You are on page 1of 68

RAPID Horizontal Formwork

Construccin
IMPORTANT:

Any safety provisions as directed by the appropriate governing


agencies must be observed when using our products.

The pictures in this brochure are snapshots of situations at


different stages of assembly, and therefore are not complete
images. For the purpose of safety, they should not be deemed
as definitive.

All of the indications regarding safety and operations


contained in this brochure, and the data on stress and loads
should be respected. ULMA Construccins Technical
Department must be consulted anytime that field changes
alter our equipment installation drawings.

Our equipment is designed to work with accessories and


elements made by our company only. Combining such
equipment with other systems is not only dangerous but also
voids any or all our warrantees.

The company reserves the right to introduce any modifications


deemed necessary for the technical development of the
product.

All rights reserved


Neither all nor part of this document may be reproduced or
transmitted in any way by any electronic or mechanical
procedure, including photocopy, magnetic recording or any
other form of information storage or retrieval system without
the written permission of ULMA Construccin.

National Book Catalogue Number: SS-889-2009


RAPID Horizontal Formwork

4 Product description
6 System components
12 Assembly instructions
24 Disassembly instructions
28 Technical solutions
32 Safety elements
36 System features
Safety note
38 Applications
42 Receiving, storing and cleaning Control note

47 General safety tips


Warning note
52 Components and accessories
60 ULMA Construccin addresses Information note

64 Our products
RAPID Horizontal Formwork

Product description
The RAPID recoverable modular formwork system is used in reinforced concrete slabs, lost pile
grid slabs, joist and vaults slabs, hanging beams, etc.
Continual formwork assures the safety of the workers both while assembling the plywood and
while putting up the joist and vaults.
Assembly can be executed without the need to use any tools other than a hammer.
There are two types of main beams; therefore it has two variants of the system: RAPID 1 m and
RAPID 0.67 m.
System elements are very durable, due to the system design and the robust materials of which it is
manufactured with surface finishes coated in epoxy paint.
The main beams used together with the props or shoring towers, comprise the Remaining
Structure of the RAPID system, while all other elements constitute the Recoverable Materials.
After concrete is poured, the recoverable materials (boards, secondary beams and recoverable
heads) can be recuperated within 3 days to be reused.
Installing board with nets under slab avoid any fall at different levels.
It is not necessary to reprop the shoring or to move the props from the time the structure is
assembled until it is completely dismantled.
Open grids, with a standard opening of 2 m, achieve highly efficient assembly processes and leave
enough space through which vehicles and mobile towers can pass.
Flexible system
Can be adapted to different geometrical shapes with varying grid dimensions, using
different dimensions of main beams and changing the direction of the grid.
To infill against columns and walls.
To provide solutions in perimeter areas with the cantilever running in the direction of the
secondary beam and with the main beam running lengthwise.
Few props per m2; can easily be reinforced to permit pouring thick slabs by either reducing the
width of the grids or by incorporating more props.
Structure can be shored with props or shoring towers.
The whole steel structure can be assembled on one side, and the plywood can then be put
up by the same or different work crews.
Safe system
Easy to incorporate handrail protection around the perimeter and holes.
Board installation can be safely executed from mobile towers positioned in the open grids,
from above after having hung nets under the formwork or with workers tied off to lifelines
between columns.
Board is installed between the main beams and the secondary beam tabs, which lock it in
place impeding its movement without the need to nail it down.

4
Construccin
5
Construccin
RAPID Horizontal Formwork

System components
The main components of the system are:

Main beam Secondary beam

Recoverable head Board

The first three elements are used to form the steel Formwork can be shored with any type of prop in our
structure, and the board is installed on top of the product range, as well as with the G Shoring,
structure, serving as the base of the formwork. depending on the height and load required.

The heads, secondary beams and board make up the The main beams, together with the prop or shoring,
recoverable structure of the system, designed so that in comprise the remaining structure of the RAPID system.
less than 72 hours after pouring the concrete, the
plywood can be reused. By replacing only the main beams with support beams,
the same components can be used for the construction
The design of edge secondary beams, where support of hanging beams, which are frequently used in slabs
the boards, prevents them slipping. or beams free from mixed slabs (poured on site +
prefabricated). G Shoring is used for shoring, and the
cross brace is selected as a function of beam thickness
and weight.

6
Construccin
RAPID Horizontal Formwork

BOARD

The board commonly used to form the RAPID system's


shuttering face is the 3 layer plywood. Users can
choose between TRIMAX and TRI qualities.

Trimax
TRIMAX is a high quality 3 layer plywood comprising
three layers of spruce wood in which the outside layers
run lengthwise while the inside layer runs crosswise.

Available manufactured thicknesses: 21 and 27 mm.

TRIMAX is resistant to boiling water and atmospheric


conditions. It is bonded with an AW 100 type bond in
accordance with NORM B3023. The outside surface is
coated with 130 g/m2 synthetic yellow melamine resin
coating, and the edges are sealed.

The inside sheets are bonded over their whole surface,


sanded and calibrated, thus assuring uniform thickness
for all TRIMAX sheets.

Due to its high quality it has a high durability.

Tri
TRI is a 3 layer plywood comprising three layers of
select softwoods (spruce or pine) in which the outside
layers run lengthwise while the inside layer runs
crosswise.

The sheet is bonded with an AW100 type bond in


accordance with NORM B3023.

Available manufactured thicknesses: 21 and 27 mm.


The outside surface is coated with 120 g/m2 synthetic
yellow melamine resin coating, and the edges are
sealed.

7
Construccin
RAPID Horizontal Formwork

SP PROP
The SP Prop has been designed for shoring horizontal There are five types of props available in the SP range
formwork systems, and other shoring requirements that of props:
may arise on construction site. It is known for its special Normal Prop
design, which permits regulating and securing at Strong Prop
specific heights thus permitting a fast approximation of SP-34 Prop
the height of the element to be shored. A threaded nut SP-40 Prop
is used to make the fine adjustment. The epoxy resin SP-50 Prop
coating techniques give it an effective anti-rust Customers can select the most appropriate of these props
protective coating. for each need based on the load and height requirements.
For making the proper selection, the working loads (kN)
charts are attached.
NORMAL PROP STRONG PROP SP-34 SP-40 SP-50
Height (m) 1.75-3.10 2.10-3.50 2.10-3.65 2.35-4.00 3.65-5.25 2.00- 3.40 2.50-4.00 3.90-5.00
1.75 23.00
1.80 23.00
1.90 23.00
2.00 23.00 26.00
2.10 23.00 23.00 26.00 26.00
2.20 21.71 22.57 26.00 26.00
2.30 20.43 22.14 26.00 26.00
2.35 19.79 21.93 26.00 22.50 26.00
2.40 19.14 21.71 26.00 22.50 26.00
2.50 17.64 20.50 26.00 22.50 26.00 28.00
2.60 15.93 18.50 26.00 22.50 26.00 28.00
2.70 14.21 16.50 26.00 22.50 25.30 28.00
2.80 12.50 14.50 26.00 22.38 24.00 28.00
2.90 11.17 13.33 24.83 22.25 22.50 28.00
3.00 9.83 12.17 23.67 22.13 21.00 28.00
3.10 8.50 11.00 22.50 22.00 19.30 28.00
3.20 10.36 20.83 21.32 17.50 28.00
3.30 9.72 19.31 20.64 16.50 27.00
3.40 9.08 17.94 19.95 15.80 26.00
3.50 8.44 16.56 19.27 25.00
3.60 15.19 18.59 24.00
3.65 14.50 18.25 15.00 23.25
3.70 17.57 14.66 22.50
3.80 16.21 13.97 21.00
3.90 14.86 13.28 19.50 22.00
4.00 13.50 12.59 18.00 22.00
4.10 12.06 22.00
4.20 11.67 22.00
4.30 11.29 22.00
4.40 10.90 22.00
4.50 8.44 22.00
4.60 8.16 22.00 For further information, see the
4.70 7.88 21.63
SP Prop Catalogue
4.80 7.60 21.25
4.90 7.10 19.88
5.00 6.60 18.50
5.10 6.10
5.20 5.60
5.25 5.40
SP Prop

This data is appropriate to be used for


new, plumbed props for which the load Construccin

is vertically centered.

