Professional Documents
Culture Documents
52536
CONFIDENTIAL
by
CONFIDENTIAL
This document is made available subject to the condition that the recipient will neither use nor disclose the contents except as agreed in
writing with the copyright owner. Copyright is vested in Shell Global Solutions International B.V., The Hague.
Neither the whole nor any part of this document may be reproduced or distributed in any form or by any means (electronic, mechanical,
reprographic, recording or otherwise) without the prior written consent of the copyright owner.
Shell Global Solutions is a trading style used by a network of technology companies of the Shell Group.
GS.06.525366.52536 1 CONFIDENTIAL
Summary
Nowadays, most of the projects are complex projects with many parties in the project,
differences in contracts and work methods of contractors towards completion of construction,
this all has to be aligned and integrated. Furthermore future owner teams have to define their
own activities and carry responsibility for the CSU schedule.
The sheer size of the project means that in order to stay in control a plan is mandatory, one
simply cannot rely on knowledge and expertise of individuals and improvisation.
Sharing and dissemination of information is key to have everybody involved in the project
phases (pre)commissioning, start-up and initial operations aligned and working effectively.
The methodology presented in this document provides the tools to develop a road map and
schedule for the execution phases of a project. The structured approach is called
systemization and is a key element of the flawless start-up initiative (FSI).
The CSU execution road map and the schedule is developed by:
Defining commissioning/ operational systems
Determine activities per system for the phases (pre) commissioning and start-up
Determine logic links between the activities and develop the execution roadmap (also
called Work Execution Flow Scheme)
Populate scheduling tool with the data and produce schedule
The developed WEFS and schedule are used for analyzing and optimizing the CSU phase by
integrating and linking activities across all units and plants. When the CSU is optimized
around a fixed date i.e. start-up milestone (product in tank) the calculated dates for system or
unit completion can be fed back into the construction and engineering phase schedules to
align and make sure that priorities are set at those project phases in line with CSU demands.
It serves therefore as an important communication tool for all parties working on a project.
Systemization can in principle be applied to any project or work process that involves assets
and activities that are logically linked, i.e. it is not restricted to green field projects. Also the
execution work involved in brown field projects can be structured according to this approach.
Therefore systemization is an integral part of the flawless turnaround initiative.
GS.06.525366.52536 2 CONFIDENTIAL
Table of Contents
Summary 1
1. Introduction 4
1.1 Assets Driving Project Schedules 4
1.2 In Control of CSU 4
1.3 Structured Approach 5
1.4 Work Process 7
1.5 Nomenclature and Terminology 8
1.5.1 System 8
1.5.2 Activity 8
1.5.3 Work Execution Flow Sheet (WEFS) 8
1.5.4 Pre-commissioning 8
1.5.5 Hand Over 9
1.5.6 Commissioning 9
1.5.7 Ready for Start-up 10
1.5.8 Start-up 10
1.5.9 Commissioning and Start-up Schedule 11
1.5.10 Turnaround Schedule 11
1.6 Abbreviations 12
2. System Definition 13
2.1 General 13
2.2 System Identification 14
2.3 System Size 15
2.4 Guidelines for Definition of Process Systems 17
2.4.1 Process Systems 17
2.4.2 Utility Systems 17
2.5 Guidelines for Definition of Non-Process Systems 19
2.5.1 Instrument Systems 19
2.5.2 Electrical Systems 19
2.5.3 Telecommunication Systems 20
2.5.4 Civil/ Structural Systems 20
2.6 Interface systems 20
2.7 System Numbering 21
3. Activity Definition 24
3.1 Work Breakdown 24
3.2 Guidelines for Activity Definition 25
3.3 Inter Relationships Between Activities 29
3.4 CSU Activity List 30
4. Work Execution Flow Scheme 32
4.1 Work Execution Flow Scheme Setup and Development 32
4.2 Work Flow Schemes 34
4.2.1 Work Flow Scheme: Roll up of WEFS 34
4.2.2 Work Flow Scheme: High Level CSU Work Plan 35
5. CSU Schedule Development 37
5.1 CSU Network Schedule 37
5.2 Basic Guidelines for Building and Maintaining a CSU Schedule 38
5.3 Network Structure 39
6. Turnaround 41
6.1 The Eight Steps of a Turnaround 41
6.2 Decontamination and Commissioning Systems 42
GS.06.525366.52536 3 CONFIDENTIAL
1. Introduction
1.1 Assets Driving Project Schedules
The project team and the future asset owners need to recognise that, at a very fundamental
level, the project schedule is driven by different factors during the various phases of the
project. By recognising these schedule drivers the project team and asset owner will be able
to develop a schedule that meets the needs of the project and ensure effective management
of transitions between each phase.
In the design phases the schedule is driven by the systems to be included in the plant.
Chemical, mechanical and process control designs are examples of such system driven
project elements. Process Flow Schemes (PFSs) are the key deliverables of this phase.
In the project specification phase the schedule is driven by site geographical area. The plot
plan is divided into areas and the design of the foundations, structures, piping, mechanical
equipment, electrical and instrumentation proceeds around the different areas of the site.
The project specifications, Process Engineering Flow Schemes (PEFSs), plot plans with
critical equipment layouts, equipment list, equipment data sheets and one-line electrical
drawings are the key deliverables of this phase.
Detailed engineering and procurement, changes the driver from area into procurement
train, in which similar items are grouped, regardless of their system or area, so that they can
be readily and efficiently handled in the requisitioning, bidding, ordering, manufacturing,
expediting, inspection, delivery and materials management activities. The PEFSs,
instrument data sheets, piping isometric drawings, purchase orders and work execution
contracts are the key deliverables of this phase.
The driving force during the initial construction phase reverts to area, which is supported with
area-based drawings. As construction nears completion, work must be completed and tested
on a systems basis.
The following figure illustrates the transitions between these project drivers.
Control Improvisation
- Thousands of activities need to be initiated, controlled and recorded
- Several hundred people involved - communication / alignment
- Reduce business and Health Safety & Environment risks
Proactive Reactive
6
The sheer size of the project means that in order to stay in control, a fact based plan that
aligns all construction and commissioning activities of the different EPC contractors and links
the commissioning activities to the start-up activities (integration) is mandatory1.
One simply cannot rely on knowledge and expertise of individuals and improvisation.
Sharing and dissemination of information is key to have everybody involved in the project
phases (pre-) commissioning, start-up and initial operations aligned and working effectively.
This structured approach is called systemization and is a key element for flawless start-
up.
To be able to control work during the CSU phase of a project, an overview of all CSU
execution work needs to be prepared. It is essential to identify all work, i.e. no gaps.
An overview of all execution work is also a prerequisite for identification of all preparation
work (procedures, training, vendor support, required resources etc.)
1
Even when the project is not so big a plan is required to maximise efficiency and optimize the use of
the available manpower versus time available (or be able to do the work with the limited manpower
that is available) to achieve the project goals.
2
Where CSU is mentioned in the text, the same applies to plant shut down and decontamination
phase
GS.06.525366.52536 6 CONFIDENTIAL
Only when an overview of all work is developed, a CSU planning model (schedule) can be
produced. In general, a planning model consists of activities that are logically linked
describing a work process for an asset from a defined starting point to a defined end point
with a timeline and resources.
The CSU planning model is used for optimizing the CSU phase by integrating and linking
activities across all systems, units and plants. When the CSU is optimized around a fixed
date i.e. start-up milestone (product in tank) the calculated dates for system or unit
completion can be fed back into the construction and engineering phase schedules to align
and make sure that priorities are set at those project phases in line with CSU demands.
To create the overview of work, assets need to be broken down to a suitable level for activity
definition providing the right level of detail for management and control of preparation and
execution of CSU
GS.06.525366.52536 7 CONFIDENTIAL
These steps lead to creating a well-defined starting point, outline and end-point for the work
process to develop the CSU roadmap and schedule.
This detailed documentation (specifications, procedures, instructions, etc.) contains all the
necessary information to assure an efficient execution of (pre-) commissioning activities,
including details about risk mitigation measures, the final integration, required materials and
information like utility requirements. When ready, this documentation should be considered
as the basic package to start execution.
GS.06.525366.52536 8 CONFIDENTIAL
The systemization process should be applied to all project civil and buildings works, utility
units, process units, site integration (interconnecting, ISBL and OSBL) and general facilities,
and all supporting power and instrument facilities in both Greenfield and Brownfield projects3.
1.5.1 System
A system is a complete assembly of piping, vessels, equipment, instruments, electrical
supplies, etc. that has a singular purpose within a unit. A system can be commissioned and
brought to ready for start-up (RFSU) status to a significant extent independently from other
systems.
1.5.2 Activity
An activity is a predefined (biggest) piece of work, which can be completed independent of
other activities when certain start conditions are fulfilled. Execution of an activity changes the
state of a system from a defined starting point to a defined end point.
After completion, the activity will result in start conditions for other activities.
1.5.4 Pre-commissioning
Pre-commissioning of a new or modified facility is the last part of the construction or scope
execution phase and is therefore sometimes also referred to as mechanical completion.
It is the system completion work that starts when a process or utility system is mechanically
erected (typically after the pressure or hydro test) and ends with the process or utility system
having achieved the status mechanically complete.
Pre-commissioning activities4 include the preparation for commissioning or testing the
Complex or any part thereof prior to ready for commissioning e.g. checking to confirm
3
Systemization can also be a useful tool for setting up a construction site with all facilities that are
required to execute the project. Quite often this is not done properly which has a big impact on project
execution (e.g. teams not located together or part of facilities has to be removed due to unforeseen
issues etc.)
4
Typical pre-commissioning activities:
Equipment checks, PEFS check (walk down) and punching
Cleaning of pipes (water flushing, air blowing, steam blowing, chemical cleaning, etc.)
including reinstatement
Instrument loop checks
Panel function tests
Energising electrical equipment and running motors light (power supplied by a commissioned
electrical system)
Alignment of and coupling of rotating equipment
Stroking of control valves
In line calibration of instruments
Initial leak/ tightness tests (at low pressure)
Preservation
GS.06.525366.52536 9 CONFIDENTIAL
containment, continuity, all materials present, internally clean, free or foreign material, etc.
Such activities are carried out on a single discipline basis and require materials, equipment
or systems to be energised, but do not require the introduction of process fluids.
At the end of pre-commissioning a system is mechanically complete (MC), i.e. clean, tight
and all components functionally tested.
1.5.6 Commissioning
Commissioning of a new or modified facility means the phase that starts when the first
process or utility system is ready for commissioning and ends with the last process system
having achieved the status commissioned.
Commissioning activities6 include the preparation for operation or operating the Complex or
any part thereof prior to RFSU, e.g. dynamic functional testing, simulation runs, etc. Safe test
media are needed for this stage to demonstrate stable interaction between systems (i.e. no
introduction of hydrocarbons).
The tests7 must simulate all operating modes/ conditions, such as start-up, ramp-up, various
processing modes/severity, shutdown, emergency modes and most important failure modes.
5
Although there may be different approaches as to whether the owner or contractor is responsible for
commissioning, in either case it is important that the owners organisation is heavily involved in the
actual execution of commissioning to ensure there is a more integrated handover.
6
Typical commissioning work:
Verifying conditions for operating the system are safe and comply with codes and regulations.
Filling process and utility systems with test medium, such as water/ glycol/ air/ nitrogen.
Charging with catalysts, filling absorbents, hot oils and cooling media
Load testing of electrical system by loading of equipment and pressuring up
Initiating flow
Establishing heat exchange, from non-fired systems
Stabilising flow
Tuning control systems
Testing utility and process systems for the hydraulic, dynamic and containment performance
Oxygen freeing
7
Typical tests to be confirmed during commissioning:
Confirming adequate behaviour characteristics from prototypes, by e.g. trial runs on simulated
feeds or test feeds to establish desired productivity and reliability
Compiling commissioned systems into more complex bigger systems for testing of required
dynamic stability and responses up to unit level
Testing security, protection and safeguarding systems for their correct and timely actions
Testing failure/effect characteristics, and consolidation actions, including reset functionality
Testing emergency modes and load shedding
GS.06.525366.52536 10 CONFIDENTIAL
1.5.8 Start-up
Start-up means the phase that starts with the receipt of the first processing feedstock
(hydrocarbon or chemical feed to be upgraded) and ends with the last operation mode on the
feed stock in the unit having achieved the status Acceptance of Work8
Load testing process information and digital control systems, and sequence of event recording
systems
Testing fire, gas detection, remote operating and emergency communication systems
8
Typical start-up activities are:
Verify readiness for introduction of hydrocarbons and or chemicals. Increase severity of work
permit system authorisation accordingly.
