Professional Documents
Culture Documents
Construccin
IMPORTANT:
4 Product description
6 System components
12 Assembly instructions
24 Disassembly instructions
28 Technical solutions
32 Safety elements
36 System features
Safety note
38 Applications
42 Receiving, storing and cleaning Control note
64 Our products
RAPID Horizontal Formwork
Product description
The RAPID recoverable modular formwork system is used in reinforced concrete slabs, lost pile
grid slabs, joist and vaults slabs, hanging beams, etc.
Continual formwork assures the safety of the workers both while assembling the plywood and
while putting up the joist and vaults.
Assembly can be executed without the need to use any tools other than a hammer.
There are two types of main beams; therefore it has two variants of the system: RAPID 1 m and
RAPID 0.67 m.
System elements are very durable, due to the system design and the robust materials of which it is
manufactured with surface finishes coated in epoxy paint.
The main beams used together with the props or shoring towers, comprise the Remaining
Structure of the RAPID system, while all other elements constitute the Recoverable Materials.
After concrete is poured, the recoverable materials (boards, secondary beams and recoverable
heads) can be recuperated within 3 days to be reused.
Installing board with nets under slab avoid any fall at different levels.
It is not necessary to reprop the shoring or to move the props from the time the structure is
assembled until it is completely dismantled.
Open grids, with a standard opening of 2 m, achieve highly efficient assembly processes and leave
enough space through which vehicles and mobile towers can pass.
Flexible system
Can be adapted to different geometrical shapes with varying grid dimensions, using
different dimensions of main beams and changing the direction of the grid.
To infill against columns and walls.
To provide solutions in perimeter areas with the cantilever running in the direction of the
secondary beam and with the main beam running lengthwise.
Few props per m2; can easily be reinforced to permit pouring thick slabs by either reducing the
width of the grids or by incorporating more props.
Structure can be shored with props or shoring towers.
The whole steel structure can be assembled on one side, and the plywood can then be put
up by the same or different work crews.
Safe system
Easy to incorporate handrail protection around the perimeter and holes.
Board installation can be safely executed from mobile towers positioned in the open grids,
from above after having hung nets under the formwork or with workers tied off to lifelines
between columns.
Board is installed between the main beams and the secondary beam tabs, which lock it in
place impeding its movement without the need to nail it down.
4
Construccin
5
Construccin
RAPID Horizontal Formwork
System components
The main components of the system are:
The first three elements are used to form the steel Formwork can be shored with any type of prop in our
structure, and the board is installed on top of the product range, as well as with the G Shoring,
structure, serving as the base of the formwork. depending on the height and load required.
The heads, secondary beams and board make up the The main beams, together with the prop or shoring,
recoverable structure of the system, designed so that in comprise the remaining structure of the RAPID system.
less than 72 hours after pouring the concrete, the
plywood can be reused. By replacing only the main beams with support beams,
the same components can be used for the construction
The design of edge secondary beams, where support of hanging beams, which are frequently used in slabs
the boards, prevents them slipping. or beams free from mixed slabs (poured on site +
prefabricated). G Shoring is used for shoring, and the
cross brace is selected as a function of beam thickness
and weight.
6
Construccin
RAPID Horizontal Formwork
BOARD
Trimax
TRIMAX is a high quality 3 layer plywood comprising
three layers of spruce wood in which the outside layers
run lengthwise while the inside layer runs crosswise.
Tri
TRI is a 3 layer plywood comprising three layers of
select softwoods (spruce or pine) in which the outside
layers run lengthwise while the inside layer runs
crosswise.
7
Construccin
RAPID Horizontal Formwork
SP PROP
The SP Prop has been designed for shoring horizontal There are five types of props available in the SP range
formwork systems, and other shoring requirements that of props:
may arise on construction site. It is known for its special Normal Prop
design, which permits regulating and securing at Strong Prop
specific heights thus permitting a fast approximation of SP-34 Prop
the height of the element to be shored. A threaded nut SP-40 Prop
is used to make the fine adjustment. The epoxy resin SP-50 Prop
coating techniques give it an effective anti-rust Customers can select the most appropriate of these props
protective coating. for each need based on the load and height requirements.
For making the proper selection, the working loads (kN)
charts are attached.
