating period m3 1
v. Cooling rate Hour/Day 24
vi. Compression pressure Maintenance kW 50
MPa 20
2 Maintenance
i. Maintenance free except for light lubricant
ii. Parts requiring lubrication should be accessible within 15 minutes
without the use of special tools or equipment.
iii. All fasteners used should comply with MS.
iv. No special tools should be required for maintenance.
3 Size and weight
i. Weight kg 2000
ii. Length m 1.7
iii. Width m 0.75
iv. Height m 1.8
4 Product life span years >10
5 Labor Manpower 1
6 Unit price (machine) <60,000

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 109


CHAPTER SIX

CONCLUSION

In the concept development phase, the needs of the target market are identified by
gathering raw data from customer thru interviews, questionnaire, and observing the
product in use via literature review in patent search. From the observation, shorter
operation time (30 - 40 seconds), and fully automatic machine with less maintenance
required are the ideal machine dreamed by the block manufacturer. The target
specifications are established after the customer needs have been identified but before
product concepts have been generated and the most promising ones selected. This process
is done in the first part of this project (figure 5.1) until the best generated concepts is
selected. In second part of this project (figure 5.2), the chosen concept is being refine it
value until the detail design is generated (mechanical, electrical, and hydraulic)

6.1 Conclusion

In reflecting on this project all objectives were successfully met. The design product
engineered that help a user to maximize the production of the hollow blocks in the minimum
cost. Whereby the current product dont have a simple hollow making machine that having a
automatic working systems features.

A major objective of the new design of hollow block making machine was to be able to ensure
that the block productivity increase compare to the current machine design. Therefore, the
decided design must be reflecting the main goal and incorporated it together with the
components design objective. After using the steps of the PDD the machine is designed with
its automated cement charging features and also having the vibrator apparatus in order to
make the cement in mold compacted. Throughout the project the work progress is kept on
track by using project management tools such as a Gantt chart. Time management was a very
crucial portion of the project because a lot of work had to be done in a short period of
time. The team learned that when a task for a project is completed, such as concept selection,
even if a table has been constructed it is a good idea to write a summary about where it came

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 110


from, how it was made/achieved and what the results were, that day so when a final reportis
being put together nothing is forgotten about past tasks.

6.2 Future Development

In the next phase, this machine can be upgraded to more user friendly by adding

the features such as automatic concrete loading into a machine container and also the
attachment of conveyer for transferring the compacted blocks directly on the machine
itself.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 111


Recommendation
The simple concrete block will continue to evolve as block manufacturers develop in new shapes
and sizes. These new blocks promise to make building construction faster and less expensive, as
well as result in structures that are more durable and energy efficient. Some of the possible block
designs for the future include a mold pattern that are available for locking mechanisms of one
block with the other block. This reduces the amount of cement.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 112


REFERENCES

[1] H.C. Sumpf, Block Machine, United States Patent Office, Application December 16, 1946,
Serial No. 716,564, Cl. 25-41.

[2] Judson A. Hereford, Block making apparatus, United States patent, Application January
1991, Serial No. 636,726, Cl. B29C 43/00.

[3] Nicholas Lyons and C.K George, Inverter for block mold, United States Patent,
Application February 1989, Serial No. 313,067, Cl. B28B 5/02.

[4] Vernon C. Duff, Machine for manufacturing hollow concrete blocks, Application July 1928,
Serial No. 293,882. Teaching material on machine design. Lecture notes of machine elements
and machine design courses by joseM. Dominguez estupinan, Mech.eng. and ato Mekonen
Gebreslasie.

[5] Mechanical Engineering Shigleys Mechanical Engineering Design, Eighth Edition Text: by
BudynasNisbett.R.S. KhuBirri, J.K. Gupta, a text book of machine design, 2002, 13th edition.

[6] Bralla james g.Handbook of product design for manufacturing: a practical guide to low
cost production, mc garw hill 1986 USA

[7] Fraenkel plwater lifiting devices for irrigation and draninage,fao, rome 1986

[ 8] Helsel jay d, cecil jensenengineering drawing and design, 5th edition glencoe/mc graw
hill USA, 1996

[9] Kreith frank the crc handbook of mechanical engineering, 1st edition crc press USA 1998

[10] KhuBirri r s, gupta j k:a text book of machine design,13th edition, eurasia publishing
house (pvt) ltd, ran nagar, new delhi, 2002.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 113


[11] Mischke charless r, joseph e shigley standrad handbook of machine designe, 2nd edition,
mc graw hill USA, 1996
[12] Nelik lev centrifugal pump and rotary pump: fundamentals with application,1st edition,
USA 1999.

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 114


APPENDIX

PART DRAWING

DAHLAK HIKA & ZELEALEM BELAY 2004 G.C Page 115

You might also like