INDEX

Schedule
Name of Work Page
No;
1 EARTH WORK 1~3
2 MORTAR 4~6
3 CONCRETE ( HAND MIXED ) 7 ~ 11
4 REINFORCED CONCRETE ( HAND MIXED ) 12 ~ 14
REINFORCED CONCRETE ( MACHINE MIXED ) 15 ~ 17
5 BRICK WORK 18 ~ 20
6 STONE WORK 21 ~ 22
7 PLASTERING AND POINTING 23 ~ 26
8 WOOD WORK 27 ~ 30
9 DOOR AND WINDOW 31 ~ 39
10 FLOORING 40 ~ 45
11 WALLING 46 ~ 51
12 CEILING 52 ~ 54
13 ROOFING 55 ~ 61
14 PAINTING AND WASHING 62 ~ 69
15 FENCING 70 ~ 72
16 IRON AND STEEL WORK 73 ~ 76
17 ROAD WORK 77 ~ 84
18 ROAD WORK ( BY MACHINE ) 85 ~ 94
19 BRIDGES 95 ~ 99
20 MISCELLANEOUS NOTES
Page3

ANALYSIS OF RATES ( Earth Work )

No. Particular Unit Quantity Rate Per Amount Remark

1 Site clearing including cutting trees and


bushes and dressing L-S According to site condation

2 Earth work in excavationfoundation in ordin-


ary soil to a depth of 5 ft. and removing the
excavated materials as directed within100 ft. Cft. 100

Workers No. 1.5 `


Sundries L-S

3 Earth work in excavating foundation in


medium soil to a depth of 5 ft. and removing
the excavated materials as directed within Cft. 100
100 ft.
Workers No. 2
Sundries L-S

4 Earth work in excavating foundation in hard


soil to a depth of 5 ft. and removing material
as directed within 100 ft. Cft. 100

Workers No. 3
Sundries L-S

5 Earth work in ordinary soil with excavated


earth filling in 6" layers watering and
ramming within 100 ft. Cft. 100

Workers No. 0.50


Workers for carrying and ramming No. 0.75
Workers for watering No. 0.25
Sundries L-S

6 Earth work over areas in ordinary ground in


cutting and levelling site including carrying
away surplus spoils spreading and levelling
within 100 ft. Cft. 100

Workers No. 1.25


Sundries L-S

7 Earth work in excavation over areas cutting


and levelling in hard soil including disposal
of surplus spoil not exceeding 100 ft. Cft. 100

Workers No. 2.5


Sundries L-S

8 Excavating in medium soil and filling and


Page3

ANALYSIS OF RATES ( Earth Work )

No. Particular Unit Quantity Rate Per Amount Remark


forming embankment lead 100 ft. lift 5 ft. Cft. 100

Maistry No. 0.125


Digger No. 1.5
Worker for carrying No. 1
Sundries L-S

9 Excavated and filling and forming embankm-


ent and lead 100 ft. lift 10 ft. Cft. 100

Maistry No. 0.2


Digger No. 1.5
Worker for carrying No. 2
Sundries L-S

10 Earth work ( Item 2,3 & 4 ) extra for every


additional 5 ft. depth Cft. 100

Workers No. 0.5

11 Earth work ( Item 2,3 & 4 ) extra for every


additional 100 ft. lead Cft. 100

Workers No. 0.5

12 Sand filling watering and ramming Cft. 100

Sand Cuft. 125


Workers for carrying and ramming No. 0.5
Workers for watering No. 0.5
Sundries L-S

13 Digging post holes under 2 ft. square in any


soil average 2 ft. depth Hole. 1

Digger No. 0.125

14 Digging post holes under 2 ft. square not


exceeding 3 ft. depth in each holes in hard
soil part return and fill Hole. 1

Digger No. 0.2

15 Digging post holes not exceeding 12 cft. In


each holes in medium soil part return and
fill Hole. 1

Digger No. 0.167

16 Digging post holes not exceeding 12 cft. In


Page3

ANALYSIS OF RATES ( Earth Work )

No. Particular Unit Quantity Rate Per Amount Remark


each holes in ordinary soil part return and
fill Hole. 1

Digger No. 0.143

17 Digging post holes not exceeding 10 cft. In


each holes in hard soil Hole. 1

Digger No. 0.2


Workers No. 0.125
Sundries L-S

18 Digging drain 1'-6" at top 9" at bottom and


average depth 12" ( ordinary soil ) Rft. 100

Workers No. 2
Sundries L-S

19 Digging drain 1'-6" at top 9" at bottom and


average depth 12" ( hard soil ) Rft. 100

Workers No. 3
Sundries L-S

20 Digging latrine pit of any size up to 10 ft.


depth in hard soil Cft. 100

Workers No. 3.375


Sundries L-S

21 Earth work in digging in sand or clay or


laterite up to 10 ft. initial depth Cft. 100

Workers No. 3
Sundries L-S

22 Earth work extra for every additional 5 ft. lift Cft. 100

Workers No. 0.5


Page3

3 Earth work in excavating foundation in


medium soil to a depth of 5 ft. and removing
the excavated materials as directed within Cft. 100
100 ft.
Workers No. 2
Sundries L-S
Page3

no L B H
5 30 40 0.5 600

100

Sand 125 cft 7.5 Sud


Workers for carrying and ramming 0.5 no 3 no
Workers for watering 0.5 no 3 no
Sundries LS
Page -4

ANALYSIS OF RATES ( Mortar )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

