You are on page 1of 7

International Journal of Advanced Engineering, Management and Science (IJAEMS) [Vol-2, Issue-4, April- 2016]

Infogain Publication (Infogainpublication.com) ISSN : 2454-1311

Impact of Distributed Generator for Loss


Reduction and Improvement in Reliability of
Distributed System
K Siva Ramudu1, K Mounika2, B Sree Ramulu3

Assistant Professor, Department of EEE, Brindavan Institute of Technology & Science, Kurnool & JNTU Anantapur, AP,
India
UG Student, Department of EEE, Brindavan Institute of Technology & Science, Kurnool & JNTU Anantapur, AP, India
UG Student, Department of EEE, Brindavan Institute of Technology & Science, Kurnool & JNTU Anantapur, AP, India

Abstract Distributed Power generation has gained a lot important, it is only half of the story. A distribution system
of attention in recent times due to constraints associated designed purely for capacity (and minimum safety
with conventional power generation and new standards) costs between 40% and 50% of a typical US
advancements in DG technologies .The need to operate the overhead design [2]. This minimal system has no
power system economically and with optimum levels of switching, no fuse cutouts, no tie switches, no extra
reliability has further led to an increase in interest in capacity and no lightning protection. Poles and hardware
Distributed Generation. By placing distributed generator are as inexpensive as possible, and feeders protection is
on an optimal location lead to improvement in voltages. limited to fuses at substations. Any money spent beyond
This paper investigates the impact of DG unit installation such a "minimal capacity design" is spent to improve
on electric losses, reliability and voltage profile of reliability. Viewed fr m this perspective, about 50% of the
distribution networks. To find optimal distributed cost of a distribution system is for reliability and 50% for
generator allocation for loss reduction subjected to capacity [3]. To spend distribution reliability dollars as
constraint of voltage regulation in distribution network. efficiently as capacity dollars, utilities must transition from
Distributed Generator offers the additional advantage of capacity planning to integrated capacity and reliability
increase in reliability levels as suggested by the planning4. Such a department will keep track of accurate
improvements in various reliability indices such as SAIFI, historical reliability data, utilize predictive reliability
SAIDI, CAIDI, ASAI and ASUI. Comparative studies are models, engineer systems to specific reliability targets and
performed and related results are addressed. The optimize spending based on cost per reliability benefit
suggested technique is programmed to IEEE-33 bus system ratios. The impact of distribution reliability on customers is
by using MATLAB software. The results clearly indicate even more profound than cost. For a typical residential
that DG can reduce the electrical line loss while customer with 90 minutes of interrupted power per year,
simultaneously improving the reliability of the system. between 70 and 80 minutes will be attributable to problems
Keywords Distributed generation, Distribution load occurring on the distribution systems [4]. This is largely
flows, loss Reduction, DG placement, Reliability. due to the radial nature of most distribution systems, the
large number of components involved, the sparsity of
I. INTRODUCTION protection devices and sectionalizing switches and the
Distribution systems deliver power from bulk power proximity of the distribution system to end-use customers.
systems to retail customers. To do this, distribution The main objective is to minimize the total real power
substations receive power from sub transmission lines and loss of the system. This method is tested for IEEE 33-Bus
step down voltages with power transformers. These standard test system. The tight connection between the
transformers supply primary distribution systems made up optimal location and size is to be studied by allocating the
of many distribution feeders. Distribution transformers step optimal size at different buses in the network and by
down voltages to utilization levels and supply secondary allocating different DG capacities at the optimal bus
mains or service drops [1]. Distribution planning resulted from the proposed method [5].
departments at electric utilities have historically A basic problem in distribution reliability assessment is
concentrated on capacity issues, focusing on designs that measuring the efficacy of past service. A common solution
supply all customers at peak demand within acceptable consists of condensing the effects of service interruptions
voltage tolerances without violating equipment ratings. into indices of system performance. Reliability indices are
Capacity planning is almost always performed with used by system planners and operators as a tool to improve
rigorous analytical tools such as power flow models. the level of service to customers. Planners use them to
Reliability, although considered important, has been a determine the requirements for generation, transmission,
secondary concern usually addressed by adding extra and distribution capacity additions. Operators use them to
capacity and feeder ties so that certain loads can be ensure that the system is robust enough to withstand
restored after a fault occurs. Although capacity planning is possible failures without catastrophic consequences.