8
Construccin
RAPID Horizontal Formwork

ALUPROP PROP
The light ALUPROP Prop supports very high load
capacities and it is manufactured in aluminium.
This prop is certified by the German Institute, SIGMA
KARLSRUHE GMBH.

Supplement 1 m can be connected on ALUPROP 4.5-6


prop, making it possible to achieve heights of 7 m
without bracing the props. The Supplement 1 m will be
fixed to outer tube of the ALUPROP Prop with
ALUPROP clamp.

The following table shows the working loads (kN) of


ALUPROP 4,5-6 with and without supplement.
In both cases, consider the inner tube down.

ALUPROP 4.5-6

h (m) Without supplement With supplement


4.50 47.10
4.60 45.70
4.70 44.20
4.80 42.80
4.90 41.40
5.00 40.00
5.10 38.60
5.20 37.20
5.30 35.80
5.40 34.40
5.50 33.00 21.60
5.60 31.60 20.90 For further information, see the
ALUPROP Users Guide
5.70 30.20 20.20
5.80 28.80 20.10
5.90 27.50 19.60
Users guide

6.00 26.10 19.10


6.10 18.50 ALUPROP
Prop

6.20 18.10
6.30 17.60
6.40 17.30
6.50 16.90 Construccin

6.60 16.30
6.70 15.50
6.80 14.70
6.90 13.90
7.00 13.10

This data is appropriate to be used


SIGMA KARLSRUHE
for new, plumbed props for which
the load is vertically centered.

9
Construccin
RAPID Horizontal Formwork

G SHORING
The G Shoring system is used to support horizontal
formwork when that formwork exceeds the maximum
height that can be reached by the props.

The system structure basically comprises its frame.


These frame elements are assembled one on top of
another until reaching the desired height, using the
different frame heights in combination with the base
jacks.

This shoring system has different heads that facilitate


shoring the main beams or the support beams as
necessary.

The following working loads are provided to guide the


user, always taking into consideration that the shoring
has been properly assembled following the assembly
instructions:

Linked towers, built using Frames For further information, see the
G-100 1.85 m, braced with crossbraces G Shoring Catalogue
and with jacks extended to a maximum
of 65 cm (H: total height of the shoring):
0<H 10 m Working load per leg:
20 kN
Independent towers, built using
Frames G-100 1.85 m and with jacks
extended to a maximum of 65 cm:
Working load per leg: 12 kN

Heights greater than 10 m require more


exhaustive technical study.

10
Construccin
RAPID Horizontal Formwork

11
Construccin
RAPID Horizontal Formwork

Assembly instructions

RAPID Formwork Basic Assembly

1 Lay the main beams on the ground with their lugs


up and assemble the recoverable heads along their
whole length.
Strike the wedge with a hammer to fix the heads.

12
Construccin
RAPID Horizontal Formwork

2 Tie the first Main beam around a column so that the


In mobile scaffolding towers, work with
system is stable from the beginning of its assembly. the brake on and do not
Lift the Main beam along with its corresponding heads, move when the operator is on top of
with 2 props and tie the Main beam to the column. them.

3 Hang the Secondary beams from the main


beams. Then, parallel to the first main
beam, assemble another main beam
supported on 2 props.

13
Construccin
RAPID Horizontal Formwork

4 Once the secondary beams are assembled,


those secondary beams that interfere with
columns, and that cannot be assembled
on the corresponding recoverable heads,
are supported on auxiliary heads and
props.

5 Install the board in the column area to


stabilize the structure.

Install the 3-layer plywood from a


mobile scaffolding tower or from a
work tower.
If that is not possible, execute this
operation from the top of the
formwork structure, but the operator
must always be tied off to a lifeline
to avoid falling, or nets under the
formwork have to be used.

14
Construccin
RAPID Horizontal Formwork

6 Then continue assembling the main beams,


assembling the window on the end of one
beam with the tabs on the head of the other
beam helped by a prop.

The prop should be extended to


approximately the necessary height.

7 Follow the same procedure with the main


beam that is assembled parallel. Afterwards
assemble the secondary beams, and be careful
to install an Edge secondary beam every 2 m.
The other secondary beams shall be
Intermediate beams.

15
Construccin
RAPID Horizontal Formwork

8 Once the steel structure is assembled,


proceed to level the formwork helped by
levels and the construction site topographer.

9 The remaining props are put up, inserting the


same in the main beam sockets at the proper
height, assuring they are properly plumbed.

16
Construccin
RAPID Horizontal Formwork

10 Assemble all boards in a safe way.

17
Construccin
RAPID Horizontal Formwork

Perimeter formwork assembly


Working procedure:

1. Assemble the cantilevers

2. Cantilevers shoring

3. Assemble the boards

1. Assemble the cantilevers


In the perimeter formwork areas, where
cantilevers are necessary, assemble the
main beams without recoverable heads
because the cantilevers will have the
recoverable heads incorporated.

2. Cantilevers shoring
Once the cantilevers are in place,
assemble the corresponding props.

On one extreme, the edge cantilever


beams have a support in which the
Safety Handrail Post can be installed
as a perimeter protection. (See
Assembly of Safety Elements)

18
Construccin
RAPID Horizontal Formwork

3. Assemble the boards

If the steel structure can be accessed from


the ground, these elements will be
assembled from that level. If it is not
accessible, use mobile towers when
installing the boards on the perimeter.

19
Construccin
RAPID Horizontal Formwork

Assembly with G Shoring


Working procedure:
For more information, see
1. Installing the base jacks and the top heads the G Shoring Catalogue

2. Installing the RAPID Formwork

G Shoring

Construccin

1. Installing the base jacks and the top heads

Install the Base jacks and the Heads 55 at the top of the shoring to support the formwork. If shoring a support
beam, the Head 70 should be used.

The shoring assembler must use


extreme caution in all phases of the
assembly and disassembly, using a
The last level of frames will not
safety harness to be tied off all the
have sockets, since base jacks must
time.
be inserted on these.

20
Construccin
RAPID Horizontal Formwork

2. Installing the RAPID Formwork

Once the G Shoring is assembled, install the RAPID Formwork as described in the
corresponding section of this catalogue. The main beams should be assembled on the Heads
55, which were installed on the top of the shoring.

correct

The head which supports the extreme


of the Main beam must be positioned
to a minimum distance from the end
of the Head 55, and it must be placed
on the Base jack at the top of the
Upper frame.

wrong

Incorrect assembly can result in the


Main beam inclination during the
assembly phase or deflection due to
transferring loads in the concrete
pouring phase.