1 Cement mortar 1:2 Cft. 100

Cement 46 cft. Lbs. 4140


Sand Cft. 92

Workers for mixing No. 4

2 Cement mortar 1:3 Cft. 100

Cement 33 cft. Lbs. 2970


Sand Cft. 100

Workers for mixing No. 4

3 Cement mortar 1:4 Cft. 100

Cement 25 cft. Lbs. 2250


Sand Cft. 100

Workers for mixing No. 4

4 Composite mortar for plaster 1:1:6 Cft. 100

Cement 16 2/3 cft. Lbs. 1500


Lime Cft. 16.667
Sand Cft. 100

Workers for mixing No. 4

5 Damp proof cement mortar 1:2 with 5%


pudlo by weight of cement Cft. 100

Cement 48 cft. Lbs. 4320


Pudlo Cft. 216
Sand Cft. 96

Workers for mixing No. 4

6 Cement mortar 1:6 Cft. 100

Cement 16 2/3 cft. Lbs. 1500


Sand Cft. 100

Workers for mixing No. 4

7 Limet mortar 1:2 Cft. 100

Lime Cft. 46
Sand Cft. 92
Page -4

ANALYSIS OF RATES ( Mortar )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

Workers for mixing No. 4

8 Limet mortar 1:1:1 Cft. 100

Lime Cft. 50
Sand Cft. 50
Surkhi Cft. 50

Workers for mixing No. 7

9 Limet mortar 1:1:1 for small work Cft. 100

Lime Cft. 50
Sand Cft. 50
Surkhi Cft. 50

Workers for mixing No. 8

10 Limet mortar 2:3:1 for plaster Cft. 100

Lime Cft. 50
Sand Cft. 75
Surkhi Cft. 25

Workers for mixing No. 7

11 Limet mortar 2:3:1 for plaster for small work Cft. 100

Lime Cft. 50
Sand Cft. 75
Surkhi Cft. 25

Workers for mixing No. 8

12 Composite mortar for plaster 1:2:6 Cft. 100

Cement 16 cft. Lbs. 1440


Lime Cft. 32
Sand Cft. 100

Workers for mixing No. 4

13 Mud mortar 1:1 Cft. 100

Selection suitable clay ( mud ) Cft. 100


Worker for mixing including watering No. 2

14 Limet mortar 1:1 Cft. 100


Page -4

ANALYSIS OF RATES ( Mortar )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Lime ( Slaked ) Cft. 75
Sand Cft. 75

Workers No. 4

15 Composite mortar 1:1/2:4 Cft. 100

Cement Cft. 24.2


Lime Cft. 12.1
Sand Cft. 96.8

Workers No. 4
Page -4

33.33333
Cement mortar 1:2 cft. 100 112

Cement 46 cft. lbs. 4140 12.32143 Bag


Sand cft. 92 0.306667 Sud

Workers for mixing


no. 4 1.333333 no

33.33333
112
Cement mortar 1:3 cft. 100

Cement 33 cft. lbs. 2970 8.839286 Bag


Sand cft. 100 0.333333 Sud

Workers for mixing


no. 4 1.333333 no
ANALYSIS OF RATES ( Brick Work )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

1 Brick work 1st class in composit mortar in


( 1:1:6 ) Cft. 100 Allow two more
workers for each
1st class bricks No. 1350 additional storey
Cement Lbs. 372 of the Bldg.allow
Lime Cft. 4.13 extra for scaffold-
Sand Cft. 24.75 ing for each add-
itional storey.
Masons No. 4
Workers No. 6
Scaffolding and sundries L-s

2 Brick work in cement mortar ( 1:3 ) Cft. 100

Cement 8 cft. Lbs. 780


1st class bricks No. 1350
Sand Cft. 26

Masons No. 4
Workers No. 6

3 Brick work 1st class in Arcees in 1:3


Cement mortar Cft 100

1st class bricks No. 1350


Cement Lbs. 780
Sand Cft. 26

Masons No. 5
Workers No. 6
Scaffolding and sundries L-s

4 Brick work 1st class in 1:2 cement mortar. Cft 100

1st class bricks No 1350


Cement Lbs 1035
Sand Cft 23

Masons No. 4
Workers No. 6
Scaffolding and sundries L-s

5 Brick work 1st class in 1:4 cement mortar. Cft 100

1st class bricks No 1350


Cement Lbs 630
Sand Cft 28

Masons No. 4
Workers No. 6

6 Cornice 6" deep 1st class brick work in


1:3 cement mortar Rft 100
ANALYSIS OF RATES ( Brick Work )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
1st class bricks No. 275
Cement Lbs. 150
Sand Cft. 5

Masons No. 4
Workers No. 3

7 9" thick Honey comb brick work 1st class


in 1:3 Cement mortar Sft 100

1st class bricks No. 700


Cement Lbs. 564
Sand Cft. 19

Masons No. 3.5


Workers No. 3.5

8 4" thick honey comb brick work 1st


class in 1:3 cement mortar Sft. 100

Cement Lbs. 800


1st class brick 9"x 4-3/8"x 2-3/4" No. 350
Sand Cft. 10

Masons No. 2
Workers No. 2

9 Brick curb 4" x 3" in cement mortar 1:3


and plastered " thick in the same mortar Rft. 100

Cement mortar 1:3 Cft. 3


1st class brick 9"x 4-3/8"x 2-3/4" No. 138
1/2" cement mortar plastering Sft. 87.5