Replace test medium for actual process medium.
Verify maintaining tightness, cleanliness, functionality, stability, adjustability of system
behaviour.
Increase severity of operating conditions in pressure and or temperature.
Fine tune instruments for new conditions, ensure proper readout.
Activate catalysts.
Run QMIs on actual process fluids.
Test all process modes, all feed and product modes, maximum capacity and turn down mode,
process dynamics, controls, operating windows and flexibility to move in windows.
Test mode-switch procedures and product property control dynamics.
Test process behaviour to emergency response.
Test run off routing.
Test injection facilities and controls.
Perform final test run, proving capacity, process technology, product properties, system
responsiveness, energy consumption, yields, flexibility, stability, reliability
GS.06.525366.52536 11 CONFIDENTIAL
A typical CSU schedule is available at various levels of detail. The lowest level is based on
single activities and is used for daily execution of the CSU work. Rolling up the detailed
schedule produces higher-level schedules for management overview, i.e. the higher-level
schedule is based on all the detailed information.
A CSU schedule can also consist of a network of schedules in the case of a complex project
e.g. multiple process plants that are part of the overall project.
1.6 Abbreviations
CSU Commissioning and Start-up
DCS Distributed Control System
EPC Engineering, Procurement and Construction
FSI Flawless Start-up Initiative
HIPPS High Integrity Pressure Protection System
IFC Issued for Construction
IFD Issued for Design
IPS Instrumented Protection System
ISBL Inside Battery Limits
KPI Key Performance Indicator
LI Lead Indicator
MCC Motor Control Centre
MC Mechanical Complete
MOC Management of Change
OSBL Outside Battery limits
PEFS (/P&ID) Process Engineering Flow Scheme (/Piping and Instrumentation Diagram)
PFS (/PFD) Process Flow Scheme (/Process Flow Diagram)
PERT Project Evaluation Review Technique
RFSU Ready for Start-up
SAT Site Acceptance Test
SAP Systems, Applications and Products in Data Processing
SU Start-up
TA Turn around
PLC Programmable Logic Controller
UPS Uninterrupted Power Supply
WEFS Work Execution Flow Scheme
GS.06.525366.52536 13 CONFIDENTIAL
2. System Definition
2.1 General
The process by which the facility is split into smaller portions, i.e. systems, is known as
system definition. Separating the assets into systems will simplify the definition of the
individual pieces of work.
Geographical
P roces s Unit
area boundarys Unit
Unit
Unit
Units: separate process units within a facility
Unit
Unit
Unit
Non
Geographical
C om m issio n in g
S ystems
Unit
Systems: separate identifiable parts of a unit where
area boundarys
Unit
Unit
Unit
commissioning progress can be made
Unit
Unit
Non
Geographical S ub-S y stems
Sub systems: the smallest part of a commissioning
area boundarys Unit
Unit
Unit
system that can be isolated and made available for
Unit
Unit
Unit
specific work execution
Systems are defined from a commissioning point of view and will be as large as possible
parts of a unit with which operations can make individual commissioning and start-up
progress.
A system is a composite assembly of hardware that has a singular purpose within a unit and
a system can be commissioned and brought to ready for start-up (RFSU) status to a
significant extent independently from other systems.
The systemization approach must be applied to all process (including utility) systems but also
to the non process systems i.e. civil and building works as well as all supporting electrical
and instrument facilities.
A multidiscipline team of operations, commissioning, and project engineers may use "issued
for Design" (IFD) Process Flow Schemes (PFS or PFD) to start identifying the
commissioning/ operational systems and the sequence for start-up. Under the agreed start-
up sequence, the system that is placed in service first is considered the provider of the
service; the system receiving the service is designated the receiver system.
For example, for timing reasons it is better to define a single tie-in as a separate system even
if it is only a very small piece of hardware (in case the tie-in is first constructed during a
shutdown/ turnaround and the new system constructed/ connected much later). Furthermore,
determine issues concerning sequence and pre-requisites for commissioning and start-up
per unit and provide lists of unit and generic site issues. The defined process and utility
systems will be in principle capable of being isolated (by block valve / spade).
Although system definition facilitates commissioning and start-up execution of the facility, it is
also advantageous to link the systemization results into other management controls (e.g.
mechanical completion, commissioning and start-up preparation management controls). For
this reason system definition should start as early as possible.
Moreover construction management needs to be informed very early in the project what the
sequence is for system completion so that timely (pre-)commissioning and start-up can take
place (start-up driven asset completion).
A unique system number will be assigned to each system. If both the contractor and owner
consistently use the system numbers, it can facilitate clearer communication and tracking of
project status between the contractor and the owner. Deliverables are defined per system.
Documentation files are accumulated per system. Handover is normally done by system.
System boundaries will normally be at manual isolation points for process and utility systems,
i.e. manual isolation valves or isolation blinds/spades. The isolation points are included in the
system that is placed in service/ handed over first.
System boundaries and system numbers shall be added to the PEFS using intelligent CAD
systems, as an item to be filtered out during normal printing e.g. PEFS issue. Attribute fields
shall be set up within all piping equipment and instruments etc. such that all items within a
system boundary will have the system number identified with it and can be reported via that
system number. This will enable the production of single system drawings and the addition of
system boundary markers to the piping data sheets (isometrics) with again links to other
databases i.e. instrument, electrical, civil such that the compilation of components up to
process/utility system level can easily be seen.
System boundaries shall be clearly indicated. An example of a system break symbol added
to the CAD file is the following:
9
Category 4 and 5 are project specific and may be not applicable for TA projects
GS.06.525366.52536 15 CONFIDENTIAL
140 140
IA P_
01 02
Note: All equipment, piping etc. to the left side of the system break symbol is in the scope of
system 140IA01, where as all equipment piping etc. to the right side of the symbol is
in the scope of 140P_02.
In addition to the above the following information block will be completed and added in the
same way above the drawing title block.
It is preferred that the systemization colour coding is also marked up electronically in the
same way using the intelligent CAD package. However, if this is not feasible for a particular
intelligent CAD package or considered too costly or time consuming, colour coding by hand
for each issue of the system definition drawings is acceptable. For a hand mark-up a fresh
set of drawings incorporating the systems breaks and the information block shall be printed
off and marked up for colour coding of the individual systems so they can be easily
recognised when looking at the drawing.
Appendix B provides narrative guidelines to assist in determining the scope of a system and
its boundaries.
The list of systems (system index) and definition of the systems shall be used in detailed
planning so that scheduling of mechanical completion is aligned with commissioning
activities.
If relatively small systems are defined the result will be a significant increase in the number of
relationships between systems and therefore it will be difficult to separate activities on a
system level. This means that a (large) number of systems will be needed to carry out a
single commissioning activity, resulting in inefficiency.
GS.06.525366.52536 16 CONFIDENTIAL
Consider the following example of a product export function spit into four systems (tank,
suction line, product export pump, discharge line):
The yellow boxes represent pre-commissioning activities, the blue boxes represent
commissioning activities.
Compare to:
Eq check Bumptest
Prod exp
syst1 Cleaning Reinstate Looptest Fill- Leak test Start& Test
static trip circulate system
tests
The pre-commissioning activities can be described well with the upper system definition, but
to carry out the first commissioning activity, filling the tank, all four systems are required.
Further more activities and vertical relationships are required to describe the commissioning
part of the work (inefficient).
The lower system definition is efficient, the commissioning activities can be described on one
line and the pre-commissioning activities represent the same work as in the upper case (no
loss of information).
If on the other hand, too large systems are defined, parallel sequences of commissioning
activities can be distinguished. This will often lead to the definition of sub-systems to reduce
the overall schedule time needed to complete all activities of the system.
Consider the following example of two product export functions (two different products)
combined to one product export system:
Eq check Bumptest
P1
Cleaning Reinstate Looptest Fill TK1- Leak test StartP1& Test sub
Prod exp static trip circulate system1
tests
Eq check Bumptest
P2
Cleaning Reinstate Looptest Fill TK2- Leak test StartP2& Test sub
static trip circulate system2
tests
In this case, it is clear that two separate commissionable systems can be identified, because
there are no vertical relationships between the commissioning activities and one part of the
system can be brought to RFSU status independent of the other part. In this case it is better
to define two product export systems.
Sub-systems
In cases where it is important to define smaller parts of a commissioning system that can be
isolated and made available for specific work execution, additional sub-systems can be
defined. This can be the case during turnarounds (TA).
Normally operations will not work on individual sub-systems, but if beneficial to the overall TA
GS.06.525366.52536 17 CONFIDENTIAL
Work (scope) execution sub systems can be defined to facilitate the scope execution and
pre-commissioning phase.
Process systems may be combined to (part of a) process unit before start-up and the
clustered systems (also referred to as Start-up (SU) Block) are normally started up in a
specific sequence, as required by the production process.
To identify process systems the following needs to be reviewed within a process unit (use
PFDs):
Functional blocks, each block has a different commissioning requirements
Circulations, to enable dynamic system testing to bring the system to RFSU status
Complex equipment, for each equipment a lot of commissioning (testing) work can be
involved
Utility services that serve the whole complex facility generally contain a utility generation part
(in utility area), a facility distribution network and utility distribution within the different process
plants.
For example Instrument air (IA); IA service may consist of following systems:
GS.06.525366.52536 18 CONFIDENTIAL
Process Plant 2
CW distribution system Cooling
Water
Servicing total facility
Generation
CW Generation systems
Process Plant 1
CW distribution system
Inside plot process
plant 1
G
MP Stm distribution
Condensate collection
A colour mark-up will be produced on one set of PEFSs showing all process and utility
systems. System boundaries will be clearly indicated. As far as practical, system end /
change points shall coincide with blinds / isolation points provided as part of the design. The
system end / change points shall also coincide as much as possible with the end / change
point of test and cleaning systems. It is recommended to set up and include the spade list for
temporary and permanent blinds required for commissioning. In line instruments and
controllers (instruments shown on the PEFS) shall be included in the process system
definition.
Generally, process and utility systems drive the WEFS development.
Mechanical Equipment
Mechanical equipment will be assigned the system number as indicated on the applicable
process system colour mark-up.
The following list provides some specific guidelines on assigning instrumentation items to
systems:
The break between instrument systems and process/ utility systems shall generally be at
the cable marshalling cabinets.
Subdivision will be applied to systems, which may serve more than one geographical
area, for example, multi core cables and junction boxes.
Individual cables and segment cables will be assigned system numbers appropriate to
the geographical area served.
External Field Bus segments will be assigned system numbers appropriate to the
geographical areas served.
Each field instrument loop will be assigned to the process system it serves.
Local indicators, pressure relief valves and other in-line devices will be assigned to the
process system they serve.
UPS, instruments and electrical supply to the telecommunication system will be assigned
instrument system numbers from the breaker at the main switchboard. This is due to the
anticipated involvement of instruments discipline in commissioning these systems.
Equipment MCCs, isolators, control cables and associated instrumentation are assigned to
the process or utility system in which the mechanical equipment is located.
Lighting, small power / convenience outlets and essential services supplies will be assigned
system numbers from the main switchboard up to the local distribution board. Downstream
GS.06.525366.52536 20 CONFIDENTIAL
subdivisions will be carried out at site, where deemed necessary, on a plant area, building,
etc., basis.
The electrical system definition shall also take into account testing requirements, contractor
scope, and safety during construction, pre-commissioning and commissioning.
Sewage services are underground piping systems and they are normally regarded as civil
facilities.
Examples are:
Oily storm water sewer
Clean water sewer
Sanitary sewer
Any requirement for early handover must be recognized where the service is needed in
conjunction with pre-commissioning activities elsewhere on the unit or plant. For example, a
significant portion, if not the entire clean water sewer should be available for disposal of
water used for hydro testing and flushing as well as rainwater.