21
Construccin
RAPID Horizontal Formwork

3. Bracing

The shoring towers are braced together to assure a better stability.


.

On-site bracing should be put up every


5 m horizontally and every 4 m vertically.

The Base jacks G 1 should not be


extended more than 0.65 m.
The Base jacks G 0.5 should not be
extended more than 0.35 m.

Base jack G 0.5 Base jack G 1

22
Construccin
RAPID Horizontal Formwork

4. Beams shoring

Concrete beams are shored using the Support beam. The Support beam is assembled
perpendicular to the hanging beam and it facilitates reinforcing the board with more
Secondary Beams under the hanging beam. Once stripping is complete, the Support beam
remains as a shoring element.

Support beam

Secondary beams

23
Construccin
RAPID Horizontal Formwork

Disassembly instructions

RAPID formwork recovery or dismantling is carried out in two phases.

In phase one, the third day after pouring the slab, dismantle the recoverable material (heads, secondary beams, 3
layer plywood). The main beams along with the props or shoring should remain supporting the slab.

In phase two (at 21 days, 28 days or at the time required in accordance with the technical specifications provided
specifically for the structure's slab and in the execution timeframes for the structure), remove the Main beams that
were supported with the props or shoring system.

1 From the ground or from a mobile tower, release the heads along one row of main beams. Strike the wedge on
each head with a hammer to free it up from the position where it is tied to the lug on the main beams.

2 The secondary beams are freed up once they are unhung


The recoverable material (heads,
from the recoverable heads. secondary beams and boards) can be
removed without letting it fall to the
ground by first placing a net below
the material recovery area.

24
Construccin
RAPID Horizontal Formwork

3 Then using a crow bar, strip the boards.

4 After the necessary time has passed, proceed to recover the main beams
along with the props or shoring used.

When moving materials from one


Organization is an essential factor for construction site to another, the
safety. materials should always be transported
on duly strapped pallets to assure that
the materials do not fall.

25
Construccin
RAPID Horizontal Formwork

G Shoring disassembly
Working procedure:

1. Lower base jacks from the top

2. Recover the main beams

1. Lower Base jacks from the top

Lower Base jacks from the top of the shoring using their adjustment screws to jack them down and separate them
from the formwork's main beams.

26
Construccin
RAPID Horizontal Formwork

2. Recover the Main beams

Remove the Main beams from the Heads 55.

For more information, see


the G Shoring Catalogue

G Shoring

Construccin

For further information on these or other types of assembly, see TECHNICAL


INSTRUCTIONS FOR ASSEMBLY available in ULMA Construccin.

27
Construccin
RAPID Horizontal Formwork

Technical solutions

INFILLING ON COLUMN

SHORING WITH PROP


When the prop is the shoring element, the Auxiliar
Secondary
head will be used to provide a stable support for the
beam
board, assembling new secondary beams on each side
of the column.

Auxiliar head

SHORING WITH G SHORING


When the shoring tower is the falsework, Heads with
Tube for infilling
fork and Tubes for infilling will be placed to provide
new supports for the board.

Head with fork

28
Construccin
RAPID Horizontal Formwork

ASSEMBLY STARTING FROM WALL


The Starting main beam and the Transversal fixation accessories allow starting the assembly from the wall in a safe
way, without any infilling.

There are two possible assemblies:

MAIN BEAM PARALLEL TO THE WALL


With the Transversal fixation it is possible to assemble
the main beam under the secondary beams, putting up
Transversal fixation
the 3 layer plywood and the secondary beams against
the wall. Likewise, it makes the system more stable
because it's fitted between the main beam and the
secondary beam opening.

Auxiliar
head

MAIN BEAM PERPENDICULAR TO THE WALL


The Starting main beam fits the gap between the first
main beam and the wall, putting the 3 layer plywood
up against the wall, avoiding any infilling. It works with
RAPID 0.67 and RAPID 1 m. Starting main beam

Main beam

29
Construccin
RAPID Horizontal Formwork

CANTILEVER Cantilever
The Cantilever is an auxiliary component that provides a beam
working space in the edge of the formwork. Props are
used as shoring element.

Edge cantilever beam

SHORING THE BEAMS


The beam is shored using the Support beam. The
Support beam is assembled perpendicular to the
Secondary beam
hanging beam and it facilitates reinforcing the board
with more Secondary Beams under the hanging beam.
Once stripping is complete, the Support beam remains
as a shoring element.

Support beam

MAIN BEAM REINFORCEMENT Main beam reinforcement


The Main beam reinforcement provides additional
supports (one or two Head 55) for the main beam
when G-shoring is the shoring system.

Head 55

30
Construccin
RAPID Horizontal Formwork

90 ASSEMBLY
The main beams direction can be changed with 90
90 Head
Head. This element provides appropriate solutions for
perimeter areas, irregular geometries or hanging beams
support, making formwork much more flexible.
It's valid for RAPID 1 m and 0.67 m.

Main beam

REMAINING BEAM
After stripping, the beams of the lost pile lightened
slabs (joist and vaults) must be compulsory shored. The
Remaining beams facilitate the shoring even if the
direction of the beams is not perpendicular to the main Main Beam
beams of formwork.

Remaining beam

31
Construccin
RAPID Horizontal Formwork

Safety elements

The main purpose of the RAPID Formwork safety concrete. These safety elements include Safety heads,
elements is to protect the perimeter of the formwork and Safety handrail posts, Handrail tubes and Toe boards.
any holes that are considered to pose a risk of falling to
the workers when forming, reinforcing and pouring This equipment comprises the protective elements used
to mark off and delimit the base or work surface.

The suitable distance to install the Safety heads is 2 m. The Safety heads permit standard assembly of the Secondary
beams, and they permit installing the Safety handrail post.

Installing the Safety head over the Intermediate Installing the Safety head on the Main beam on
main beam. the border or on the perimeter of the formwork.

32
Construccin
RAPID Horizontal Formwork

Once all the Safety handrail posts are installed, proceed to finish putting
up Handrail by assembling the Handrail tubes perpendicular to the Posts
and tying these with their clamps.

Safety handrail S-V Tube

Toe board

The Safety handrail post has tie


holes, which are lined up with the
Safety head tie holes, permitting a
pin to be used to fasten these
components.

It is only necessary to insert pins


when the requirements or the
formwork assembly is put up in
extreme conditions such as areas that
are not protected, areas subject to
strong wind forces, etc.

In the case of cantilevers, the


solution will be provided by the Edge
cantilever beams, which facilitate the
insertion of safety posts and does
not require the placement of safety
heads.

33
Construccin
RAPID Horizontal Formwork

Once the formwork is fully equipped with all lateral protections, attention is now given to protect the slab borders in
the stripping phase. The Plastic handrail support is used for this purpose.

Installing the Plastic handrail support

When stripping the recoverable materials, the slab protections must be put up so as to completely close off the
whole perimeter.