NORMAL PROP STRONG PROP SP-34 SP-40 SP-50
Height (m) 1.75-3.10 2.10-3.50 2.10-3.65 2.35-4.00 3.65-5.25 2.00- 3.40 2.50-4.00 3.90-5.00
1.75 23.00
1.80 23.00
1.90 23.00
2.00 23.00 26.00
2.10 23.00 23.00 26.00 26.00
2.20 21.71 22.57 26.00 26.00
2.30 20.43 22.14 26.00 26.00
2.35 19.79 21.93 26.00 22.50 26.00
2.40 19.14 21.71 26.00 22.50 26.00
2.50 17.64 20.50 26.00 22.50 26.00 28.00
2.60 15.93 18.50 26.00 22.50 26.00 28.00
2.70 14.21 16.50 26.00 22.50 25.30 28.00
2.80 12.50 14.50 26.00 22.38 24.00 28.00
2.90 11.17 13.33 24.83 22.25 22.50 28.00
3.00 9.83 12.17 23.67 22.13 21.00 28.00
3.10 8.50 11.00 22.50 22.00 19.30 28.00
3.20 10.36 20.83 21.32 17.50 28.00
3.30 9.72 19.31 20.64 16.50 27.00
3.40 9.08 17.94 19.95 15.80 26.00
3.50 8.44 16.56 19.27 25.00
3.60 15.19 18.59 24.00
3.65 14.50 18.25 15.00 23.25
3.70 17.57 14.66 22.50
3.80 16.21 13.97 21.00
3.90 14.86 13.28 19.50 22.00
4.00 13.50 12.59 18.00 22.00
4.10 12.06 22.00
4.20 11.67 22.00
4.30 11.29 22.00
4.40 10.90 22.00
4.50 8.44 22.00
4.60 8.16 22.00 For further information, see the
4.70 7.88 21.63
SP Prop Catalogue
4.80 7.60 21.25
4.90 7.10 19.88
5.00 6.60 18.50
5.10 6.10
5.20 5.60
5.25 5.40
SP Prop
is vertically centered.
8
Construccin
RAPID Horizontal Formwork
ALUPROP PROP
The light ALUPROP Prop supports very high load
capacities and it is manufactured in aluminium.
This prop is certified by the German Institute, SIGMA
KARLSRUHE GMBH.
ALUPROP 4.5-6
6.20 18.10
6.30 17.60
6.40 17.30
6.50 16.90 Construccin
6.60 16.30
6.70 15.50
6.80 14.70
6.90 13.90
7.00 13.10
9
Construccin
RAPID Horizontal Formwork
G SHORING
The G Shoring system is used to support horizontal
formwork when that formwork exceeds the maximum
height that can be reached by the props.
Linked towers, built using Frames For further information, see the
G-100 1.85 m, braced with crossbraces G Shoring Catalogue
and with jacks extended to a maximum
of 65 cm (H: total height of the shoring):
0<H 10 m Working load per leg:
20 kN
Independent towers, built using
Frames G-100 1.85 m and with jacks
extended to a maximum of 65 cm:
Working load per leg: 12 kN
10
Construccin
RAPID Horizontal Formwork
11
Construccin
RAPID Horizontal Formwork
Assembly instructions
12
Construccin
RAPID Horizontal Formwork
13
Construccin
RAPID Horizontal Formwork
14
Construccin
RAPID Horizontal Formwork
15
Construccin
RAPID Horizontal Formwork
16
Construccin
RAPID Horizontal Formwork
17
Construccin
RAPID Horizontal Formwork
2. Cantilevers shoring
2. Cantilevers shoring
Once the cantilevers are in place,
assemble the corresponding props.
18
Construccin
RAPID Horizontal Formwork
19
Construccin
RAPID Horizontal Formwork
G Shoring
Construccin
Install the Base jacks and the Heads 55 at the top of the shoring to support the formwork. If shoring a support
beam, the Head 70 should be used.
20
Construccin
RAPID Horizontal Formwork
Once the G Shoring is assembled, install the RAPID Formwork as described in the
corresponding section of this catalogue. The main beams should be assembled on the Heads
55, which were installed on the top of the shoring.
correct
wrong
21
Construccin
RAPID Horizontal Formwork
3. Bracing
22
Construccin
RAPID Horizontal Formwork
4. Beams shoring
Concrete beams are shored using the Support beam. The Support beam is assembled
perpendicular to the hanging beam and it facilitates reinforcing the board with more
Secondary Beams under the hanging beam. Once stripping is complete, the Support beam
remains as a shoring element.