Often underground services have no isolation points at unit battery limits hence it is possible
that a complete Plant wide service is subject to one completion.
Outside Fence10
Examples:
External feed lines from third parties
External product lines to third parties
External electrical power cables
External telecoms
Inside Fence11
In principle each interconnecting line/ cable that is routed via a pipe rack connecting systems
in different geographical areas may be a separate system (different Contractor, timing, area)
Examples:
From process plant 1 to process plant 2
From process plant to product storage
10
External interfaces with the outside world, different company
11
Interfaces between plants/ areas, same company
GS.06.525366.52536 21 CONFIDENTIAL
Utility distribution network connecting utility area with the different process plants
Chemical distribution network connecting chemical storage with the different process
plants Electrical distribution network
Tie-ins
Tie-ins (connections to existing systems) are an integral part of the corresponding system,
unless otherwise specified. Tie-ins that are required independently of the corresponding
system, for example, tie-ins to third parties (electrical grid, feed stock lines, product lines etc.)
will be clearly marked and assigned a separate system number.
Only in case of tie-ins to existing lines, a hydro test pack may extend into existing systems.
Note: Variations on this system numbering can be applied as long as a unique number
is allocated to a system, and within a system unique activity numbers are defined.
Scope
Uniform system numbering applicable to both systemization for green field projects and
systemization for existing brown field organisations (e.g. systemization for Flawless
Turnaround)
Definitions
Character = Alpha-numerical characters like A-Z, 0-9
Digit = Numerical value 0-9
Letter = Alphabetic character A-Z
Constraints
Primavera Project Planner12 is one of the common used scheduling tools.
The maximum number of characters for the system number is eight taking into mind that
Primavera can accommodate activity numbers of maximum ten characters. This will leave
two characters for the activity sequence number for each system.
Constraints of the CAD package also need to be considered when developing the system
numbering scheme. Additionally, if system numbers will be added to other databases, e.g.
Intools, Winpcs, these requirements need to be considered as well.
Guideline
The following system numbering protocol or similar is advised to be used with Primavera
(P3)13:
Char: 1 2 3 4 5 6 7 8 9 10
A A A B B C C (C) D D
12
In case scheduling software other than Primavera Project Planner is utilised on a project, the system
numbering should be modified to meet the numbering requirements of that software tool.
13
To make large network easier to analyse, its helps to identify activities with a smart activity
numbering system. It makes analysing of the network schedules a lot easier if links (predecessors or
successors) can be recognized from the activity number.
GS.06.525366.52536 22 CONFIDENTIAL
Function Unit number Service Code (Sub) System Sequence Activity Sequence
reference indicator indicator
Examples:
Unit 1400 AAA = 140
Unit 3400 AAA = 340
Unit 8380 AAA = 838
Service Code BB
Two characters used to identify the service code of the process/utility system. A list of
commonly used acronyms is shown in appendix A. It is important to adjust the service code
to bring it in line with the acronyms used on the project/site PEFS.
Examples:
Boiler Feed Water BB = BF
Flare BB = F_ _ is one underscore _
st
1 Distillation system of BB = P_ P stands for process system
fractionation unit HCU
In case sub systems are used (or anticipated to be used for future turnarounds), it is
suggested to keep the first two Cs as identifier for the main systems as above and the third
C as the indicator of the sub-system (A-Z). The main system (e.g. 02) will then include as
well the all sub-systems (02A to 02Z) of that main system.
Examples:
Boiler Feed Water system 1 CC = 01 No use of sub systems on
Boiler Feed Water system 2 CC = 02 the project
st
1 Distillation system of fractionation CC = 01
unit HCU
nd
2 Distillation system of CC = 02
fractionation unit HCU
nd th
2 Distillation 14 sub-system of CCC = 02M Use of sub systems on the
fractionation unit HCU project; Maximum 99 systems
with each possibly 24 sub-
systems (I and O excluded)
should be sufficient for one unit.
Especially for Flawless Turnaround a systemization master file with sub-systems should be
created.
14
In case the unit numbering is of the format ##00 (where # is a digit; U-1100, U-3900, U-8800), this
leaves the opportunity to change the standard proposed numbering system from AAABBBCCDD to
ZAABBBCCDD (where Z can be a project identifier or train number and AA the shortened unit
number).
15
I and O are excluded as these characters are too similar to zero and one
GS.06.525366.52536 23 CONFIDENTIAL
Systems are defined from a commissioning point of view and will be as large as possible
parts of a unit with which Operations can make individual commissioning and start-up
progress.
Sub-systems may be defined as smaller parts of systems (i.e. one equipment, one special
instrument), which can be isolated and made available for Turnaround execution work as a
separate scope item. The sub-system will only be used in the turnaround if there is a specific
need for it.
Using two digits (01-99) for the activity sequence indicator should be sufficient to reference to
all activities for one (sub-)system.
Examples:
Green field project
Pre-commissioning activities DD = 00 till 19 The ranges can be changed
Commissioning activities DD = 20 till 49 according to the number of activities
Start-up activities DD = 50 till 99
Referring to the 8-Step Flawless
Turnaround Turnaround approach
Shut-down activities DD = 00 till 09
Decontamination activities DD = 10 till 19
Scope execution activities DD = 20 till 59
Pre-commissioning activities DD = 60 till 79
Commissioning activities DD = 80 till 89
Start-up activities DD = 90 till 99
Examples
140CW0232 Unit 1400, Cooling Water system 2, Overall system, activity
32 (TA=scope execution activity; Project=Com activity)
th
400P_03D95 Unit 4000, Process system 3, 4 sub-system D, Start-Up
activity 95
905P_0205 Unit 9050, Process system 2, Overall system including all
sub-systems or not having sub-systems defined
330MS01A20 Unit 3300, Medium Pressure Steam, System 1, sub-system
A, activity 20 (TA= start of scope execution activity; Project=
start of Com activity)
GS.06.525366.52536 24 CONFIDENTIAL
3. Activity Definition
3.1 Work Breakdown
After the system definition has been completed (and hence the assets are broken up into
smaller parts) the process of defining activities for each system can be started. It is
recommended to start the activity definition after the system definition has been finished and
prior to determining the relationships between the activities of different systems.
What is an activity?
An activity is a predefined (biggest) piece of work, which can
be completed independent of other activities when certain
start conditions are fulfilled.
Executing an activity changes the status of a system
Dry functional testing (DCS available)
Important:
Identification of vertical relationships
(= between different systems)
All activities on all systems make up the total (defined) work to be executed for the entire
facility.
For the definition of activities two aspects are very important. The first is the level of detail
and the second is that all activities added together shall cover the complete work process
without any gap or overlap.
GS.06.525366.52536 25 CONFIDENTIAL
This means that the complete work process could be described as one activity, but also as
thousands of activities depending of the level of detail. The optimum is when the level of
detail is such that it can be easily utilised to plan and control the execution of the work
process. It also means that all the relationships can be indicated between the various
activities.
The activities will normally be defined as sequential steps per system. Sometimes two or
more parallel strings of activities can be distinguished. In that situation it is strongly advised
to check the system definition for the size and limits and consider splitting into two separate
systems whose activities can be carried out in parallel.
According to what has been discussed above an activity can be defined as a predefined
(biggest) piece of work, which can be completed independent of other work, when certain
start conditions are fulfilled. Execution of an activity changes the status of a system from a
defined starting point to a defined end point, i.e. a system that is mechanically erected and
critical items removed becomes upon completion of the cleaning activity a clean system
and upon reinstatement a cleaned and closed system.
After completion, the activity will result in start conditions for other activities.
Tightness
Test
The activities will be the building blocks for the development of the logic and work execution
flow schemes (WEFS), but will also be used to specify other requirements (human resources
including vendor support, special tools, temporary equipment, utilities, etc.).
Activity definition will thus be the basis for many more steps in preparation for the CSU
phase.
In order to come to a well-balanced activity definition the main functions and requirements of
systems need to be reviewed first.
Thinking in main system functions helps in identifying the system specific activities and
prerequisites. Then defining the activities can start using a project activity list template. The
listed activities should be checked later against the generic CSU activity sequence (see
further in this paragraph).
The level of detail of an activity definition should be such that the activity description provides
enough information to a qualified operator and/or commissioning engineer to split up the
GS.06.525366.52536 27 CONFIDENTIAL
activity into one or more tasks, which are developed into detailed CSU procedures at a later
stage.
The following lists give an overview of standard activities for the pre-commissioning,
commissioning and start-up phases. These are the kind of activities that are found in every
CSU plan.
PRESSURIZE SWITCH
The activity description can also include all preparation work and must be linked to the
previous and the next activity without any gap or overlap.
GS.06.525366.52536 28 CONFIDENTIAL
16 hrs 12 hrs
Tightness
Test
28 hrs
Walk down system and Pressurize with N2 up to 25% of Test P Disconnect temporary facilities
check isolations at system
Maintain pressure for 1 hr, monitor pressure
Connect hoses for decline
temporary N2 connection
Pressurize with N2 up to 50% of Test P
All flanges where leaks
Etc.
are to be monitored are
taped Depressurise (keep inert)
In this example the bottom line single tightness test activity represents exactly the same
amount of work (in terms of tasks to be done and activity durations) as the upper line
Prepare -Tightness Test - Reinstate. For efficiency reasons and overview it might be better to
list just the activity Tightness Test as one activity, as long as no gaps or overlaps are
introduced in the sequence of activities, however splitting it up as above is not wrong.
It needs always to be verified that the activity definition serves as a logical basis for task
definition, i.e. when the activities are worked out in tasks, this should follow a logical
sequence of work also, with no gaps. The activity then is a roll up of tasks, like in the
example above.
Commissioning and start-up activities relate in most cases to a set of standard activities per
system.
Generally, the system is first walked down and the status is checked (Evaluate), i.e. all pre-
commissioning testing is completed. Then the system will be prepared (Compile, Connect) to
enable component testing (pumps, instruments, etc.). Next the system is charged with a test
medium and energized (pressurized) to establish a liquid or gas flow for system testing under
dynamic conditions. It is possible that at this stage some controllers can also be checked and
tuned.
Next in the generic sequence are the more complicated system safeguarding tests (for which
it may be necessary to combine and line up related systems first). In all of these steps the
components of the system will be tested with increasing severity of process conditions,
varying from benign test media via mild process conditions to normal operating process
conditions. A testing program needs to be developed to structure all the testing activities in
component tests, (complex) system tests, unit and plant tests
8. Inert
9. Replace with process medium
10. Circulate on process medium Integrated multi
11. Ramp up temperatures and pressures disciplinary
12. Feed cut in & Tune, Stabilize system tests
13. Operation at low throughput
14. Operations at maximum throughput Integrated multi
15. Trip testing & failure recovery disciplinary
16. Test Emergency Mode plant tests
17. Operating modes testing
18. Reliability test (initial period of Operation)
19. Performance test
20. Performance measurement, lessons learnt and changes
21. Declare system ready for controlled production
This set of standard activities can be used as a check list for earlier defined activities or can
be used to start with and adjust for specific system requirements. The 21 steps above are
typical for commissioning and start-up with the exception that for start-up the steps for one
system are more related to steps of another system for the execution. A couple of systems
may need to be integrated in order to progress with the start-up activities; start-up activities
tend to be multiple system/ unit related rather than single system related.
The objective is to create a realistic road map of activities, to be represented in a WEFS and
to derive a realistic CSU schedule.
Vertical logic relationships between activities on different systems are not only hard technical
links but can also belong to a different category:
Technical
To inert a system Nitrogen is required
To start up a boiler, Boiler Feed Water is required
Process flow relationships
HSE
Connect to flare before introducing hydrocarbons in the process plant.
Safety systems (Fire and Gas, Fire Fighting equipment, sprinkler etc) and
communications systems fully operational during commissioning phase
16
There is also a Start to Finish relationship (SF, successor activity must be started in order to finish
the predecessor activity), but that is very rarely used.