Tube
Safety handrail S-V

Insert the Safety handrail posts on


the Plastic handrail supports, which
are embedded in the slab

Toe board

34
Construccin
RAPID Horizontal Formwork

NETS UNDER FORMWORK


Nets under formwork are the most effective solution to prevent falls during the assembly of the board.
That way it fulfills the European Directive 92/57/EEC, which gives priority to collective protections against the
individual ones.
Because of its versatility, RAPID System has a hook that can be fixed in the formwork and in the props.

RAPID formwork with the nets have been verified by


AIDICO "Technological Institute of Construction of
Valencia through a series of tests.

35
Construccin
RAPID Horizontal Formwork

System features

There are two variants of the RAPID System according to the type of the Main beam:
RAPID 0.67 m
RAPID 1 m

RAPID 0.67 m

The system can be applied to any type of work because of its flexibility and strength. With this variant of the RAPID
both props such as secondary beams are assembled every 67 cm. Sockets, to enter the props have 32 mm.

RAPID 1 m

RAPID 1 m can save up to 25% of the cost of material, particularly in the implementation of reduced thickness slabs
or lightened ones. By locating the secondary beams each 1 meter, the props can be arranged to coincide with the
interval (B layout) or every 0.5 m (A + B layout), it is possible to use lighter props and therefore cheaper ones. The
sockets are different for each layout to facilitate the proper assembly: one round, 25 mm diameter socket (B layout)
and one square, 20 mm socket (A layout).

Both systems are compatible and share the same accessories.

36
Construccin
RAPID Horizontal Formwork

The following tables provide the maximum slab thicknesses with RAPID System, depending on the board and grid
dimension.

RAPID 0.67 m

BOARD SHORING SECONDARY BEAM THmax (cm) BOARD SHORING SECONDARY BEAM THmax (cm)

. .
PROP PROP
REINF 1.5 REINF 1.5

REINFORCEMENT . REINFORCEMENT .
PROP REINF 1.5 PROP REINF 1.5

. .

3 LAYER PLYWOOD 21 mm
3 LAYER PLYWOOD 27 mm

REINF 1.5 REINF 1.5

. .
REINF 1.5 REINF 1.5
SHORING

SHORING

. .
REINF 1.5 REINF 1.5

382 + Main beam 382 + Main beam


reinforcement . reinforcement .
2 intermediate 2 intermediate REINF 1.5
REINF 1.5 supports
supports

382 + Main beam 382 + Main beam


reinforcement . reinforcement .
1 intermediate REINF 1.5 1 intermediate REINF 1.5
support support

RAPID 1 m

LAYOUT B (props every 1 m)

BOARD SHORING SECONDARY BEAM THmax (cm)

3 LAYER PLYWOOD .
PROP
27 mm REINF 1.5

3 LAYER PLYWOOD .
PROP REINF 1.5
21 mm

LAYOUT A+B (props every 0.5 m)


BOARD SHORING SECONDARY BEAM THmax (cm)

3 LAYER PLYWOOD .
PROP
27 mm REINF 1.5

3 LAYER PLYWOOD .
PROP
21 mm REINF 1.5

37
Construccin
RAPID Horizontal Formwork

Applications

INFILLING ON COLUMN
Shoring with prop
This component is supported by a prop, and it serves
the same purpose as the Recoverable head. It must be
used for infilling to incorporate one or two additional Auxiliar head
supports to the board.

Secondary beam

Shoring with G Shoring

This component is used for the same purposes as the


Auxiliar head when the steel structure is assembled Head with fork
with G Shoring.

Tube for infilling

Secondary beam

38
Construccin
RAPID Horizontal Formwork

ASSEMBLY AGAINST THE WALL WITHOUT INFILLINGS


Parallel to the wall with transversal fixation

Transversal fixation

Perpendicular to the wall with Starting main beam

Starting main beam

39
Construccin
RAPID Horizontal Formwork

CANTILEVER
Using the Cantilever beam and Edge cantilever beam
allows forming beyond the projection of the slab to
make the working platform, using an inclined prop as
shoring. Cantilever beam

Edge cantilever beam

BEAM SHORING
The beam is shored using the Support beam. The Support beam is assembled
perpendicular to the beam and it facilitates reinforcing the board with more Secondary
Secondary beam
Beams under the hanging beam. Once stripping is complete, the Support Beam
remains as a shoring element.

Edge Secondary
beam

Support beam

40
Construccin
RAPID Horizontal Formwork

MAIN BEAM REINFORCEMENT


Main beam reinforcement allows reinforcing the main
beam when it is shored with G Shoring, placing one or
two Heads 55 like additional support.
Main beam reinforcement

Head 55

ULMA Branch (Madrid)

90 ASSEMBLY
It permits changing the direction of the Main beams by 90.
90 HEAD

Main beam

41
Construccin
RAPID Horizontal Formwork

Receiving, storing and cleaning

RECEIVING MATERIALS ON SITE


Mark off, fence off and close off the working area
when appropriate.

Receive transport vehicles on site after obtaining the


necessary permits when applicable.

The storage zone will be established and duly marked.

UNLOADING MATERIAL
Mechanical unload
All the material will arrive grouped and strapped.

The person in charge of receiving the material


will check the condition of the pallets or packages.

The forklift route will be marked in order to avoid


interferences with personnel.

The forklift worker will store the materials following


the working instructions provided by the person in
charge of storage.

In no case shall the worker in charge of storage or


receiving, stay in the forklift travel route.

Unload with crane


The worker in charge of unloading shall not stay
underneath the load.

The worker will wait until the load is practically on the


ground before guiding it to the proper place.

Manual unload
Loads bigger than 25 kg will not be handled by one
person.

42
Construccin
RAPID Horizontal Formwork

STORAGE
The Main beams, the Secondary beams, the Support
beams and the Boards are supplied on properly strapped
packages. Other elements are supplied in bulk in boxes
or in pallets.

The storage of the different components has to be done


always after their cleaning and each use.

The Boards should be piled off separately from the


ground level on brackets and in an covered area.

Prolonged exposure to sunlight and


rain may damage the Boards.

LIFTING MATERIAL
The biggest parts should be lifted or lowered by hoist to
the different floors (or different heights) in packages that
are strapped on both ends. Material shall be suspended
by slings strapped to the tower crane hook. The other
elements are moved in boxes.

CLEANING
The cleanliness of the formwork surfaces should be
checked before assembling the materials that comprise
part of the formwork. After each use, the boards should
be cleaned with release agent applying it with brush.

Do not use wire brushes that can


damage the surface of the board.

43
Construccin
RAPID Horizontal Formwork

CRITERIA FOR ELIMINATING NON-VALID PARTS

Provided below is the criteria for identifying parts that, due to deformations or breakage that may occur,
are considered not valid for use because these damages imply a risk of accidents to the operators who are
handling the material or a risk of breakage to some system component when it is loaded.

Main beam: Secondary beams:


Lugs: breakage or crack in Torn tie hole on Head.
the weld.
Sockets: breakage.

Board:
Head:
Excessive deformation in
Broken or bent tab. center of Board.
Support lug on broken Wooden layers in Board
wedge. coming unglued.

44
Construccin
RAPID Horizontal Formwork

USING THE RELEASE AGENT


Release agent is used to keep concrete from sticking to the formwork, thus increasing number of
times formwork can be used.