Support beam
Secondary beams
23
Construccin
RAPID Horizontal Formwork
Disassembly instructions
In phase one, the third day after pouring the slab, dismantle the recoverable material (heads, secondary beams, 3
layer plywood). The main beams along with the props or shoring should remain supporting the slab.
In phase two (at 21 days, 28 days or at the time required in accordance with the technical specifications provided
specifically for the structure's slab and in the execution timeframes for the structure), remove the Main beams that
were supported with the props or shoring system.
1 From the ground or from a mobile tower, release the heads along one row of main beams. Strike the wedge on
each head with a hammer to free it up from the position where it is tied to the lug on the main beams.
24
Construccin
RAPID Horizontal Formwork
4 After the necessary time has passed, proceed to recover the main beams
along with the props or shoring used.
25
Construccin
RAPID Horizontal Formwork
G Shoring disassembly
Working procedure:
Lower Base jacks from the top of the shoring using their adjustment screws to jack them down and separate them
from the formwork's main beams.
26
Construccin
RAPID Horizontal Formwork
G Shoring
Construccin
27
Construccin
RAPID Horizontal Formwork
Technical solutions
INFILLING ON COLUMN
Auxiliar head
28
Construccin
RAPID Horizontal Formwork
Auxiliar
head
Main beam
29
Construccin
RAPID Horizontal Formwork
CANTILEVER Cantilever
The Cantilever is an auxiliary component that provides a beam
working space in the edge of the formwork. Props are
used as shoring element.
Support beam
Head 55
30
Construccin
RAPID Horizontal Formwork
90 ASSEMBLY
The main beams direction can be changed with 90
90 Head
Head. This element provides appropriate solutions for
perimeter areas, irregular geometries or hanging beams
support, making formwork much more flexible.
It's valid for RAPID 1 m and 0.67 m.
Main beam
REMAINING BEAM
After stripping, the beams of the lost pile lightened
slabs (joist and vaults) must be compulsory shored. The
Remaining beams facilitate the shoring even if the
direction of the beams is not perpendicular to the main Main Beam
beams of formwork.
Remaining beam
31
Construccin
RAPID Horizontal Formwork
Safety elements
The main purpose of the RAPID Formwork safety concrete. These safety elements include Safety heads,
elements is to protect the perimeter of the formwork and Safety handrail posts, Handrail tubes and Toe boards.
any holes that are considered to pose a risk of falling to
the workers when forming, reinforcing and pouring This equipment comprises the protective elements used
to mark off and delimit the base or work surface.
The suitable distance to install the Safety heads is 2 m. The Safety heads permit standard assembly of the Secondary
beams, and they permit installing the Safety handrail post.
Installing the Safety head over the Intermediate Installing the Safety head on the Main beam on
main beam. the border or on the perimeter of the formwork.
32
Construccin
RAPID Horizontal Formwork
Once all the Safety handrail posts are installed, proceed to finish putting
up Handrail by assembling the Handrail tubes perpendicular to the Posts
and tying these with their clamps.
Toe board
33
Construccin
RAPID Horizontal Formwork
Once the formwork is fully equipped with all lateral protections, attention is now given to protect the slab borders in
the stripping phase. The Plastic handrail support is used for this purpose.
When stripping the recoverable materials, the slab protections must be put up so as to completely close off the
whole perimeter.
Tube
Safety handrail S-V
Toe board
34
Construccin
RAPID Horizontal Formwork
35
Construccin
RAPID Horizontal Formwork
System features
There are two variants of the RAPID System according to the type of the Main beam:
RAPID 0.67 m
RAPID 1 m
RAPID 0.67 m
The system can be applied to any type of work because of its flexibility and strength. With this variant of the RAPID
both props such as secondary beams are assembled every 67 cm. Sockets, to enter the props have 32 mm.
RAPID 1 m
RAPID 1 m can save up to 25% of the cost of material, particularly in the implementation of reduced thickness slabs
or lightened ones. By locating the secondary beams each 1 meter, the props can be arranged to coincide with the
interval (B layout) or every 0.5 m (A + B layout), it is possible to use lighter props and therefore cheaper ones. The
sockets are different for each layout to facilitate the proper assembly: one round, 25 mm diameter socket (B layout)
and one square, 20 mm socket (A layout).