www.ijaems.com Page | 117


International Journal of Advanced Engineering, Management and Science (IJAEMS) [Vol-2, Issue-4, April-
2016]
Infogain Publication (Infogainpublication.com) ISSN : 2454-
1311
Reliability indices are considered to be reasonable and Fig 4.1: Single line diagram of two buses of a distribution
logic way to judge the performance of an electrical power system.
system [6]. Reliability indices used for the purpose of
analysis in power system. The proposed methodology is Where R and X are resistance and reactance of the
tested on a standard IEEE-33 bus radial distribution system branch. PLk and QLk are the active and reactive powers of
and the scenarios yields efficiency in improvement of node k. ILi is the current flowing in the line. Subscript L
voltage profile and reduction of power loss, it also permits in PLS and QLS refers to the load connected
an increase in reliability of the system. Initially, a flat voltage (1 p.u) of all the nodes is assumed
and load currents and charging currents of all the loads are
II. LOADFLOWS computed using Eqs. (3.1) and (3.2) respectively.
In this paper, a modified load-flow technique is considered The load current of node k is
for solving radial distribution networks. The proposed PLk ( k ) jQ Lk ( k )
method involves only the evaluation of a simple algebraic I Lk ( k ) =
V * (k ) (2.1)
expression of receiving-end voltages also node and line
identification utilized [7] in load flow has been proposed.
The proposed method is very efficient. It is also observed for k = 2, 3,. nb
that the proposed method has good and fast convergence Where PLk(k) and QLk(k) are active and reactive power
characteristics. The proposed method uses the simple of load connected to node k, respectively.
voltage equation. The proposed method takes the zero The charging current at node k is
initial loss for computation of voltage of each node and I Ck ( k ) = y 0 ( k ) * V ( k ) (2.2)
considers flat voltage start to incorporate voltage
convergence. for k = 2, 3 nb
A. Assumptions Here shunt admittance yo is considered as small.
It is assumed that three-phase radial distribution networks D. Branch current
are balanced and represented by their single-line diagrams Branch Current I(n) is equal to the sum of the load
and charging capacitances are neglected at the distribution currents of all the nodes beyond that branch n plus the sum
voltage levels. of the charging currents of all the nodes beyond that branch
B. Solution methodology n i.e.,
The load flow method of radial distribution network can be nb nb

solved in three sets of equations. I (n) = I Lk ( k ) + I Ck ( k )


1. Identification of the nodes beyond all the k = n +1 i = n +1
(2.3)
branches. Where branch impedance is Z = R + j X
2. Determination of branch currents. Therefore, if it is possible to identify the nodes beyond
3. Determine the nodal voltages. all the branches, it is possible to compute all the branch
C. Procedure to determine the voltage at each bus currents.
The distribution load flow method is used to calculate the E. Voltage at buses
voltage at each bus and total real and reactive power losses. A generalized equation of receiving-end voltage,
Before proceeding to the fundamentals of power system sending-end voltage, branch current and branch impedance
control and stability limits, some factors influencing active is
and reactive power flows on the power system are needed V (a2) = V (a1) - I (i) * Z (i) (2.4)
to be discussed. The power transfer between two buses is
related to some parameters: Where i is the branch number and a1 and a2 are
Sending and receiving bus voltages a1 = RE (i)
Power angles between two buses a2 = SE (i)
Series impedances of the transmission line connecting Where RE (i) is the receiving end and SE (i) is the
the two buses. sending end of branch i.
Consider a single line diagram of two buses of a radial F. Power losses
distribution system as shown in Fig.4.1, the number of The real and reactive power loss of branch i are
branches nb and the number of buses t are related through given
t = nb+1. at Sth bus. Lreal (i) = |I (i) |2 * R (i) (2.5)
Vk VS Lreactive (i) = |I (i) |2 * X (i) (2.6)
Where Lreal (i) and Lreactive (i) are the active and reactive
power losses at branch i.
Algorithm : Identification of nodes beyond a branch
ILi Step 1. Read the system data.
PLk+jQLk PLS+jQLS Step 2. i =1
Step 3. k = i + 1, set ip = 0
Step 4. nc = 0

www.ijaems.com Page | 118


International Journal of Advanced Engineering, Management and Science (IJAEMS) [Vol-2, Issue-4, April-
2016]
Infogain Publication (Infogainpublication.com) ISSN : 2454-
1311
if {RE (i) = SE(k)} and {ip = 0} go to n
step 10
Otherwise go to step 12
PLr= I i =1
2
ri Ri (3.3)

