DEMOLICIONES
DEM0001 DEM. CIMIENTOS DE PIEDRA. DEMOLICION AM3
DEM0002 DEM. CIM. CONC. ARM. S/REC. ACERO. DEMOLICION AM3
DEM0004 DEM. MUROS DE ADOBE Y TEPETATE DEMOLICION DM3
DEM0009 DEM. MURO TAB/BLOCK 14 CM. SIN/REC. DEMOLICION AM2
DEM0010 DEM. MURO TAB/BLOCK 14 CM. CON/REC. DEMOLICION AM2
DEM0014 DEM. CONC. ARMADO EN ESTRUCTURA. DEMOLICION AM3
DEM0020 DEM. PISO CONC. SIMPLE 8-10 CM. ESP. DEMOLICION AM2
DEM0022 DEM. PISO CONC. ARMADO 8-10 CM. ESP. DEMOLICION AUnidad
DEM0028 DEM. APLANADOS MURO/PLAFN 2.5 CM. ESP. DEMOLICION AM2
DEM0029 DEM. FALSO PLAFN DE YESO. DEMOLICION AM2
DEM0043 DEM. CONC. ASFLTICO 5-7 CM. ESP. DEMOLICION DM2
PRELIMINARES
LTZ0001 LIMPIEZA DEL TERRENO A MANO. LIMPIEZA DEL M2
EXC0001 EXCAV. MANUAL CEPAS SUELO TIPO II EXCAVACIN AM3
LTZ0005 TRAZO Y NIVELACIN MANUAL TRAZO Y NIVE M2
CIMENTACIN
CIM0001 CIM. MANPOSTERIA 60,30 X 80 CM. MORT.1:5 CIMENTACION M3
RELL01CC RELLENO CIM. COMP. BAILARINA 90% RELLENO EN CM3
RELL01CM RELLENO CIM. COMP. MANUAL RELLENO DE CM3
CASTILLOS Y COLUMNAS
CAST001V CASTILLO 15X15 , FC=150, 4 VARS. #3, 2 C CASTILLO CONM
CAST002V CASTILLO 15X15 , FC=200, 4 VARS. #3, 2 C CASTILLO CONM
CAST003V CASTILLO 15X15 , FC=250, 4 VARS. #3, 2 C CASTILLO CONM
CAST004V CASTILLO 15X20 , FC=150, 4 VARS. #3, 2 C CASTILLO CONM
CAST005V CASTILLO 15X20 , FC=200, 4 VARS. #3, 2 C CASTILLO CONM
CAST010V CASTILLO CON SECCION DE 15X30 CM DE CONC CASTILLO CONM
CAST006V CASTILLO 15X20, FC=250, 4 VARS. #3, 2 C CASTILLO CONM
CAST007V CASTILLO 20X20 , FC=150, 4 VARS. #3, 2 C CASTILLO CONM
CAST008V CASTILLO 20X20 , FC=200, 4 VARS. #3, 2 C CASTILLO CONM
CAST009V CASTILLO 20X20, FC=250, 4 VARS. #3, 2 C CASTILLO CONM
FIRMES
PLA05-100 PLANTILLA CONC. SIMPLE F`C =100 KG/CM2 PLANTILLA DE M2
PIS05-100 FIRME 5 CM, FC 100, RN, AGR. 3/4". FIRME DE CONM2
PIS05-150 FIRME 5 CM, FC 150, RN, AGR. 3/4". FIRME DE CONM2
PIS08-150 FIRME 8 CM, FC 150, RN, AGR. 3/4". FIRME DE CONM2
PIS08-200 FIRME 8 CM, FC 200, RN, AGR. 3/4". FIRME DE CONM2
PIS10-150 FIRME 10 CM, FC 150, RN, AGR. 3/4". FIRME DE CONM2
PIS10-200 FIRME 10 CM, FC 200, RN, AGR. 3/4". FIRME DE CONM2
PIS15-150 FIRME 15 CM, FC 150, RN, AGR. 3/4". FIRME DE CONM2
PIS15-200 FIRME 15 CM, FC 200, RN, AGR. 3/4". FIRME DE CONM2
MUROS
MURLAD7 MURO TRR, 7 CM, MOR 1:5, JUNTA 1.5, AC. MURO DE TABIM2
MURLAD14 MURO TRR, 14 CM, MOR 1:5, JUNTA 1.5, AC. MURO DE TABIM2
MURLAD28 MURO TRR, 28 CM, MOR 1:5, JUNTA 1.5, AC. MURO DE TABIM2
MURTAB10 MURO TAB, 10 CM, MOR 1:5, JUNTA 1.5, AC. MURO DE TABIM2
MURTAB14 MURO TAB, 14 CM, MOR 1:5, JUNTA 1.5, AC. MURO DE TABIM2
MURTAB28 MURO TAB, 28 CM, MOR 1:5, JUNTA 1.5, AC. MURO DE TABIM2
MURPRET15 MUR. PRETIL PERIM. 7X14X28, 15 CM. MURO DE PRET
M
MUROS ESPECIALES
MURTABI1 MURO LAMBRN DE TABLAROCA TIPO INTERIOR M2
MURTABE1 MURO LAMBRN DE TABLAROCA TIPO INTEMPERI M2
MURTABI2 MURO DE TABLAROCA A 2 CARAS TIPO INTERIO M2
MURTABE2 MURO DE TABLAROCA A 2 CARAS TIPO INTEMPE M2
MURMIXID MURO MIXTO TABLAROCA TIPO INTERIOR - DUR M2
MURMIXED MURO MIXTO TABLAROCA TIPO INTEMPERIE - D M2
MURMIXIE MURO DE TABLAROCA TIPO INTERIOR - INTEM M2
MURDUR2 MURO A 2 CARAS DE DUROK. M2
PLATAB001 PLAFN DE TABLAROCA M2
PLAPOLI001 PLAFN DE POLIESTIRENO DE 1" DE ESP. CON M2
DETTAB001 FABRICACIN DE DETALLES DE TABLAROCA (EN M2
DETTAB002 FABRICACIN DE BOQUILLAS. ML
MDURINT MURO LAMBRIN DE DUROK M2
ENTREPISOS Y CUBIERTAS
LOSA10-200 LOSA TECHO 10 CM, VAR. #3, FC=200 LOSA DE 10 C M2
LOSA10-250 LOSA TECHO 10 CM, VAR. #3, FC=250 LOSA DE 10 C M2
HERRERA Y CANCELERA
ACABADOS
PIS0080 PISO DE CERMICA VITROMEX 33X33 CM. SUMINISTRO YM2
PIN0001 PINTURA VINILICA EN MUROS Y PLAFONES SUMINISTRO YM2
PIN0002 SUMINISTRO Y APLICACIN DE PINTURA ESMAL SUMINISTRO YM2
IMP0001 IMPERMEABILIZACIN DE LOSA DE AZOTEA SUMINISTRO YM2
APL0025 EMBOQ. REPELLADO C/CEMENTO Y ARENA 1:6 EMBOQUILLADO
M
APL0022 APLANADO PLAFONES C/MORTERO Y ARENA 1:5 APLANADO ENM2
PSO0001 ACABADO ESCOBILLADO INTEGAL PSO CONC. ACABADO ESCO
M2
PSO0002 ACABADO PULIDO INTEGRAL PISO CONC. ACABADO PULIM2
ACARREOS
ACR0009 ACARREO CARR. SACOS: CEM. MORT. CAL. ACARREO EN C
M3
ACR0012 ACARREO CARR. AGREGADOS MORT. CONCRETOS. ACARREO EN C
M3
ACR0013 ACARREO CARR. PIEDRA BRAZA. ACARREO EN C
M3
ACR0037 ACARREO A MANO MADERA P/CIMBRA. ACARREO A MAMIL
ACR0082A ACARREO EN CAM. A PRIM. KM. VOL. MED. M3
CUADRILLAS
CUAD001 CUADRILLA 001(1 PEON) JOR
CUAD005 CUADRILLA 005(5 PEONES) JOR
CUAD040 CUADRILLA 040(1ALBANIL+1PEON) JOR
CUAD060 CUADRILLA 060 (1 PINTOR) JOR
CIMBRAS
CFZAP CIMB./DESCIM, ACAB. COMN FRONTERAS/ZAP. CIMBRA Y DESM2
CDADO CIMB./DESCIM, ACAB. COMN CONTRATRABES CIMBRA Y DESM2
CCADE CIMB./DESCIM, ACAB. COMN CADENAS. CIMBRA Y DESM2
CCAST CIMB./DESCIM, ACAB. COMN CASTILLOS. CIMBRA Y DESM2
CCOL30X30 CIMB./DESCIM, ACAB. COMN COLUMNAS 30X30 CIMBRA Y DESM2
CCOL50X50 CIMB./DESCIM, ACAB. COMN COLUMNAS 50X50 CIMBRA Y DESM2
VACIADOS
VDACAS150 VAC. DALA Y CAST, FC=150, RN. AGR. 3/4" VACIADO DE CM3
VDACAS200 VAC. DALA Y CAST, FC=200, RN. AGR. 3/4" VACIADO DE CM3
VDACAS250 VAC. DALA Y CAST, FC=250, RN. AGR. 3/4" VACIADO DE CM3
VCL200 VAC. COLUMNAS P.B, FC=200, RN, AGR 3/4" VACIADO DE CM3
VCL250 VAC. COLUMNAS P.B, FC=250, RN, AGR 3/4" VACIADO DE CM3
VZTL150 VAC. ZAP. CIM, FC=150, RN. AGR. 3/4" VACIADO DE CM3
VZTL200 VAC. ZAP. CIM, FC=200, RN. AGR. 3/4" VACIADO DE CM3
VZTL250 VAC. ZAP. CIM, FC=250, RN. AGR. 3/4" VACIADO DE CM3
VCOL150 VAC, COLUMAS S/E, FC=150, RN, AGR. 3/4" VACIADO DE CM3
VCOL200 VAC, COLUMAS S/E, FC=200, RN, AGR. 3/4" VACIADO DE CM3
VCOL250 VAC, COLUMAS S/E, FC=250, RN, AGR. 3/4" VACIADO DE CM3
VTRABE200 VAC. TRABES S/E, FC=200, RN, AGR.3/4" VACIADO DE CM3
VTRABE250 VAC. TRABES S/E, FC=250, RN, AGR.3/4" VACIADO DE CM3
VLOSA150 VAC.. LOSAS S/E, FC=150, RN, AGR.3/4" VACIADO DE CM3
VLOSA200 VAC.. LOSAS S/E, FC=200, RN, AGR.3/4" VACIADO DE CM3
VLOSA250 VAC., LOSAS ,S/E, FC=250, RN. AGR.3/4" VACIADO DE CM3
VCIM100R VAC.. CIMENTACIN, FC=100, RN, AGR.3/4" VACIADO DE CO
M3
VCIM150R VAC.. CIMENTACIN, FC=150, RN, AGR.3/4" VACIADO DE CO
M3
VCIM200R VAC.. CIMENTACIN, FC=200, RN, AGR.3/4" VACIADO DE CO
M3
VCIM250R VAC.. CIMENTACIN, FC=250, RN, AGR.3/4" VACIADO DE CO
M3
RENDIMIENTO POR ETAPA
FCO100R CONCRETO F'C=100 KG/CM2, RESISTENCIA NORMAL, AGR.MAX. 3/4, FABRICADO EN OBRA EN M3
REVOLVEDORA DE 1 SACO; ACARREO MATERIAL PRIMERA ESTACION 20.00 M.