GS.06.525366.52536 30 CONFIDENTIAL
Constraint
It is not possible to commission two steam turbines at the same time (lack of resources
and vendor support; same for Gas Turbines)
It is not possible to commission two cold boxes of an Air Separation Unit at the same time
Quantities of imported media, e.g. water supply for pre-commissioning
Contract
Commissioning (e.g. functional testing) and start-up activities shall be executed from the
DCS
Note: It is important is to list all premises made regarding relationships, keep track and
verify!!
One activity list will be prepared per commissioning / operational system. The activity list is a
spreadsheet containing the following information per activity:
1. Activity number: this is the system number plus two additional characters (see
system numbering section)
2. Activity: concise description of the work
3. Description: column to provide detail behind the activity for procedure writing
4. Clarifying Notes/Remarks: any clarification to the activity description and/ or special
items to be listed regarding safety, special tools, first fills, temporary equipment,
vendor requirements, etc.
5. Phase: indicate project execution phase: pre-commissioning, commissioning, start-
up, ramp-up, initial operations
6. Relationships: indicate relationships with other systems (link to activity)
7. Duration: estimated duration of the activity
8. Calendar: indicate calendar for pre-commissioning, commissioning, start-up work, i.e.
10, 16 or 24 hrs/day
9. Estimated Man hours: calculated on the basis of human resources required to
execute the activity and the activity duration.
10. Human resources, which people (skills, discipline) are to execute the activity
All activities listed on one system jointly define the total scope of work to be done on the
particular system. All testing activities (component tests as well as (complex) system tests)
should be included in the activity lists.
GS.06.525366.52536 31 CONFIDENTIAL
While making the activity listings it is important to indicate relationships with activities in other
systems as well as the need for special tools, temporary facilities and consumables. For
schedule development it is also required to indicate preliminary durations as well.
Activity sheets can also be used as a basis for writing procedures and/or work instructions.
GS.06.525366.52536 32 CONFIDENTIAL
After the system definition is done and the number of systems is known for each plant/ unit,
some thought needs to be given on how to divide the systems over the drawings:
In case of a small unit (less than a total of 75 utility and process systems) one WEFS
can be developed
In case of a large complex consisting of multiple plants (each 100-150 systems) we
may need to develop two sheets per plant.
The layout is such that on the left hand side of the drawing all the systems are listed
vertically, starting with basic utility systems17 first, then the rest of the utility systems18, then
auxiliaries19 and finally the process systems.
17
DCS, power, instrument air/ tool air, etc, supporting the (pre-)commissioning of the rest of the utility
systems and pre-commissioning of process systems
18
Cooling water, Steam and Condensate systems, etc, supporting the commissioning of process
systems
19
Flare, Drain, Fuel Gas, etc., supporting the start-up of process systems
GS.06.525366.52536 33 CONFIDENTIAL
Activities
Systems
Relationships
WEFS Development
Make sure that all logic link references between the different sheets of WEFSs (when
applicable) are consistent.
Make sure that all testing activities are incorporated into the CSU logic and reflected
on the WEFS.
The drawing should be readable from left to right, meaning that the X-axis represents
a (non-linear) timeline. Therefore, try to avoid backward relationships when linking
activities.
Make sure that the CSU philosophy is well reflected in the WEFS.
Do not show durations of activities on the WEFS in any format, since this does not
contribute to the readability of the drawing and in general it is a good practice to avoid
duplication of information for reasons of document maintenance.
GS.06.525366.52536 34 CONFIDENTIAL
CSU philosophy
20
Only level 3 WEFS is suited for execution of activities, therefore the high level logic charts are
referred to as Work Flow Schemes. (WFS)
GS.06.525366.52536 35 CONFIDENTIAL
Level 321 WEFS is the lowest detail of WEFS for use by the people on the work
floor, i.e. shift supervisors.
Activities (level 4) within the same system that have only horizontal links with each other can
be grouped together to bigger (level 3) groups. It is recommended to build the WEFS based
on level 3 groups to maximize the overview of CSU activities and to keep it as simple as
possible.
To create the level 2 WFS we define groups of level 3 group activities, across multiple
systems. This process is called roll-up. In this case we may loose vertical links. Again for
creating the level 1 WFS we roll-up the level 2 etc. The higher-level activity always consists
of a group of lower level activities. The CSU schedule is set up with the same approach.
This grouping is visualized in the WFS/WEFS by drawing circles, boxes or clouds around the
activities that are grouped together. These clouds are put in a different layer to enable
switching on and off.
The difference with the WFS as described in the paragraph above is that in this case the
WFS is the lowest level of logic developed, it is not a roll up of a lower (level 3) WEFS.
Block schemes or initial Process Flow Schemes are used to identify SU blocks, i.e. parts of a
unit that can be started up individually.
Typically SU blocks are put on the vertical axis of the WFS and the phases pre-
commissioning, commissioning, start up, ramp up are used as activities22.
The aim is to frame the CSU phase of the project and generate information (via high level
CSU schedule (planning model), see next chapter) on:
CSU philosophy (determine main steps for CSU)
CSU total duration
Project milestones
Critical path
Hand over sequence of systems, SU blocks or units
Interfaces
Resources
This information can be used for early decision making and also can be used for the
Engineering Procurement and Construction contracts.
21
Note level 3 and level 4 are both based on single activities, the difference is that in level 3 the
horizontally linked level 4 activities (within the same system) are grouped and it still shows all the
vertical links.
22
Since very rough building blocks are used to develop the logic, the CSU can be optimized when
building the detailed CSU execution logic in the detailed engineering phase of the project, because the
logic links can be defined more accurate.
GS.06.525366.52536 36 CONFIDENTIAL
A planning model:
Consists of Activities that are logically linked describing a work process for an Asset from a
defined starting point to a defined end point with a Timeline and Resources
The CSU schedule should be a clear reflection of the CSU phase, containing all of the work
scope, resources, contractual milestones, logical relationships and interfaces with the outside
world. It should present the timeline of the CSU phase. The schedule should be built in is
such a way that it is telling the story of the CSU.
The information from the activity lists and the WEFS is used to produce a CSU network
schedule for the facility. Actually, the WEFS can be read as a PERT chart. When durations of
activities are added as well as start dates for commissioning per system, a Gantt chart (a
popular type of bar chart that illustrates a project schedule) can be produced from the data.
The CSU schedule can be used as a tool to optimize the CSU phase and decision making
(based on facts) and is an enabler to control the project:
Sequence of hand-over; start-up driven asset completion23
Logic evaluation, estimating product in tank date, first shipment date or other milestones;
Critical path analysis for the CSU and early identification of potential problem areas
What if? scenario studies (potentially resulting in fall back plans)
Estimate of the number of resources, by assigning man power (disciplines) to the single
activities
Identification, timing and duration of vendor/ specialist support required at site
Levelling (balancing) of man power
Alignment of the different parties of one organization
Status, progress, forecast monitoring and driving the execution of the agreed plan.
But beside this normal schedule information, the schedule can also be used to generate
information on:
Monitoring of potential problems;
Utility requirements and/or production;
Logging of identified novelties and complexities;
Logging of % mitigation for novelty and/or complexity items;
Adoption of durations for novelties and complexities (in line with % mitigated);
Timing and assigning of specialist and or vendor representatives;
Timing and identification of utilities (service, quality, amounts, etc.);
Workday (shifts) evaluation;
Coinciding events
Identification of hazards
Basis for HSE in transition programs.
Typically the CSU schedule is not directly linked to the construction schedule.
Reasons for this are mainly that commissioning and start-up is performed by another
organization (often the owners involvement becomes leading) and the calculation units of
23
This also means handover from construction to CSU team or when systems are not handed over
(e.g. power supply) it defines the date when the power shall be available for testing of other systems.
GS.06.525366.52536 38 CONFIDENTIAL
days for engineering up to construction has to be changed to hours with several calendar
(shift) changes. It is necessary though to have a CSU schedule available as early as
possible. Because the construction schedule and the CSU schedule are two independent
schedules some clear interfaces between these two schedules need to be defined (for
example, start and end points of the schedules and information transfer). It is recommended
that in a project control procedure the interface and the transfer of data is outlined to avoid
misunderstandings between the various key stakeholders.
The activities in the CSU schedule should have a weight based on man-hours. The physical
progress should be measured in tasks completed.
It is recommended that a complex or novel activity, as identified in the FSI module novelty
and complexity be marked in the schedule. One can now add a risk factor percentage of
mitigation to the duration of this activity duration. Meaning that if the novel or complex item
level of mitigation is increased the duration of this activity could be corrected (reduced)
accordingly.
Resource Loading
It is highly recommended that the CSU schedule is resource loaded. After building the initial
schedule based on the activity sheets and WEFS, critical resources need to be added to the
schedule, like operators and critical CSU support staff like process control engineers, etc.
After loading of the critical resources, the resource loading profiles of the project need to be
analyzed for each critical resource. It should be checked if the numbers required look
reasonable (as being expected), and that the availability of that resource matches the
requirements. If requirements are too high or there are high peaks, Primavera has the option
to level the resources. This will indicate if it is possible to execute these phases of the project
within the allocated timeframe and with the required / available resources.
Complementary to normal scheduling for CSU some other information can be linked to the
schedule model such as utility requirements, storage capacity, production flows. These can
be placed in time now, for better understanding / scheduling.
Analysis
A critical path analysis should be carried out on the level 4 schedule. The most important
check is do I see in here what I expect to see? A large number of activities with a large float
are suspicious and need to be verified for missing logic links (links between activities).
It is highly recommended to introduce key milestones to the CSU schedule. The milestones
are defined as hammock activities. Milestones have to be evenly distributed over the
complete duration of the CSU phase. These milestones should be seen as schedule lead
indicators (LIs).
GS.06.525366.52536 39 CONFIDENTIAL
Management of Change
A management of change procedure should be developed and agreed to control changes to
the schedule. It is very important that any changes made are depicted in the activity sheets,
WEFS and the schedule. Consistency of these three documents is important for success.
Blank
Blank
Blank
Train identification is either in activity code (1st character) or WBS structure (1st character)
To make large networks easier to analyse, its helps to identify activities with a smart
activity numbering system. It makes analysing of the network schedules a lot easier if
links can be recognized from the activity number. Reference is made to Section 2.6,
system numbering.
GS.06.525366.52536 41 CONFIDENTIAL
6. Turnaround
PLEASE NOTE THAT THIS CHAPTER IS IN DEVELOPMENT AND NEEDS TO BE
ALIGNED WITH THE FLAWLESS TURNAROUND MODULE
In brown field TA (revamp) projects the following eight distinct phases can be distinguished:
Compared to a green field project, a brown field TA (or revamp) project has additional
phases in which different type of work needs to be executed. In case the scope execution in
a brown field project can be considered the equivalent to the construction phase of a green
field project and the post turnaround the equivalent to initial operations, the additional steps
are steps 1-3 in the picture below:
Step 1:
Pre Step 2:
Turnaround Shut Down Step 3:
Decontamination Step 4:
RFSD:
Scope
Ready For Execution
Shut Down RFO:
Release From
RSO Operations
Ready to Start
Operation Step 5:
Pre-
Step 6: Commissioning
Step 8: Step 7: Commissioning
Post Start Up MC:
Mechanical
Turnaround RFC Complete
RFSU: Ready For
PA: Commissioning
Ready For
Plant
Acceptance Start Up
1: Pre-Turnaround
In the pre-turnaround phase the unit or plant is prepared for shutdown. At the end of this
phase the plant is Ready For Shut-down (RFSD).
2: Shut-down
RFSD is the actual start of the turnaround and the units will be shutdown independently. The
shut down activities are unit related activities, i.e. feed cut out affects the whole unit.
GS.06.525366.52536 42 CONFIDENTIAL
3: Decontamination
After shutting down the unit will be decontaminated, the decontamination activities are
related to systems within the unit.
Typical decontamination activities are:
Decontaminate
o Steam-out/ purge with nitrogen
o Flushing (water/ soap/ chemical as applicable)
o Rinse
o Drain
o Depressurize
Check for Hydrocarbon free
De-energize
o Electrical motors
o Steam and E-tracing
Isolate for scope execution
After decontamination all energy sources are confirmed to be isolated and the systems are
Released From Operations (RFO) (in some cases also called Released To Construction
(RTC)). The systems are handed over from operations to the maintenance team that actually
carries out the scope execution.