The release agent plays an important role in assuring the quality of the concrete surface. It serves
the purpose of assuring there are no surface holes and that color is uniform.

To avoid bonding between the concrete and the formwork surface, the release agent creates a
water resistant film, thus assuring that the water and the cement suspended in the surface
cannot come in contact with the formwork surface.

The properties of the release agent should be compatible with the concrete and with the
formwork on which it is going to be applied. This compatibility should comply with the following
characteristics:

It should not cause holes nor generate color variations or other surface defects.

With the objective of avoiding interactions in the concrete curing and hardening process,
it must not be soluble in water.

It must make the formwork more durable.

It must not be a health hazard to the workers who handle it.

As well as improving the concrete surface, the release agent minimizes the damages inflicted on
the formwork surface. It also facilitates striping all types of molds and reduces residues, thus
achieving long life board surfaces.

Additional information on the release agent

The release agent recommended by ULMA Construccin should be applied directly to


surfaces, and it is formulated from mineral and chemical components with properties superior
to conventional oils. Chemically, it forms an impermeable film over the board, which protects
the formwork and the concrete.

45
Construccin
RAPID Horizontal Formwork

PRECAUTIONS

Health and safety

It should be applied uniformly on The release agent can be preserved


the wall in thin coats. Correct use for a maximum of 12 months when
guidelines should always be taken stored, well sealed, in its original
into account. containers under normal storage
conditions.

Non-absorbent surfaces require one


If used at temperatures above 60, single application. New wooden
consult our Technical Department. surfaces not covered with
polyurethane should be recovered
with release agent if the wood
soaks in the first coat of release
agent applied.

Fire

The release agent has a high flash


point, and therefore it should not
be exposed to open flames or other
sources of ignition. (Flash point
>60)

Cleaning and removing

The formwork surfaces should be


cleaned carefully before applying
the release agent. It can be
brushed, rolled or sprayed on.
When possible it is recommended
to use a sprayer.

46
Construccin
RAPID Horizontal Formwork

General safety tips

RECOMMENDATIONS

The prop support must be


horizontal with a flat surface and
stable base.

The prop must be plumbed.


YES

The load applied over the prop


will be vertical and centered.
Horizontal loads must not be
exerted on the prop.

YES

The props must individually be


used between the support and the
load. It is not advised to join these
together in order to use them at
higher heights since that could lead
to collapses and decreased working
loads.

47
Construccin
RAPID Horizontal Formwork

Do not use the formwork as a


material storage platform, loading
specific areas.
Always distribute loads uniformly by
sorting out the stored materials.

Do not drop objects or jump on the


shuttering boards.

Pour the concrete in layers or levels


of uniform thickness and continually
vibrate. Do not permit concrete to
accumulate or build up in mounds to
be subsequently leveled out.

48
Construccin
RAPID Horizontal Formwork

HANDLING AND MAINTENANCE CONDITIONS

Follow the Project instructions strictly.


Always follow the Manufacturers General Instructions.
Always follow Internal Safety Standards.
The assembly of the mechanical elements and the board should be conducted safely, using
either mobile towers, nets under the formwork or lifelines.
The props should be used properly, observing load limits, plumbing and with stable
support.
When height of prop is exceeded, use shoring system.
Personal and group safety equipment:
1. The personal protective equipment should include: hard hat, safety footwear, gloves and
tool holder belt. It can also include an anti-fall harness and lifeline.
2. If necessary, use protective goggles or masks, hearing protection, breathing masks,
reflective jackets and any other element required in the relevant occupational Health
and Safety guidelines.
3. The safety handrail should be used as group protection, and, when applicable mobile
towers, nets under the formwork and perimeter scaffolding will also be used.
Safety Heads must be assembled in order to install the handrail on the steel structure. The
housing is included in the perimeter solution.
Pallets and boxes must be used when transporting material to the construction site and on
the jobsite.
For proper assembly, the following should be verified between uses: cleanliness of the
board and support areas.

49
Construccin
RAPID Horizontal Formwork

GENERAL CONSIDERATIONS
Holes should be protected with covers, The formwork must be put up and
handrails, nets or meshes to prevent dismantled by competent personnel
people from falling from one level to assigned by the site manager to avoid any
another. wrong operations.
The sides of the formwork structure or Do not leave any element partially
perimeter scaffolding will have regulatory assembled.
handrails.
Properly brace the structure when it is
Use 15 cm toe boards in the perimeter assembled.
handrails.
Do not work with formwork when wind
Check formwork elements and safety speeds are in excess of 60 km/h.
elements. Replace as necessary. Confirm:
Check safety hooks and slings before
That no knocks or blows have damaged lifting or stripping the formwork.
their section.
Use suitable anchoring and certified slings
That they are not bent. and hoists when lifting.
That their attachments are correct and When moving material in slings, secure it
effective. to make sure that it does not come loose
in transit.
Check the following in timber or plastic
elements: Do not drive under hanging loads or in
areas where machinery is operating.
That they have no knocks, cracks or
knots that may reduce their resistance. Mark off and impede circulation in
working areas.
That they are properly secured to their
supports. Use tool holder belts with pockets for
small parts.
Replace as necessary.
Fit the equipment with the necessary
To access the formwork standard ladders,
mechanical lift mechanisms.
ladder turrets or regulation catwalks
should be used. Move only through signposted areas on
the working zone.
In mobile scaffolding towers, work with
the brake on and do not move them Train personnel in manual load handling.
when the worker is on top of them.
Use comfortable and safe postures when
Follow the specific procedure in the loading difficult bulky loads.
assembly and disassembly of perimeter
Manual load conveying should be carried
formwork.
out with right body positions.
Keep work areas clean and organized at
Conduct a general revision of the
all times. Leave material organized and
formwork after the assembly is complete.
stacked. Do not leave material
disorganized on the formwork or on the
ground.

50
Construccin
RAPID Horizontal Formwork

POURING CONCRETE

Prior to pouring concrete make sure: Check the state of the formwork before
undertaking any disassembly work.
That the formwork is assembled correctly,
observing the layout. The horizontal loads to be supported by
temporary building elements on site are
To install the Reinforcement props where
defined in the EN 12812:2004 standard,
necessary.
Formwork: verification requirements and
To level the formwork. general design (Section 8.2.2.2.) and are
quantified as 1% of the vertical loads, Q1 and
To steep the formwork surface with release
Q2, where Q1 are permanent loads and Q2
agent.
variable vertical loads.
To install the Plastic handrail supports along
Similarly, in this section it is considered that
the perimeter of the freshly poured concrete
these loads are transmitted to the structure
slab for the subsequent placement of Safety
through the formwork elements which,
handrail post on the slab.
attached to the structure, restrict the horizontal
During the vibration process, the vibrators will movement of the formwork.
never come in contact with the formwork to
It also indicates in a note that this effect is due
assure that the loads and overloads considered
to actions such as those caused by pumped
for each slab thickness will not be exceeded.
concrete pouring.
Avoid undue stockpiling of material as well as
The formwork is designed taking into account
accumulations and abrupt pouring of concrete.
the transfer of horizontal forces into the actual
Pouring the concrete in several phases is structure.
recommended in cases where the maximum
The horizontal load is transferred from one part
admissible thickness may be exceeded.
to another until this stress is absorbed by a
Avoid sudden emptying of the bucket on rigid element of the structure, such as a
the formwork. Pour the concrete from a height column, wall, etc. If there are no fixed points
at which rough movements will not be on the structure for bracing, the use of stable
produced in the formwork. shoring with its relevant attachments is
necessary.
The formwork should be removed only when
the concrete is strong enough.

