You are on page 1of 2

Daily Report

Project 14- Cristal 001/00 Project Site: 115/34.5 KV Cristal S/S Date: 17/12/2016
No:
Weather
Temperature 28C Humidity Cloudy Storm

Manpower ABB HVAC FF RTC Activities

Site Manager 1 1 Work Schedule / Started


Civil Activities:
Testing Team Leader 1 1. Painting of handrail.
2. Installation of remaining toilet accessories.
QA/QC Engineer 1 3. Installation of sockets at power transformers area.
4. Installation pumps connection.
Testing Engineer 5. Closing of punch list points.
Mechanical Engineer
Electrical engineer
Foreman 1
Electrician
Safety Officer 1 1
Steel fixer
carpenter 2
Masons 2
Small power
Labor 1 Work Completed / In progress
Civil Activities:
Equipment operator 1. Painting of handrail (In progress)
2. Installation of remaining toilet accessories (Completed)
Driver 1 3. Installation of sockets at power transformers area (In progress)
Tea boy 1 4. Installation pumps connection (In progress)
5. Closing of punch list points (In progress)
Fence technician
FA Programmer
HVAC
Firefighting
Other

Deviations / Interruptions / Hindrances

Tool Equipment
Hand tools,1- bobcat & 2-compactor,

Total: 4 10
Page 1 of 2
Daily Report

Installation of sockets at power transformers area

Installation of remaining toilet accessories


Page 2 of 2