Professional Documents
Culture Documents
As mentioned in the previous sections, the water supply to the project area can be
delivered by connecting to existing water supply in Beladin and Maludam. However, the
Maludam water treatment plant is currently operating in 24 hours and the potential to
upgrade the plant to cater the new water demand in the project area is limited due to its
close proximity to the sea and saline intrusion coupling with the draught season which
In view of this, the water supply to the project area is recommended to be connected to
new Beladin water supply system which is currently in the construction process under
project BALB (SAMBUNGAN BEKALAN AIR DARI SIMPANG KAKI WONG KE PUSA-
BELADIN, BETONG, SARAWAK) implemented by KKLW. The water supply to Beladin is
sourced from recently completed Kaki Wong Water Treatment Plant (WTP) which has a
capacity of 25mld serving Saratok region and surrounding area. According to JBALB,
there is an excess of 10mld from this WTP for future water demand in Saratok and
surrounding area.
However, based on the gathered data from the above project, the new booster station
and elevated water tank proposed in Beladin is only designed to cater water demand in
Beladin area. A hydraulic analysis has been performed to simulate the water supply
system to Beladin from Pusa new reservoir. It was found that the residual pressure head
at Beladin is about 15m (as shown in Diagram 1) which satisfy the minimum residual
pressure head of 10m as stipulated in JKR design guideline and sufficient for supplying
Diagram 1 - Hydraulic Analysis Diagram for Water Supply from New Pusa Reservoir to
Pusa and Beladin (Peak Hour Flow)
Diagram 2 - Hydraulic Analysis Diagram for Water Supply from New Pusa Reservoir to
Pusa, Beladin and extended to Sepinang (Peak Hour Flow)
From Diagram 2, it is anticipated that continuously drawing water through direct
connecting to such system will cause water supply interruption in Beladin (residual
pressure drop to 3m) when the water demand increases and the residual pressure at
Sepinang is only about 2m which does not meet the minimum requirement of 10m.
Therefore, the option to lay a 450m OD HDPE pipeline from Beladin to Sepinang is not
feasible. In view of this, a separate pumping system including water storage tank is
recommended to be provided for water supply to Sepinang area. It is also to avoid any
alteration to the proposed Beladin water supply system which may impede the
construction progress.
The recommended water supply system for the project area is shown in Figure 3 as
Option 1. The water from the new Beladin booster station will be channelled to the
The water is then gravitated to the project area through proposed 12km 280mm
diameter HDPE pipe running along existing Jalan Maludam-Pusa until Kpg Sepinang for
delivery of water to the settlement located along the road and for fire fighting purpose.
From the projected water demand as shown in the Table 2 above, the demand at Year
2046 is about 0.6mld (417 litre/min). However, based on JKR design guideline, for
residential scheme, the water supply system shall also designed to cater for Class D risk
of fire flow requirement which is 1140 litre/min. Based on this, the fire flow requirement
is governing the design of water supply system to the project area. In order to meet the
fire flow requirement and to satisfy the minimum residual pressure head of 10m as
stipulated in JKR design guideline, the available pressure head at the tapping source shall
be high enough to ensure delivery of the required flow with sufficient pressure through
proposed pipeline to the discharge point. The flow hydraulic analysis of the proposed
pipeline system is shown in the Diagram 4.
Diagram 3 - Hydraulic Analysis Diagram for Water Supply from New Pusa Reservoir to
Pusa and Beladin with Sepinang Demand included (Peak Hour Flow)
Diagram 4 - Hydraulic Analysis Diagram for Proposed Water Supply System (Option 1)
from Proposed Reservoir to Sepinang (ADD & Fire Flow)
As the level of existing high level tank at Beladin is about 17m which is insufficient to
provide the required head of 25m as indicated in the Diagram 4, the proposed system is
not recommended to connect directly to the existing pipeline system at Beladin.
However, it is proposed to draw water from new Beladin water supply system as
mentioned above by providing booster station, ground suction tank and elevated water
storage tank with sufficient height to meet the required pressure head. The proposed
height and capacity of elevated tank are 25m and 0.6ml respectively to provide 1-day
The proposed booster station is recommended to be located within the new Beladin
booster station site as the land acquisition is not required and space is adequate. The
layout of the proposed booster station as shown in Figure 3 consists of one (1) pump
house for pump room, generator room & main switch board room, one (1) ground
suction tank and one (1) elevated reservoir. The ground tank is sized to be 50m3 comply
with the two (2) hours pumping storage requirement. Whereas, the elevated reservoir will
have 0.6ML capacity for one day storage.
In addition, branch off pipeline from the main pipeline to all the kampungs and
communication pipe of maximum length of 50m up to meter stand for each household
will be provided. The pipeline shall be laid along the access road to the kampungs. The
communication pipe shall be a combination of 90mm and 25mm HDPE pipe.
In conclusion, it is anticipated that the full scope of works for this project based on
Option 1 shall include but not limited to the following:-
f) M&E works.
The estimated construction cost is about RM9.24mil (excluding 6% GST) as shown in
Section 6.0.
One duty and two standby booster pumps shall be installed in the proposed pump
house to pump the water from ground suction tank to the proposed elevated reservoir.
The design operating point and pumping head for the booster pumps will be confirmed
by M&E engineer upon finalisation of booster pump station.
5.3 Development Planning
Due to the budgetary constraint of the project, the development of the proposed water
supply can be implemented in two phases as outlined in Option 2. For the immediate
planning of supplying water to the project area, the proposed 280mm diameter HDPE
supply system. The estimated length of this pipeline is about 11.5km. Based on hydraulic
modelling shown in Diagram 5, the proposed pipeline can cater at least up to Year 2025
demand.
section shall be constructed including approximately 0.5km length 280mm HDPE pipe to
be laid from the proposed booster station to connect to the proposed 11.5km 280mm
HDPE pipeline implemented in Phase 1.
The estimated construction costs (excluding 6% GST) for Phase 1 and Phase 2 are shown
in Section 6.0 amounting to RM4.79mil and RM4.45mil respectively.
Diagram 5 - Hydraulic Analysis Diagram for Water Supply from New Pusa Reservoir to
Pusa, Beladin and extended to Sepinang (Option 2) (Peak Hour Flow)
Alternatively, the consultant has looked into Option 3 which is a long term solution for
water supply system to Sepinang with cheaper construction cost as compared to Option
1. This option involves direct pumping to Sepinang with booster station to be provided
at the new Beladin booster station as mentioned in Section 5.1. The elevated reservoir is
not required in this option but bigger ground suction tank of 0.6ML capacity for one day
storage is required. However, there is a possibility that the project area may experience
water interruption due to electrical power supply. The proposed booster station is not
recommended to be sited at new land along the way to Sepinang to avoid land
acquisition process which is time consuming and if sited on existing booster station site,
only siting application is required. The proposed water supply system for the project area
(Option 3) is shown in Figure 5. The estimated construction costs (excluding 6% GST) for
this option is shown in Section 6.0 amounting to RM8.04mil.
Project
Option 1 Option 2 Option 3
Component