36
Construccin
RAPID Horizontal Formwork
The following tables provide the maximum slab thicknesses with RAPID System, depending on the board and grid
dimension.
RAPID 0.67 m
BOARD SHORING SECONDARY BEAM THmax (cm) BOARD SHORING SECONDARY BEAM THmax (cm)
. .
PROP PROP
REINF 1.5 REINF 1.5
REINFORCEMENT . REINFORCEMENT .
PROP REINF 1.5 PROP REINF 1.5
. .
3 LAYER PLYWOOD 21 mm
3 LAYER PLYWOOD 27 mm
. .
REINF 1.5 REINF 1.5
SHORING
SHORING
. .
REINF 1.5 REINF 1.5
RAPID 1 m
3 LAYER PLYWOOD .
PROP
27 mm REINF 1.5
3 LAYER PLYWOOD .
PROP REINF 1.5
21 mm
3 LAYER PLYWOOD .
PROP
27 mm REINF 1.5
3 LAYER PLYWOOD .
PROP
21 mm REINF 1.5
37
Construccin
RAPID Horizontal Formwork
Applications
INFILLING ON COLUMN
Shoring with prop
This component is supported by a prop, and it serves
the same purpose as the Recoverable head. It must be
used for infilling to incorporate one or two additional Auxiliar head
supports to the board.
Secondary beam
Secondary beam
38
Construccin
RAPID Horizontal Formwork
Transversal fixation
39
Construccin
RAPID Horizontal Formwork
CANTILEVER
Using the Cantilever beam and Edge cantilever beam
allows forming beyond the projection of the slab to
make the working platform, using an inclined prop as
shoring. Cantilever beam
BEAM SHORING
The beam is shored using the Support beam. The Support beam is assembled
perpendicular to the beam and it facilitates reinforcing the board with more Secondary
Secondary beam
Beams under the hanging beam. Once stripping is complete, the Support Beam
remains as a shoring element.
Edge Secondary
beam
Support beam
40
Construccin
RAPID Horizontal Formwork
Head 55
90 ASSEMBLY
It permits changing the direction of the Main beams by 90.
90 HEAD
Main beam
41
Construccin
RAPID Horizontal Formwork
UNLOADING MATERIAL
Mechanical unload
All the material will arrive grouped and strapped.
Manual unload
Loads bigger than 25 kg will not be handled by one
person.
42
Construccin
RAPID Horizontal Formwork
STORAGE
The Main beams, the Secondary beams, the Support
beams and the Boards are supplied on properly strapped
packages. Other elements are supplied in bulk in boxes
or in pallets.
LIFTING MATERIAL
The biggest parts should be lifted or lowered by hoist to
the different floors (or different heights) in packages that
are strapped on both ends. Material shall be suspended
by slings strapped to the tower crane hook. The other
elements are moved in boxes.
CLEANING
The cleanliness of the formwork surfaces should be
checked before assembling the materials that comprise
part of the formwork. After each use, the boards should
be cleaned with release agent applying it with brush.
43
Construccin
RAPID Horizontal Formwork
Provided below is the criteria for identifying parts that, due to deformations or breakage that may occur,
are considered not valid for use because these damages imply a risk of accidents to the operators who are
handling the material or a risk of breakage to some system component when it is loaded.
Board:
Head:
Excessive deformation in
Broken or bent tab. center of Board.
Support lug on broken Wooden layers in Board
wedge. coming unglued.
44
Construccin
RAPID Horizontal Formwork
The release agent plays an important role in assuring the quality of the concrete surface. It serves
the purpose of assuring there are no surface holes and that color is uniform.
To avoid bonding between the concrete and the formwork surface, the release agent creates a
water resistant film, thus assuring that the water and the cement suspended in the surface
cannot come in contact with the formwork surface.
The properties of the release agent should be compatible with the concrete and with the
formwork on which it is going to be applied. This compatibility should comply with the following
characteristics:
It should not cause holes nor generate color variations or other surface defects.
With the objective of avoiding interactions in the concrete curing and hardening process,
it must not be soluble in water.
As well as improving the concrete surface, the release agent minimizes the damages inflicted on
the formwork surface. It also facilitates striping all types of molds and reduces residues, thus
achieving long life board surfaces.