LEGAL REFERENCES AND STANDARDS ON HEALTH AND SAFETY


IN THE WORKPLACE AND ENVIRONMENTAL RISKS
Council Directive 89/391/EEC on the Directive 95/63/EC concerning the minimum safety
introduction of measures to encourage and health requirements for the use of work
improvements in the safety and health of equipment by workers at work.
workers at work.
Council Directive 92/57/EEC on the implementation
Council Directive 89/656/EEC on the minimum of minimum safety and health requirements at
health and safety requirements for the use by temporary or mobile construction sites.
workers of personal protective equipment at
the workplace.

51
Construccin
RAPID Horizontal Formwork

Components and accessories


Basic Elements
WEIGHT (KG) CODE WEIGHT (KG) CODE

Recoverable head 1.9 1860001 Main beam


Main beam 2/1 socket 0.5 9.3 1860316
Main beam 3/1 socket 0.5 13 1860314
Main beam 4/1 socket 0.5 17.3 1860312

Main beam
Main beam 2/0,67 11 1860010
Main beam 3,35/0,67 17 1860012
Main beam 4/0,67 20.8 1860014

Secondary beam
Reinf. second. beam 1.5 9.3 1860504
Secondary beam 2 12.6 1860060

Secondary beam 1 4.4 1860057


Secondary beam 1.5 6.4 1860058

52
Construccin
RAPID Horizontal Formwork

Auxiliary components

WEIGHT (KG) CODE WEIGHT (KG) CODE

Secondary beam Auxiliar head 1.4 1860067


Edge Reinforced
secondary beam 1.5 9.9 1860505
Edge secondary beam 2 13.5 1860143

Head with fork 2.6 1860110

Secondary beam
Edge secondary beam 1 5.4 1860145
Edge secondary beam 1.5 7.4 1860144

Cantilever
Cantilever 6.8 1860031
Edge cantilever beam 8.2 1860146

Board
3-layer plywood 1000 x 503 x 27 7.2 7251130
3-layer plywood 1330 x 503 x 27 9.6 1860512
3-layer plywood 2000 x 503 x 21 11.4 7251131
3-layer plywood 2000 x 503 x 27 15 7251132

Starting main beam 2.4 1860318

53
Construccin
RAPID Horizontal Formwork

WEIGHT (KG) CODE WEIGHT (KG) CODE

90 head 2.9 1860310 Main beam 5 1860284


reinforcement

Remaining beam 8.8 1860300

Transversal fixation 0.18 1860320

Support beam
Support beam 1 14 1860510
Support beam 1,34 18.6 1860497
Support beam 2,2 24.6 1860513

54
Construccin
RAPID Horizontal Formwork

Safety elements

WEIGHT (KG) CODE WEIGHT (KG) CODE

Safety head 1.5 1860518 Tube 42/4070 with socket 8.4 2023800

Safety handrail S-V 3.9 1860516

Coupler
Right angel coupler 42/42 1.2 2012600
Swivel Coupler 42/42 1.3 2012400
Safety handrail 1.5 9.6 2211156

Tube 42
Tube 42/0.5 1 2033300
Tube 42/1 2 2033500
Tube 42/1.55 3 2033700
Tube 42/2.1 4.1 2033800
Tube 42/3.1 6.4 2034000

55
Construccin
RAPID Horizontal Formwork

WEIGHT (KG) CODE WEIGHT (KG) CODE

Tube 48 Extending ledger 3.24 2211172


Tube 48/1.6 5.5 2125290
Tube 48/2.1 7 2125291
Tube 48/2.6 8.7 2125647
Tube 48/3.1 11.4 2125249
Tube 48/3.6 12.1 2125648
Tube 48/4.1 14.6 2125250
Tube 48/5 18 2125251
Tube 48/6 21.4 0200600

Safety net
Safety net 1 x 10 1.7 1860708
Safety net 1.5 x 10 2.5 1860660
Safety net 2 x 10 3.3 1860657

1100
Tube 48/4100 with socket 13.14 2125649 10000

1500
10000

2100
10000
Coupler 48
Swivel coupler 48/48 1.3 2125147
Right angel coupler 48/48 1.2 2125148

Safety net hook 0.05 1860661

56
Construccin
RAPID Horizontal Formwork

Consumable materials Props


WEIGHT (KG) CODE WEIGHT (KG) CODE

Plastic handrail support 0.1 1860533 SP Prop


Normal Prop 1.75/3.1 10 2150000
Normal Prop 2.1/3.5 10.6 2150500
Strong Prop 2.1/3.65 13.6 2154300
Strong Prop 2.35/4 15.1 2159333
Strong Prop 3.65/5.25 18.8 2154400
SP-34 Prop 12.1 2170340
SP-40 Prop 16.3 2170400
SP-50 Prop 23.1 2170500

Plug 42 0.007 1904100

Release agent container


Release agent container 25 l. 22 7230422
Release agent container 210 l. 200 7230421

ALUPROP Prop
ALUPROP 1.65/2.8 17.4 2220010
ALUPROP 2.2/3.7 21.4 2220020
ALUPROP 3.3/4.8 25.1 2220030
ALUPROP 4.5/6 29.2 2220040

Sprayer 2.2 7230433

57
Construccin
RAPID Horizontal Formwork

G Shoring
WEIGHT (KG) CODE WEIGHT (KG) CODE

SUPPLEMENT 1 m 4.4 2220055 Base plate 1.2 2000300

Base jack
Base jack 0.5 3.2 2000600
Base jack 1 6.2 2000700

ALUPROP Clamp 1.1 2220080

Head
Head 55 1.2 1860088
Head 70 1.9 1860500

58
Construccin
RAPID Horizontal Formwork

WEIGHT (KG) CODE WEIGHT (KG) CODE

Frame Platform
Frame G-100 1 12.5 2003300 Platform G 1.065 7.69 1860580
Frame G-100 1.55 13.4 2003500 Platform G 1.57 11.23 1860572
Frame G-100 1.85 15.5 2003600 Platform G 2.075 15 1860582

Extending platform
Extending platform 1-1.5 12.5 2067035
Extending platform 1.5-2.35 17.3 2067048
Extending platform 2-2.7 20.5 2067043

Crossbrace
Two-coloured crossbrace 1 3.9 1860507
Two-coloured crossbrace 1.5 4.8 1860101
Two-coloured crossbrace 2 5.8 1860107
Two-coloured crossbrace 1.5/0.75 4.2 1860098
Two-coloured crossbrace 2/0.75 5.4 1860104

59
Construccin
Production Plant
ULMA C y E, S. Coop.
Ps. Otadui, 3 - P.O. Box 13
20560 OATI (Guipzcoa)
SPAIN
Phone: + 34 943 034900
Fax: + 34 943 034920
www.ulma-c.com