Masons No. 0.5


Workers No. 0.33

10 Brick work 1st class in lime mortar 1:1:1 Cft. 100

Lime mortar 1:1:1 Cft. 26


1st class brick 9"x 4-3/8"x 2-3/4" No. 1350

Masons No. 4
Workers No. 5
Scaffolding and sundries L-s

11 Brick work 1st class in arches in lime


mortar 1:1:1 Cft. 100

Lime mortar 1:1:1 Cft. 26


1st class brick 9"x 4-3/8"x 2-3/4" No 1350

Masons No. 5
Workers No. 5
Scaffolding and sundries L-s
ANALYSIS OF RATES ( Brick Work )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
12 Brick work 1st class in lime mortar ( 1:2 ) Cft 100

Lime Cft. 12
1st class brick 9"x 4-3/8"x 2-3/4" No 1350
Sand Cft. 24

Masons No. 4
Workers No. 6

13 Brick work 1st class in lime mortar ( 1:1 ) Cft. 100

Lime mortar 1:1 Cft. 26


1st class brick 9"x 4-3/8"x 2-3/4" No. 1350

Masons No. 4
Workers No. 5

14 Cornice 6" deep 1st class brick work in


1:1 lime mortar Rft. 100

Lime mortar 1:1 Cft. 5


1st class brick 9"x 4-3/8"x 2-3/4" No. 275

Masons No. 4
Workers No. 3

15 Hony comb work with brick 1st class and


plastered one coat 3/8" lime mortar Cft. 100

Lime mortar 1:1:1 Cft. 19


1st class brick 9"x 4-3/8"x 2-3/4" No. 700

Masons No. 9
Workers No. 6

16 Brick work in mud with sun burnt bricks Cft. 100

Sun burnt bricks No. 1350


Clay Cft. 30

Masons No. 3
Workers No. 5
Scaffolding and sundries L-s
Brick work in cement mortar ( 1:3 )
2 cft. 100

Cement 8-2/3 cft. lbs. 780 lbs. 100


1st class bricks no. 1350 no.
Sand cft. 26 cft.

Masons no. 4 no.


Workers no. 6 no.

9 4-1/2" thick honey comb brick work 1st


class in 1:3 cement mortar cft. 100

8 Cement lbs. 300 lbs.


1st class brick 9"x 4-3/8"x 2-3/4" no. 350 no.
Sand cft. 10 cft.

Masons no. 2 no.


Workers no. 2 no.

4 Brick work 1st class in 1:2 cement mortar. Cft 100

1st class bricks No 1350


Cement Lbs 1035 9.241071
Sand Cft 23 0.23

Masons No. 4
Workers No. 6
Scaffolding and sundries L-s
112

6.96428571 Bag
1350 No
0.26 sud

4 No
6 No

112

5000 133.9286
17500
500

100
100

Bag
Sud
ANALYSIS OF RATES ( Concrete ' Hand mixed ' )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

1 Cement concrete with stone ballast


1-1/2" gauge 1:3:6 Cft. 100

Cement 16 cft. Lbs. 1440


Stone ballast 1-1/2" gauge Cft. 96
Sand Cft. 48

Masons No. 1
Workers No. 8

2 Cement concrete 1:2:4 with 1/4" to 3/4"


stone chipping or river shingle aggregate Cft. 100

Cement 23 cft. Lbs. 2070


Stone Cft. 92
Sand Cft. 46

Masons No. 1
Workers No. 10

3 Mixing only cement concrete 1:2:4 with 1/2"


to 3/4" gauge stone chipping or river shingle
aggregate Cft. 100

Masons No. 1
Workers No. 5

4 Cement concrete with 3/4" stone ballast or


river shingle aggregate 1:2:5 Cft. 100

Cement 19 cft. Lbs. 1710


Stone ballast 3/4" gauge Cft. 94
Sand Cft. 47

Masons No. 1
Workers No. 10

5 Cement concrete 1:1-1/2:3 with 1/4" to 3/4"


stone or river shingle aggregate Cft. 100

Cement 19 cft. Lbs. 2790


Stone or river shingle 1/4" to 3/4" gauge Cft. 92
Sand Cft. 46

Masons No. 1
Workers No. 10

6 1-1/2" Thick cement concrete 1:2:4 with


5% pudlo to the weight of cement for damp
ANALYSIS OF RATES ( Concrete ' Hand mixed ' )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
proof course Cft. 100

Cement 2-3/4 cft. Lbs. 248


pudlo Lbs. 12
Stone ballast 1/4" to 3/4" gauge Cft. 12
Sand Cft. 6

Masons No. 1
Workers No. 1

7 Cement concrete 1:2:4 with ironite 10% to


the weight of cement Cft. 100

Cement 21 cft. Lbs. 1890


Ironite Lbs. 189
Stone ballast 1/4" to 3/4" gauge Cft. 92
Sand Cft. 46

Masons No. 1
Workers No. 10

8 1" Thick cement concrete 1:2:4 with 5%


pudlo to the weight of cement for damp
proof course Cft. 100

Cement Lbs. 173


pudlo Lbs. 8.75
Stone ballast 1/4" to 3/4" gauge Cft. 8
Sand Cft. 4

Masons No. 0.75


Workers No. 0.75

9 Cement concrete 1:6:12 using 1/4" to 3/4"


stone or rivre shingle aggregate infoundation Cft. 100

Cement Lbs. 765


Sand Cft. 51
Stone or river shingle Aggregate 1/4" to 3/4" Cft. 102

Masons No. 1
Workers No. 10

10 Cement concrete 1:4:8 using 3/4" to 1"


stone or rivre shingle aggregate Cft. 100

Cement Lbs. 1170


Sand Cft. 52
Stone or river shingle Aggregate 1/4" to 3/4" Cft. 104
ANALYSIS OF RATES ( Concrete ' Hand mixed ' )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