45
Construccin
RAPID Horizontal Formwork
PRECAUTIONS
Fire
46
Construccin
RAPID Horizontal Formwork
RECOMMENDATIONS
YES
47
Construccin
RAPID Horizontal Formwork
48
Construccin
RAPID Horizontal Formwork
49
Construccin
RAPID Horizontal Formwork
GENERAL CONSIDERATIONS
Holes should be protected with covers, The formwork must be put up and
handrails, nets or meshes to prevent dismantled by competent personnel
people from falling from one level to assigned by the site manager to avoid any
another. wrong operations.
The sides of the formwork structure or Do not leave any element partially
perimeter scaffolding will have regulatory assembled.
handrails.
Properly brace the structure when it is
Use 15 cm toe boards in the perimeter assembled.
handrails.
Do not work with formwork when wind
Check formwork elements and safety speeds are in excess of 60 km/h.
elements. Replace as necessary. Confirm:
Check safety hooks and slings before
That no knocks or blows have damaged lifting or stripping the formwork.
their section.
Use suitable anchoring and certified slings
That they are not bent. and hoists when lifting.
That their attachments are correct and When moving material in slings, secure it
effective. to make sure that it does not come loose
in transit.
Check the following in timber or plastic
elements: Do not drive under hanging loads or in
areas where machinery is operating.
That they have no knocks, cracks or
knots that may reduce their resistance. Mark off and impede circulation in
working areas.
That they are properly secured to their
supports. Use tool holder belts with pockets for
small parts.
Replace as necessary.
Fit the equipment with the necessary
To access the formwork standard ladders,
mechanical lift mechanisms.
ladder turrets or regulation catwalks
should be used. Move only through signposted areas on
the working zone.
In mobile scaffolding towers, work with
the brake on and do not move them Train personnel in manual load handling.
when the worker is on top of them.
Use comfortable and safe postures when
Follow the specific procedure in the loading difficult bulky loads.
assembly and disassembly of perimeter
Manual load conveying should be carried
formwork.
out with right body positions.
Keep work areas clean and organized at
Conduct a general revision of the
all times. Leave material organized and
formwork after the assembly is complete.
stacked. Do not leave material
disorganized on the formwork or on the
ground.
50
Construccin
RAPID Horizontal Formwork
POURING CONCRETE
Prior to pouring concrete make sure: Check the state of the formwork before
undertaking any disassembly work.
That the formwork is assembled correctly,
observing the layout. The horizontal loads to be supported by
temporary building elements on site are
To install the Reinforcement props where
defined in the EN 12812:2004 standard,
necessary.
Formwork: verification requirements and
To level the formwork. general design (Section 8.2.2.2.) and are
quantified as 1% of the vertical loads, Q1 and
To steep the formwork surface with release
Q2, where Q1 are permanent loads and Q2
agent.
variable vertical loads.
To install the Plastic handrail supports along
Similarly, in this section it is considered that
the perimeter of the freshly poured concrete
these loads are transmitted to the structure
slab for the subsequent placement of Safety
through the formwork elements which,
handrail post on the slab.
attached to the structure, restrict the horizontal
During the vibration process, the vibrators will movement of the formwork.
never come in contact with the formwork to
It also indicates in a note that this effect is due
assure that the loads and overloads considered
to actions such as those caused by pumped
for each slab thickness will not be exceeded.
concrete pouring.
Avoid undue stockpiling of material as well as
The formwork is designed taking into account
accumulations and abrupt pouring of concrete.
the transfer of horizontal forces into the actual
Pouring the concrete in several phases is structure.
recommended in cases where the maximum
The horizontal load is transferred from one part
admissible thickness may be exceeded.
to another until this stress is absorbed by a
Avoid sudden emptying of the bucket on rigid element of the structure, such as a
the formwork. Pour the concrete from a height column, wall, etc. If there are no fixed points
at which rough movements will not be on the structure for bracing, the use of stable
produced in the formwork. shoring with its relevant attachments is
necessary.
The formwork should be removed only when
the concrete is strong enough.
