The procedure, documents checklist, and processing timeline for obtaining NOC are
given in the table below.
4 Procedure & a) The applicant will have to submit all documents mentioned
below to the corresponding approving authority.
Documents
Required Height of building up to 17.00 mts:
http://www.tnfrs.tn.nic.in/Annendix%20III%20-
%20Non%20MSB.pdf
i. Site Plan
v. Section drawing
i. Site Plan
v. Section drawing
The procedure, documents checklist, and processing timeline for obtaining Fire License
are given in the table below.
3 Approving Height of building upto 17.00 mts: District Officer, Fire and
Authority Rescue Services Department
4 Procedure & a) The applicant will have to submit all documents mentioned below
Documents to the corresponding approving authority.
Required
Height of building upto 17.00 mts:
1. Requisition Letter addressed to Approving Authority with the
signature of authorised signatory.
2. Copy of NOC received during Pre Establishment/ Planning
Stage.
3. Copy of any other NOC received from other Competent
Authorities such as PCB, DTCP,Labour.
Height of building above 17.00 mts/Building with more than
single basement and height may be less than 17.00mts:
1. Requisition Letter addressed to Approving Authority with the
signature of authorised signatory.
2. Copy of NOC received during Pre Establishment/ Planning
Stage.
3. Copy of any other NOC received from other Competent
Authorities such as PCB, DTCP, Labour.
4. Copy of following plans approved by the concerned Competent
Authority along with their covering letter:
i. Site Plan
5 Processing 15 days
Time