Step 5. if {ip = 0} go to step 10 Where Iai and Iri are the active and reactive components of
Otherwise go to step 6 current of branch i.For a given configuration of a single-
Step 6. it = 1 source radial network, the loss associated with the active
Step 7. if {RE(i) = ie(i, ip+1)}then nc = 1 component of branch currents (PL-*a) can be minimized by
Otherwise go to step 8 placing DG units, and the loss associated with the reactive
Step 8. it = it +1 component of branch currents (PLr) can be minimized by
If {it ip} go to step 7 supplying part of the reactive power demand locally [9].
Otherwise go to step 9 For formulating new real power and losses following
Step 9. if {nc = 1} go to step 12 formulae are derived
Otherwise go to step 11 Pnew=Pp.u-DG Where DG is varied upto 5MW
Step 10. ie (i, ip + 1) = RE(i) New Spu is given by
Step 11. ip = ip +1 Spu=Pnew+jQpu (3.4)
IN(ip) =1 Corresponding current values is calculated as
ie(i, ip + 1) = RE(i) Inew=(Spu)*/(V1)*
N(i) = ip + 1, The loss associated with the active and reactive
Step 12. s=s+1 components of branch currents can be written as
If {s nb} go to step 6 n
Otherwise go to step 13 PL a = 2
I newai Ri (3.5)
Step 13. if {iP =0} go to step 14 i =1
Otherwise go to step 15 n
Step 14. ie(i, ip + 1) = RE(i)
N(i) = ip + 1, go to step 15
PLr= I i =1
2
newri Ri (3.6)

Step 15. i=i+1 Where Inewai and Inewri are the active and reactive
If {i nb-1}go to step 3 components of current of branch i.
Otherwise go to step 16 B. Algorithm for DG Placement
Step 16. ie(nb, 1) = RE(nb) Step 1: Read system data and conduct load flow analysis
N(nb) = 1 for the original system.
Step 17. Stop Step 2: Initialize DG=0.25
By using this algorithm we can find the identification of Step 3: Pnew =Ppu
nodes beyond all branches. Step 4: i=1
Step 5: At bus i Pnew (i)=Ppu(i)-DG
Step 6: Conduct load flow, find the losses for new P
III. DG PLACEMENT METHODOLOGY value.
The basic idea behind the method is that when a DG is Step 7: Check i<N if yes go to step 5 with i=i+1 else next
placed at a bus, the real load connected to that bus is step.
compensated and hence the branch currents are reduced. Step 8: After calculating losses for all the buses with new P
This causes reduction in system real power loss [8]. The values, loss with minimum
description of the method is given in the following sections. Value is assigned to N corresponding location to Y.
Step 9: Check DG=<5MW if yes go to step 3 with
A. Background DG=DG+0.25 else stop.
The total I2R loss (PLt) in a distribution system having n
number of branches is given by
n IV. RELIABILITY
Plt =
2

i =1
I ti R i (3.1) To measure system performance, the electric utility
industry has developed several measures of reliability.
Here Ii and Ri are the current magnitude of branch current These reliability include measures of outage duration,
and the resistance of the ith branch. The branch current can frequency outages, system availability, and response time
be obtained from the load flow solution. The branch performance indices, important definitions for reliability
current has two components, active component (Ia) and including what are momentary interruptions, momentary
reactive component (Ir). The loss associated with the active interruption events, and sustained interruptions [10].
and reactive components of branch currents can be written Momentary Interruption -
as A single operation of an interrupting device that results in a
n voltage zero.
PLa =
i =1
I ai2 R i (3.2) Momentary Interruption Event -

