You are on page 1of 11

9/4/2017 How does Top Down Estimation in Primavera P6 work?

Do Duy Khuong Blog

Advertisements

Do Duy Khuong Blog


Primavera P6, Microsoft Project Tips & Tricks

How does Top Down Estimation in


Primavera P6work?

In Primavera we have a function called Top Down Estimation which help us


tocalculate an estimated gure forLabor and Non-labor unit based onestimation
weights. It can apply to WBS and Activity.

https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 1/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog

I will show you how to do it.

We have a simple project and each activity is assigned the resource Test. By default
each activity will have 40 units.

We will use Top Down Estimation to redistribute the unit to make it more realistic.

To perform top-down estimation, you must rst assign estimation weights to WBS
and activities. These estimation weights are used to determine how units are
distributedamong WBS and activities.

Go to WBS window. Show Est Weight column.

https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 2/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog

Now we enter the weight for each WBS.

Go to Activitieswindow. Show Est Weight column.

Now we enter the weight for each activity.

https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 3/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog

Go to Tool -> Top Down Estimation

Primavera show you the current units in your project. Now you will enter the new
units you want to apply to your project.

https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 4/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog

Click on Apply button.

Now you can see WBS and activities have new budgeted units.

The units are distribute according to Est Weight which we assigned to them.

For example: Foundation get 40% of 1000 units = 400 units. Bored Pile get 70% of 400
units = 280 units.

With this function, we can quickly distribute units to activities.

https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 5/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog

Advertisements

Rate this:

6 Votes

Share this:

Share 1 Share 30 More

Related:

How to assign resource / resource loading / make resource plan in Primavera P6

In "Primavera P6"

https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 6/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog

What is Cost Account in Primavera P6 used for?

In "Primavera P6"

Which Fields can be imported into Primavera P6 from Excel (XLS) Spreadsheet?

In "Import / Export"

Author: Khuong Do
Khuong Do is a Project Planner in Civil, Transportation and Oil & Gas Industry. He has worked
as a Primavera Consultant Specialist since 2006 . He holds a Civil Engineering degree and a
Bachelor of Information Management System. Now he is working in Petronas RAPID project,
one of the biggest Re nery and Petrochemical complex, in Pengerang Malaysia.
View all posts by Khuong Do

Khuong Do /

15 thoughts on How does Top Down Estimation in


Primavera P6work?

https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 7/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog

Ibrahim
July 13, 2016 at 10:55 AM

Thank you , but this option in p6 is not good for larg projects.

Like

doduykhuong
July 13, 2016 at 11:25 AM

Yeah, I think its only for making a draft resource load.


Especially when you already had a similar project and you will bring the estimation
weight from that project to this one.

Like

Anonymous
July 13, 2016 at 12:54 PM

would anybody elaborate, whats the use of this option in practically handling projects
through primavera.

Like

Walid
July 14, 2016 at 6:38 PM

Thanks

Like

rongconlonton
September 9, 2016 at 10:05 AM

https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 8/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog

Thanks.

Like

sunil
November 6, 2016 at 4:14 PM

all are ne, but i want to know what is the space management in primavera

Like

doduykhuong
November 7, 2016 at 8:33 AM

Hi,
I dont think P6 Professional has that module

Like

ALI
November 9, 2016 at 3:34 PM

Can we use budgeted non-labor units instead.

Like

sunil
November 24, 2016 at 4:47 PM

THANK YOU

Like

https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 9/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog

sunil
November 24, 2016 at 4:50 PM

AND ALSO I WANT TO KNOW THE TOTAL BUDGET COST AND MANPOWER
HISTOGRAM IN PRIMAVERA

Like

doduykhuong
November 26, 2016 at 9:10 AM

Hi Sunil,
For Manpower histogram, you can refer to this article
https://doduykhuong.com/2016/09/25/how-to-make-a-labor-equipment-
mobilization-plan-in-primavera-p6/

Like

sunil
December 7, 2016 at 12:38 PM

Thank you
I have a another doubt. How can we calculate the monthly expenses in primavera.
From the resource assignment we can calculate monthly budgeted total cost, total
labour cost, non labour and material also like that can we calculate for expenses also,
is this possible?
Please let me know.

Like

Gopinath N
February 21, 2017 at 6:10 PM

https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 10/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog

Hi Doduykhuong, Nice Article but it would be complete if you could cover the other
elds in the Top down estimation window.

Like

doduykhuong
February 22, 2017 at 5:49 AM

Hi Gopinath. Thanks for your compliment.


I intend to provide the basic information rst. Maybe in future I will write more
about it.

Like

Israr Ahmed Memon


April 24, 2017 at 2:06 PM

doduykhuong Thanks For Sharing this . Can You Please write about Function Point
in Top Down Estimation

Like

Do Duy Khuong Blog /

https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 11/11

You might also like