FCO150M CONCRETO F'C=150 KG/CM2, RESISTENCIA NORMAL, AGR.MAX. 3/4, FABRICADO EN OBRA POR M3
MEDIOS MANUALES; ACARREO MATERIAL PRIMERA ESTACION 20.00 M.
FCO150R CONCRETO F'C=150 KG/CM2, RESISTENCIA NORMAL, AGR.MAX. 3/4, FABRICADO EN OBRA EN M3
REVOLVEDORA DE 1 SACO; ACARREO MATERIAL PRIMERA ESTACION 20.00 M.
FCO200M CONCRETO F'C=200 KG/CM2, RESISTENCIA NORMAL, AGR.MAX. 3/4, FABRICADO EN OBRA POR M3
MEDIOS MANUALES; ACARREO MATERIAL PRIMERA ESTACION 20.00 M.
FCO200R CONCRETO F'C=200 KG/CM2, RESISTENCIA NORMAL, AGR.MAX. 3/4, FABRICADO EN OBRA EN M3
REVOLVEDORA DE 1 SACO; ACARREO MATERIAL PRIMERA ESTACION 20.00 M.
FCO250M CONCRETO F'C=250 KG/CM2, RESISTENCIA NORMAL, AGR.MAX. 3/4, FABRICADO EN OBRA POR M3
MEDIOS MANUALES; ACARREO MATERIAL PRIMERA ESTACION 20.00 M.
FCO250R CONCRETO F'C=250 KG/CM2, RESISTENCIA NORMAL, AGR.MAX. 3/4, FABRICADO EN OBRA EN M3
REVOLVEDORA DE 1 SACO; ACARREO MATERIAL PRIMERA ESTACION 20.00 M.
ACR0037 ACARREO A MANO A 20 M DE DISTANCIA HORIZONTAL, DE MADERA PARA CIMBRA, INCLUYENDO MIL
CARGA Y DESCARGA.
AREF2 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA, FY=3000 KG/CM2, No. 2 TON
DIAMETRO 1/4" (ALAMBRN), SIN INCLUIR TRASLAPES; ACARREO MATERIAL PRIMERA ESTACION
= 20.00 M
AREF2 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA, FY=3000 KG/CM2, No. 2 TON
DIAMETRO 1/4" (ALAMBRN), SIN INCLUIR TRASLAPES; ACARREO MATERIAL PRIMERA ESTACION
= 20.00 M
AREF2.5 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA, FY=4200 KG/CM2, No.2.5 TON
DIAMETRO 5/16", SIN INCLUIR GANCHOS, TRASLAMPES NI ANCLAJES,ACARREO MATERIAL
PRIMERA ESTACION =20.00 M
AREF3 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA, FY=4200 KG/CM2, No.3 TON
DIAMETRO 3/8", SIN INCLUIR GANCHOS, TRASLAMPES NI ANCLAJES,ACARREO MATERIAL
PRIMERA ESTACION =20.00 M
AREF5 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA, FY=4200 KG/CM2, No.5 TON
DIAMETRO 5/8", SIN INCLUIR GANCHOS, TRASLAMPES NI ANCLAJES,ACARREO MATERIAL
PRIMERA ESTACION =20.00 M
AREF6 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA, FY=4200 KG/CM2, No.6 TON
DIAMETRO 3/4", SIN INCLUIR GANCHOS, TRASLAMPES NI ANCLAJES,ACARREO MATERIAL
PRIMERA ESTACION =20.00 M
AREF10 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA, FY=4200 KG/CM2, No.10 TON
DIAMETRO 1 ", SIN INCLUIR GANCHOS, TRASLAMPES NI ANCLAJES,ACARREO MATERIAL
PRIMERA ESTACION =20.00 M
AREF12 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA, FY=4200 KG/CM2, No.12 TON
DIAMETRO 1 ", SIN INCLUIR GANCHOS, TRASLAMPES NI ANCLAJES,ACARREO MATERIAL
PRIMERA ESTACION =20.00 M
CCAST CIMBRA Y DESCIMBRA ACABADO COMN EN CASTILLOS DE SECCIN MAYOR A 0.020 M2, M2
INCLUYE: MATERIALES Y MANO DE OBRA.
CCOL30X30 CIMBRA Y DESCIMBRA ACABADO COMN CON DUELA, EN COLUMNAS DE 30 X 30 CM. HASTA M2
UNA ALTURA DE 3.50 M. INCLUYE: MATERIALES Y MANO DE OBRA.
VDACAS150 VACIADO DE CONCRETO HECHO EN OBRA CON REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS M3
DE SECCIN >0.02 M2, FC=150 KG/CM2, RESISTENCIA NORMAL, TAMAO MXIMO DE
AGREGADO 20 MM. (3/4"), INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a. ESTACIN A 20 M.
MATERIALES Y MANO DE OBRA.
FCO150R CONCRETO FC=150 KG/CM2, RESISTENCIA NORMAL M3 0.00 1.030000 $1,043.39 $1,074.70
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA CON
REVOLVEDORA DE 1 SACO, ACARREO DE
MATERIALES A 1a ESTACION A 20 M.
VDACAS200 VACIADO DE CONCRETO HECHO EN OBRA CON REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS M3
DE SECCIN >0.02 M2, FC=200 KG/CM2, RESISTENCIA NORMAL, TAMAO MXIMO DE
AGREGADO 20 MM. (3/4"), INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a. ESTACIN A 20 M.
MATERIALES Y MANO DE OBRA.
VDACAS200 VACIADO DE CONCRETO HECHO EN OBRA CON REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS M3
DE SECCIN >0.02 M2, FC=200 KG/CM2, RESISTENCIA NORMAL, TAMAO MXIMO DE
AGREGADO 20 MM. (3/4"), INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a. ESTACIN A 20 M.
MATERIALES Y MANO DE OBRA.
FCO200R CONCRETO F'C=200 KG/CM2, RESISTENCIA NORMAL, M3 0.00 1.030000 $1,130.96 $1,164.89
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA EN
REVOLVEDORA DE 1 SACO, ACARREO MATERIAL
PRIMERA ESTACION=20.00M
VDACAS250 VACIADO DE CONCRETO HECHO EN OBRA CON REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS M3
DE SECCIN >0.02 M2, FC=250 KG/CM2, RESISTENCIA NORMAL, TAMAO MXIMO DE
AGREGADO 20 MM. (3/4"), INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a. ESTACIN A 20 M.
MATERIALES Y MANO DE OBRA.
FCO200R CONCRETO F'C=250 KG/CM2, RESISTENCIA NORMAL, M3 0.00 1.030000 $1,222.73 $1,259.42
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA EN
REVOLVEDORA DE 1 SACO, ACARREO MATERIAL
PRIMERA ESTACION=20.00M
FCO200R CONCRETO F'C=200 KG/CM2, RESISTENCIA NORMAL, M3 0.00 1.030000 $1,130.96 $1,164.89
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA EN
REVOLVEDORA DE 1 SACO, ACARREO MATERIAL
PRIMERA ESTACION=20.00M
FCO250R CONCRETO F'C=250 KG/CM2, RESISTENCIA NORMAL, M3 0.00 1.030000 $1,222.73 $1,259.42
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA EN
REVOLVEDORA DE 1 SACO, ACARREO MATERIAL
PRIMERA ESTACION=20.00M
FCO150R CONCRETO FC=150 KG/CM2, RESISTENCIA NORMAL M3 0.00 1.030000 $1,043.39 $1,074.70
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA CON
REVOLVEDORA DE 1 SACO, ACARREO DE
MATERIALES A 1a ESTACION A 20 M.
FCO250R CONCRETO F'C=250 KG/CM2, RESISTENCIA NORMAL, M3 0.00 1.030000 $1,222.73 $1,259.42
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA EN
REVOLVEDORA DE 1 SACO, ACARREO MATERIAL
PRIMERA ESTACION=20.00M
FCO150R CONCRETO FC=150 KG/CM2, RESISTENCIA NORMAL M3 0.00 1.030000 $1,043.39 $1,074.70
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA CON
REVOLVEDORA DE 1 SACO, ACARREO DE
MATERIALES A 1a ESTACION A 20 M.
FCO200R CONCRETO F'C=200 KG/CM2, RESISTENCIA NORMAL, M3 0.00 1.030000 $1,130.96 $1,164.89
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA EN
REVOLVEDORA DE 1 SACO, ACARREO MATERIAL
PRIMERA ESTACION=20.00M
FCO250R CONCRETO F'C=250 KG/CM2, RESISTENCIA NORMAL, M3 0.00 1.030000 $1,222.73 $1,259.42
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA EN
REVOLVEDORA DE 1 SACO, ACARREO MATERIAL
PRIMERA ESTACION=20.00M
FCO200R CONCRETO F'C=200 KG/CM2, RESISTENCIA NORMAL, M3 0.00 1.030000 $1,130.96 $1,164.89
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA EN
REVOLVEDORA DE 1 SACO, ACARREO MATERIAL
PRIMERA ESTACION=20.00M
FCO250R CONCRETO F'C=250 KG/CM2, RESISTENCIA NORMAL, M3 0.00 1.030000 $1,222.73 $1,259.42
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA EN
REVOLVEDORA DE 1 SACO, ACARREO MATERIAL
PRIMERA ESTACION=20.00M
VLOSA150 VACIADO DE CONCRETO HECHO EN OBRA CON REVOLVEDORA DE 1 SACO, EN LOSAS PLANAS Y M3
RETICULARES DE SUPERESTRUCTURA, FC=150 KG/CM2, RN. AGR. MAX. 20 MM. (3/4"), INCLUYE:
VIBRADO, CURADO Y ACARREO A UNA 1a. ESTACIN DE 20 M. DISTANCIA HORIZONTAL,
MATERIALES Y MANO DE OBRA.
