Professional Documents
Culture Documents
200
Transfer inovci 24/2012 2012
forward, it passes over a spreader, or torpedo, Requirements for production were to meet
within the barrel, which causes mixing. This stage all main dimensions in tolerances, no visual defects
is determined by an injection velocity (rate), a (burns, stains) and to control the internal surface of
pressure, and a time. Injection velocity is the rate at bore.
which the plunger moves forward.
Stage 2: Pack stage
As the melt enters the mold, it cools and
introduces shrinkage. The pack stage is necessary to
force more melt into the mold to compensate for
shrinkage.
Stage 3: Hold stage
When no more material can be forced into
the mold, melt can still leak back through the gate.
The hold stage applies forces against the material in
the cavity until the gate freezes to prevent leaking
of the melt. In some machines, pack and hold are
combined into a single second or holding stage.
The aim of this paper is to identify and
select the optimal conditions for the technological
process of injection molding of selected part to
determine the optimal conditions. Injection process
is affected by number of factors that influences on
productivity and accuracy of injection molding as
well as on the overall cost associated with its
production.
2. EXPERIMENTAL SECTION
201
Transfer inovci 24/2012 2012
202
Transfer inovci 24/2012 2012
Form was deficiently tempered and the problem several tests were made based on the values from
with ejection of inlet occurred. To ensure trouble- the material list (melting point of the material is
free production the optimal temperature of the mold 255 C). Temperature profiles of jet and screw is
was determined to 75 C. shown in Table 1.
Determination of optimal temperature mode At each temperature profile were measured
several cycles of injection and injection parameters
The original model was modified in terms
(dosing time, mold filling time and the maximum
of suitable technological changes, as the core forms
pressure of the melt). These were measured by
were also damaged, shown in Figure 4. After
weighing pressed moldings in various temperature
changing the model, simulation was performed; this
profiles and investigated the material pillow (the
didnt revealed serious short comings. The aim of
amount of melt that stays as a reserve material in
the simulation was to determine the appropriate
the injection machine). Weight of moulds was
technological parameters of injection. As the main
determined by the weight Helagocalibration
parameter of interest was the injection temperature.
accuracy with 0,001 grams (Table 2).
To determine the optimum temperature mode,
Discussion of measured values for different holding pressure phase. For the same
temperature profiles reason, was excluded and temperature profile No.4
with nozzle temperature 315 C. In the remaining
Table 1 and Table 2 shows that when the two profiles it was necessary to consider the
temperatures at the nozzle and the screw are higher, advantages and convenience of use. Although the
the time of the dosage lowers. Dosing Time is at all difference between the weight and filling time were
temperature profiles less than 3 seconds, and minimal, there was a significant difference in the
cooling of moulds takes up to 10 seconds. maximum filling pressure. For this reason, as the
At the temperature profile No.1 is optimum temperature profile was chosen profile
temperature of nozzle and screw very high. At these No. 2, with a temperature of nozzle 325 C.
temperatures, the risk of degradation possibility of After evaluating of moulds at different
the material often occurs. This profile would be speeds of injection was injection rate of 30 ccm/s
able to shorten the production cycle, but does not chosen as the most suitable. The reason for this
guarantee the quality pressings. For the production choice was high quality of moulds, without failures
of these moulds, even temperature profile No.5 was and burns. Determination of the holding pressure
inconvenient with a temperature of 300C at nozzle. was primary based on the weight of the moldings.
The reason was the relatively high pressure of By the increasing time of holding pressure, the
molding and low quality. More time is needed for cooling time was gradually reduced. Reducing the
the injection and probably would require a longer cooling time with raising the holding pressure
203
Transfer inovci 24/2012 2012
204