Professional Documents
Culture Documents
Advertisements
https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 1/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog
We have a simple project and each activity is assigned the resource Test. By default
each activity will have 40 units.
We will use Top Down Estimation to redistribute the unit to make it more realistic.
To perform top-down estimation, you must rst assign estimation weights to WBS
and activities. These estimation weights are used to determine how units are
distributedamong WBS and activities.
https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 2/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog
https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 3/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog
Primavera show you the current units in your project. Now you will enter the new
units you want to apply to your project.
https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 4/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog
Now you can see WBS and activities have new budgeted units.
The units are distribute according to Est Weight which we assigned to them.
For example: Foundation get 40% of 1000 units = 400 units. Bored Pile get 70% of 400
units = 280 units.
https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 5/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog
Advertisements
Rate this:
6 Votes
Share this:
Related:
In "Primavera P6"
https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 6/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog
In "Primavera P6"
Which Fields can be imported into Primavera P6 from Excel (XLS) Spreadsheet?
In "Import / Export"
Author: Khuong Do
Khuong Do is a Project Planner in Civil, Transportation and Oil & Gas Industry. He has worked
as a Primavera Consultant Specialist since 2006 . He holds a Civil Engineering degree and a
Bachelor of Information Management System. Now he is working in Petronas RAPID project,
one of the biggest Re nery and Petrochemical complex, in Pengerang Malaysia.
View all posts by Khuong Do
Khuong Do /
https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 7/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog
Ibrahim
July 13, 2016 at 10:55 AM
Thank you , but this option in p6 is not good for larg projects.
Like
doduykhuong
July 13, 2016 at 11:25 AM
Like
Anonymous
July 13, 2016 at 12:54 PM
would anybody elaborate, whats the use of this option in practically handling projects
through primavera.
Like
Walid
July 14, 2016 at 6:38 PM
Thanks
Like
rongconlonton
September 9, 2016 at 10:05 AM
https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 8/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog
Thanks.
Like
sunil
November 6, 2016 at 4:14 PM
all are ne, but i want to know what is the space management in primavera
Like
doduykhuong
November 7, 2016 at 8:33 AM
Hi,
I dont think P6 Professional has that module
Like
ALI
November 9, 2016 at 3:34 PM
Like
sunil
November 24, 2016 at 4:47 PM
THANK YOU
Like
https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 9/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog
sunil
November 24, 2016 at 4:50 PM
AND ALSO I WANT TO KNOW THE TOTAL BUDGET COST AND MANPOWER
HISTOGRAM IN PRIMAVERA
Like
doduykhuong
November 26, 2016 at 9:10 AM
Hi Sunil,
For Manpower histogram, you can refer to this article
https://doduykhuong.com/2016/09/25/how-to-make-a-labor-equipment-
mobilization-plan-in-primavera-p6/
Like
sunil
December 7, 2016 at 12:38 PM
Thank you
I have a another doubt. How can we calculate the monthly expenses in primavera.
From the resource assignment we can calculate monthly budgeted total cost, total
labour cost, non labour and material also like that can we calculate for expenses also,
is this possible?
Please let me know.
Like
Gopinath N
February 21, 2017 at 6:10 PM
https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 10/11
9/4/2017 How does Top Down Estimation in Primavera P6 work? Do Duy Khuong Blog
Hi Doduykhuong, Nice Article but it would be complete if you could cover the other
elds in the Top down estimation window.
Like
doduykhuong
February 22, 2017 at 5:49 AM
Like
doduykhuong Thanks For Sharing this . Can You Please write about Function Point
in Top Down Estimation
Like
https://doduykhuong.com/2016/07/08/how-does-top-down-estimation-in-primavera-p6-work/ 11/11