FCO150R CONCRETO FC=150 KG/CM2, RESISTENCIA NORMAL M3 0.00 1.030000 $1,043.39 $1,074.70
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA CON
REVOLVEDORA DE 1 SACO, ACARREO DE
MATERIALES A 1a ESTACION A 20 M.
VLOSA200 VACIADO DE CONCRETO HECHO EN OBRA CON REVOLVEDORA DE 1 SACO, EN LOSAS PLANAS Y M3
RETICULARES DE SUPERESTRUCTURA, FC=200 KG/CM2, RN. AGR. MAX. 20 MM. (3/4"), INCLUYE:
VIBRADO, CURADO Y ACARREO A UNA 1a. ESTACIN DE 20 M. DISTANCIA HORIZONTAL,
MATERIALES Y MANO DE OBRA.
FCO200R CONCRETO F'C=200 KG/CM2, RESISTENCIA NORMAL, M3 0.00 1.030000 $1,130.96 $1,164.89
AGREGADO MAXIMO 3/4", FABRICADO EN OBRA EN
REVOLVEDORA DE 1 SACO, ACARREO MATERIAL
PRIMERA ESTACION=20.00M
VLOSA250 VACIADO DE CONCRETO HECHO EN OBRA CON REVOLVEDORA DE 1 SACO, EN LOSAS PLANAS Y M3
RETICULARES DE SUPERESTRUCTURA, FC=250 KG/CM2, RN. AGR. MAX. 20 MM. (3/4"), INCLUYE:
VIBRADO, CURADO Y ACARREO A UNA 1a. ESTACIN DE 20 M. DISTANCIA HORIZONTAL,
MATERIALES Y MANO DE OBRA.
LC LL
MEDIDA ZAPATA 1.20 1.20 M LC = LADO CORTO FC = FACTOR DE CONTACTO
SECCIN CIMBRADA DE DADO 0.50 0.50 M LL = LADO LARGO FD = FACTOR DE DESPERDICIO
PT = PIE TABLN FU = FACTOR DE USOS
PERALTE DE ZAPATA 0.30 M
ALTURA DE DADO 0.80 M PZAS = CANT. DE PIEZAS UTILIZADAS DE ESA MADERA
ESP.Y ANCHO = ESPESOR Y ANCHO DE LA MADERA
FACTOR DE DESPERDICIO 20.00 % MTS. = LONGITUD O LARGO DE LA MADERA
PROFUNDIDAD DE ESTACA 0.15 M DATOS QUE SE PUEDEN PROPONER O DEJAR EN CERO
HOLGURA YUGO 1 EXTREMO 0.05 M
SEPARACIN YUGO 0.50
LC LL
CARAS CIMBRADAS DE ZAPATA 2 2
CARAS CIMBRADAS DE DADO 2 2
CONTRATRABE (DADO)
CONTACTO LADO CORTO DUELA 5 2 1 20 0.80 2
0.80 17.50 1.60 10.94 13.13 5 2.63 1.26
CONTACTO LADO LARGO DUELA 5 2 1 20 0.80 2
CANT. DE YUGOS EN DADO BARROTE 5 2 4 3 3.42 22.42 1.60 14.01 16.81 5 3.36 5.38
CLCULO DE PIE TABLN PARA CIMBRA DE UN CASTILLO, COLUMNA, TRABE, DALA O CADENA
ELEMENTO CONSTRUCTIVO 2
Elemento Horizontal
TOTAL Y1 (DIAS)= 285.00 Factor para Salario Integrado X1/Y1 1.3439 Suma en % de prestaciones del IMSS 17.62 %
- - - - - - - - - -
1 CABO 220.00 14.52 - 3.22 2.09 3.14 16.70 5.23 9.41 2.20 11.00 1.7168
2 ALBAIL 290.00 14.52 - 3.22 2.76 4.13 22.01 6.89 12.40 2.90 14.50 1.7002
3 CARPINTERO 300.00
14.52 - 3.22 2.85 4.28 22.77 7.13 12.83 3.00 15.00 1.6984
4 PINTOR 300.00 14.52 - 3.22 2.85 4.28 22.77 7.13 12.83 3.00 15.00 1.6984
5 PLOMERO 300.00 14.52 - 3.22 2.85 4.28 22.77 7.13 12.83 3.00 15.00 1.6984
6 ELECTRICISTA 320.00
14.52 - 3.22 3.04 4.56 24.29 7.60 13.68 3.20 16.00 1.6953
7 PEON 209.01 14.52 - 3.22 1.99 2.98 15.86 4.96 8.94 2.09 10.45 1.7204
8 AYUDANTE EN GRAL. 209.01 14.52 - 3.22 1.99 2.98 15.86 4.96 8.94 2.09 10.45 1.7204
9 HERRERO 300.00 14.52 - 3.22 2.85 4.28 22.77 7.13 12.83 3.00 15.00 1.6984
10 CHOFER 209.01 14.52 - 3.22 1.99 2.98 15.86 4.96 8.94 2.09 10.45 1.7204
TOPOGRAFO $435.80 14.52 - 3.22 4.14 6.21 33.08 10.35 18.63 4.36 21.79 1.6827
- - - - - - - - - -
- - - - - - - - - -
PERSONAL TCNICO ADMINISTRATIVO - - - - - - - - - -
A1 SECRETARIA $130.00 14.52 - 1.24 1.85 9.87 3.09 5.56 1.30 6.50 1.7979
A2 DIBUJANTE $150.00 14.52 - 1.43 2.14 11.39 3.56 6.41 1.50 7.50 1.7779
A3 BODEGUERO $150.00 14.52 - 1.43 2.14 11.39 3.56 6.41 1.50 7.50 1.7779
A4 SUPERVISOR $200.00 14.52 - 3.22 1.90 2.85 15.18 4.75 8.55 2.00 10.00 1.7237
A5 CONTADOR $200.00 14.52 - 3.22 1.90 2.85 15.18 4.75 8.55 2.00 10.00 1.7237
A6 ADMINISTRADOR $600.00 14.52 - 3.22 5.70 8.55 45.54 14.25 25.65 6.00 30.00 1.6731
A7 - - - - - - - - - -
- - - - -
1 CABO 220.00 6.60 17.62 5.00 1.7365 382.03
2 ALBAIL 290.00 5.01 17.62 5.00 1.7151 497.38
3 CARPINTERO 300.00 4.84 17.62 5.00 1.7129 513.87
4 PINTOR 300.00 4.84 17.62 5.00 1.7129 513.87
5 PLOMERO 300.00 4.84 17.62 5.00 1.7129 513.87
6 ELECTRICISTA 320.00 4.54 17.62 5.00 1.7088 546.82
7 PEON 209.01 6.95 17.62 5.00 1.7412 363.93
8 AYUDANTE EN GRAL. 209.01 6.95 17.62 5.00 1.7412 363.93
9 HERRERO 300.00 4.84 17.62 5.00 1.7129 513.87
10 CHOFER 209.01 6.95 17.62 5.00 1.7412 363.93
- - - - -
- - - - -
- - - - -
PERSONAL TCNICO ADMINISTRATIVO - - - - -
A1 SECRETARIA $130.00 11.17 17.62 5.00 1.7979 233.73
A2 DIBUJANTE $150.00 9.68 17.62 5.00 1.7779 266.69
A3 BODEGUERO $150.00 9.68 17.62 5.00 1.7779 266.69
A4 SUPERVISOR $200.00 7.26 17.62 5.00 1.7454 349.08
A5 CONTADOR $200.00 7.26 17.62 5.00 1.7454 349.08
A6 ADMINISTRADOR $600.00 2.42 17.62 5.00 1.6803 1,008.18
A7 - - - - -
SALARIO
INTEGRADO
-
377.70
493.06
509.52
509.52
509.52
542.50
359.58
359.58
509.52
359.58
733.32
-
-
-
233.73
266.69
266.69
344.74
344.74
1,003.86
-
ANLISIS, CLCULO E INTEGRACIN DE LOS COSTOS HORARIOS
DE LA MAQUINARIA Y EQUIPO DE CONSTRUCCIN
EQUIPO No.
DATOS GENERALES Gasolina Diesel Otro
(Pm) Precio de la maquina como nueva $1,200,000.00 (Ah )Cantidad de aceite consumido por hora 10.00
(Pn) Precio de las llantas $12,000.00 (Ga) Relacin capacidad del carter entre 20.00
(Vm) Valor de la mquina $1,187,910.00 tiempo de cambios aceite
(Vr) Valor de rescate 30 %Vm $360,000.00 (t) Horas enrte cambio de lubricante 30.00
(Ve) Vida econmica de la mquina 14,600.00 Horas (Pa) Precio de lubricante $40.00
(IC) Instrumentos de captacin 1.00 (Vn) Vidad de las llantas 50.00
(i) Tasa de interes anual 18.00 (Ht) Horas efectivas por turno 8.00
(Hea) Horas efectivas por ao 2,920.00 Horas (Po) Costo horario por operacin $70.00
(s) Prima anual promedio 9.00 % (Sr) Salario real del personal operador $80.00
(Ko) Mantenimiento mayor y menor 5.00 % (Ppe) Valor de piezas especiales consideradas como nuevas $90.00
(Gh) Cantidad de combustible por hora 2.00 Lt (Vpe) Vida econmica de las piezas especiales 100.00
(Pc) Precio del combustible $12.00 Lt
I CARGOS FIJOS
I.1 Depreciacin D= (Vm-Vr)/Ve = 56.71
I.2 Inversin Im= (Vm+Vr) i /2Hea = 4,770.96
I.3 Seguros Sm= (Vm+Vr) s /2Hea = 2,385.48
I.4 Mantenimiento Mn= Ko x D = 283.53
(1) SUMA CARGOS FIJOS = 7,496.67
II. CONSUMOS
II.1 Combustibles CO= Gh x Pc = 24.00
II.2 Otras fuentes de energa =
II.3 Lubricantes Lb= (Ah+Ga) x Pa = 1,200.00
II.4 Llantas N= Pn/Vn = 240.00
II.5 Piezas Especiales Ae= Ppe/Vpe 0.90
(2) SUMA CONSUMOS = 1,464.90
III. OPERACIN
CATEGORAS CANTIDAD SALARIO REAL IMPORTE
OPERADOR 001 1 $10.00 10
$0.00 0
$0.00 0
$0.00 0
$0.00 0
(Po)= $10.00
III.1 OPERACIN Po=Sr/Ht
(3) SUMA OPERACIN
(1)+(2)+(3)= 8,971.57
Lt
Lt/Hr.