51
Construccin
RAPID Horizontal Formwork
Main beam
Main beam 2/0,67 11 1860010
Main beam 3,35/0,67 17 1860012
Main beam 4/0,67 20.8 1860014
Secondary beam
Reinf. second. beam 1.5 9.3 1860504
Secondary beam 2 12.6 1860060
52
Construccin
RAPID Horizontal Formwork
Auxiliary components
Secondary beam
Edge secondary beam 1 5.4 1860145
Edge secondary beam 1.5 7.4 1860144
Cantilever
Cantilever 6.8 1860031
Edge cantilever beam 8.2 1860146
Board
3-layer plywood 1000 x 503 x 27 7.2 7251130
3-layer plywood 1330 x 503 x 27 9.6 1860512
3-layer plywood 2000 x 503 x 21 11.4 7251131
3-layer plywood 2000 x 503 x 27 15 7251132
53
Construccin
RAPID Horizontal Formwork
Support beam
Support beam 1 14 1860510
Support beam 1,34 18.6 1860497
Support beam 2,2 24.6 1860513
54
Construccin
RAPID Horizontal Formwork
Safety elements
Safety head 1.5 1860518 Tube 42/4070 with socket 8.4 2023800
Coupler
Right angel coupler 42/42 1.2 2012600
Swivel Coupler 42/42 1.3 2012400
Safety handrail 1.5 9.6 2211156
Tube 42
Tube 42/0.5 1 2033300
Tube 42/1 2 2033500
Tube 42/1.55 3 2033700
Tube 42/2.1 4.1 2033800
Tube 42/3.1 6.4 2034000
55
Construccin
RAPID Horizontal Formwork
Safety net
Safety net 1 x 10 1.7 1860708
Safety net 1.5 x 10 2.5 1860660
Safety net 2 x 10 3.3 1860657
1100
Tube 48/4100 with socket 13.14 2125649 10000
1500
10000
2100
10000
Coupler 48
Swivel coupler 48/48 1.3 2125147
Right angel coupler 48/48 1.2 2125148
56
Construccin
RAPID Horizontal Formwork
ALUPROP Prop
ALUPROP 1.65/2.8 17.4 2220010
ALUPROP 2.2/3.7 21.4 2220020
ALUPROP 3.3/4.8 25.1 2220030
ALUPROP 4.5/6 29.2 2220040
57
Construccin
RAPID Horizontal Formwork
G Shoring
WEIGHT (KG) CODE WEIGHT (KG) CODE
Base jack
Base jack 0.5 3.2 2000600
Base jack 1 6.2 2000700
Head
Head 55 1.2 1860088
Head 70 1.9 1860500
58
Construccin
RAPID Horizontal Formwork
Frame Platform
Frame G-100 1 12.5 2003300 Platform G 1.065 7.69 1860580
Frame G-100 1.55 13.4 2003500 Platform G 1.57 11.23 1860572
Frame G-100 1.85 15.5 2003600 Platform G 2.075 15 1860582
Extending platform
Extending platform 1-1.5 12.5 2067035
Extending platform 1.5-2.35 17.3 2067048
Extending platform 2-2.7 20.5 2067043
Crossbrace
Two-coloured crossbrace 1 3.9 1860507
Two-coloured crossbrace 1.5 4.8 1860101
Two-coloured crossbrace 2 5.8 1860107
Two-coloured crossbrace 1.5/0.75 4.2 1860098
Two-coloured crossbrace 2/0.75 5.4 1860104
59
Construccin
Production Plant
ULMA C y E, S. Coop.