www.ijaems.com Page | 119


International Journal of Advanced Engineering, Management and Science (IJAEMS) [Vol-2, Issue-4, April-
2016]
Infogain Publication (Infogainpublication.com) ISSN : 2454-
1311
An interruption of duration limited to the period required to Ni= Total number of customers
restore service by an interrupting device. This must be interrupted.
completed within five minutes. NT = Total number of customers served.
Sustained Interruption
Any interruption not classified as a momentary event. D Average Service Availability Index (ASAI)
The most common distribution indices include the System The Average Service Availability Index (ASAI) is the ratio
Average Interruption Duration Index (SAIDI), Customer of the total number of customer hours that service was
Average Interruption Duration Index (CAIDI), System available during a given time period to the total customer
Average Interruption Frequency Index (SAIFI), and the hours demanded [12]. This is sometimes called the service
Average Service Availability Index (ASAI). reliability index. The ASAI is usually calculated on either
a monthly basis (730 hours) or a yearly basis (8,760 hours),
A System Average Interruption Duration Index (SAIDI) but can be calculated for any time period. The ASAI is
The most often used performance measurement for a found as, ASAI = [1 ( (ri * Ni) / (NT* T))] *
sustained interruption is the System Average Interruption 100
Duration Index (SAIDI). This index measures the total Where, ASAI = Average System Availability
duration of an interruption for the average customer during Index, percent.
a given time period. SAIDI is normally calculated on = Summation function.
either monthly or yearly basis; however, it can also be T = Time period under study, hours.
calculated daily, or any other time period. ri= Restoration time, hours.
To calculate SAIDI, each interruption during the time Ni = Total number of customers interrupted.
period is multiplied by the duration of the interruption to NT = Total number of customers served.
find the customer-minutes of interruption. The customer-
minutes of all interruptions are then summed to determine
the total customer-minutes [11]. To find the SAIDI value, V. RESULT ANALYSIS
the customer-minutes are divided by the total customers. The proposed model is tested on IEEE-33 bus system. For
The formula is, SAIDI =(ri * Ni ) / NT this we require system data. Data for 33-bus system. Figure
Where, SAIDI = System Average Interruption 1 shows the IEEE standard 33 bus system.
Duration Index, minutes. Number of busses=33; Number of branches=32;
= Summation function. Base voltage=12.66 kV;Base MVA=5.246 MVA;
ri= Restoration time, minutes.
Ni = Total number of customers interrupted.
NT = Total number of customers served.

B Customer Average Interruption Duration Index


(CAIDI)
Once an outage occurs the average time to restore
service is found from the Customer Average Interruption
Duration Index (CAIDI). CAIDI is calculated similar to
SAIDI except that the denominator is the number of
customers interrupted versus the total number of utility
customers. CAIDI is, CAIDI =(ri * Ni ) / ( Ni ) Fig.1: Single Line Diagram of the Test Network
Where CAIDI = Customer Average Interruption
Duration Index, minutes. Table 1: The Load Data of IEEE-33Bus System
= Summation function. Sen Rec
B QL
ri= Restoration time, minutes. din ievi Resista Reacta PL
us (K
Ni= Total number of customers interrupted. g ng nce nce(Oh (K
N VA
No No (Ohms) ms) W)
o R)
C System Average Interruption Frequency Index (SAIFI) de de
The System Average Interruption Frequency Index (SAIFI) 1 1 2 0.0922 0.0470 100 60
is the average number of times that a system customer 2 2 3 0.4930 0.2511 90 40
experiences an outage during the year (or time period 3 3 4 0.3660 0.1864 120 80
under study). The SAIFI is found by divided the total 4 4 5 0.3811 0.1941 60 30
number of customers interrupted by the total number of 5 5 6 0.8190 0.7070 60 20
customers served. SAIFI, which is a dimensionless 6 6 7 0.1872 0.6188 200 100
number, is, SAIFI =(Ni) / NT 7 7 8 0.7114 0.2351 200 100
Where, SAIFI = System Average Interruption 8 8 9 1.0300 0.7400 60 20
Frequency Index. 9 9 10 1.0440 0.7400 60 20
= Summation function. 10 10 11 0.1966 0.0650 45 30
11 11 12 0.3744 0.1238 60 35