Horas
Lt
Horas
Horas
Horas
PROGRAMA MONTOS MENSUALES DE UTILIZACIN DE PERSONAL TCNICO, ADMINISTRATIVO Y DE SERVICIOS ENCARGADOS DE LA DIRECCIN,
SUPERVISIN Y ADMINISTRACIN DE LOS TRAAJOS
MONTO DE LA OBRA ACTUAL (C. D.) 775319.99 Ttulo del periodo SEM1 SEM2 SEM3 SEM 4 SEM 5
MONTO DE CONTRATOS VIGENTES (AO) $0.00 Ao
PERIODICIDAD SEMANAL Das naturales 7 7 7 7 4
Fecha de Inicio: Das por periodo 7 7 7 7 7
Fecha de terminacin: Factor 1.0000 1.0000 1.0000 1.0000 0.5714 0.0000 0.0000 0.0000 0.0000
Duracin en Dias: 1.00
MONTO DE LA OBRA ACTUAL (C. D.) $775,319.99 MONTO DE CONTRATOS VIGENTES (AO) $0.00 PERIODICIDAD
III.- SERVICIOS
3.1 $ - $ -
3.2 $ - $ -
3.3 $ - $ -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
SEMANAL
de los trabajos)
MONTO2
-
1,970.38
1,906.33
1,503.86
-
-
3,876.60
6,202.56
-
4,651.92
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
20,111.65
8.19
NOTA: ESTA HOJA NO SE DEBE AGREGAR AL REPORTE DE INDIRECTOS
PORQUE YA SE CONOCEN LOS % A LOS QUE SE QUIERE LLEGAR
PORCENTAJES PROPUESTOS PARA
CONOCER LOS SALARIOS PROMEDIOS PERIODICIDAD
INDIRECTOS PERSONAL DE OFICINA 5.81 % DIARIA
INDIRECTOS PERSONAL DE CAMPO 7.50 % SEMANAL
INDIRECTOS VARIOS (RENTA, MOBILIARIO, ETC.) 1.69 % QUINCENAL
TOTAL DE INDIRECTOS 15.00 % MENSUAL
EJEMPLO
PERSONAL ADMINISTRATIVO $ 83.00
Cant. Categora Salario TOTAL
1 ADMINISTRADOR DE OBRA $ 35.00 $ 35.00
2 AUXILIAR CONTABLE $ 20.00 $ 40.00
1 auxiliar a $ 8.00 $ 8.00
TOTAL $ 83.00
Tarjetas de anlisis de Urecios Unitarios
TRAZ0001 TRAZO Y NIVELACION DE TERRENO CON HILO CAL; DEJANDO REFERENCIA PARA EJECUCION DE
LOS TRABAJOS
Cdigo Concepto Unidad Rend. Cantidad Costo
MANO DE OBRA
CUAD001 CUADRILLA 001 (1 ALBAIL +1 PEON) JOR 100.00 0.010000 $852.64
5 % PARTICIPACION DE CABO, 30% ,HERRAMIENTA MENOR,
2.25%SEG E HIG
BASICOS
CYA0001B ANDAMIO DE CABALLETE FORMADO POR 2 CABALLETES DE PZA 0.00 0.181810 $50.00
1.10 M DE ALTO Y UN TABLON DE 0.30 X 2.50 X 11/2", PARA
AMORTIZARSE SEN 20 USO, EN TRABAJOS DE ALBAILERIA.
BASICOS
CYA0001B ANDAMIO DE CABALLETE FORMADO POR 2 CABALLETES DE PZA 0.00 0.080000 $50.00
1.10 M DE ALTO Y UN TABLON DE 0.30 X 2.50 X 11/2", PARA
AMORTIZARSE SEN 20 USO, EN TRABAJOS DE ALBAILERIA.
BASICOS
CYA0001B ANDAMIO DE CABALLETE FORMADO POR 2 CABALLETES DE PZA 0.00 0.076920 $50.00
1.10 M DE ALTO Y UN TABLON DE 0.30 X 2.50 X 11/2", PARA
AMORTIZARSE SEN 20 USO, EN TRABAJOS DE ALBAILERIA.
BASICOS
CYA0001B ANDAMIO DE CABALLETE FORMADO POR 2 CABALLETES DE PZA 0.00 1.530000 $50.00
1.10 M DE ALTO Y UN TABLON DE 0.30 X 2.50 X 11/2", PARA
AMORTIZARSE SEN 20 USO, EN TRABAJOS DE ALBAILERIA.
DEM0028 DEMOLICION A MANO DE APLANADOS DE MEZCLA, YESO O PASTAS EN MUROS O PLAFONES DE 2.5
CM. DE ESPESOR PROMEDIO. SIN INCLUIR ACARREOS, HASTA 2.50 M DE ALTURA
BASICOS
CYA0001B ANDAMIO DE CABALLETE FORMADO POR 2 CABALLETES DE PZA 0.00 0.040000 $50.00
1.10 M DE ALTO Y UN TABLON DE 0.30 X 2.50 X 11/2", PARA
AMORTIZARSE SEN 20 USO, EN TRABAJOS DE ALBAILERIA.
DEM0029 DEMOLICION A MANO DE FALSO PLAFON DE YESO, SIN INCLUIR ACARREOS, HASTA 2.50 M DE
ALTURA.
BASICOS
CYA0001B ANDAMIO DE CABALLETE FORMADO POR 2 CABALLETES DE PZA 0.00 0.052630 $50.00
1.10 M DE ALTO Y UN TABLON DE 0.30 X 2.50 X 11/2", PARA
AMORTIZARSE SEN 20 USO, EN TRABAJOS DE ALBAILERIA.
EXC0001 EXCAVACIN A MANO DE CEPAS PARA CIMENTACIN, EN SUELO TIPO II, HASTA UNA ALTURA DE
CEPA DE 2.00 M. NO INCLUYE ACARREO.
LTZ0005 TRAZO Y NIVELACIN POR MEDIOS MANUALES DEL TERRENO PLANO, PARA DESPLANTE DE
ESTRUCTURAS, ESTABLECIENDO EJES AUXILIARES, PASOS Y REFERENCIAS. INCLUYE:MATERIALES
Y MANO DE OBRA.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 100.00 0.010000 $963.48
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Costo directo
INDIRECTO 0.1
UTILIDADES 0.15
COSTO TOTAL
CIM0001 CIMENTACION DE MANPOSTERIA DE PIEDRA BRAZA ASENTADA CON MEZCLA MORTERO - ARENA EN
PROPORCION 1:5, SEC. 60,30 X 80 CM. INCLUYE ACARREO DE MATERIAL A 1 ESTACION A 20 M. DE
DISTANCIA HORIZONTAL.
CIM0001 CIMENTACION DE MANPOSTERIA DE PIEDRA BRAZA ASENTADA CON MEZCLA MORTERO - ARENA EN
PROPORCION 1:5, SEC. 60,30 X 80 CM. INCLUYE ACARREO DE MATERIAL A 1 ESTACION A 20 M. DE
DISTANCIA HORIZONTAL.
BASICOS
MEZ0002 MORTERO MORTERO - ARENA PROPORCION 1:5 M3 0.00 0.325500 $604.70
SUBCONTRATOS
ACR0082A ACARREO EN CAMION A PRIMER KILOMETRO, MEDIDO EN M3 0.00 1.200000 $32.00
BANCO ABUNDAMIENTO 1.22, INCLUYE CARGA A MANO
MATERIAL SUELTO.
RELL01CC RELLENO EN CEPAS CON MATERIAL DE BANCO, COMPACTANDO AL 90% PROCTOR, CON
COMPACTADOR (BAILARINA), EN CAPAS DE 20 CM.
SUBCONTRATOS
BAI0001 COMPACTADOR BAILARINA HR 0.00 0.300000 $46.13
CAST001V CASTILLO CON SECCION DE 15X15 CM DE CONCRETO F'C=150 KG/CM2, R. N. AGR. MAX. 3/4,
REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 20 CM, CON CIMBRA
COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 10.84 0.092251 $963.48
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.092251 $50.00
BASICOS
AREF3 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.002340 $21,253.51
ESTRUCTURA, FY=4200 KG/CM2, No.3, DIAMETRO 3/8", SIN
INCLUIR GANCHOS, TRASLAPES NI ANCLAJES, ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO 0.1
UTILIDADES 0.15
COSTO TOTAL
CAST002V CASTILLO CON SECCION DE 15X15 CM DE CONCRETO F'C=200 KG/CM2, R. N. AGR. MAX. 3/4,
REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 20 CM, CON CIMBRA
COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 10.84 0.092251 $963.48
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.092251 $50.00
BASICOS
AREF3 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.002340 $21,253.51
ESTRUCTURA, FY=4200 KG/CM2, No.3, DIAMETRO 3/8", SIN
INCLUIR GANCHOS, TRASLAPES NI ANCLAJES, ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO 0.1
UTILIDADES 0.15
COSTO TOTAL
CAST003V CASTILLO CON SECCION DE 15X15 CM DE CONCRETO F'C=250 KG/CM2, R. N. AGR. MAX. 3/4,
REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 20 CM, CON CIMBRA
COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 10.84 0.092251 $963.48
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.092251 $50.00
BASICOS
AREF3 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.002340 $21,253.51
ESTRUCTURA, FY=4200 KG/CM2, No.3, DIAMETRO 3/8", SIN
INCLUIR GANCHOS, TRASLAPES NI ANCLAJES, ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO 0.1
UTILIDADES 0.15
COSTO TOTAL
CAST004V CASTILLO CON SECCION DE 15X20 CM DE CONCRETO F'C=150 KG/CM2, R. N. AGR. MAX. 3/4,
REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 20 CM, CON CIMBRA
COMN 2 CARAS.