ULMA Worldwide
EUROPE IDF chafaudages Branch Tarnos Branch Poland
22 Bis, rue Gustave Eiffel 40, rue de lIndustrie ULMA Construccion Polska S.A.
Germany
Z.I. de la Marinire Z.I. de Tarnos 03-115 WARSAW
ULMA Betonschalungen 91070 BONDOUFLE 40220 TARNOS ul. Klasykw 10
und Gerste GmbH Phone: + 33 1 69 11 63 30 Phone: + 33 5 59 64 44 45 Phone: + 48 22 506 70 00
Paul-Ehrlich-Strae 8 Fax: + 33 1 69 11 63 31 Fax: + 33 5 59 64 44 84 Fax: + 48 22 814 31 31
D-63322 RDERMARK www.ulma-c.pl
Phone: + 49 6074 9294 0 IDF Construction Branch Lons Branch
Fax: + 49 6074 9294 101 27, rue Gustave Eiffel 9, Avenue Larregain WSCHD REGION
www.ulma-c.de Z.I. de la Marinire Z.I. du Monhauba WARSZAWA Branch
91070 BONDOUFLE 64140 LONS
Nordwest Branch Phone: + 33 1 69 11 63 40 Phone: + 33 5 59 62 71 97 Warszawa Office
Stresemannallee 4c Fax: + 33 1 69 11 63 37 Fax: + 33 5 59 13 84 33 03-197 WARSAW
D-41460 NEUSS ul. Laurowa 39
Phone: + 49 2131 40201 0 Eguilles Branch Italy Phone: + 48 22 506 72 50
Fax: + 49 2131 40201 99 50, alle Meulire ALPI, S.P.A. Fax: + 48 22 747 19 16
Z.I. - Route de Berre Zona Industriale Est
Sdwest Branch 13510 EGUILLES I-39035 MONGUELFO (BZ) Olsztyn Office
Manfred - Wrner - Str. 115 Phone: + 33 4 42 64 62 30 Phone: + 39 0474 947 400 10-467 OLSZTYN
D-73037 GPPINGEN Fax: + 33 4 42 64 62 31 Fax: + 39 0474 947 499 ul. Sprztowa 3, lok. 18
Phone: + 49 7161 50608 42 www.alpionline.net Phone: + 48 89 537 73 10
Fax: + 49 7161 50608 43 Saint Herblain Branch Fax: + 48 89 532 04 95
11, rue Fondeur Kazakhstan
France Z.I. du Tisserand ULMA Kazakhstan LUBLIN Branch
ULMA, S.A.R.L. 44800 SAINT HERBLAIN 01000 ASTANA Lublin Office
27, rue Gustave Eiffel Phone: + 33 2 51 80 48 04 6/2, Tashenova St. 4th floor, offices 7,9 20-327 LUBLIN
Z.I. de la Marinire Fax: + 33 2 51 80 48 05 Phone:/Fax: + 7 7172 58 05 19 ul. Wroska 2
91070 BONDOUFLE Phone: + 7 7172 37 93 48 Phone: + 48 81 749 72 90
Phone: + 33 1 69 11 54 50 La Chapelle www.ulma-c.kz Fax: + 48 81 744 04 90
Fax: + 33 1 69 11 54 54 dArmentires Branch
www.ulma-c.fr Zone Industrielle Biaystok Office
Rue Andr Ampre 15-100 BIAYSTOK
59930 LA CHAPELLE ul. 1. Armii Wojska Polskiego 9, lok. 203
DARMENTIRES Phone: + 48 85 676 73 00
Phone: + 33 3 20 07 11 86 Fax: + 48 85 675 06 53
Fax: + 33 3 20 07 11 68

60
Construccin
ZACHD REGION Nowa Sl Office Porto Branch Ukraine
POZNA Branch 67-100 NOWA SL Zona Industrial da Feiteira ULMA Formwork Ukraine Ltd.
61-317 POZNA ul. Kociuszki 29 Rua das Casas Queimadas 01013 KIEV
ul. Ostrowska 484 Phone: + 48 68 376 77 60 717 Grij 3, Derevoobrobna St.
Phone: + 48 61 838 75 30 Fax: + 48 68 387 02 21 wew. 357 4415-439 VILA NOVA DE GAIA Phone: + 380 44 255 14 92
Fax: + 48 61 863 01 60 PORTO Fax: + 380 44 255 14 94
POUDNIE REGION Phone: + 351 227 418 820 www.ulma-c.com
BYDGOSZCZ Branch KRAKW Branch Fax: + 351 227 418 829

Bydgoszcz Office Krakw Office Czech Republic


85-739 BYDGOSZCZ 31-670 KRAKW ULMA Construccin CZ, s.r.o.
ul. Fordoska 199 ul. Powstacw 66 Prmyslov 1009
Phone: + 48 52 323 76 80 Phone: + 48 12 620 73 70 294 71 BENTKY NAD JIZEROU
Fax: + 48 52 345 25 65 Fax: + 48 12 647 34 22 Phone: + 420 326 910 600
Fax: + 420 326 910 601
Szczecin Office Katowice Office www.ulma-c.com
70-676 SZCZECIN 40-203 KATOWICE
ul. Gerarda Merkatora 7 al. Rodzieskiego 188b Slovak Republic
Phone: + 48 91 485 77 30 Phone: + 48 32 356 74 80 ULMA Construccion SK, s.r.o.
Fax: + 48 91 462 53 11 Fax: + 48 32 353 33 90 Rybnin 38/K
831 06 BRATISLAVA
GDASK Branch D Branch Phone: + 421 2 4910 2911 - 13, 18
80-298 GDASK 94-250 D Fax: + 421 2 4910 2922
ul. Budowlanych 27 ul. niwna 4/8 www.ulma-c.com
Phone: + 48 58 522 78 00 Phone: + 48 42 666 73 20
Fax: + 48 58 667 02 04 Fax: + 48 42 650 03 25 Romania
ULMA Cofraje s.r.l.
WROCAW Branch Portugal Sos Chitilei, 200
Wrocaw Office ULMA Portugal Lda. 012405 - Sector 1 - BUCHAREST
50-541 WROCAW Zona Industrial - Rua A, s/n Phone: + 40 31 425 13 22 / 23
ul. Armii Krajowej 53 Vale de Figueira Fax: + 40 31 425 13 24
Phone: + 48 71 391 76 30 2695 SO JOO DA TALHA - LISBON www.ulma-c.ro
Fax: + 48 71 367 30 90 Phone: + 351 219 947 850
Fax: + 351 219 558 022
www.ulma-c.pt

61
Construccin
Production Plant
ULMA C y E, S. Coop.
Ps. Otadui, 3 - P.O. Box 13
20560 OATI (Guipzcoa)
SPAIN
Phone: + 34 943 034900
Fax: + 34 943 034920
www.ulma-c.com