Masons No. 1
Workers No. 10

11 Lime concrete ( 1:1:1:6 ) with gravel


aggerate Cft. 100

Gravel Cft. 100


Lime motar 1:1:1 Cft. 38

Masons No. 0.5


Workers No. 7
Sundries L-s

12 Lime concrete 1:1:4 in foundation using


medium brick aggregate Cft. 100

Lime mortar Cft. 34


Brick bat aggragate Cft. 100

Masons No. 0.5


Workers No. 7
Sundries L-s

13 Lime concrete 1:2:6 with gravel or broken


brick aggregate Cft. 100

Gravel Cft. 100


Lime Cft. 17.5
Sand Cft. 35

Masons No. 0.5


Workers No. 10

14 Lime concrete ( 1:1:1:6 ) with broken brick


or stone ballast Cft. 100

Stone or brick ballast 1" gauge Cft. 100


Lime motar 1:1:1 Cft. 34

Masons No. 0.5


Workers No. 7
Sundries L-s

15 Composite concrete with stone ballast,river


shingle or hill gravel 1:2:5:10 Cft 100

Cement 9 cft. Lbs 810


Stone ballast 3/4"gauge river shingle or Cft. 90
hill gravel
ANALYSIS OF RATES ( Concrete ' Hand mixed ' )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Lime Cft. 18
Sand Cft. 45

Masons No. 1
Workers No. 10

16 Cement concrete ( 1:3:5 ) using medium


fine stone or river shingle aggreate Cft. 100

Cement Cft. 17.9


Sand Cft. 53.7
Stone or river shingle aggregate 3/4" to 1/2" Cft. 89.5

Masons No. 1
Workers No. 10

17 Mixing only granolithic mix( 1:2 ) with


1/4" down granite chipping with ordinary
cement Cft. 100

Cement Lbs. 3568


Sand Cft. 7.5
1/4" Granite chipping Cft. 104

Masons No. 1
Workers No. 5

18 Mixing only granolithic mix( 1:2 ) with


1/4" down granite chipping with ordinary
cement Cft. 100

Cement Lbs. 4320


Sand Cft. 9
1/4" Granite chipping Cft. 96

Masons No. 1
Workers No. 5

19 Mixing only Terrazo mix( 1:3 ) with 1/4"


marble chipping with coloured cement Cft. 100

Colour-crete Lbs. 3240


1/4" Marble chipping Cft. 108

Masons No. 1
Workers No. 5

20 Mixing only Terrazo mix( 1:2 ) with 1/4"


chipping with coloured cement Cft. 100
ANALYSIS OF RATES ( Concrete ' Hand mixed ' )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Colour- crete Lbs. 4320
1/4" Marble chipping Cft. 96

Masons No. 1
Workers No. 5

21 Timber shuttering ( form work ) Sft. 100 (1)+ 1 Carp;


for Beam,
Timber scantling Cft. 15 lintel & Walls.
Tinber planks 1" Sft. 110
Nails and spikes Lbs. 3
M-S bolts & washer if required (2)+ 2 Cap;
for Stairs &
Carpenters No. 4 Columns
Workers No. 2
(3)+ 2 Cap;
for T&G

(4)+ 1 Cap;
for Each
additional
Story height.

(5)Shuttering
can be use
min; of 3
times

(6)Add timber
planks 10
sft. For T&
G work.

`
1 Cement concrete with stone ballast
1-1/2" gauge 1:3:6 100 100

Cement 16 cft. lbs. 1440 12.857 bag 112


Stone cft. 96 0.960 Sud
Sand cft. 48 0.480 Sud

Masons no. 1 1.000 no


Workers no. 8 8.000 no

2 Cement concrete 1:2:4 with 1/4" to 3/4"


stone chipping or river shingle aggregate 100 100

Cement 23 cft. lbs. 2070 18.482 bag 112


Stone cft. 92 0.920 Sud
Sand cft. 46 0.460 Sud

Masons no. 1 1.000 no


Workers no. 10 10.000 no

21 Timber shuttering ( form work )


100.00 Sft
sft. 100

Timber scantling cft. 15 15.000 cft.


0.161
Tinber planks 1" sft. 110 9.167 cft.
Nails and spikes lbs. 3 3.000 lbs. 0.833333
M-S bolts & washer if required
Carpenters no. 4 4.000 no.
Workers no. 2 2.000 no.
13 Lime concrete 1:2:6 with gravel or broken
brick aggr Cft. 100

Gravel Cft. 100 1 Sud


Lime Cft. 17.5 0.175 Sud
Sand Cft. 35 0.35 Sud

Masons No. 0.5 0.5


Workers No. 10 10
3time
ANALYSIS OF RATES (Concrete mixed by Machine)

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount Remark

1 Mixing & Placing cement con: 1:3:6


with stone ballast or river shingle or
brick agg:11/2" gauge wheeled by hand
in barrows Cft 100

Cement 16 cft Lbs 1440


Stone ballast or river shingle or
brick agg:11/2" gauge Cft 96
Sand Cft 48
Fuel Gal 2

Mason No 1
Workers No 6
Machine driver No 0.5

2 Mixing only cement conc: 1:2:4 with


1/2" to 3/4" stone chipping on river
shingle aggregrate wheeled by hand
in barrows Cft 100