MATERIALES
MALA0180 ALAMBRE RECOCIDO No. 18 KG 0.00 0.130000 $13.00
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 9.79 0.102145 $963.48
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.102145 $50.00
BASICOS
AREF3 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.002520 $21,253.51
ESTRUCTURA, FY=4200 KG/CM2, No.3, DIAMETRO 3/8", SIN
INCLUIR GANCHOS, TRASLAPES NI ANCLAJES, ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO 0.1
UTILIDADES 0.15
COSTO TOTAL
CAST005V CASTILLO CON SECCION DE 15X20 CM DE CONCRETO F'C=200 KG/CM2, R. N. AGR. MAX. 3/4,
REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 20 CM, CON CIMBRA
COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 9.79 0.102145 $963.48
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.102145 $50.00
BASICOS
AREF3 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.002520 $21,253.51
ESTRUCTURA, FY=4200 KG/CM2, No.3, DIAMETRO 3/8", SIN
INCLUIR GANCHOS, TRASLAPES NI ANCLAJES, ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO 0.1
UTILIDADES 0.15
COSTO TOTAL
CAST010V DALA CON SECCION DE 15X30 CM DE CONCRETO F'C=200 KG/CM2, R. N. AGR. MAX. 3/4,
REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 15 CM, CON CIMBRA
COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 9.64 0.103734 $963.48
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.103734 $50.00
BASICOS
AREF3 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.002300 $21,253.51
ESTRUCTURA, FY=4200 KG/CM2, No.3, DIAMETRO 3/8", SIN
INCLUIR GANCHOS, TRASLAPES NI ANCLAJES, ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO 0.1
UTILIDADES 0.15
COSTO TOTAL
CSAT006V CASTILLO CON SECCION DE 15X20 CM DE CONCRETO F'C=250 KG/CM2, R. N. AGR. MAX. 3/4,
REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 15 CM, CON CIMBRA
COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 9.79 0.102145 $963.48
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.102145 $50.00
BASICOS
AREF3 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.002520 $21,253.51
ESTRUCTURA, FY=4200 KG/CM2, No.3, DIAMETRO 3/8", SIN
INCLUIR GANCHOS, TRASLAPES NI ANCLAJES, ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO 0.15
UTILIDADES 0.1
COSTO TOTAL
CAST007V CASTILLO CON SECCION DE 14X20 CM DE CONCRETO F'C=150 KG/CM2, R. N. AGR. MAX. 3/4,
REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 15 CM, CON CIMBRA
COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 8.74 0.114416 $963.48
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.114416 $50.00
BASICOS
AREF3 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.002520 $21,253.51
ESTRUCTURA, FY=4200 KG/CM2, No.3, DIAMETRO 3/8", SIN
INCLUIR GANCHOS, TRASLAPES NI ANCLAJES, ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO 0.15
UTILIDADES 0.1
COSTO TOTAL
CAST008V CASTILLO CON SECCION DE 20X20 CM DE CONCRETO F'C=200 KG/CM2, R. N. AGR. MAX. 3/4,
REFORZADO CON 4 VARILLAS DE 3/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 20 CM, CON CIMBRA
COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 8.74 0.114416 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.114416 $0.00
BASICOS
AREF3 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.002520 $6,278.58
ESTRUCTURA, FY=4200 KG/CM2, No.3, DIAMETRO 3/8", SIN
INCLUIR GANCHOS, TRASLAPES NI ANCLAJES, ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
CAST009V CASTILLO CON SECCION DE 30x45 CM DE CONCRETO F'C=250 KG/CM2, R. N. AGR. MAX. 3/4,
REFORZADO CON 4 VARILLAS DE 5/8" DIAM. Y ESTRIBOS DE 1/4" DIAM. A CADA 15 CM, CON CIMBRA
COMN 4 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 8.74 0.114416 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.114416 $0.00
BASICOS
AREF3 HABILITADO Y ARMADO DE ACERO DE REFUERZO EN TON 0.00 0.002520 $7,278.58
ESTRUCTURA, FY=4200 KG/CM2, No.3, DIAMETRO 3/8", SIN
INCLUIR GANCHOS, TRASLAPES NI ANCLAJES, ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO 0.1
UTILIDADES 0.15
COSTO TOTAL
DALA001A DALA CON SECCION DE 15X15 CM DE CONCRETO F'C=150 KG/CM2, R. N. AGR. MAX. 3/4" REFORZADA
CON ARMADURA ELECTROSOLDADA ARMEX 15X15-4, CON CIMBRA COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 12.76 0.078370 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.078370 $0.00
BASICOS
CCADE CIMBRA Y DESCIMBRA ACABADO COMN EN CADENAS DE M2 0.00 0.300000 $80.65
DESPLANTE Y CERRAMIENTO DE SECCIN MAYOR A 0.020
M2, INCLUYE: MATERIALES Y MANO DE OBRA.
VDACAS150 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.022500 $759.21
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIN >0.02 M2, FC=150 KG/CM2, RESISTENCIA
NORMAL, TAMAO MXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIN A 20 M. MATERIALES Y
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
DALA002A DALA CON SECCION DE 15X15 CM DE CONCRETO F'C=200 KG/CM2, R. N. AGR. MAX. 3/4" REFORZADA
CON ARMADURA ELECTROSOLDADA ARMEX 15X15-4, CON CIMBRA COMN 2 CARAS.
DALA002A DALA CON SECCION DE 15X15 CM DE CONCRETO F'C=200 KG/CM2, R. N. AGR. MAX. 3/4" REFORZADA
CON ARMADURA ELECTROSOLDADA ARMEX 15X15-4, CON CIMBRA COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 12.76 0.078370 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.078370 $0.00
MATERIALES
MARM0018 ARMADURA SOLDADA CASTILLO ARMEX 15X25-4 MT 0.00 1.030000 $4.65
BASICOS
CCADE CIMBRA Y DESCIMBRA ACABADO COMN EN CADENAS DE M2 0.00 0.300000 $80.65
DESPLANTE Y CERRAMIENTO DE SECCIN MAYOR A 0.020
M2, INCLUYE: MATERIALES Y MANO DE OBRA.
VDACAS200 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.022500 $773.81
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIN >0.02 M2, FC=200 KG/CM2, RESISTENCIA
NORMAL, TAMAO MXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIN A 20 M. MATERIALES Y
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
DALA003A DALA CON SECCION DE 15X15 CM DE CONCRETO F'C=250 KG/CM2, R. N. AGR. MAX. 3/4" REFORZADA
CON ARMADURA ELECTROSOLDADA ARMEX 15X15-4, CON CIMBRA COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 12.76 0.078370 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.078370 $0.00
MATERIALES
MARM0018 ARMADURA SOLDADA CASTILLO ARMEX 15X25-4 MT 0.00 1.030000 $4.65
BASICOS
CCADE CIMBRA Y DESCIMBRA ACABADO COMN EN CADENAS DE M2 0.00 0.300000 $80.65
DESPLANTE Y CERRAMIENTO DE SECCIN MAYOR A 0.020
M2, INCLUYE: MATERIALES Y MANO DE OBRA.
VDACAS250 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.022500 $773.81
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIN >0.02 M2, FC=250 KG/CM2, RESISTENCIA
NORMAL, TAMAO MXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIN A 20 M. MATERIALES Y
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
DALA004A DALA CON SECCION DE 15X20 CM DE CONCRETO F'C=150 KG/CM2, R. N. AGR. MAX. 3/4" REFORZADA
CON ARMADURA ELECTROSOLDADA ARMEX 15X20-4, CON CIMBRA COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 12.12 0.082508 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.082508 $0.00
MATERIALES
MARM0018 ARMADURA SOLDADA CASTILLO ARMEX 15X25-4 MT 0.00 1.030000 $4.65
BASICOS
CCADE CIMBRA Y DESCIMBRA ACABADO COMN EN CADENAS DE M2 0.00 0.350000 $80.65
DESPLANTE Y CERRAMIENTO DE SECCIN MAYOR A 0.020
M2, INCLUYE: MATERIALES Y MANO DE OBRA.
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
DALA005A DALA CON SECCION DE 15X20 CM DE CONCRETO F'C=200 KG/CM2, R. N. AGR. MAX. 3/4" REFORZADA
CON ARMADURA ELECTROSOLDADA ARMEX 15X20-4, CON CIMBRA COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 12.12 0.082508 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.082508 $0.00
MATERIALES
MARM0018 ARMADURA SOLDADA CASTILLO ARMEX 15X25-4 MT 0.00 1.030000 $4.65
BASICOS
CCADE CIMBRA Y DESCIMBRA ACABADO COMN EN CADENAS DE M2 0.00 0.350000 $80.65
DESPLANTE Y CERRAMIENTO DE SECCIN MAYOR A 0.020
M2, INCLUYE: MATERIALES Y MANO DE OBRA.
VDACAS200 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.030000 $773.81
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIN >0.02 M2, FC=200 KG/CM2, RESISTENCIA
NORMAL, TAMAO MXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIN A 20 M. MATERIALES Y
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
DALA006A DALA CON SECCION DE 15X20 CM DE CONCRETO F'C=250 KG/CM2, R. N. AGR. MAX. 3/4" REFORZADA
CON ARMADURA ELECTROSOLDADA ARMEX 15X20-4, CON CIMBRA COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 12.12 0.082508 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.082508 $0.00
MATERIALES
MARM0018 ARMADURA SOLDADA CASTILLO ARMEX 15X25-4 MT 0.00 1.030000 $4.65
BASICOS
CCADE CIMBRA Y DESCIMBRA ACABADO COMN EN CADENAS DE M2 0.00 0.350000 $80.65
DESPLANTE Y CERRAMIENTO DE SECCIN MAYOR A 0.020
M2, INCLUYE: MATERIALES Y MANO DE OBRA.
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
DALA007A DALA CON SECCION DE 20X20 CM DE CONCRETO F'C=150 KG/CM2, R. N. AGR. MAX. 3/4" REFORZADA
CON ARMADURA ELECTROSOLDADA ARMEX 15X20-4, CON CIMBRA COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 11.48 0.087108 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.087108 $0.00
MATERIALES
MARM0018 ARMADURA SOLDADA CASTILLO ARMEX 15X25-4 MT 0.00 1.030000 $4.65
BASICOS
CCADE CIMBRA Y DESCIMBRA ACABADO COMN EN CADENAS DE M2 0.00 0.400000 $80.65
DESPLANTE Y CERRAMIENTO DE SECCIN MAYOR A 0.020
M2, INCLUYE: MATERIALES Y MANO DE OBRA.
