Professional Documents
Culture Documents
Technical principles for turbine rotor high-speed dynamic
balancing
2010-05-01 2010-05-01
Issued on May 1, 2010 Implemented on May 1, 2010
Issued by Harbin Turbine Company Limited
B/Z58.422010
Preface
B/Z58.422007
B/Z58.422010
Technical principle for turbine rotor high-speed dynamic
balancing
1
Scope
(50Hz 60Hz)
All values shall satisfy the requirements of drawing and the relevant
provisions and acceptable certificate shall be given before the rotor
entering the test chamber to do balancing. And workpiece shall be checked
whether it meet the following balancing requirement:
2
B/Z58.422010
aNDT
NDT (
Any rotor is not allowed to operate in the condition with temperature under
non-toughness transition temperature NDT of rotor material. This
requirement has special meaning for cold season (especial for HP/IP rotors
of steam turbine).
b 15
600rpm 20 20
If the rotor just gets into test chamber from outside with temperature below
15, it should rotate to speed at least 600 rpm and stay indoor with
temperature 20C or above at least for specified hours to meet the
requirement for rotor temperature.
out temperature stop time
7 24
-1 38
-18 52
c
3
B/Z58.422010
During the test, if the measured data at the specific speed is not stable
or the measured data with several times is quite different, the relative
operation time shall be necessary to extent at each specific speed to
measure the stable data. In addition, if the low-speed and high-speed
balancing accuracy can not meet the requirements at the same time, the
high-speed balancing shall be regarded as standard.
3.4 300MW
For the rotor with capacity of 300MW or above, when speed is over first
critical speed, before the speed is decreased, the jacking oil shall be put into
running and then the speed can be decreased to increase stability of rotor.
4 (Cleaning of bearing)
4.1 A
1h3h 35 1min2min
Tilted pad bearing: Firstly it shall be cleaned with HP forced wind to
blow, and then make the oil circulating, and the time shall be determined by
4
B/Z58.422010
the strainer conditions, and if the strainer pressure decreases, strainer shall
be cleaned, and meanwhile the circulating time for filling the oil shall be
extended; generally for 1h-3h, during oil circulation, the jacking oil can be
put into running for three to five times, and each time shall be about 1min-
2min.
4.3
After cleaning, the bearing and the horizontal split rotor prepared to
assemble shall be covered well with the gauze immediately. It shall be
careful to set the jacking oil seal ring well while installing the bearing, and
the direction of inlet and outlet shall be checked.
90
Attention: for safety, in any case, the temperature of the bearing shall
be less than 90.
5 (Cleaning and lifting for rotor )
JB/T4058
Before lifting the rotor, check the different adjustment positions and
platform trailer, and carefully clean the rotor journal surface and bearing
working surface in compliance with JB/T4058 standard, to ensure there is
no residual metal flash, burrs, welding slag, grease and rust at the rotor
journal and the blade shroud, place the rotor on pedestal bearing with
attention to the rotation direction, and try best to make it in consistence
with its own rotation direction of rotor.
6
Installation for the pedestal, bearing and connection collar
6.1 .
The rotor shall be installed strictly according to the dynamic balancing
5
B/Z58.422010
process requirements.
6.2
Clearance between bearing pad and oil retaining ring: it must
guarantee the requirements for the clearance at the top of bearing pad, and
the clearance of oil retaining ring shall be adequate.
6.3 0.05 mm
1g
for the rotor which need to be installed with connection collar, the run-
out of this rotor should no more then 0.05 mm, and connection screw must
be weighted, and weight difference shall be within 1g.
7
Inspection after rotor installation
7.1
The spare power supply shall be inspected and started, and the
supplying power operation time shall be not less than 6min. The automatic
switch-over performance shall be tested periodically.
8.2
Confirm the inherent critical speed, vibration mode, overspeed and
balance accuracy of rotor.
8.3 ,
The operator shall be in his work post and startup all work system and
make records at any time, for starting the rotor to conduct balancing.
9
Balance of rotor
9.1 ,
The technical data shall be input to control panel according to
7
B/Z58.422010
requirement and low speed balancing is ready.
9.2
Under the condition that equipments and instruments are in normal
state, the rotor can be startup.
9.3 30%40%
300g
9.4
90 60 32
9 6 36
10 7 48 12
8
30%-40% of first critical speed of rotor shall be regarded as low speed
balancing speed. the rotor shall be operated at low speed for a certain time
until the vibration amplitude value changes little. If the residual unbalance
weight of both plane 1 and plane 2 are about 300 g separately, and
weighting for low speed balancing is not required and record the data then
stop the machine. Otherwise, it shall execute according to item 9.4. (for the
balancing weight which balancing groove max. allowable weight is
equivalent to 90 degree arc, the allowable continuous balance weight arc is
60 degree; and max allowable No. is 9 for 32 balance hole, and max.
continuous No. is 6; and max allowable No. is 10 for 36 balance hole, and
max. continuous No. is 7; and max allowable No. is 12 for 48 balance hole,
and max. continuous No. is 8)
9.4
The balance weight shall be added complying with the records and
calculation result, and it shall speed up to this speed value and record
values until the speed value is acceptable, otherwise it shall be repeated.