Cement 23 cft Lbs 2070


Stone chipping or river shingle cft 92
Sand cft 46
Fuel Gal 2

Mason No 1
Workers No 3
Machine driver No 0.5

3 Mixing and Placing in cement conc:


1:4:8 with 3/4" to 11/2" stone ballast
or river shingle agg. Wheeled by hand
in barrows Cft 100

Cement 13 cft Lbs 1170


Stonechipping or river shingle3/4"-11/2" Cft 104
Sand Cft 52
Fuel Gal 2

Mason No 1
Workers No 8
Machine driver No 0.5

4 Mixing and Placing in cement conc:


1:11/2:3 with 1/4" to 3/4" stone ballast
or river shingle agg. Wheeled by hand
in barrows Cft 100

Cement 31 cft Lbs 2790


Stone or shingle 1/4"- 3/4" Cft 92
Sand Cft 46
Fuel Gal 2
Mason No 1
Workers No 8
Machine driver No 0.5

5 Transporting & Placing consolidating


cement conc:(not reinforced) Cft 100
Load 100' & 15' above or below mixer

(a) Foundation & floors

Mason No 1
Workers No 5

(b) Walls

Mason No 1
Workers No 7

Load 100' & 30' above or below mixer

(a) Foundation & floors

Mason No 1
Workers No 6

(b) Walls

Mason No 1
Workers No 8

6 Transporting & Placing consolidating


cement conc:( reinforced) Cft 100
Load 100' & 15' above or below mixer

(a) Foundation & floors

Mason No 2
Workers No 6

(b) Walls

Mason No 2
Workers No 8

( c ) Columns

Mason No 2
Workers No 9

Load 100' & 30' above or below mixer

(a) Foundation & floors

Mason No 2
Workers No 7

(b) Walls
Mason No 2
Workers No 9

( c ) Columns

Mason No 2
Workers No 10
ANALYSIS OF RATES ( Flooring )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

1 Brick on edge flooring in lime mortar and


pointed with cement mortar 1:2 Sft. 100

1st class bricks 9"x 4-3/8"x 2-3/4" No. 550


Lime mortar 1:1:1 Cft. 12
Cement mortar 1:2 Cft. 1

Masons No. 2
Workers No. 4.5
Sundries L-s

2 Brick on edge flooring in cement mortar 1:3 Sft. 100

1st class bricks 9"x 4-3/8"x 2-3/4" No. 550


Cement mortar 1:3 Cft. 12

Masons No. 2
Workers No. 3.5
Sundries L-s

3 Brick on edge flooring lad in composite


( 1:1:6 ) Sft. 100

1st class bricks 9"x 4-3/8"x 2-3/4" No. 550


Composite mortar 1:1:6 Cft. 12

Masons No. 2
Workers No. 3.5
Sundries L-s

4 Brick laid flat in flooring in cement mortar


( 1:3 ) Sft. 100

1st class bricks 9"x 4-3/8"x 2-3/4" No. 345


Cement mortar 1:3 Cft. 8

Masons No. 1.5


Workers No. 1.5

5 Brick laid flat in flooring lad in composite


mortar ( 1:1:6 ) Sft 100

Brick 1st class No. 345


Composite mortar 1:1:6 Cft. 8
Masons No. 1.5
Workers No. 1.5

6 6"x 6"Glazed tiles flooring laid in composite


mortar ( 1:3 ) Sft. 100
ANALYSIS OF RATES ( Flooring )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

6"x 6"Glazed tiles No. 420 5% Wastage


Cement Lbs. 135
Sand Cft. 4.5

Masons No. 2.5


Workers No. 2

7 18"x 18"x 1" Polished marble flooring laid in


cement mortar 1:3 Sft. 100

18"x 18"x 1"Marble slab No. 47 7% Wastage


Cement Lbs. 135
Sand Cft. 4.5

Masons No. 2.5


workers No. 2.5

8 1-1/2"Thick 1:2:4 cement concrete flooring


laid in slab of 5' square. Sft. 100

Cement Lbs. 259 For all cement


Sand Cft. 5.75 rendering work
Stone Aggregate 1/4" to 3/4" Cft. 11.5 in floors add
1/4 mason for
Masons No. 0.75 each 100 sft.
Workers No. 1.5 of floor area.

9 2"Thick cement concrete 1:2:4 flooring


using stone or river shingle aggregate Sft. 100

Cement lbs. 345


Sand Cft. 7.5
Stone or river shingle aggregate Cft. 15

Masons No. 0.75


Workers No. 2
Sundries L-s
10 3"Thick cement concrete 1:2:4 with river
shingle aggregate Sft. 100

Cement Lbs. 518


Sand Cft. 11.5
River shingle Cft. 23
Battens & Sundries Cft. 1.5

Masons No. 0.75


Workers No. 3
Carpenters No. 0.167
ANALYSIS OF RATES ( Flooring )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
11 4-1/2" Thick cement 1:2:4 floor using
medium fine stone or river shingle aggregate Sft. 100

Cement Lbs. 777


Sand Cft. 17.25
River shingle Cft. 34.5
Battens & Sundries Cft. 2.25

Masons No. 1
Workers No. 4.5
Carpenters No. 0.167

12 1"Thick P.C.C ( 1:2:4 ) floor using fine stone


river shingle or brick aggregate Sft. 100

Cement concrete ( 1:2:4 ) Cft. 8.333


Batten & sundries L-s

Masons No. 0.75


Workers No. 1

13 3"lime concrete ( 1:2:6 ) floor using stone,


river shingle or brick aggregate Sft. 100

Lime Cft. 4.37


Sand Cft. 8.74
Aggregate Cft. 25

Masons No. 0.5


Workers No. 3

14 4-1/2"lime concrete ( 1:2:6 ) floor using


stone, river shingle or brick aggregate Sft. 100

Lime Cft. 6.56


Sand Cft. 13.12
Aggregate Cft. 37.5

Masons No. 0.5


Workers No. 3

15 3"lime concrete ( 1:1:4 ) under lay floor


using brick aggregate Sft. 100

Lime concrete ( 1:1:4 ) Cft. 25

Masons No. 0.25


Workers No. 2

16 1/2"Thick mastic asphalt flooring Sft. 100


ANALYSIS OF RATES ( Flooring )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