www.ijaems.com Page | 120


International Journal of Advanced Engineering, Management and Science (IJAEMS) [Vol-2, Issue-4, April-
2016]
Infogain Publication (Infogainpublication.com) ISSN : 2454-
1311
12 12 13 1.4680 1.1550 60 35 Table 3: Optimal Locations and Losses for
13 13 14 0.5416 0.7129 120 80 Corresponding Dg Size
14 14 15 0.5910 0.5260 60 10 DG
0.25 0.50 0.75 1.00 1.25 1.50 1.75
15 15 16 0.7463 0.5450 60 20 size
16 16 17 1.2890 1.7210 60 20 Opt.
Loca 17 15 14 30 30 29 8
17 17 18 0.7320 0.5740 90 40 tion
18 2 19 0.1640 0.1565 90 40 Loss
19 19 20 1.5042 1.3554 90 40 107. 86.89 73.49 64.66 57.8 54.08 50.32
with
2 1 1 4 21 9 9
20 20 21 0.4095 0.4784 90 40 DG
21 21 22 0.7089 0.9373 90 40
22 3 23 0.4512 0.3083 90 50 DG size 2.00 2.25 2.50 2.75 3.00 3.25 3.5
23 23 24 0.8980 0.7091 420 200 Opt.
24 24 25 0.8960 0.7011 420 200 Locatio 7 6 6 6 6 6 6
25 6 26 0.2030 0.1034 60 25 n
Loss
26 26 27 0.2842 0.1447 60 25 46.7 44.3 43.1 43.6 45.8 49.5 54.8
with
27 27 28 1.0590 0.9337 60 20 88 78 86 74 07 53 79
DG
28 28 29 0.8042 0.7006 120 70
29 29 30 0.5075 0.2585 200 600
30 30 31 0.9744 0.9630 150 70 DG size 3.75 4.00 4.25 4.50 4.75 5.00
31 31 32 0.3105 0.3619 210 100 Opt.
6 6 6 5 4 3
32 32 33 0.3410 0.5302 60 40 Location
Loss with 61.7 70.1 80.0 88.6 93.7 97.2
First load flow is conducted for IEEE-33 bus test system. DG 54 48 32 85 88 74
The power loss due to active component of current is
136.9836 kW and power loss due to reactive component of The results of the DG placement method by proposed
the current is 66.9252 kW. A programme is written in method are shown below table.
MATLAB by using load flow algorithm which is discussed
above. By executing that programme total loss in the Table 4: DG Placement Method Results of 33 bus system
power system and p.u nodal voltages are obtained and
DG Location 6
listed in Table 2.
DG Size(MW) 2.5601
PLt PLa PLr
Table 2: Total losses of 33-Bus system from load flows
Loss Before
136.9836 66.9252
Loss due to DG Placement(kW) 203.9088
Total loss in
Loss due to real reactive part Loss After DG
kW 105.0924 43.1513 61.8781
part of I in kW of I in kVAR Placement(kW)
% Reduction
48.46 68.498 7.5336
in Loss
136.9836 66.9252 203.9088
By placing 2.5601 MW DG unit at Bus 6 the total real
power loss is reduced to 105.0924 kW from 203.9088 kW
and the loss associated with active component of the
branch current (PLa) is reduced to 43.1513 kW from
136.9836 kW. The reduction in total power loss is 48.46%
and 68.498% reduction is achieved in the loss associated
with active component of the branch current (PLa) [14, 15].
The reduction in the loss associated with reactive
component of the branch current (PLr) is very small as it is
already mentioned that placement of DG effects only
Fig 2: p.u Nodal Voltages active component of branch current. Though the objective
is to reduce the losses, the voltage profile is also
A program is written in MATLAB to implement single substantially improved as well. The below table shows the
DG placement algorithm [13]. For the first iteration the voltages profile after and before placement of DG.
maximum saving is occurring at bus 6. The candidate
location for DG is bus 6 with a loss saving of 93.8323 kW.

www.ijaems.com Page | 121


International Journal of Advanced Engineering, Management and Science (IJAEMS) [Vol-2, Issue-4, April-
2016]
Infogain Publication (Infogainpublication.com) ISSN : 2454-
1311
1
Voltage Profile With & Without DG Unit
Distribution System Reliability IEEE/PES
With out DG
0.99 With DG Displacement and Distribution Conference &
0.98
Exhibition, Asia and Pacefic, vol. 9, 2005, pp.1-6.
Voltage Magnitude in p.u