Please pay attention that the distribution state of original unbalance weight
8
B/Z58.422010
shall be controlled well when low speed balancing is done, and first critical
speed and high-speed balance situation shall be also considered to avoid or
reduce the contradiction of first critical speed and high-speed in order to
make the good basis for high-speed balance.
9.5 : 100200r/min
, 8.3 9.6
The data at the proper speed shall be selected as the data used for
balance calculation, and input the computer balance program to conduct the
relative calculation. The weights add adjustment shall be conducted on the
basis of calculation result and actual situation. We must be careful when we
add weights on couple.
9.6.2
balancing accuracy requirement of flexible rotor
a) 200MW
VB VC
The turbine unit with capacity of 200MW or below: it is defined that
the average square root VB (working speed) of bearing vibration speed and
VC (critical speed) are used to evaluate its balancing accuracy.
VB2.5mm/sVC2.8mm/s
VB1.5mm/sVC1.8mm/s
200MW
Steam turbine for power generation: VB2.5mm/sVC2.8mm/s
Industrial steam turbine: VB1.5mm/sVC1.8mm/s
9
B/Z58.422010
b) 300MW
115%-120% 115%
120% 10
60Hz 112%
115%
10
B/Z58.422010
Overspeed is 112%-120% of rated speed, under any condition, the
speed of rotor shall not be allowed to exceed 120% of rated speed. The
speed of rotor for overspeed test in the workshop shall not be allowed to
repeatly exceed 15% of rated speed (max. calculated speed), the overspeed
exceeding 15% of rated speed shall be done only once, and within the
speed up range of 115% -120% of rated speed, the final overspeed value
shall be decided by the vibration condition of rotor in the process, and
within the speed range of 115% -120% of rated speed, the speed shall not
be allowed to stop, and the accumulated time from 115% to 120% of rated
speed for overspeed process shall be never allowed to exceed 10 min.
The overspeed of the 60Hz turbine rotor is 112% of rated speed, and
max. speed shall not be allowed to exceed 115% of rated speed.
9.8
Balancing at rated speed after overspeed
1 min
500
9.5 9.6
Before overspeed, if the vibration during speed up and of rated speed
is acceptable, then decrease the speed to rated after overspeed, and hold
stable running for 1min, and the record data, shutdown. If there is one item
of vibration is not acceptable before over speed and rated speed, and the
vibration data after overspeed and during speed decreased to rated is
acceptable, and re-speed up to rated speed when the speed decreased to
500rpm, if all vibration data is acceptable, that means rotor balancing
complete. If one of the vibration data before overspeed and rated is not
acceptable, and it is still not acceptable after overspeed until speed
decreases to zero, clause 9.5 and 9.6 shall be followed until the requirement
11
B/Z58.422010
is met.
9.9
Speed down and shutdown
,
Be sure that the balance weight on rotor is same as in record, and lock
balance weight according to requirement of drawing, and inform the shift
responsible person after the weight is locked.
12
B/Z58.422010
10.2
( B)
To settle the test data and diagram, and fill the test report, the test report
can come into effective after signature of related personnel and department
seal (see Appendix B), and keep them in archive.
11
Dismantle rotor
:
To release the balancing state and note the followings while
dismantling rotor.
After lifting the rotor, the bearing and oil inlet shall also be covered
well with the coated abrasive or clean cloth. If have possibility, the upper
cover shall be timely packed well.
12
Field cleaning and rotor delivery inspection
12.1
To clean chamber, pedestal, bearing and oil retaining ring, etc.
12.2
To shut off all power in the chamber, and close the door.
12.3
To submit the rotor and test reports to related department for inspection.
All balancing procedures end.
13
Usage and Maintenance of Equipments
13
B/Z58.422010
A (Appendix A)
(Harbin Turbine Company, Ltd.)
Technical Requirements and Records for Installation of Rotor (high speed balancing)
Rotor description Drawing No.
Heat No. Job No.
Connection end of rotor ,
Span of platform trailer Universal joint No.
Bearing I II
1 3
Oil retaining ring
2 4
I II
Set value Set value
mm mm
I II
Measured value Measured value
Operator Operator
1 2 3 4
Universal
joint
Upper cover of bearing I II
I II
Pedestal anchor erector
I II
Pedestal oil pipe erector
Run out
Connection disk Erector Barring inspection
Remarks
14
B/Z58.422010
B (Appendix B)
(Harbin Turbine Company, Ltd.)
Test report for the dynamic balancing of rotor
Product description Rotor Drawing No.
description
Job No. Heat No. Test date
(Technical data )
Balance speed Overspeed Overspeed time
r/min
r/min
Calculation of first critical Measurement of first critical
speed speed
(High-speed dynamic balancing test)
mm/s
Allowable value of bearing vibration at working speed
I: mm/s : mm/s
Residual value of bearing vibration at working speed
mm/s
Allowable value of first critical bearing vibration
I: mm/s : mm/s
Residual value of first critical bearing vibration
(Weights add situations )
Weights add positions Total weight Total quantity
Balancing result
Recorded by Checked by Chief director
15