Asphalt Lbs. 448


Coal tar Lbs. 14
Sand Cft. 2.5
Fire wood Cft. 6

Masons No. 1
Workers No. 4

17 6"Gravel flooring well watered and rammed Sft. 100

Gravel at site Cft. 58

Workers No. 1.5

18 6"Earth floor well watered and rammed Sft. 100

6"Earth consolidated Cft. 48

Worker for carrying,laying & ramming No. 0.625


Worker for watering No. 0.25

19 Finishing and laying smooth 3/8" thick


terrazzo floor 1:2 with 1/4" marble chipping
on 3/8" thick average screed in cement
mortar 1:3 ( cast in situ ) Sft. 100

Terrazzo 1:2 Cft. 3.125


Cement mortar 1:3 Cft. 3.125
Approved metal plastic dividing strip Rft. 50

Masons No. 1
Grider using maching Day. 0.5
Polosher using maching Day. 0.25
Oxalic acid dresser Day. 0.5
Carborandum stone L-s
Wax polish L-s
Oxalic acid L-s

20 Finishing and laying smooth 1/2"granolithic


finish with ( 1:2 ) with 1/4"granite chippings
on 1"thick. Average screed in cement
mortar ( 1:3 ) cast in situ Sft. 100

Granolithic ready mixed Cft. 4.167


Cement mortar ( 1:3 ) Cft. 8.333
Approved metal plastic dividing strip Rft. 50

Masons No. 1
Grider Day. 0.25
ANALYSIS OF RATES ( Flooring )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Polosher using maching Day. 0.5
Sodium silicate dresser Day. 0.5
Carborandum stone L-s
Sodium silicate L-s

21 Laterite or kankar filling in floor spread and


consolidated in 6" layers to line and level
surface including watering and consolidating Cft. 100

Laterite or kankar Cft. 116

Worker for carrying,laying & consolidating No. 2


Worker for watering No. 0.25

22 4"Thick laterite or kankar well watered and


rammed. Sft. 100

Laterite or kankar Cft. 38

Worker for carrying,laying & ramming No. 0.75


Worker for watering No. 0.125

23 6"Thick laterite or kankar well watered and


rammed. Sft. 100

Laterite or kankar Cft. 58

Worker for watering & ramming No. 1.5

24 1"Tongue and grooved plank flooring with 4"


x 1" plank. Sft. 100

4"x 1" T & G planks Cft. 10.96 15% Wastage


Nails Lbs. 2

Carpenters No. 2
Workers No. 1

25 1"Butt joint plank flooring with 4"x 1" planks Sft. 100

4"x 1"Butt joint plank , 345 Rft. Cft. 9.6 15% Wastage
Nails Lbs. 2

Carpenters No. 1.5


Workers No. 1

26 Parquet flooring teak blocks 9"x 3"x 1"


wax polished. Sft. 100

Coal tar Gal. 2


ANALYSIS OF RATES ( Flooring )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Asphalt Gal. 7
Turpentine pint. 2
Teak blocks, 9"x 3"x 1-1/2" No. 580
Fuel Cft. 4
Bees Wax Lbs. 2

Carpenters No. 6
Workers No. 8
Sundries
6"x 6"Glazed tiles flooring laid in composite 400
mortar ( 1:3 ) Sft. 100 112

6"x 6"Glazed tiles no. 420 1680 no.


Cement lbs. 135 4.821429 Bag
Sand Cft. 4.5 0.18 Cft.

Masons no. 2.5 10 no.


Workers no. 2 8 no.

1-1/2"Thick 1:2:4 cement concrete flooring


using stone or river shingle aggregate 100 Sft
112
Sft. 100

Cement lbs. 259 2.3125 Bag


Sand Cft. 5.75 0.0575 Sud
Stone Aggregate 1/4" to 3/4" Cft. 11.5 0.115 Sud

Masons no. 0.75 0.75 No


Workers no. 1.5 1.5 No
6"x 6"Glazed tiles flooring laid in composite 400

47 59 0.38 1053.74

1039.88 13.86 1.782


100
6"x 6"Glazed tiles flooring laid in composite 400
112 1440 135.4809
96 1011.59
48 505.7952
6"x 6"Glazed tiles flooring laid in composite 400

112

2773 100 74.37

8329.44
832944
300.3765
13.3056
#REF!
ANALYSIS OF RATES ( Plastering & Pointing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