0.97

0.96
[4] E. Diaz-Dorado, J. Cidras, E. Miguez, Application
0.95
of evolutionary algorithms for the planning of urban
0.94 distribution networks of medium voltage, IEEE
0.93 Trans. Power Systems , vol.17,no.3, pp.879-884,Aug
0.92
2002.
0.91
0 5 10 15 20
Bus Number
25 30 35 [5] M. Mardaneh, G. B. Gharehpetian, Siting and sizing
Fig.2: Voltage Profile with and without DG unit of DG units using GA and OPF based technique,
TENCON. IEEE Region 10 Conference,vol.3,pp.331-
The results of proposed method are shown in the Table 5 334,21- 24,Nov.2004.
and can be compared with the results associated without [6] Silvestri A.Berizzi, S.Buonanno, Distributed
DG. It can be seen from the results that the reliability generation planning using genetic algorithms
indices will experience considerable changes when DG Electric PowerEngineering, Power Tech Budapest 99,
modelling is changed. Comparing the failure rates and Inter. Conference, pp.257,1999.
unavailability associated with two cases of with and [7] Das D., Kothari D.P. and Kalam A., Simple and
without DG installation, it can be seen that DG installation efficient method for load flow solution of radial
can improve reliability indices considerably especially distribution networks, Electrical Power & Energy
SAIFI, SAIDI & ASUI and the effects are more obvious Systems, vol. 17, no. 5, pp. 335-346,1995.
for ending sections of the feeder [16]. [8] K. Siva Ramudu1, M. Padma Lalitha2, P. Suresh
Babu Siting and Sizing of DG for Loss Reduction
and Voltage Sag Mitigation in RDS Using ABC
Algorithm International Journal of Electrical and
Computer Engineering (IJECE) Vol. 3, No. 6,
December 2013, pp. 814~822.
[9] K. Siva Ramudu1, M. Padma Lalitha2, P. Suresh
VI. CONCLUSION Babu Optimal Placement of DG for Loss Reduction
Use of distributed generation is one of the many strategies and Voltage Sag Mitigation in Radial Distribution
electric utilities are considering to operate their systems in Systems using ABC Algorithm ACEEE Int. J. on
the deregulated environment. Inclusion of DG at the Electrical and Power Engineering , Vol. 5, No. 1,
distribution level results in several benefits, among which February 2014.
are congestion relief, loss reduction; voltages profile [10] K. Siva Ramudu1, M. Padma Lalitha2, P. Suresh
improvement and improvement in reliability. This project Babu Siting and Sizing of DG for Loss Reduction
has considered the benefit of DG on loss reduction, voltage and Voltage Sag Mitigation in RDS Using ABC
improvement and Reliability for a simple case of a radial Algorithm Proceedings of 10th IRAJ International
distribution line. The results clearly indicate that DG can Conference, 27th October 2013, Tirupati, India. ISBN:
reduce the electrical line loss while simultaneously 978-93-82702-36-8.
improving the reliability of the system. However, the [11] M.Padma Lalitha,V.C.Veera Reddy, N.UshaOptimal
inclusion of DG does not always guarantee the reduced line DG placement for maximum lossreduction in radial
loss. The DG rating and location are important factors for distribution systemInternational journal of emerging
line loss reduction. Therefore, these factors have to be technologies& applications in engineering,
considered very carefully in order to determine the best technology & sciences, Vol 2,Issue 2, Jul 2009,
location of DG. The improvement in reliability indices is pp:719-723.
maximum with DG at feeder end. Power losses decrease as [12] Dervis Karaboga and Bahriye Basturk, Artificial Bee
location of DG from feeder end increases. We arrived at an Colony (ABC)Optimization Algorithm for Solving
optimal location by keeping into account these two Constrained Optimization Problems,Springer-Verlag,
mutually opposing factors. IFSA 2007, LNAI 4529, pp. 789798, 2007.
[13] Karaboga, D. and Basturk, B., On the performance
REFERENCES of artificial bee colony(ABC) algorithm, Elsevier
Applied Soft Computing, Vol. 8, pp.687697,2007.
[1] CIGRE WG 3723, Impact of increasing
[14] Hemamalini S and Sishaj P Simon., Economic load
contribution of is persed generation on power system,
dispatch with valve-pointeffect using artificial bee
final report, September 1998.
colony algorithm, xxxii national systems
[2] Dugan R.C., Price S.K.: Issues for distributed
conference,NSC 2008, pp.17-19, 2008.
generations in the US. Proc. IEEE PES, Winter
[15] Fahad S. Abu-Mouti and M. E. El-Hawary Optimal
Meeting, January 2002, vol. 1, pp. 121126.
Distributed GenerationAllocation and Sizing in
[3] M. Fotuhi-Firuzabad, A. Rajabi-Ghahnavie, An
Distribution Systems via artificial bee
Analytical Method to Consider DG Impacts on

www.ijaems.com Page | 122


International Journal of Advanced Engineering, Management and Science (IJAEMS) [Vol-2, Issue-4, April-
2016]
Infogain Publication (Infogainpublication.com) ISSN : 2454-
1311
Colonyalgorithm, IEEE transactions on power
delivery, Vol. 26, No. 4, 2011.
[16] S. M. Farashbashi-Astaneh, A. Dastfan Optimal
Placement and Sizing of DG for Loss
Reduction,Voltage Profile Improvement and Voltage
Sag Mitigation, International Conference on
Renewable Energies and Power Quality
(ICREPQ10)Granada (Spain), 23th to 25th March,
2010.

www.ijaems.com Page | 123

You might also like