In the scope execution phase all scope items of the turnaround are executed, and after pre
commissioning (equipment checks, component functional testing, initial leak testing) the TA
scope item is declared mechanically complete (MC) on an individual basis. When all scope
items within an operational system become MC, then the system becomes Ready for
Commissioning (RFC).
The CSU activities in brown field projects are very similar to the CSU activities in green field
projects, the difference is that in brown field projects there are two execution phases that are
system based, decontamination as well as commissioning phase.
For commissioning, systems can be defined to suit best the dynamic testing / tightness
testing requirements (testing circuits).
Note: Ideally, an identical system definition can be used when describing decontamination as
well as commissioning activities.
It is important is identify all activities to be executed; system definition shall always support
these anticipated activities during execution phases of a green field or brown field project.
Commissioning24 is leading; most likely several commissioning systems can be
decontaminated together.
24
In green field projects commissioning consists of a significant amount of (dynamic) functional testing
of systems with test media to prove correct functionality.
This is not so much the case in brown field projects since the system dynamic behaviour is in most
cases well known and the system related activities may be limited to tightness testing/ oxygen freeing.
GS.06.525366.52536 44 CONFIDENTIAL
Primavera can also supply a PERT chart (a network diagram) of a schedule, showing
activities and relationships. However the readability of these charts is not straightforward
since they require long lengths of paper. People that use a logic chart can therefore not use
these print outs for easy tracking or publishing and as said readability is very limited.
GS.06.525366.52536 45 CONFIDENTIAL
Initially, project teams define the final Key Performance Indicator(s) for each Q area, the path
to meeting the final KPI is developed (Q plans with intermediate lead indicators).
All of this FSI related work will result in a minimum of surprises during the CSU phase and
therefore a manageable CSU phase.
Activities and timing are built into each CSU plan to verify the quality of work done in the
preparation phase.
8.1 Tightness
Each CSU plan will have tightness testing activities performed during pre-commissioning and
commissioning, i.e. stepwise pressuring up a system with benign fluids ultimately close to
operating pressure. In pre-commissioning this could mean a low-pressure leak test using air,
during commissioning operational tightness testing using nitrogen verifying internal and
external tightness.
Adhering to the Tightness Q plan will result in a minimum of leaks during commissioning and
start-up and therefore will make the schedule more predictable.
The system PEFSs could be used as a starting point for the development of tightness test
packages. During the system definition phase, as a minimum a check needs to be done to
verify that the bulk of the tightness packages (> 99%) are not crossing any system
boundaries.
8.2 Cleanliness
The cleanliness aspects are addressed in the flushing, blowing, jetting and/or steam blowing
activities during the pre-commissioning phase. A clean build philosophy and mindset will
result in minimum cleanliness issues. In each CSU plan verifications on system cleanliness
shall be built in (visual inspections, pulling strainers, start-up screens etc.).
The systems PEFSs should be used as a starting point to develop the details for these
activities. During the systems definition phase as a minimum a check needs to be done to
verify that the bulk of the cleanliness packages (> 99%) are not crossing any system
boundaries.
8.3 Integrity
The integrity of rotating equipment, static equipment, instruments and electrical components
are verified during all component testing in the pre-commissioning and commissioning
phases. In principle all equipment and components will be tested under increasing severities,
from static testing with benign fluids to dynamic testing with process media under operating
conditions.
Adhering to the Integrity Q plans for the various disciplines will result in a minimum of
integrity issues during (pre-)commissioning and start-up and therefore will make the schedule
more predictable.
It is recommended to mark a complex or novelty related activity in the schedule. One can
now add a risk factor percentage of mitigation to the duration of this activity duration.
Meaning that if the novel or complex item level of mitigation is increased the duration of this
activity could be corrected (reduced) accordingly.
8.5 Testing
Structured and fit for purpose testing during the (pre-)commissioning and start-up phases of
the project increases the likeliness that the systems and ultimately the facility will perform
consistently and according to the design intent with minimum disturbance during the first
operational cycle.
Testing represents a significant part of the total work scope during the CSU phase of the
project and identified tests should be embedded in the logical sequence of CSU activities, a
test confirms that the preceding activities have been concluded satisfactorily.
FAT
SAT
Manufacturing Shop test
Component Tightness
Cleanliness
Structured testing programs in accordance with the test pyramid will define the (static)
component tests, the (complex dynamic) system tests, unit tests and plant or facility tests. All
identified tests will be integrated into CSU activities or a stand-alone CSU activity depending
on the scope and type of test/ activity.
Example:
Testing a pressure transmitter (component) can be part of an operational tightness
test activity.
Testing a pump can be part of a establish circulation activity.
A unit performance test can be a stand-alone activity.
GS.06.525366.52536 47 CONFIDENTIAL
Example: a dynamic test of a compressor system on N2 as test medium will require at least a
mechanically complete status (all Pre-commissioning activities completed), auxiliary systems
(lube oil, seal gas) fully operational as well as a relief to safe location. Also vendor rep at site
Testing WS
System definition
Define circulations/
steps (part of CSU)
Activity
description
List tests within those
(system/unit tests)
Logic development
Plant CSU Schedule
Interactions btwn units
Utility interactions
Facility test
Integration,
Combination of ind.
logics & schedules Keep the circulations / steps & test philosophy already in mind
while defining your systems !
GS.06.525366.52536 48 CONFIDENTIAL
1. Where there is an interface of two systems and one isolation valve, the valve shall be
included in the system that supplies or provides the service to the other system under
the accepted start-up logic. This applies even if that valve was design engineered into
the other system.
2. Where there is an interface of two systems and two or more isolation valves, the
system boundary of the system that is providing the service to the other system will
include only the first isolation valve.
3. Where there is an interface of two systems and no isolation valves, the system
boundary of the system receiving the service will include the piping between the two
systems to a major isolation header of the system providing the service.
b) Each piping reference on a PEFS to or from another PEFS should be checked to establish
which PEFS will have the system boundary. This will eliminate having piping spools and
valves in more than one system.
Since the scoping of valves associated with a heat exchanger is sometimes confusing, the
following four guidelines are suggested:
GS.06.525366.52536 52 CONFIDENTIAL
a) Where the service system has manual isolation valves to the heat exchanger, the service
system shall be scoped to include these valves.
b) Where the service system has a control valve or motor-operated valve interfacing with the
heat exchanger, these valves will be scoped with the heat exchanger, since they are
controlled by inputs from the receiving system.
c) Where the service system has both manual isolation valves and control or motor-operated
valves interfacing with a heat exchanger, the manual isolation valves will be scoped with
the service system and the control or motor-operated valves scoped with the heat
exchanger as part of the receiving system.
d) Where there are no valves in the service system interfacing with the heat exchanger, all
piping back to the service system header will be scoped with the heat exchanger as part
of the receiving system.
a) Main supply and branch headers that provide cooling to other systems in normal service.
b) Branch headers providing make-up or back-up supply from and including the first isolation
valve on the header.
a) The steam side begins at the economiser inlet, includes the waterwalls and drum(s), and
ends at the superheater outlet header.
b) The fireside include the FD fans, overfire / underfire / primary air fans, air heaters and
ductwork leaving the unit and terminating at the beginning of the flue gas treatment
equipment. In combined cycle installations with an isolation damper installed between the
combustion turbine and the steam generator, the fireside begins at the downstream side
of the isolation damper.
c) The steam side extends to and includes the unit drain isolation valves. Excluded are
branch headers after the first isolation valves to feed pump turbines, soot blowers, plant
heating, etc.
a) All fans, ducts, filters and dampers required for air balancing supply and/or exhaust fans
will be scoped the same as the main building ventilation system.
b) All fans, ducts, filters, and dampers that operate independently of the main airflow stream
or merely re-circulate part of the main airflow stream will be scoped as a subsystem of the
main building ventilation system.
Note: Outgoing system voltages will typically include the distribution buses for the system
voltage, the step down transformer (including auxiliaries) supplying the voltage along
with its high side breaker, all distribution bus incoming breakers from the step down
transformers, all bus tie breakers, and all associated relay protection.
c) Subsequent system voltages will typically include the distribution buses for the system
voltage, the step down transformer (including auxiliaries) supplying the voltage along with
GS.06.525366.52536 54 CONFIDENTIAL
its high side breaker, all distribution bus incoming breakers from the step down
transformers, all bus tie breakers and all associated relay protection.
Note: Incoming breakers from auxiliary generating units and outgoing breakers to motors
and lower voltage systems will typically not be included.
d) Motor control centres (MCCs) will typically include MCC buses, incoming feeder breakers,
supply breakers on load centres and any MCC tie breakers. Outgoing breakers will not
be included. They will typically be included with the system they service.
B.2.6 DC Systems
DC systems will typically include AC supply breakers to the source of DC generation, storage
batteries, DC buses and panels, breakers on panels for incoming DC bus supplies and bus
ties. Outgoing breakers from the DC buses and panels to DC equipment will typically not be
included.
System
D Switchgear / bus
System
System E
G
System
F
Transformer / bus
M
Generator
Load
System
H MCC / bus
System
I
M Load
GS.06.525366.52536 56 CONFIDENTIAL
SYSTEM
E
SYSTEM
A
SYSTE
M SYSTEM
C D
SYSTEM
B
GS.06.525366.52536 57 CONFIDENTIAL
SYSTEM
A SYSTEM
B
SYSTEM
A
SYSTEM
B
GS.06.525366.52536 58 CONFIDENTIAL
SYSTEM
E
SYSTEM
F
SYSTEM SYSTEM
A D
SYSTEM SYSTEM
C B
GS.06.525366.52536 59 CONFIDENTIAL
SERVICE
WATER
SYSTEM
A
CLOSED
COOLING HEAT
WATER EXCHANGER
SYSTEM B
SERVICE
WATER
SYSTEM
A
GS.06.525366.52536 60 CONFIDENTIAL
Following is a template and example of an activity list. The activity list is set up per
commissioning system and the listed activities as well as the logic relationships are the basis
for developing the WEFS.
The activity list can also contain data to build the CSU schedule from, like resources per
activity and activity duration.
"U3400 activity
list_example.xls"
GS.06.525366.52536 61 CONFIDENTIAL
Identification/ C&SU
Procedure
Generation
Premises:
Define assets limits
Define Work Process
Start/end point 2 Work Break down 3 CSU Roadmap
Define CSU activities Work logic
1 Asset Break down per Commissioning Integration (process
system plants/units, utilities &
Define offsites, interfaces with
Commissioning - Activity description outside fence assets)
systems - Logic relationships
Work Execution Flow
- Resources/ vendor
Marked up PFS Scheme (WEFS)
support/special tools
Marked up PEFS - Temporary facilities
System list - Durations 4 CSU Planning
model
Include Testing
scope! Tool for managing CSU
execution /interfaces
CSU activity list per
system Primavera model
The WEFS does not show durations or time data, however, it does read from left to right
when following a logical sequence of events.
The system definition and the CSU activity lists enable the WEFS to be generated, and both
the WEFS structure and CSU activity lists content provide the data necessary for
constructing the Primavera model, covering the activities within the contractors scope.
25
a work flow scheme (WFS) can also be used for combination of systems, such as start-up blocks
26
e.g. Project Spec part III ch 5
27
T-13.377.420
GS.06.525366.52536 63 CONFIDENTIAL
Activities
Systems
Relationships
E.2.1 Layout
The following describes the typical layout of a WEFS. It, and the guidelines to follow, are
based on years of experience within SGSI, and serve to make the WEFS accessible and
easy to read and understand. Use the template and example files provided below as
illustrations.
GS.06.525366.52536 64 CONFIDENTIAL
On the left hand side of the drawing all the systems inside the contractors scope are listed
vertically in the main body of the drawing, starting with non-process systems first28, then
basic utility systems29, then the rest of the utility systems30, then auxiliaries31 and finally the
process systems. The upper area of the drawing is reserved for three areas:
a) The milestone area; where all relevant milestones are to be shown.
b) The interface area for all activities outside the Contractors scope (e.g. flare, other
ICs activities).
c) The interface area for all activities inside the Contractors scope. This is applicable
when more than one WEFS is necessary to cover all the systems in the area. For
clarity it is highly recommended to divide up this interface area into sub-areas, each
corresponding to another WEFS.