1 Plastering with demp proof cement mortar


3/4" thick 1:2 Sft. 100

Cement 3.6 cft. Lbs. 324


Pudlo ( 5% by weight of cement ) Lbs. 16.2
Sand Cft. 7.2

Masons No. 1.5


Workers No. 3
Sundries L-s

2 Plastering with 1:2 cement mortar 1/2"thk. Sft. 100

Cement Lbs. 225


Sand Cft. 5

Masons No. 1
Workers No. 2

3 Plastering with 1:3 cement mortar 1/2"thk. Sft 100

Cement Lbs. 150


Sand Cft. 5

Masons No. 1
Workers No. 2

4 Plastering with 1:3 cement mortar 3/4"thk. Sft 100

Cement Lbs. 225


Sand Cft. 7.5

Masons No. 1.5


Workers No. 3

5 Plastering with 1:4 cement mortar 1/2"thk. Sft. 100

Cement Lbs. 112.5


Sand Cft. 5

Masons No. 1
Workers No. 2

6 Plastering 1/2" thk. With lime mortar 1:1 Sft. 100

Lime mortar 1:1 Cft. 5

Masons No. 1
Workers No. 2
ANALYSIS OF RATES ( Plastering & Pointing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Sundries L-s

7 Plastering 1/2" thk. With lime mortar 1:2 Sft. 100

Lime Cft. 2.5


Sand Cft. 5

Masons No. 1
Workers No. 2
Sundries L-s

8 Plstering with lime mortar 1/2"thk. 2:3:1 Sft. 100

Lime mortar for plaster 2:3:1 Cft. 5

Masons No. 1
Workers No. 2
Sundries L-s

9 Plstering with 1:2:6 composite mortar 1/2"


thick. Sft. 100

Cement0.8 cft. Lbs. 72


Lime Cft. 1.6
Sand Cft. 4.8

Masons No. 1
Workers No. 2
Sundries L-s

10 Plstering with 1:1:6 composite mortar 1/2"


thick. Sft. 100

Cement 0.83 cft. Lbs. 75


Lime Cft. 0.83
Sand Cft. 5

Masons No. 1
Workers No. 2
Sundries L-s

11 Plastering 1/2" thick cement mortar 1:3


with 5% pudlo by weight of cement Sft. 100

Cement mortar 1:3 Cft. 5


Pudlo Lbs. 7.5

Masons No. 1
Workers No. 2
Sundries L-s
ANALYSIS OF RATES ( Plastering & Pointing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

12 Mud plastering 1/4" thick Sft. 100

Tempered clay chopped-straw and Cft. 2.5


cow-dung

Masons No. 1
Workers No. 1

13 Pointing with 1:1:6 composite mortar Sft. 100

Cement Lbs 30
Lime Cft. 0.33
Sand Cft. 2

Masons No. 1
Workers No. 2
Sundries L-s

14 Pointing with 1:2:6 composite mortar Sft. 100

Cement Lbs. 29
Lime Cft. 0.64
Sand Cft. 1.92

Masons No. 1
Workers No. 2
Sundries L-s

15 Pointing with cement mortar 1:2 Sft. 100

Cement Lbs. 83
Sand Cft. 2

Masons No. 1
Workers No. 2

16 Pointing with cement 1:3 to full depth of


tiles, mable tiles, marseilles tiles, glazed
tiles, etc. Sft. 100

Cement Lbs. 15
Sand Cft. 0.5

Masons No. 1
Workers No. 2
Colouring materials and sundries L-s

17 Pointing with cement mortar 1:3 Sft. 100


ANALYSIS OF RATES ( Plastering & Pointing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Cement Lbs. 60
Sand Cft. 2

Masons No. 1
Workers No. 2

18 Pointing with lime mortar 2:3:1 Sft. 100

Lime mortar for plster 2:3:1 Cft. 2

Masons No. 1
Workers No. 2
Sundries L-s

19 Pointing with lime mortar 1:1 Sft. 100

Lime mortar 1:1 Cft. 2

Masons No. 1
Workers No. 2
Sundries L-s
400
Plastering with 1:2 cement mortar 1/2"thcft. 100 112

Cement lbs. 225 8.035714 Bag


Sand cft. 5 0.2 Sud

Masons no. 1 4 no
Workers no. 2 8 no

1000
112
Plastering with 1:3 cement mortar 1/2"thsft 100

Cement lbs. 150 13.39286 Bag


Sand cft. 5 0.5 Sud

Masons no. 1 10 no
Workers no. 2 20 no

1000
112
Plastering with 1:3 cement mortar 3/4"thsft 100

Cement lbs. 225 20.08929


Sand cft. 7.5 0.75

Masons no. 1.5 15


Workers no. 3 30
ANALYSIS OF RATES ( Reinforced Concrete ' mixed by machine' )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

1 Mixing and placing cement concrete 1:3:6


with stone ballast or river shingles or brick
aggreagate 1-1/2" gauge whelled by hand
in barrows Cft. 100

Cement 16 cft. Lbs. 1440


Stone Ballast, shingles or
brick Aggreagate 1-1/2" gauge Cft. 96
Sand Cft. 48
Fuel Gals. 2

Masons No. 1
Workers No. 6
Machine drivers No. 0.5

2 Mixing only cement concrete 1:2:4, with


1/2" to 3/4" gauge stone chipping on river
shingle aggregate wheeled by hand in
barrows. Cft. 100

Cement 23 cft. Lbs. 2070


Stone shipping or river shingle Cft. 92
Sand Cft. 46
Fuel Gals. 2

Masons No. 1
Workers No. 3
Machine drivers No. 0.5

3 Mixing and placing cement concrete 1:4:8


with 3/4" to 1-1/2" stone ballast or river
shingles aggreagate whelled by hand in
barrows. Cft. 100

Cement 13 cft. Lbs. 1170


Stone Ballast, shingles or
brick Aggreagate 3/4" to 1-1/2" gauge Cft. 104
Sand Cft. 52
Fuel Gals. 2