VDACAS150 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.040000 $759.21
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIN >0.02 M2, FC=150 KG/CM2, RESISTENCIA
NORMAL, TAMAO MXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIN A 20 M. MATERIALES Y
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
DALA008A DALA CON SECCION DE 20X20 CM DE CONCRETO F'C=200 KG/CM2, R. N. AGR. MAX. 3/4" REFORZADA
CON ARMADURA ELECTROSOLDADA ARMEX 15X20-4, CON CIMBRA COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 11.48 0.087108 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.087108 $0.00
MATERIALES
MARM0018 ARMADURA SOLDADA CASTILLO ARMEX 15X25-4 MT 0.00 1.030000 $4.65
BASICOS
CCADE CIMBRA Y DESCIMBRA ACABADO COMN EN CADENAS DE M2 0.00 0.400000 $80.65
DESPLANTE Y CERRAMIENTO DE SECCIN MAYOR A 0.020
M2, INCLUYE: MATERIALES Y MANO DE OBRA.
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
DALA009A DALA CON SECCION DE 15X30 CM DE CONCRETO F'C=250 KG/CM2, R. N. AGR. MAX. 3/4" REFORZADA
CON ARMADURA ELECTROSOLDADA ARMEX 15X20-4, CON CIMBRA COMN 2 CARAS.
DALA009A DALA CON SECCION DE 15X30 CM DE CONCRETO F'C=250 KG/CM2, R. N. AGR. MAX. 3/4" REFORZADA
CON ARMADURA ELECTROSOLDADA ARMEX 15X20-4, CON CIMBRA COMN 2 CARAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 11.48 0.087108 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.087108 $0.00
MATERIALES
MARM0018 ARMADURA SOLDADA CASTILLO ARMEX 15X25-4 MT 0.00 1.030000 $4.65
BASICOS
CCADE CIMBRA Y DESCIMBRA ACABADO COMN EN CADENAS DE M2 0.00 0.400000 $80.65
DESPLANTE Y CERRAMIENTO DE SECCIN MAYOR A 0.020
M2, INCLUYE: MATERIALES Y MANO DE OBRA.
VDACAS250 VACIADO DE CONCRETO HECHO EN OBRA CON M3 0.00 0.040000 $773.81
REVOLVEDORA 1 SACO, EN DALAS Y CASTILLOS DE
SECCIN >0.02 M2, FC=250 KG/CM2, RESISTENCIA
NORMAL, TAMAO MXIMO DE AGREGADO 20 MM. (3/4"),
INCLUYE: VIBRADO, CURADO, ACARREO A UNA 1a.
ESTACIN A 20 M. MATERIALES Y
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
PLA05-100 PLANTILLA DE CONCRETO SIMPLE F`C =100 KG/CM2, RESISTENCIA NORMAL, DE 5 CM. ESPESOR,
AGREGADO MAXIMO 3/4" (20 MM.) INCLYE: MATERIALES Y MANO DE OBRA.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 20.00 0.050000 $655.40
BASICOS
FCO100R CONCRETO F'C=100 KG/CM2, RESISTENCIA NORMAL, M3 0.00 0.051500 $236.89
AGR.MAX. 3/4, FABRICADO EN OBRA EN REVOLVEDORA DE 1
SACO; ACARREO MATERIAL PRIMERA ESTACION 20.00 M.
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
PIS05-100 FIRME DE CONCRETO SIMPLE F`C =100 KG/CM2, RESISTENCIA NORMAL, DE 5 CM. ESPESOR,
AGREGADO MAXIMO 3/4" (20 MM.) ACABADO ESCOBILLADO. INCLYE: MATERIALES Y MANO DE
OBRA.
BASICOS
ACR0012 ACARREO EN CARRETILLA, POR CADA 20 M DE DISTANCIA M3 0.00 0.051500 $46.82
HORIZONTAL, SUBSECUENTES A LOS PRIMEROS, DE
AGREGADOS, MORTERO, CONCRETOS.
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
PIS05-150 FIRME DE CONCRETO SIMPLE F`C =150 KG/CM2, RESISTENCIA NORMAL, DE 5 CM. ESPESOR,
AGREGADO MAXIMO 3/4" (20 MM.) ACABADO ESCOBILLADO. INCLYE: MATERIALES Y MANO DE
OBRA.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 15.00 0.066667 $655.40
BASICOS
ACR0012 ACARREO EN CARRETILLA, POR CADA 20 M DE DISTANCIA M3 0.00 0.051500 $46.82
HORIZONTAL, SUBSECUENTES A LOS PRIMEROS, DE
AGREGADOS, MORTERO, CONCRETOS.
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
PIS08-150 FIRME DE CONCRETO SIMPLE F`C =150 KG/CM2, RESISTENCIA NORMAL, DE 8 CM. ESPESOR,
AGREGADO MAXIMO 3/4" (20 MM.) ACABADO ESCOBILLADO. INCLYE: MATERIALES Y MANO DE
OBRA.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 15.00 0.066667 $655.40
BASICOS
ACR0012 ACARREO EN CARRETILLA, POR CADA 20 M DE DISTANCIA M3 0.00 0.082400 $46.82
HORIZONTAL, SUBSECUENTES A LOS PRIMEROS, DE
AGREGADOS, MORTERO, CONCRETOS.
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
PIS08-200 FIRME DE CONCRETO SIMPLE F`C =200 KG/CM2, RESISTENCIA NORMAL, DE 8 CM. ESPESOR,
AGREGADO MAXIMO 3/4" (20 MM.) ACABADO ESCOBILLADO. INCLYE: MATERIALES Y MANO DE
OBRA.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 15.00 0.066667 $655.40
BASICOS
ACR0012 ACARREO EN CARRETILLA, POR CADA 20 M DE DISTANCIA M3 0.00 0.084000 $46.82
HORIZONTAL, SUBSECUENTES A LOS PRIMEROS, DE
AGREGADOS, MORTERO, CONCRETOS.
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
PIS10-150 FIRME DE CONCRETO SIMPLE F`C =150 KG/CM2, RESISTENCIA NORMAL, DE 10 CM. ESPESOR,
AGREGADO MAXIMO 3/4" (20 MM.) ACABADO ESCOBILLADO. INCLYE: MATERIALES Y MANO DE
OBRA.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 15.00 0.066667 $655.40
BASICOS
ACR0012 ACARREO EN CARRETILLA, POR CADA 20 M DE DISTANCIA M3 0.00 0.103000 $46.82
HORIZONTAL, SUBSECUENTES A LOS PRIMEROS, DE
AGREGADOS, MORTERO, CONCRETOS.
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
PIS10-200 FIRME DE CONCRETO SIMPLE F`C =200 KG/CM2, RESISTENCIA NORMAL, DE 10 CM. ESPESOR,
AGREGADO MAXIMO 3/4" (20 MM.) ACABADO ESCOBILLADO. INCLYE: MATERIALES Y MANO DE
OBRA.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 15.00 0.066667 $655.40
BASICOS
ACR0012 ACARREO EN CARRETILLA, POR CADA 20 M DE DISTANCIA M3 0.00 0.103000 $46.82
HORIZONTAL, SUBSECUENTES A LOS PRIMEROS, DE
AGREGADOS, MORTERO, CONCRETOS.
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
PIS15-150 FIRME DE CONCRETO SIMPLE F`C =150 KG/CM2, RESISTENCIA NORMAL, DE 15 CM. ESPESOR,
AGREGADO MAXIMO 3/4" (20 MM.) ACABADO ESCOBILLADO. INCLYE: MATERIALES Y MANO DE
OBRA.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 12.00 0.083333 $655.40
BASICOS
ACR0012 ACARREO EN CARRETILLA, POR CADA 20 M DE DISTANCIA M3 0.00 0.153000 $46.82
HORIZONTAL, SUBSECUENTES A LOS PRIMEROS, DE
AGREGADOS, MORTERO, CONCRETOS.
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
PIS15-200 FIRME DE CONCRETO SIMPLE F`C =200 KG/CM2, RESISTENCIA NORMAL, DE 15 CM. ESPESOR,
AGREGADO MAXIMO 3/4" (20 MM.) ACABADO ESCOBILLADO. INCLYE: MATERIALES Y MANO DE
OBRA.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 12.00 0.083333 $655.40
BASICOS
ACR0012 ACARREO EN CARRETILLA, POR CADA 20 M DE DISTANCIA M3 0.00 0.153000 $46.82
HORIZONTAL, SUBSECUENTES A LOS PRIMEROS, DE
AGREGADOS, MORTERO, CONCRETOS.
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
MURLAD7 MURO DE TABIQUE ROJO RECOCIDO DE 71428 CM. DE 7 CM. DE ESP. (CAPUCHINO), ASENTADO
CON MEZCLA MORTERO-ARENA 1:5, JUNTAS DE 1.5 CM. DE ESP. ACABADO COMN HASTA UNA
ALTURA DE 3.5 M.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 12.00 0.083333 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.083000 $0.00
BASICOS
MEZ0011 MEZCLA MORTERO-ARENA 1:5 M3 0.00 0.011600 $355.96
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
MURLAD14 MURO DE TABIQUE ROJO RECOCIDO DE 71428 CM. DE 14 CM. DE ESP. ASENTADO CON MEZCLA
MORTERO-ARENA 1:5, JUNTAS DE 1.5 CM. DE ESP. ACABADO COMN HASTA UNA ALTURA DE 3.5 M.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 10.00 0.100000 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.056625 $0.00
BASICOS
MEZ0011 MEZCLA MORTERO-ARENA 1:5 M3 0.00 0.040000 $355.96
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
MURLAD28 MURO DE TABIQUE ROJO RECOCIDO DE 71428 CM. DE 28 CM. DE ESP. ASENTADO CON MEZCLA
MORTERO-ARENA 1:5, JUNTAS DE 1.5 CM. DE ESP. ACABADO COMN HASTA UNA ALTURA DE 3.5 M.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 6.49 0.154083 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.056625 $0.00
BASICOS
MEZ0011 MEZCLA MORTERO-ARENA 1:5 M3 0.00 0.055000 $355.96
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
MURTAB10 MURO DE TABICN DE CONCRETO LIGERO DE 10 1428 DE 10 CM. DE ESP. (CAPUCHINO),
ASENTADO CON MEZCLA MORTERO-ARENA 1:5, JUNTAS DE 1.5 CM. DE ESP. ACABADO COMN
HASTA UNA ALTURA DE 3.5 M.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 10.00 0.100000 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 1.000000 $0.00
BASICOS
MEZ0011 MEZCLA MORTERO-ARENA 1:5 M3 0.00 0.018600 $355.96
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
MURTAB14 MURO DE TABICN DE CONCRETO LIGERO DE 101428 DE 14 CM. DE ESP. ASENTADO CON
MEZCLA MORTERO-ARENA 1:5, JUNTAS DE 1.5 CM. DE ESP. ACABADO COMN HASTA UNA ALTURA
DE 3.5 M.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 10.00 0.100000 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 1.000000 $0.00
BASICOS
MEZ0011 MEZCLA MORTERO-ARENA 1:5 M3 0.00 0.031800 $355.96
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO 0.1
UTILIDADES 0.15
COSTO TOTAL
MURTAB28 MURO DE TABICN DE CONCRETO LIGERO DE 101428 DE 28 CM. DE ESP. ASENTADO CON
MEZCLA MORTERO-ARENA 1:5, JUNTAS DE 1.5 CM. DE ESP. ACABADO COMN HASTA UNA ALTURA
DE 3.5 M.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 10.00 0.100000 $655.40
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 1.000000 $0.00
BASICOS
MEZ0011 MEZCLA MORTERO-ARENA 1:5 M3 0.00 0.078100 $355.96
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: BASICOS
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 5.00 0.200000 $655.40
APL0025 EMBOQUILLADO EN REPELLADO, DE 6 CM. DE ANCHO, CON M 0.00 1.000000 $24.78
MORTERO DE CEMENTO Y ARENA PROPORCION DE 1:6,
PERFILANDO UNA ARISTA; ALTURA HASTA 3.00 M, ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M.