The following documents are provided to help generate a readable WEFS. Moreover, by
following the guidelines a consistent set of WEFS across the project will be obtained:
"WEFS template.vsd"
Visio-WEFS ULSD
example logic.pdf
This example is taken from an older project and does not contain some of the refinements
developed later and discussed in this guideline. However, it gives a good overview of the
layout.
28
Field Auxiliary Rooms, DCS, Fire & Gas detection, electrical distribution systems, Civil & Structural
systems (when important for the CSU execution logic)
29
Instrument air/ tool air, raw water, fire water etc, supporting the (pre-)commissioning of the rest of
the utility systems and pre-commissioning of process systems
30
Cooling water, Steam and Condensate systems, etc, supporting the commissioning of process
systems
31
Flare, Drain, Fuel Gas, etc., supporting the start-up of process systems
32
Note that this template consists of two sheets:
Sheet 1 is a blank template, Sheet 2 is the example for a Water distillation Unit 3400, consisting of
three systems
GS.06.525366.52536 65 CONFIDENTIAL
E.2.2 Guidelines
In this section some guidelines are given on how a WEFS can be developed.
t ie in r e a d y
63 A O S B L 1 B u i ld s y s te m / 2 Fl u s h in g 3 M C / P r e p d o c s/ 4 V e r if y st a t u s /l in e 6 3A O S B L
D H T 2 S to rm li n e s TO S y s te m u p - p u t in D H T2 S t o r m
o p e r a ti o n
S e wer S e we r
t ie in r e a d y
10 A O S B L 1 B u i ld s y s te m / 2 Fl u s h in g 3 M C / P r e p d o c s/ 4 V e r if y st a t u s /l in e 1 0A O S B L
D HT 2 S e we r li n e s TO S y s te m u p - p u t in D H T2 S e w e r
o p e r a ti o n
COS COS
t ie in r e a d y
07 A O S B L 1 B u i ld s y s te m / 2 A ir b l o w in g 3 M C / P r e p d o c s/ 4 - 6 W a l kd o w n / 7 - 9 L e a k t e st - 1 0 Ve r i f y st a t u s / 0 7A O S B L
D HT 2 C oo- li n e s TO S y s te m p r e p a r e s ys t e m - c o m m H T- lo ck li n e u p - f ill - D H T2 C o o -
c o n n e c t - fl u s h B LB V p r e s s u r iz e - p u t
l in g W a te r f r o m s ys t e m s ys t e m s t a n d b y l i n g W a te r
t ie in r e a d y
04 A O S B L 1 B u i ld s y s te m / 2 A ir b l o w in g 3 M C / P r e p d o c s/ 4 -7 W a lk d o w n / 8 V e r if y s ta tu s / lin e 0 4A O S B L
D H T 2 U ti l it y li n e s TO S y s te m p re p a r e s y s te m - up-purge- D H T2 U ti l i ty
c o n n e c t- l e a k t e s t- p r e s su r iz e - p u t
A ir A ir
b lo w i n g c o n n e c t- l e a k t e s t s ys t e m s t a n d b y
S te a m S t eam
t ie in r e a d y
09 A O S B L 1 B u i ld s y s te m / 2 A ir b l o w in g 3 M C / P r e p d o c s/ 4 - 6 W a l kd o w n / 7 - 9 C o m m H T- 1 0 Ve r i f y st a t u s / 0 9A O S B L
D HT 2 LP li n e s TO S y s te m p r e p a r e s ys t e m - i so la t e t r a p s /l o c k li n e u p - f ill - D H T2 L P
c o n n e c t - le a k t e s t B L B V - f ill l in e p r e s s u r iz e - p u t
C ond R et ur n s ys t e m s t a n d b y C o n d R e tu r n
t ie in n o t r e a d y
Interfaces:
28 A O S B L 1 B u i ld s y s te m / 2 A ir b l o w in g 3 M C / P r e p d o c s/ 4 - 8 W a l kd o w n / 8 V e r if y st a t u s /l in e 2 8A O S B L
D HT 2 Liq li n e s TO S y s te m p r e p sy s - c o n n e c t - u p - fi ll- p r e s s u r iz e - D H T2 L iq
le a k te s t - c o m m p u t sy s t e m
B D /S l o p s H T- l o c k B L B V s tandby B D /S lo p s
t ie in r e a d y
01 A O S B L 1 B u i ld s y s te m / 2 C hec k 3 M C / P r e p d o c s/ 4 - 6 W a l kd o w n / 7 - 8 C o n n e ct - 9 V e r if y s t a tu s / li n e 0 1A O S B L
D H T 2 F l a re li n e s c l e a n li n e s s TO S y s te m p r e p a r e s ys t e m - c om m / purge t o u p - p u r g e -p u t D H T2 F l a r e
lo c k B L B V - B LB V D H T s ys t e m i n
r e m o v e i so b li n d o p e r a t io n
t ie in r e a d y
16 A O S B L 1 B u i ld s y s te m / 2 A ir b l o w in g 3 M C / P r e p d o c s/ 4 - 6 W a l kd o w n / 7-8 O 2 f ree- 9 V e r if y s t a tu s / li n e 1 6A O S B L
D HT 2 F uel li n e s TO S y s te m p r e p a r e s ys t e m - c om m H T u p - f il l- p r e s su ri z e - D H T2 F u e l
C o n n e c t - le a k te s t p u t s y st e m
G as s ta n d b y Gas
t ie in r e a d y
17 A O S B L 1 B u i ld s y s te m / 2 A ir b l o w in g 3 M C / P r e p d o c s/ 4 - 6 W a l kd o w n / 7 O2 f ree 8 V e r if y s t a tu s / li n e 1 7A O S B L
D HT 2 li n e s TO S y s te m p r e p a r e s ys t e m - u p - f il l- p r e s su ri z e - D H T2
C o n n e c t - le a k te s t p u t s y st e m
N a tu r a l G a s N a tu ra l G a s
Logic links (=
t ie in r e a d y
30 A O S B L 1 B u i ld s y s te m / 2 A ir b l o w in g 3 M C / P r e p d o c s/ 4 - 7 W a l kd o w n / 8 V e r if y s t a tu s / li n e 3 0A O S B L
D HT 2 H G O li n e s TO S y s te m p r e p a r e s ys t e m - u p - f il l- p r e s su ri z e - D H T2 H G O
dependencies,
c om m to B LB V s ta n d b y
t ie in r e a d y
23 A O S B L 1 B u i ld s y s te m / 2 A ir b l o w in g 3 M C / P r e p d o c s/ 4 - 7 W a l kd o w n / 8 V e r if y s t a tu s / li n e 2 3A O S B L
temporary systems
D HT 2 S o ur li n e s TO S y s te m p r e p a r e s ys t e m - u p - f il l- p r e s su ri z e - D H T2 S o u r
Vertical
c o n n c t - le a k t e s t- p u t s y st e m
W tr to R C C U c om m to B LB V s ta n d b y W tr to R C C U
6 3 IS B L 0 F lu sh in g 1 M C /P r e p d o c s / 2-3 W al k dow n/ 4 V e r if y st a t u s /l in e 6 3 ISBL
S to rm S e w e r T O Sy s t e m p r e p a r e s ys t e m - u p - p u t in S t or m S e wer
R e m o v e p lu g a t o p e r a ti o n
BL
1 0 IS B L 0 F lu sh in g 1 M C /P r e p d o c s / 2-3 W al k dow n/ 4 V e r if y st a t u s /l in e 1 0 ISBL
S e wer CO S T O Sy s t e m p r e p a r e s ys t e m - u p - p u t in S e we r C O S
R e m o v e p lu g a t o p e r a ti o n
BL
R e g u la r W tr S u p
0 6 IS B L Fi r e 0 F lu s h i n g 1 M C /P r e p d o c s / 2-6 W al k dow n/ 7 V e r if y st a t u s /l in e 0 6 I S B L F ir e
W tr /D e l u g e / T O Sy s t e m p r e p a r e s ys t e m - u p - p u t in W tr /D e l u g e /
link relationships)
is o la te - r e m o v e o p e r a ti o n
U ti li ty W a te r b li n d - Fl u s h - L e a k U ti l it y W a te r
t e st
0 7 IS B L 0 F lu s h i n g 1 M C / Pr e p d o c s / 2 W a l kd o w n / 4 C om m H T 5 - 6 Fl u sh f r o m 7 V e r i fy s t a tu s/ li n e 0 7 ISBL
C ooling T O S ys t e m p r e p a r e s ys t e m s y st e m - le a k te st u p - f il l- f lu s h - C o o li n g
p r e s s u r iz e - p u t i n
W a te r o p e r a t io n W at er
U L SD
Utilities
0 4 IS B L IB L U T I 0 4 ISBL
0 A ir b l o w in g 1 M C / P r e p d o c s/ TO 2 - 4 W a lk d o w n / 5 V e r if y s t a tu s / li n e
U ti li ty A i r TO S y s te m p r e p a r e s y s te m - u p - p r e s s u r iz e - p u t U ti l it y A i r
r e m o v e b lin d - le a k in o p e r a t io n
tes t
0 5 IS B L In - 0 A ir b l o w in g 1 M C / P r e p d o c s/ 2 - 3 W a lk d o w n / 4-5 C om m 6 V e r if y st a t u s /l in e 0 5 I S B L In -
s tr u m e n t A ir TO S y s te m p r e p a r e s y s te m - in s t r u m - le a k t e s t u p - p r e s su r i z e - s tr u m e n t A i r
r e m o v e b lin d p urge-c hec k D P -
p u t in o p e r a t io n
0 2 IS B L 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 - 3 W a lk d o w n / 5 C o m m in st r u m - 6 V e r if y st a t u s /l in e 0 2 ISBL
N it ro g e n TO S y s te m p r e p a r e s y s te m - le a k t e st - p u r g e / u p - p r e s s- p u r g e - N i tro g e n
r e m o v e b lin d c hec k O 2 c h e ck O 2 - p u t in
o p e r a t io n
0 3 IS B L 0 S te a m b lo w i n g 1 M C / Pr e p d o c s / 2 W a l kd o w n / 3-4 C om m 5-8 w arm up 9 C h e ck f o r 1 0 - 1 1 V e r i fy 0 3 ISBL
2 0 0 # S te a m T O S ys t e m p r e p a r e s ys t e m in st r u m - le a k te s t s lo w l y- p r e s s - te st sn u ff in g s tm s ta t u s / lin e u p - p u t 2 00# S t eam
t raps o p e r a t io n in o p e r a t io n -
rec hec k t raps
0 9 IS B L L P 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 7 C o m m in st r m - 8 p u t t r a p s in 9 - 1 0 V e r if y st a t u s / 0 9 IS B L L P
C ond R et ur n TO S y s te m p r e p a r e s y s te m c om m H T -rem s erv i c e li n e u p - p u t in C o n d R e tu r n
b l in d - f lu s h b a c k- o p e r a t io n - r e c h e c k
le a k t e s t t raps
0 8 IS B L 0 A ir b lo w in g f o r 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3-6 C om m 7 - 1 0 F ill w it h 1 1 Ve r if y st a t u s / 0 8 ISBL
G l yc o l s k id /f in e c le a n f o r TO S y s te m p r e p a r e s y s te m in st r u m - P re p P P g ly c o l- f lu s h - r e p l li n e u p - G ly c ol
h eader s e r v ic e - l in e u p f i lt e r s- c o m m p r e s s u r iz e - p u t i n
S y s te m R V 's - le a k te s t a ir c o o le r s o p e r a t io n S y s te m
3 9 IS B L 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 5 C o m m in st r m - 6 - 7 O 2 fr e e - le a k 8 - 1 1 F ill w it h f lu i d 12-13 C om m H 2 1 4 V e r if y s ta t u s / 3 9 ISBL
S e a l B a r ri e r TO S y s te m p r e p a r e s y s te m c o m m H T - lin e u p tes t u n d e r N 2 -f l u sh - b la n k - c o m p l fl u s h li n e u p - S e a l B a r r ie r
R V 's re p l f i lt e r s- p r e s s p r e s s u r iz e - p u t i n
F lu i d S y s te m te s t - p r e p P P s e r v o p e r a ti o n F l u i d S y s te m
General Auxiliaries
2 8 IS B L L i q 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 6 C o m m in st r m - 7 V e r i fy s t a tu s/ li n e 2 8 I S B L Liq
B D f r V 39 23 TO S y s te m p r e p a r e s y s te m c o m m H T - le a k u p - p r e s s u r iz e - p u t B D fr V 3 9 2 3
t e s t- r e m o v e b l in d in o p e r a t io n
U LS D
0 1 IS B L 1 C hec k 2 M C / Pr e p d o c s / 3 W a l kd o w n / 4 - 7 C o m m H T- 8 - 9 C o m m in st r - 1 0 - 1 4 F il l d r u m - 1 5 O 2 f re e 16-18 R em ov e R FS U 1 9 V e r if y s ta t u s / 0 1 ISBL
F la re c le a n lin e ss T O S ys t e m p r e p a r e s ys t e m P r e s s w i th a ir - I n s ta l l t e m p p r e ss > 5 0 kp a - te m p co n n e c ti o n - li n e u p - p u t in F lar e