Ps. Otadui, 3 - P.O. Box 13
20560 OATI (Guipzcoa)
SPAIN
Phone: + 34 943 034900
Fax: + 34 943 034920
www.ulma-c.com
ULMA Worldwide
EUROPE IDF chafaudages Branch Tarnos Branch Poland
22 Bis, rue Gustave Eiffel 40, rue de lIndustrie ULMA Construccion Polska S.A.
Germany
Z.I. de la Marinire Z.I. de Tarnos 03-115 WARSAW
ULMA Betonschalungen 91070 BONDOUFLE 40220 TARNOS ul. Klasykw 10
und Gerste GmbH Phone: + 33 1 69 11 63 30 Phone: + 33 5 59 64 44 45 Phone: + 48 22 506 70 00
Paul-Ehrlich-Strae 8 Fax: + 33 1 69 11 63 31 Fax: + 33 5 59 64 44 84 Fax: + 48 22 814 31 31
D-63322 RDERMARK www.ulma-c.pl
Phone: + 49 6074 9294 0 IDF Construction Branch Lons Branch
Fax: + 49 6074 9294 101 27, rue Gustave Eiffel 9, Avenue Larregain WSCHD REGION
www.ulma-c.de Z.I. de la Marinire Z.I. du Monhauba WARSZAWA Branch
91070 BONDOUFLE 64140 LONS
Nordwest Branch Phone: + 33 1 69 11 63 40 Phone: + 33 5 59 62 71 97 Warszawa Office
Stresemannallee 4c Fax: + 33 1 69 11 63 37 Fax: + 33 5 59 13 84 33 03-197 WARSAW
D-41460 NEUSS ul. Laurowa 39
Phone: + 49 2131 40201 0 Eguilles Branch Italy Phone: + 48 22 506 72 50
Fax: + 49 2131 40201 99 50, alle Meulire ALPI, S.P.A. Fax: + 48 22 747 19 16
Z.I. - Route de Berre Zona Industriale Est
Sdwest Branch 13510 EGUILLES I-39035 MONGUELFO (BZ) Olsztyn Office
Manfred - Wrner - Str. 115 Phone: + 33 4 42 64 62 30 Phone: + 39 0474 947 400 10-467 OLSZTYN
D-73037 GPPINGEN Fax: + 33 4 42 64 62 31 Fax: + 39 0474 947 499 ul. Sprztowa 3, lok. 18
Phone: + 49 7161 50608 42 www.alpionline.net Phone: + 48 89 537 73 10
Fax: + 49 7161 50608 43 Saint Herblain Branch Fax: + 48 89 532 04 95
11, rue Fondeur Kazakhstan
France Z.I. du Tisserand ULMA Kazakhstan LUBLIN Branch
ULMA, S.A.R.L. 44800 SAINT HERBLAIN 01000 ASTANA Lublin Office
27, rue Gustave Eiffel Phone: + 33 2 51 80 48 04 6/2, Tashenova St. 4th floor, offices 7,9 20-327 LUBLIN
Z.I. de la Marinire Fax: + 33 2 51 80 48 05 Phone:/Fax: + 7 7172 58 05 19 ul. Wroska 2
91070 BONDOUFLE Phone: + 7 7172 37 93 48 Phone: + 48 81 749 72 90
Phone: + 33 1 69 11 54 50 La Chapelle www.ulma-c.kz Fax: + 48 81 744 04 90
Fax: + 33 1 69 11 54 54 dArmentires Branch
www.ulma-c.fr Zone Industrielle Biaystok Office
Rue Andr Ampre 15-100 BIAYSTOK
59930 LA CHAPELLE ul. 1. Armii Wojska Polskiego 9, lok. 203
DARMENTIRES Phone: + 48 85 676 73 00
Phone: + 33 3 20 07 11 86 Fax: + 48 85 675 06 53
Fax: + 33 3 20 07 11 68
60
Construccin
ZACHD REGION Nowa Sl Office Porto Branch Ukraine
POZNA Branch 67-100 NOWA SL Zona Industrial da Feiteira ULMA Formwork Ukraine Ltd.
61-317 POZNA ul. Kociuszki 29 Rua das Casas Queimadas 01013 KIEV
ul. Ostrowska 484 Phone: + 48 68 376 77 60 717 Grij 3, Derevoobrobna St.
Phone: + 48 61 838 75 30 Fax: + 48 68 387 02 21 wew. 357 4415-439 VILA NOVA DE GAIA Phone: + 380 44 255 14 92
Fax: + 48 61 863 01 60 PORTO Fax: + 380 44 255 14 94
POUDNIE REGION Phone: + 351 227 418 820 www.ulma-c.com
BYDGOSZCZ Branch KRAKW Branch Fax: + 351 227 418 829
61
Construccin
Production Plant
ULMA C y E, S. Coop.
Ps. Otadui, 3 - P.O. Box 13
20560 OATI (Guipzcoa)
SPAIN
Phone: + 34 943 034900
Fax: + 34 943 034920
www.ulma-c.com
ULMA Worldwide
62
Construccin
ULMA in Spain
63
Construccin
RAPID Horizontal Formwork
Our products
Horizontal Formworks
RAPID Recoverable VR Table
Formwork Horizontal formwork for any
Formwork that can be easily slab type
and quickly recovered from
assembly
CC-4 Horizontal
Formwork
Aluminium horizontal
formwork, light, fast setting
and stripping
64
Construccin
RAPID Horizontal Formwork
Notes
65
Construccin
RAPID Horizontal Formwork
Notes
66
Construccin
ULMA C y E, S. Coop.
E00CBS11