ULMA Worldwide

AMERICA Sul Branch West Branch (Phoenix) ASIA-AFRICA


Rua Dr. Joo Incio, 195/199 1530 West Houston Avenue
Argentina Navegantes - Poa RS Gilbert, ARIZONA 85233 P.R. China
ULMA Andamios y CEP: 90230-180 Phone: + 1 480 304 4942 ULMA Formworks China R.O.
Encofrados Argentina, S.A. Phone/Fax: + 55 51 3337 1003 Fax: + 1 480 304 4948 #1009 Fortunegate Mall
Bernardo de Irigoyen 722 6A
1701 West Beijing Road
CP1072AAP CAPITAL FEDERAL Chile Mid-Atlantic Branch (Baltimore) SHANGHAI, 200040
Phone/Fax: + 541 14 3425132 ULMA Chile - Andamios y 8235 Patuxent Range Road Phone: + 86 21 62887070
www.ulma-c.com.ar Moldajes, S.A. Jessup, MARYLAND 20794 Fax: + 86 21 62885980
Vizcaya n 325 - Pudahuel Phone: + 1 443 296 9852 www.ulma-c.com
Brazil (Ruta 68, Camino Noviciado) Fax: + 1 443 296 9860
ULMA Brasil - Frmas e SANTIAGO UAE
Escoramentos Ltda. Phone: + 56 2 5990530 Mexico ULMA Formworks UAE L.L.C.
Rua Joo Dias Ribeiro, 210 Fax: + 56 2 5990535 ULMA Cimbras y Andamios Plot No. 597- 547
Jd. Sagrado Corao de Jesus www.ulma-c.cl de Mxico S.A. de C.V. Dubai investments Park
Itapevi - SP Va Gustavo Baz Prada 2160 P.O. Box. 282286
CEP: 06693-810 Norte Branch Acceso 5 DUBAI
Phone/Fax: + 55 11 3883 1300 General Borgoa 934 of. 70 54060 Col. La Loma Phone: + 971 4 8858208
www.ulma-c.com.br ANTOFAGASTA TLALNEPANTLA Fax: + 971 4 8858209
Phone: + 56 5 5246770 (Mexico State) www.ulma-c.com
Rio de Janeiro Branch Fax: + 56 5 5246960 Phone: + 52 55 5361 6783
Rua Sargento Silva Nunes, 137 Fax: + 52 55 2628 3549 Singapore
Ramos - Rio de Janeiro - RJ Sur Branch www.ulma-c.com.mx ULMA Formwork
CEP: 21040-231 OHiggins 940 of. 904 Singapore PTE. LTD.
Phone/Fax: + 55 21 2560 2757 CONCEPCIN Peru 2 Senoko Way
Phone/Fax: + 55 21 2560 5541 Phone: + 56 4 12522930 ULMA Encofrados Per, S.A. 758027 SINGAPORE
Fax: + 56 4 12228321 Av. Argentina 2882 Phone: + 65 6758 2338
Centro-Oeste Branch LIMA Fax: + 65 6758 8523
Quadra 3, Lotes 680/700 USA Phone: + 51 1 613 6700 www.ulma-c.com
Setor Industrial Leste ULMA Form Works, Inc. Fax: + 51 1 613 6710
Gama - Brasilia DF 58 Fifth Avenue www.ulma-c.com.pe
CEP: 72445-030 Hawthorne - NEW JERSEY 07506
Phone/Fax: + 55 61 3556 6226 Phone: + 1 973 636 2040 Norte Branch
Fax: + 1 973 636 2045 Ctra. Pomalca, km 2,7
Salvador Branch www.ulma-c.us Chiclayo - LAMBAYEQUE
Travessa Dois de Fevereiro, 145 Phone: + 51 7 460 8181
Centro - Lauro de Freitas - BA Fax: + 51 7 460 8182
CEP: 42700-000
Phone/Fax: + 55 71 3288 2003

62
Construccin
ULMA in Spain

ANDALUCA Branch CASTILLA Branch GALICIA Branch LEVANTE Branch


Pol. Ind. Fridex Ctra. Burgos - Portugal, km 116 Pol. Ind. Espritu Santo Pol. Ind. Los Vientos
Autova Sevilla - Mlaga, km 4,2 47270 CIGALES (Valladolid) Rua Bell, 24-26 Gregal, 7 - Apdo. 76
41500 ALCAL DE GUADAIRA Phone: 983 581009 15650 CAMBRE (La Corua) 46119 NQUERA (Valencia)
(Sevilla) Fax: 983 581021 Phone: 981 649802 Phone: 96 1399130
Phone: 95 5630044 Fax: 981 649060 Fax: 96 1399096
Fax: 95 5630020 Pol. Ind. de Roces, 5
Gustavo Eiffel, 46 Generoso Domnguez, s/n Pol. Ind. La Serreta
Camino Nuevo, s/n 33211 GIJN (Asturias) Portela - Tameiga Cal, s/n
18210 PELIGROS (Granada) Phone: 98 5168038 36416 MOS (Pontevedra) 30500 MOLINA DE SEGURA
Phone: 958 405028 Fax: 98 5167513 Phone: 986 344045 (Murcia)
Fax: 958 405328 Fax: 986 304809 Phone: 968 642679
CATALUA Branch Fax: 968 641276
ARAGN Branch Pol. Ind. Sud - Est NORTE Branch
Pol. Ind. El Pradillo II Pintor Velzquez, 7 y 9 Pol. Ind. Goiain
Aneto, 2 - Parcela 23 08213 POLINYA (Barcelona) Av. San Blas, 1
50690 PEDROLA (Zaragoza) Phone: 93 7132727 01170 LEGUTIANO (lava)
Phone: 976 654645 Fax: 93 7133643 Phone: 945 001100
Fax: 976 654635 Fax: 945 001111
Pol. Ind. Son Noguera
CANARIAS Branch Cas Rossos, 12-14 Iturritxualde, 3
Pol. Ind. Las Majoreras 07620 LLUCMAJOR 48160 DERIO (Vizcaya)
Los Llanillos, 33 (Illes Balears) Phone: 94 4521425
35259 INGENIO (Las Palmas) Phone: 971 669850 Fax: 94 4522468
Phone: 928 789212 Fax: 971 121512
Fax: 928 789538
CENTRO Branch
Pol. Ind. Valle de Gimar Pol. Ind. Sur
Manzana XIII - Parcelas 21 y 22 28863 COBEA (Madrid)
38509 GIMAR (Tenerife) Phone: 91 6523199
Phone: 922 505020 Fax: 91 6528828
Fax: 922 501101
Ctra. N-401 Madrid-C. Real, km 87
45110 AJOFRN (Toledo)
Phone: 925 011000
Fax: 925 011008

63
Construccin
RAPID Horizontal Formwork

Our products

Horizontal Formworks
RAPID Recoverable VR Table
Formwork Horizontal formwork for any
Formwork that can be easily slab type
and quickly recovered from
assembly

RECUB Recoverable Coffer ENKOFLEX Formwork


Formwork Horizontal formwork using
Speed and safety in wooden beams, easy to
assembly and removal assemble and very versatile

ENKOFORM H-120 Bracing Wood Panels for


System Formwork
A multipurpose system, Panels that adhere to the
capable of resolving the highest of site demands
diverse types of construction
work

CC-4 Horizontal
Formwork
Aluminium horizontal
formwork, light, fast setting
and stripping

64
Construccin
RAPID Horizontal Formwork

Notes

65
Construccin
RAPID Horizontal Formwork

Notes

66
Construccin
ULMA C y E, S. Coop.
E00CBS11

Ps. Otadui, 3-P.O.Box 13


20560 OATI (Guipzcoa)
SPAIN
Phone: + 34 943 034
Fax: + 34 943 034920
ww w.ulma-c.com

You might also like