l eak tes t- c o n n e c t io n t o s a f e p rep P P s erv -pre- R e m o v e b li n d - o p e r a ti o n
b lo w d o w n lo ca ti o n p are-run i n pu m ps open B LB V
1 6 IS B L 0 A ir b lo w in g / f in e 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 5 Fu n ct io n t e st 6 in s t a ll N 2 e lb o w 7 - 8 O 2 fr e e - 10-11 R em B L 1 2 V e r if y s ta t u s / 1 6 ISBL
F uel G as c l e a n in g f o r TO S y s te m p r e p a r e s y s te m in st r u m - C o m m d i sc o n n N 2 e lb o w b lin d - O p e n B L B V li n e u p - F ue l G as
h e a t e r p ip i n g H T - le a k te s t p r e s s u r iz e - p u t i n
f u ll o p e r a t io n
1 7 IS B L 0 A ir b lo w in g / f in e 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 4 Fu n ct io n t e st 5 in s t a ll N 2 e lb o w 6 - 7 O 2 fr e e - 8 C o m m st e a m 9-10 R e m B L 1 1 V e r if y s ta t u s / 1 7 ISBL
N a tu r a l G a s c l e a n in g f o r TO S y s te m p r e p a r e s y s te m in st r u m - le a k te s t d i sc o n n N 2 e lb o w tr a c in g b lin d - O p e n B L B V li n e u p - N a tu ra l G a s
h e a t e r p ip i n g ru n N G t o f la re p r e s s u r iz e - p u t i n
hdr o p e r a ti o n
2 1 IS B L 0 A ir b lo w in g / f in e 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 5 Fu n ct io n t e st 6 in s t a ll N 2 e lb o w 7 - 8 O 2 fr e e - 9 V e r i fy s t a t u s/ li n e 2 1 ISBL
V e n t G a s fr c l e a n in g f o r TO S y s te m p r e p a r e s y s te m in st r u m - C o m m d i sc o n n N 2 e lb o w u p - p u t in V e n t G a s fr
h e a t e r p ip i n g H T - le a k te s t o p e r a ti o n
V 3 906 V 3 90 6
1 1 IS B L 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 5 Fu n ct io n t e st 6 - 7 O 2 fr e e - le a k 8 - 1 0 F il l/ p la c e l iq 11-13C om m H 2 1 4 V e r if y s ta t u s / 1 1 ISBL
F e e d fr o m TO S y s te m p r e p a r e s y s te m in st r u m - C o m m tes t le v e ls - p r e s s te st - b la n k sy s t e m - li n e u p - u n d e r H 2 F e e d fro m
H T - lin e u p R V 's p r e p P P se r v ic e p r e p - r u n in f e e d w it h g a s o il r e a d y
S to ra g e pum p f o r o p e ra ti o n S t or age
3 0 IS B L 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 5 Fu n ct io n t e st 6 - 7 O 2 fr e e - le a k 8 - 1 0 F il l/ p la c e l iq 11-13C om m H 2 1 4 V e r if y s ta t u s / 3 0 ISBL
H G O fr o m TO S y s te m p r e p a r e s y s te m in st r u m - C o m m tes t le v e ls - p r e s s te st - b la n k sy s t e m - li n e u p - u n d e r H 2 H G O fro m
H T - lin e u p R V 's p r e p P P se r v ic e p r e p - r u n in p u m p w it h g a s o il r e a d y
D 3 9 0 2 /3 f o r o p e ra ti o n D 3 9 0 2 /3
2 5 IS B L 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 6 Fu n ct io n t e st 7 V e r i fy s t a t u s/ li n e 2 5 ISBL
W as h W t r f r TO S y s te m p r e p a r e s y s te m in st r u m - c o m m up-read y f or W a s h W tr fr
H T - le a k t e s t- l in e o p e r a ti o n
V 3 412 u p R V 's V 3 41 2
2 3 IS B L 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 6 Fu n ct io n t e st 7 V e r i fy s t a t u s/ li n e 2 3 ISBL
S o u r W tr fr TO S y s te m p r e p a r e s y s te m in st r u m - c o m m up-read y f or S o u r W tr fr
H T - le a k t e s t- l in e o p e r a ti o n
C H P S /C L P S u p R V 's C H P S /C L P S
1 0 /4 3 IS B L 4 3 IS B L s ys t e m 4 3 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 4 Fu n ct io n t e st 5-7 l ube t es t - 8 - 1 1 P u r g e w i th 1 2 V e r if y s t a tu s- 13 P rep t o s t art 1 4 - 1 6 E s ta b H 2 17-18 P erf l oad 19-22 C ool dow n- 1 0 /4 3 IS B L
H 2 m ak e u p/ C 39 00A B C h e m i ca l TO S y s te m p r e p a r e s y s te m in st r u m - lin e u p b u m p t e s t- n o N 2 - p r e s s - le a k under N 2 ready C 3900A /B r e c - in c r p r e s s- c h k -s w in g c o m p sh u t d o w n h tr - H 2 m a k e u p/
c le a n in g R V 's v a lv e r u n t e st - p r e p fo r fo r c i rc u l a t io n e s t a b m i n H 2 f lo w co o l to 7 0 d g r -
R ec C om p C h e m C le a n o p e r a t io n t o s t art heat er sh u td o w n c o m p R ec Co m p
1 2 IS B L 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 Fu n c t io n t e st 4 - 7 Pu rg e w it h 8 V e r if y s ta tu s - H P 1 2 ISBL
F e e d to TO S y s te m p r e p a r e s y s te m in st r u m N 2 - p r e s s - le a k ci r c u it u n d e r N 2 F e e d to
C h a r g e H tr o p e r a t io n fo r c i rc u l a t io n C h a rg e H t r
UL SD
1 4 IS B L 0 C l e a n in g a s 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 4 Fu n ct io n t e st 5 - 8 Pu rg e w it h 9 V e r if y s ta tu s - H P 1 0 - 1 1 C l e a n - c ir c / 1 2 - 1 3 Ev a c u a t e 1 4 - 1 7 C a t lo a d - 1 8 P r e p f o r u n it 1 9 - 2 0 A c ti v a t e 2 1 - 2 2 Ze r o c h e c k 2 3 R a m p u p to in N O P 1 4 ISBL
R e a c to r r e q u ir e d TO S y s te m p r e p a r e s y s te m in st r u m - lin e u p N 2 - p r e s s - le a k ci r c u it /r e a c t o r h o ld te m p H P c i r cu it /p u t N 2 - lin e u p R x - N 2 c a t a ly s t a c t iv a t io n c a ta - l y st - s ta r t o f in s t ru m e n ts - b r in g n o rm a l t h r o u g h p u t R e a c to r
t e st - p r e p fo r under N 2 ready prep reac t or f or le a k t e st - p r e s s U LS D ac c proc o n sp e c
o p e r a t io n fo r c i rc u l a t io n c a t lo a d in g w it h H 2 *R e a c t o r S e c ti o n
1 5 IS B L 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 4 Fu n ct io n t e st 5 - 8 Pu rg e w it h 9 V e r if y s ta tu s - H P 1 0 Fi ll /p l a c e li q 11-13 R em ov e H 2 1 4 V e r if y s ta t u s - 1 5 - 1 6 C l e a n - c ir c / 1 5 ISBL
R e a c to r E f fl TO S y s te m p r e p a r e s y s te m in st r u m - lin e u p N 2 - p r e s s - le a k ci r c u it u n d e r N 2 le v e l s b l in d / p r e s s u n it - H P C ir c u it r e a d y h o ld te m p R e a c to r E ffl
R V 's t e st - p r e p fo r re a d y f o r le a k t e st - in c r fo r o p e r a t io n
to V 3 9 0 5 o p e r a t io n o p e r a t io n pres s to V 3 9 0 5
1 8 IS B L 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 4 Fu n ct io n t e st 5 - 8 Pu rg e w it h 9 V e r if y s ta tu s - H P 1 8 ISBL
Q ue nc h O il TO S y s te m p r e p a r e s y s te m in st r u m - C o m m N 2 - p r e s s - le a k ci r c u it u n d e r N 2 Q u e n c h O il
HT t e st - p r e p fo r re a d y f o r
to R e a ct o r o p e r a t io n o p e r a t io n to R e a c to r
1 9 IS B L 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 4 Fu n ct io n t e st 5 - 8 Pu rg e w it h 9 V e r if y s ta tu s - H P 1 9 ISBL
L i q u id f ro m TO S y s te m p r e p a r e s y s te m in st r u m - C o m m N 2 - p r e s s - le a k ci r c u it u n d e r N 2 L iq u i d fro m
HT t e st - p r e p fo r re a d y f o r
H HP S o p e r a t io n o p e r a t io n H H PS
2 0 IS B L G a s 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 4 Fu n ct io n t e st 5 - 8 Pu rg e w it h 9 V e r if y s ta tu s - H P 2 0 I S B L G as
fr o m V 3 9 0 5 TO S y s te m p r e p a r e s y s te m in st r u m - lin e u p N 2 - p r e s s - le a k ci r c u it u n d e r N 2 fr o m V 3 9 0 5
R V 's t e st - p r e p fo r re a d y f o r
o p e r a t io n o p e r a t io n
2 1 IS B L G a s 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 5 Fu n ct io n t e st 6 - 9 Pu rg e w it h 1 0 V e r if y s t a tu s- 2 1 I S B L G as
fr o m V 3 9 0 6 TO S y s te m p r e p a r e s y s te m in st r u m - c o m m N 2 - p r e s s - le a k H P c ir c u it u n d e r fr o m V 3 9 0 6
Process
H T - lin e u p R V 's t e st - p r e p fo r N 2 r e a d y fo r
o p e r a t io n o p e r a t io n
2 2 IS B L 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 4 Fu n ct io n t e st 5 - 8 Pu rg e w it h 9 V e r if y s ta tu s - H P 2 2 ISBL
L i q u id f ro m TO S y s te m p r e p a r e s y s te m in st r u m - C o m m N 2 - p r e s s - le a k ci r c u it u n d e r N 2 L iq u i d fro m
HT t e st - p r e p fo r re a d y f o r
C HP S o p e r a t io n o p e r a t io n C H PS
2 4 IS B L 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 5 Fu n ct io n t e st 6 in s t a ll N 2 e lb o w 7 - 1 0 O 2 f re e - le a k 1 1 V e r if y s t a tu s- 1 2 - 1 3 Fi ll/ p la ce liq 1 4 V e r if y s t a t u s- 1 5 L in e u p 16 S t art of U LS D 2 4 ISBL
S tr i p p e r O /H TO S y s te m p r e p a r e s y s te m in st r u m - C o m m t e s t- d i sc o n n N 2 st r ip p e r s e c ti o n le v e ls - p r e p P P u n d e r N 2 w i th s t ri p p e r s e c t io n ac c proc edure S t ri p p e r O /H
H T - te s t /r u n in e l b o w - lin e u p under N 2 s e r v ic e g a s o il r e a d y f o r *S tr i p p e r S e c ti o n
to V 3 9 0 7 fans R V 's o p e r a t io n to V 3 9 0 7
2 6 IS B L 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 4 Fu n ct io n t e st 2 6 ISBL
S tr i p p e r B /M TO S y s te m p r e p a r e s y s te m in st r u m - C o m m S t ri p p e r B /M
HT
D 390 2 D 39 02
2 7 IS B L 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 6 C o m m in st r m - 7 V e r i fy s t a tu s/ li n e 2 7 ISBL
W a s h O i l/ TO S y s te m p r e p a r e s y s te m c o m m H T - le a k u p - p r e s s u r iz e - p u t W as h O il/
t e s t- r e m o v e b l in d in o p e r a t io n
D ry S lo p D ry S l o p
2 9 IS B L 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 4 Fu n ct io n t e st 5 V e r i fy s t a tu s/ li n e 2 9 ISBL
flow scheme
f o r o p e ra ti o n
3 8 IS B L 0 A ir b lo w in g 1 M C / P r e p d o c s/ 2 W a lk d o w n / 3 - 4 Fu n ct io n t e st 5 - 6 O 2 fr e e - le a k 7 - 9 F il l/ p la c e l iq 10-12 C om m F G 1 3 V e r if y s ta t u s / 3 8 ISBL
S to v e O il TO S y s te m p r e p a r e s y s te m in st r u m - lin e u p tes t le v e ls - p r e s s te st - b la n k sy s t e m - li n e u p - u n d e r F G S t ov e O il
R V 's p r e p P P se r v ic e p r e p - r u n in p u m p w it h g a s o il r e a d y
S p li tte r P r o d f o r o p e ra ti o n S p l it te r P ro d
4 0 IS B L 0 C le a n i n g a s 1 M C / Pr e p d o c s / 2 W a l kd o w n / 3 - 4 Fu n ct io n t e st 5 - 7 F il l- F lu s h - r e p l 8 V e r i fy s t a tu s/ li n e 4 0 ISBL