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Subtotal: .
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
LOSA10-200 LOSA DE 10 CM. DE PERALTE EN TECHO DE CUBIERTA, FABRICADA CON CONCRETO F`c = 200
KG/CM2 AGREGADO MAXIMO 3/4" INCLUYE CIMBRA ,DESCIMBRA, KG. DE ACERO DE REFUERZO X
M3 DE CONCRETO, MATERIALES MANO DE OBRA Y EQUIPO
CLOSA HAB. Y COL. DE CIMBRA CON TARIMAS DE DUELA PARA M2 0.00 1.000000 $62.40
LOSA DE CONCRETO.
Subtotal: BASICOS
Subtotal: .
Costo directo
INDIRECTO 0.1
UTILIDADES 0.15
COSTO TOTAL
LOSA10-250 LOSA DE 10 CM. DE PERALTE EN TECHO DE CUBIERTA, FABRICADA CON CONCRETO F`c = 250
KG/CM2 AGREGADO MAXIMO 3/4" INCLUYE CIMBRA ,DESCIMBRA, KG. DE ACERO DE REFUERZO X
M3 DE CONCRETO, MATERIALES MANO DE OBRA Y EQUIPO
CLOSA HAB. Y COL. DE CIMBRA CON TARIMAS DE DUELA PARA M2 0.00 1.000000 $62.40
LOSA DE CONCRETO.
Subtotal: BASICOS
Subtotal: .
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
PTA0001 SUMINISTRO Y COLOCACIN DE PUERTA DE 0.70 X 2.10 M. INCLUYE: CHAPA MODELO 715 Y PINTURA
BASE.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 2.50 0.400000 $655.40
APL0025 EMBOQUILLADO EN REPELLADO, DE 6 CM. DE ANCHO, CON M 0.00 1.000000 $24.78
MORTERO DE CEMENTO Y ARENA PROPORCION DE 1:6,
PERFILANDO UNA ARISTA; ALTURA HASTA 3.00 M, ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M.
VENT0001 SUMINISTRO Y COLOCACIN DE VENTANA METLICA DE 0.70 X 0.60 M. INCLUYE: PINTURA BASE Y
BOQUILLAS.
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 2.50 0.400000 $655.40
APL0025 EMBOQUILLADO EN REPELLADO, DE 6 CM. DE ANCHO, CON M 0.00 1.000000 $24.78
MORTERO DE CEMENTO Y ARENA PROPORCION DE 1:6,
PERFILANDO UNA ARISTA; ALTURA HASTA 3.00 M, ACARREO
MATERIAL PRIMERA ESTACION = 20.00 M.
PIS0080 SUMINISTRO Y COLOCACIN DE PISO DE CERMICA DE 33X33 CM. VITROMEX MODELO DOS
AMRICAS COLOR BLANCO, ASENTADO CON PEGAPISO COLOR GRIS Y JUNTEADOR COLOR GRIS
MARCA PERDURA.
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Costo directo
INDIRECTO 0.1
UTILIDADES 0.15
COSTO TOTAL
PIN0001 SUMINISTRO Y APLICACIN DE PINTURA VINLICA EN MUROS Y PLAFN CON YESO, INCLUYENDO
UNA MANO DE SELLADOR Y DOS MANOS DE PINTURA CALIDAD BERELINTE COLOR BLANCO Y
PREPARACIN DE SUPERFICIE.
MANO DE OBRA
CUAD060 CUADRILLA 060 (1 PINTOR) JOR 20.00 0.050000 $327.70
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.050000 $0.00
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 0.050000 $0.00
MATERIALES
MPIN0001 PINTURA ESMALTE CUB 0.00 0.009734 $1,089.56
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
BASICOS
MEZ0005 MORTERO CEMENTO-ARENA 1:6 M3 0.00 0.001440 $165.89
APL0022 APLANADO EN PLAFN DE LOSA, PULIDO A LLANA CON MEZCLA DE MORTERO Y ARENA
PROPORCION DE 1:5, DE 2.5 CM. DE ESPESOR PROMEDIO.
BASICOS
MEZ0011 MEZCLA MORTERO-ARENA 1:5 M3 0.00 0.032500 $355.96
SUBCONTRATOS
EAN0001 ANDAMIO METALICO DE 2 X 2 PZA 0.00 1.000000 $0.00
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 45.45 0.022002 $655.40
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
MANO DE OBRA
CUAD040 CUADRILLA 040 (1ALBANIL+1PEON) JOR 30.00 0.033333 $655.40
Subtotal: MATERIALES
Subtotal: MANO DE OBRA
Costo directo
INDIRECTO
UTILIDADES
COSTO TOTAL
MANO DE OBRA
CU CUADRILLA JOR 30.00 0.033333 $655.40 $21.85
AD 040
040 (1ALBANIL+1
PEON)
Importe
$8.53
$3.20
$11.72
$11.72
$1.17
$1.76
$14.65
m2
Importe
$8.53
$3.20
$11.72
$11.72
$1.17
$1.76
$14.65
m3
Importe
$73.88
$9.09
$73.88
$9.09
$82.97
$8.30
$12.45
$103.71
m2
Importe
$32.51
$4.00
$32.51
$4.00
$36.51
$3.65
$5.48
$45.63
M2
Importe
$62.51
$3.85
$62.51
$3.85
$66.36
$6.64
$9.95
$82.95
M3
Importe
$625.12
$76.50
$625.12
$76.50
$701.62
$70.16
$105.24
$877.02
M2
Importe
$24.37
$24.37
$24.37
$2.44
$3.66
$30.47
M2
Importe
$54.03
$54.03
$54.03
$5.40
$8.10
$67.54
M2
Importe
$16.25
$2.00
$16.25
$2.00
$18.25
$1.83
$2.74
$22.82
M2
Importe
$21.39
$2.63
$21.39
$2.63
$24.02
$2.40
$3.60
$30.02
M2
Importe
$18.29
$18.29
$18.29
$1.83
$2.74
$22.86
M2
Importe
$15.03
$130.58
$145.62
$145.62
$14.56
$21.84
$182.02
M3
Importe
$146.16
$146.16
$146.16
$14.62
$21.92
$182.70
M2
Importe
$0.00
$0.42
$0.00
$0.00
$9.63
$0.42
$9.63
$10.05
$1.01
$1.51
$12.57
M3
M3
Importe
$350.36
$196.83
$38.40
$350.36
$196.83
$38.40
$585.59
$58.56
$87.84
$731.98
M3
Importe
$93.41
$13.84
$93.41
$107.25
$10.72
$16.09
$134.06
M2
Importe
$24.85
$2.82
$27.67
$27.67
$2.77
$4.15
$34.59
Importe
$1.00
$88.88
$4.61
$49.73
$22.94
$28.47
$41.34
$1.00
$88.88
$147.09
$236.97
$23.70
$35.55
$296.22
Importe
$1.00
$88.88
$4.61
$49.73
$22.94
$28.47
$43.37
$1.00
$88.88
$149.12
$239.00
$23.90
$35.85
$298.75
Importe
$1.00
$88.88
$4.61
$49.73
$22.94
$28.47
$45.49
$1.00
$88.88
$151.25
$241.13
$24.11
$36.17
$301.41
Importe
$1.69
$98.41
$5.11
$53.56
$38.53
$33.21
$55.12
$1.69
$98.41
$185.53
$285.64
$28.56
$42.85
$357.05
Importe
$1.69
$98.41
$5.11
$53.56
$38.53
$33.21
$57.82
$1.69
$98.41
$188.24
$288.34
$28.83
$43.25
$360.43
Importe
$1.69
$99.95
$5.19
$48.88
$29.82
$56.94
$93.72
$1.69
$99.95
$234.55
$336.18
$33.62
$50.43
$420.23
Importe
$1.69
$98.41
$5.11
$53.56
$38.53
$33.21
$60.66
$1.69
$98.41
$191.07
$291.18
$43.68
$29.12
$363.97
Importe
$1.69
$110.24
$5.72
$53.56
$41.29
$37.96
$73.49
$1.69
$110.24
$212.02
$323.94
$48.59
$32.39
$404.93
Importe
$0.33
$74.99
$0.00
$15.82
$15.81
$26.37
$30.95
$0.33
$74.99
$88.95
$164.27
$0.00
$0.00
$164.27
Importe
$0.33
$74.99
$0.00
$18.34
$17.61
$34.37
$61.90
$0.93
$104.99
$118.95
$224.87
$22.49
$33.73
$281.09
Importe
$0.33
$4.79
$51.36
$0.00
$24.20
$17.08
$5.12
$51.36
$41.28
$97.76
$0.00
$0.00
$97.76
M
M
Importe
$0.33
$51.36
$0.00
$4.79
$24.20
$17.41
$5.12
$51.36
$41.61
$98.09
$0.00
$0.00
$98.09
Importe
$0.33
$51.36
$0.00
$4.79
$24.20
$17.41
$5.12
$51.36
$41.61
$98.09
$0.00
$0.00
$98.09
Importe
$0.33
$54.08
$0.00
$4.79
$28.23
$22.78
$5.12
$54.08
$51.01
$110.21