C 390 0A B r e q u i re d T O S ys t e m p r e p a r e s ys t e m in st r u m - lin e u p f i lt e r s u p - p r e s s u r iz e - p u t C 39 00A B
R V 's in o p e r a t io n
Lu be O il S y s L u b e O i l S ys
4 1 IS B L 0 C le a n i n g a s 1 M C / Pr e p d o c s / 2 W a l kd o w n / 3 - 5 Fu n ct io n t e st 6 - 8 F il l- F lu s h - r e p l 9 V e r i fy s t a tu s/ li n e 4 1 ISBL
Equipment Auxiliaries
C 390 0A B r e q u i re d T O S ys t e m p r e p a r e s ys t e m in st r u m - c o m m f i lt e r s u p - p r e s s u r iz e - p u t C 39 00A B
H T - lin e u p R V 's in o p e r a t io n
L b rc O i l S y s
Horizontal
L b rc O i l S y s
4 2 IS B L 0 C le a n i n g a s 1 M C / Pr e p d o c s / 2 W a l kd o w n / 3 - 5 Fu n ct io n t e st 6 V e r i fy s t a tu s/ li n e 4 2 ISBL
C 390 0A B r e q u i re d T O S ys t e m p r e p a r e s ys t e m in st r u m - c o m m u p - p r e s s u r iz e - p u t C 39 00A B
H T - lin e u p R V 's in o p e r a t io n
D is t p c b ttl D i s t p c b t tl
4 5 IS B L 0 C le a n i n g a s 1 M C / Pr e p d o c s / 2 W a l kd o w n / 3 - 4 Fu n ct io n t e st 5 - 7 F il l- F lu s h - r e p l 8 V e r i fy s t a tu s/ li n e 4 5 ISBL
P 3 901 L ube r e q u i re d T O S ys t e m p r e p a r e s ys t e m in st r u m - lin e u p f i lt e r s u p - p r e s s u r iz e - p u t P 3 90 1 Lub e
R V 's in o p e r a t io n
O i l S y s te m O i l S ys t e m
4 6 IS B L 0 C le a n i n g a s 1 M C / Pr e p d o c s / 2 W a l kd o w n / 3 - 4 Fu n ct io n t e st 5 - 7 F il l- F lu s h - r e p l 8 V e r i fy s t a tu s/ li n e 4 6 ISBL
P 3 907 L ube r e q u i re d T O S ys t e m p r e p a r e s ys t e m in st r u m - lin e u p f i lt e r s u p - p r e s s u r iz e - p u t P 3 90 7 Lub e
R V 's in o p e r a t io n
O i l S y s te m O i l S ys t e m
link
4 7 IS B L 0 C le a n i n g a s 1 M C / Pr e p d o c s / 2 W a l kd o w n / 3 - 5 Fu n ct io n t e st 6 - 8 F il l- F lu s h - r e p l 9 V e r i fy s t a tu s/ li n e 4 7 ISBL
S e al B F S k d r e q u i re d T O S ys t e m p r e p a r e s ys t e m in st r u m - c o m m f i lt e r s u p - p r e s s u r iz e - p u t S e al B F S k d
H T - lin e u p R V 's in o p e r a t io n
P 3 902 A B P 3 90 2A B
C om pr es s or 1 Pr e p h a s e 1 P H A S E 1A 2 M o d if ic a t io n s I n s t r u m e n t Ai r C om pr es s or
B u il d i n g w ork o p e r a ti n g p a n e l/ f r o m d i st r ib u ti o n B u i ld in g
e le c t ri c a l r o o m i n b u i ld in g
C800/801 MODS
C om pr es s or 1 S hutdow n- 2 M o d if ic a t io n s 3 M o d if ic a t io n s 4 M o d if ic a t io n s C om pr es s or
C 800 C 8 0 0 /p u r g e - b la n k C 8 0 0 / H 2 sy s te m V e n t / g ly c o l/ f la r e / in s t r u m e n t sy s t e m C 80 0
Phase 1 A-B-C 2 3
n it ro g e n / lu b r i ca -
t io n s y st e m s
5 M o d if ic a t io n s PH A S E 2 6 M C / P r e p d o c s/ 7 W a lk d o w n / 8 - 1 0 Fu n ct io n t e s t 1 1 - 1 3 lu b e t e s t- 1 4 - 1 7 P u r g e w it h 1 8 V e r if y s t a tu s-
C800/801 MODS
The drawing should be readable from left to right, meaning that the X-axis represents
a (non-linear) timeline. Hence there are no backward flowing links (Relationships in
the illustration). Links are always vertical lines (dots-arrows).
Make sure that the WEFS reflects the CSU philosophy.
Make sure that all testing activities incorporated in the system activity sheets and
reflected on the WEFS.
To make the drawings easier to read and understand the activities from the CSU
ACTIVITY LIST (within a commissioning system) can be grouped and shown on the
WEFS in a single box provided there are no vertical links in between these activities.
For example, instead of showing two activities, Tightness test and Oxygen free, they
can also be combined:
E5-E8
Tightness test
O2 free
Do not show durations of activities on the WEFS in any format, since these are not
updated when the primavera is updated. In general it is good practice to avoid
duplication of information in different documents for reasons of document
maintenance.
GS.06.525366.52536 66 CONFIDENTIAL
Logic relationships
o This note applies to the links in the interface area. Make sure that all logic link
references, external or between the different sheets of WEFS are consistent.
The reference box in the interface area should mention the COM-number33
when the link is outside own scope, or mention the system in case the link is
to another drawing, but inside own scope. Always include a short descriptor in
the box. This descriptor should correspond to the description on the System
Activity Sheet and, if applicable, on the Logic Link Summary. Also include in
brackets the Service Code if applicable.
COM 093
Example outside own scope: Instrument Air
available (IA)
N-UU-Bb-Sxy
Example inside own scope: RFSU syst Sxy
In this case provider system Sxy needs to be RFSU for the following activity
on the WEFS. System Sxy is within own scope but is located on another
drawing. If the interface area is divided up in WEFS (see section on Layout),
the box appears in the sub-area of the WEFS drawing on which system Sxy is
located.
o Ensure that links between any two WEFS drawings (own scope) appear on
both drawings. It is not recommended to force the links to appear on the
same lateral location (as is common practice with PEFS drawings), as it
reduces the flexibility of arranging the layout of the WEFS.
o Ensure that all logic links are also mentioned in the activity sheets with a short
explanation why the link is there.
o All links are by default Finish-to-Start relationships. If this is not intended (only
in very few occasions) the correct relationship should be specified on the
WEFS such as Start-to-Start or Finish-to-Finish relationships. Lags can then
be indicated between different activities (see template)
E.2.3 Standardisation
The following recommended guidelines help improve the readability of the WEFS and make
them uniform in appearance across the project:
Activity boxes are standard size 15 x 8 mm like in the template; the right hand side of
the boxes is aligned with a multiple of 3 cm, i.e. the boxes are positioned at 9, 12, 15,
18 etc. cm. Vertical guides (dotted grey lines) are provided in the template to align
the boxes.
To accentuate important systems like power, control & safeguarding and instrument
air we use red, green and blue arrows, respectively, for the relationships (refer to
template)
The boxes shall be coloured as indicated by the legend on the template (i.e. pre-
commissioning = light green, commissioning = light blue etc.)
33
COM-numbers are defined in the Commissioning Interface Packages to be issued by PMC:
(T-4.184.586 - .594)
GS.06.525366.52536 67 CONFIDENTIAL
To the right of the list of commissioning systems the grouping to SU block level is
indicated (refer to template)
To the left of the list of commissioning systems the plant name is indicated (refer to
template)
All important notes and holds should be mentioned on the WEFS.
N-UU-Bb-P01
01
<system 1> <Activity 01>
L1
L4
N-UU-Bb-P02
02
<system 2> <Activity 02>
L2
N-UU-Bb-P03
03
<system 3> <Activity 03>
L3
N-UU-Bb-P04
04 05
<system 4> <Activity 4> <Activity 5>
Here there are links between the following activity pairs: 01/02, 02/03 03/05 and 01/05,
called L1, L2, L3 and L4, respectively. Due to the order in the logic, link L4 is not strictly
necessary, because activity 01 will surely take place before activity 05. This is what is
meant by the indirect link. When many of these indirect links are present, the drawing
can become cluttered and difficult to read. In principle link L4 in the example can be left
out, however, care must be taken when changing the logic at a later date. The link
represented by L4 must not be overlooked as L1, L2 or L3 may have been removed
during changes to the logic. It is advised not to remove these indirect links until the logic
has been completed. An alternative is to draw them on a different layer that can be
made invisible for presentation purposes and switched on during development work.
E.3 Narrative
It is important to capture the reason why a logic link exists, be it internal (within the contractor
scope) or external. This must be recorded in the CSU activity list or a separate document
(narrative), and should contain sufficient detail to enable an Operator to write procedures
based on this information, including WEFS and Schedule. Another reason for providing the
explanatory text is that the logics from different contractors will need to be integrated to form
a logic of the complex. It should be possible to roll up the info into an integrated CSU
execution plan
GS.06.525366.52536 68 CONFIDENTIAL
Each item listed represents a link on the WEFS that connects to the logic of another
contractor, be it a utility provision or another activity. All these items appear in the interface
area at the top of the WEFS. The descriptor corresponds to that on the System Activity
Sheet and, if applicable, the narrative.
Hence there are five interrelated documents that describe and explain the CSU plan and
schedule and how they relate to those of other areas:
1. System definitions
2. System Activity Sheets
3. WEFS logic
4. Narrative describing the reason for each logic link
5. Logic Link Summary
GS.06.525366.52536 69 CONFIDENTIAL
Bibliographic Information
This report has been classified as Confidential and is not subject to US Export Control
regulations.
Report distribution
Copies of the report will be sent to those listed below via email (E) or in paper format (P) as
specified. (E is the preferred method for distribution within GS and P should only be used if
specifically requested by the customer).
Address info should be as complete as possible (certainly for external parties), i.e. company
name, reference indicator, postal address and number of paper copies if applicable.
Add/remove lines as required.
Access to this report is restricted to those listed in the Distribution List only because of
commercially sensitive information.