$0.00
$0.00
$110.21
Importe
$0.33
$54.08
$0.00
$4.79
$28.23
$23.21
$5.12
$54.08
$51.44
$110.64
$0.00
$0.00
$110.64
Importe
$0.33
$54.08
$0.00
$4.79
$28.23
$23.21
$5.12
$54.08
$51.44
$110.64
$0.00
$0.00
$110.64
Importe
$0.33
$57.09
$0.00
$4.79
$32.26
$30.37
$5.12
$57.09
$62.63
$124.84
$0.00
$0.00
$124.84
Importe
$0.33
$57.09
$0.00
$4.79
$32.26
$30.95
$5.12
$57.09
$63.21
$125.42
$0.00
$0.00
$125.42
M
M
Importe
$0.33
$57.09
$0.00
$4.79
$32.26
$30.95
$5.12
$57.09
$63.21
$125.42
$0.00
$0.00
$125.42
M2
Importe
$0.16
$32.77
$12.20
$0.16
$32.77
$12.20
$45.13
$0.00
$0.00
$45.13
M2
Importe
$0.16
$43.69
$2.41
$12.20
$14.98
$0.16
$43.69
$29.59
$73.44
$0.00
$0.00
$73.44
M2
Importe
$0.16
$43.69
$2.41
$13.09
$14.98
$0.16
$43.69
$30.48
$74.33
$0.00
$0.00
$74.33
M2
Importe
$0.16
$43.69
$3.86
$20.94
$14.98
$0.16
$43.69
$39.78
$83.63
$0.00
$0.00
$83.63
M2
Importe
$0.16
$43.69
$3.93
$22.11
$14.98
$0.16
$43.69
$41.02
$84.87
$0.00
$0.00
$84.87
M2
Importe
$0.16
$43.69
$4.82
$26.17
$14.98
$0.16
$43.69
$45.97
$89.82
$0.00
$0.00
$89.82
M2
Importe
$0.16
$43.69
$4.82
$27.63
$14.98
$0.16
$43.69
$47.43
$91.28
$0.00
$0.00
$91.28
M2
Importe
$0.16
$54.62
$7.16
$38.88
$14.98
$0.16
$54.62
$61.02
$115.80
$0.00
$0.00
$115.80
M2
Importe
$0.16
$54.62
$7.16
$41.05
$14.98
$0.16
$54.62
$63.19
$117.97
$0.00
$0.00
$117.97
M2
Importe
$56.70
$0.05
$54.62
$0.00
$4.13
$56.75
$54.62
$4.13
$115.50
$0.00
$0.00
$115.50
M2
Importe
$86.40
$0.11
$65.54
$0.00
$14.24
$86.51
$65.54
$14.24
$166.29
$0.00
$0.00
$166.29
M2
Importe
$154.80
$0.19
$100.99
$0.00
$19.58
$154.99
$100.93
$19.58
$275.50
$0.00
$0.00
$275.50
M2
Importe
$30.72
$65.54
$0.00
$6.62
$30.72
$65.54
$6.62
$102.88
$10.29
$10.29
$0.00
M2
Importe
$65.34
$65.54
$0.00
$11.32
$76.66
$65.54
$11.32
$153.52
$15.35
$23.03
$191.90
M2
Importe
$79.37
$65.54
$0.00
$27.80
$79.37
$65.54
$27.80
$172.71
$0.00
$0.00
$172.71
Importe
$10.80
$131.08
$24.78
$10.80
$131.08
$24.78
$166.66
$16.67
$16.67
$0.00
M2
Importe
$55.95
$140.20
$62.40
$296.15
$62.40
$358.55
$35.86
$53.78
$448.19
M2
Importe
$57.56
$140.20
$62.40
$197.76
$62.40
$260.16
$0.00
$0.00
$260.16
PZA
Importe
$1,800.80
$262.16
$24.78
$262.16
$24.78
$2,087.74
$313.16
$2,400.90
PZA
Importe
$0.00
$262.16
$24.78
$262.16
$24.78
$286.94
$0.00
$0.00
$286.94
M2
Importe
$99.42
$13.49
$5.07
$54.62
$117.98
$54.62
$172.60
$17.26
$25.89
$215.75
M2
Importe
$1.31
$6.16
$0.00
$16.39
$0.00
$7.47
$16.39
$23.86
$0.00
$0.00
$23.86
M2
Importe
$15.28
$0.00
$10.61
$10.61
$15.28
$25.89
$0.00
$0.00
$25.89
M2
Importe
$0.00
$0.00
$0.00
$21.85
$21.85
$21.85
$0.00
$0.00
$21.85
Importe
$24.54
$0.24
$24.54
$0.24
$24.78
$0.00
$0.00
$24.78
M2
Importe
$72.82
$11.57
$0.00
$72.82
$11.57
$84.39
$0.00
$0.00
$84.39
M2
Importe
$0.56
$14.42
$0.56
$14.42
$14.98
$0.00
$0.00
$14.98
M2
Importe
$11.20
$21.85
$11.20
$21.85
$33.05
$0.00
$0.00
$33.05
UTILIDAD PROPUESTA
CARGOS ADICIONALES
8.19
3.00
8.99
10.00
2.00
5.00
0.52
CLAVE CONCEPTO UNIDAD CANTIDAD P.U. Importe
1 PRELIMINARES
1.1 TRAZO Y NIVELACION DE TERRENO CON HILO CAL; M2 563.87 12.57 7,087.01
DEJANDO REFERENCIA PARA EJECUCION DE LOS
TRABAJOS
2 EXCAVACIONES Y DEMOLICIONES
2.1 EXCAVACION EN ZANJA Y EN TERRENO TIPO II CON M3 320.40 182.70 58,537.30
HERRAMIENTA DE MANO; PICO Y PALA HASTA UNA
PROFUNDIDAD DE 2.00 MTS. EN SECO PARA
DESPLANTE DE ESTRUCTURAS.
3 CIMENTACION
3.1 COMPACTACION DEL TERRENO NATURAL AL 85%. M2 196.00 34.59 6,779.93
3.4 ZAPATA DE 17.5 CMS DE ESP. PROMEDIO Y 1.0 DE ML 69.37 573.61 39,791.15
ANCHO, ARMADA CON 6 VARILLAS NO. 4
TRANSVERSALMENTE; Y 10 LONGITUDINALMENTE DEL
NO. 3 CON CONTRATRABE DE 35X25 CMS. DE
CONCRETO ARMADO CON 4 VARILLAS DEL NO. 4 Y
ANILLOS @ 15 CMS DEL NO. 2 F'C= 250 KG/CM2.
CONCRETO HECHO EN OBRA, CIMBRA COMUN.
3.5 ZAPATA DE 17.5 CMS DE ESP. PROMEDIO Y 1.20 DE ML 89.00 573.61 51,051.07
ANCHO, ARMADA CON 6 VARILLAS NO. 4
TRANSVERSALMENTE; Y 10 LONGITUDINALMENTE DEL
NO. 3 CON CONTRATRABE DE 35X25 CMS. DE
CONCRETO ARMADO CON 4 VARILLAS DEL NO. 4 Y
ANILLOS @ 15 CMS DEL NO. 2.5 F'C= 250 KG/CM2.
CONCRETO HECHO EN OBRA, CIMBRA COMUN.
3.6 MURO DE ENRASE CON TABIQUE DE CONCRETO M2 137.60 191.90 26,405.93
MACIZO DE 10X14X25 CMS. ASENTADO CON
MORTERO-ARENA 1:5.
4 ALBAILERIA
4.1 MURO COMUN DE TABIQUE ROJO RECOCIDO M2 386.00 166.29 64,187.94
5 ESTRUCTURA
5.1 LOSA MACIZA DE CONCRETO ARMADO DE HASTA 12 M2 180.00 448.19 80,673.75
CMS. DE ESPESOR. ARMADA CON VARILLA DEL NO. 3
@ 15 CMS. EN AMBOS SENTIDOS CON LOS BASTONES
Y BALLONETAS DE ACUERDO A PLANO. CIMBRA
COMUN Y CONCRETO DE 200 KG/CM2.
5.2 LOSA ALIGERADA CON CASETON 40X40X25 CMS; DE M2 93.90 448.19 42,084.81
30 CMS DE ESPESOR Y NERVADURAS DE 8 CMS. CON 3
VARILLAS DEL NO. 3 MALLA Y LO NECESARIO PARA SU
EJECUCION.
5.3 COLUMNA DE CONCRETO DE 5.0 MTS. DE LONGITUD PZA 7.00 281.09 1,967.61
Y DE 30X45 DE SECCION ARMADO CON 6 VARILLAS
DEL NO. 5 O EQUIVALENTE ANILLOS @ 15 CMS. DEL
NO. 2.5
7 INSTALACION HIDRAULICA
7.1 SUMINISTRO E INSTALACION DE EQUIPO PZA 1.00 1,987.05 1,987.05
HIDRONEUMATICO CON TANQUE DE 126 LITROS Y
MOTOR DE 1 HP MONOFASICO.
8 INSTALACION SANITARIA
8.1 SUMINISTRO E INSTALACION DE DESCARGA PZA 15.00 98.04 1,470.60
SANITARIA DE LAVABOS Y MINGITORIOS, INNODOROS Y
COLADERAS EN PVC SANITARIO DE 2 A 4" CON
ACCESORIOS Y CEMENTO, AS COMO TODO LO
NECESARIO PARA SU FUNCIONAMIENTO. P.U.O.T.
9 MUEBLES SANITARIOS
9.1 CONSTRUCCION DE LOSA DE CONCRETO PARA PZA 1.00 1,197.52 1,197.52
ALOJAR OVALINES, DIMENSIONES DE 0.60X2 MTS DE
10 CMS. DE ESPESOR Y F'C= 150 KG/CM2 TERMINADA
CON AZULEJO Y ACERO DE REFUERZO DEL NO. 3 @ 15
CMS. EMPOTRADA EN LOS MUROS.
11 CARPINTERIA
11.1 SUMINISTRO Y COLOCACION DE PUERTAS DE PZA 5.00 2,400.90 12,004.51
MADERA TIPO TAMBOR A BASE DE BASTIDOR Y
TRIPLAY, CON CHAPA.
Suma ###
BELTRAN PRIETO OSCAR F. 16% IVA ###
PRESUPUESTO PROPUESTO CONST.III. Total ###
presupuesto $ 899,371.18