Masons No. 1
Workers No. 8
Machine drivers No. 0.5

4 Mixing and placing cement concrete


1:1:3 with stone ballast or river shingles
or brick aggreagate 1/4" to 3/4"gauge
whelled by hand in barrows Cft. 100
ANALYSIS OF RATES ( Reinforced Concrete ' mixed by machine' )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Cement 31 cft. Lbs. 2790
Stone Ballast, shingles or
brick Aggreagate 1/4" to 3/4" gauge Cft. 92
Sand Cft. 46
Fuel Gals. 2

Masons No. 1
Workers No. 8
Machine drivers No. 0.5

5 Transporting, placing and consoldating


cement concrete ( not reinforced )
Cft. 100
Lead 100' and 15' above or below mixer
(A) Foundation and Floors
Masons No. 1
Workers No. 5

(B) Walls
Masons No. 1
Workers No. 7

Lead 100' and 30' above or below mixer


(A) Foundation and Floors
Masons No 1
Workers No 6

(B) Walls
Masons no. 1
Workers No. 8

6 Transporting, placing and consoldating


cement concrete ( reinforced )
Cft. 100
Lead 100' and 15' above or below mixer
(A) Foundation and Floors
Masons No. 2
Workers No. 6

(B) Walls
Masons No. 2
Workers No. 8

(C) Columns
Masons No. 2
Workers No. 9

Lead 100' and 30' above or below mixer


(A) Foundation and Floors
Masons No. 2
ANALYSIS OF RATES ( Reinforced Concrete ' mixed by machine' )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Workers No. 7

(B) Walls
Masons No. 2
Workers No. 9

(C) Columns
Masons No. 2
Workers No. 10
Mixing and placing cement concrete 1:3:6 1000
112
cft. 100

Cement 16 cft. lbs. 1440 128.5714 Bag


Stone Ballast, shingles or
brick Aggreagate 1-1/2" gauge cft. 96 9.6 Sud
Sand cft. 48 4.8 Sud
Fuel gals. 2 20 gals.

Masons no. 1 10 no.


Workers no. 6 60 no.
Machine drivers no. 0.5 5 no.

Mixing only cement concrete 1:2:4


1000
112
cft. 100

Cement 23 cft. lbs. 2070 184.8214 Bag


Stone shipping or river shingle cft. 92 9.2 Sud
Sand cft. 46 4.6 Sud
Fuel gals. 2 20 gals.

Masons no. 1 10 no.


Workers no. 3 30 no.
Machine drivers no. 0.5 5 no.
ANALYSIS OF RATES ( Reinforced Concrete ' Hand mixed ' )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

1 Reinforced concrete work 1:2:4 Cft. 100

Cement 23 cft. Lbs. 2070


Corse aggreagate 1/4" to 3/4" gauge Cft. 92
Sand Cft. 46

Masons No. 2
Workers No. 15

2 R.C.C 1:2-1/2:5 mile furlong and boundary


posts for 91 posts Cft. 100

Cement 19 cft. Lbs. 1710


no.6 G-I plain wire Lbs. 255
Coal tar for filling in letters Lbs. 3
Ballast 1/4" to 3/4" gauge Cft. 94
Sand Cft. 47
Shuttering lump sum allowing same form to L-s
be use several times

Masons No. 3
Workers No. 20

3 R.C.C 1:2:4 intermediate fence posts 6' long


6" sq. base, 4" sq. top for 92 posts Cft. 100

Cement 23 cft. Lbs. 2070


3/8" M-S rods Lbs. 872
Binding wire Lbs. 80
Ballast 1/4" to 3/4" gauge Cft. 92
Sand Cft. 46
Shuttering lump sum allowing same form to L-s
be use several times

Masons No. 3
Workers No. 20

4 R.C.C 1:2:4 gate and corner posts 6' long


8" sq. base, 6" sq. top for 42 posts Cft. 100

Cement 23 cft. Lbs. 2070


3/8" M-S rods Lbs. 464
Binding wire Lbs. 44
Ballast 1/4" to 3/4" gauge Cft. 92
Sand Cft. 46
ANALYSIS OF RATES ( Reinforced Concrete ' Hand mixed ' )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Shuttering lump sum allowing same form to L-s
be use several times

Masons No. 3
Workers No. 20

5 R.C.C pipe for culvert 12" dia.2' long, 2-1/2"


thick, 1:2:4 for one pipe Cft. 100

Cement Lbs. 32
Triangular meah rif style no.245 Sft. 8
Binding wire Lbs. 0.2
Ballast 1/4" to 3/4" gauge Cft. 1.45
Sand Cft. 0.72
Special shuttering for pipe L.s

Masons No. 0.125


Workers No. 0.75

6 R.C.C pipe for culvert 24" dia.2' long, 2-1/2"


thick, 1:2:4 for one pipe Cft. 100

Cement Lbs. 61
Triangular meah rif style no.245 Sft. 14.5
Binding wire Lbs. 0.2
Ballast 1/4" to 3/4" gauge Cft. 2.66
Sand Cft. 1.34
Special shuttering for pipe L.s

Masons No. 0.25


Workers No. 1.5

7 R.C.C pipe for culvert 36" dia.2' long, 3-1/2"


thick, 1:2:4 for one pipe Cft. 100

Cement Lbs. 130


Triangular meah rif style no.245 Sft. 22
Binding wire Lbs. 0.2
Ballast 1/4" to 3/4" gauge Cft. 5.8
Sand Cft. 2.9
Special shuttering for pipe L.s

Masons No. 1
Workers No. 2

8 R.C.C pipe for culvert 48" dia.2' long, 5"


ANALYSIS OF RATES ( Reinforced Concrete ' Hand mixed ' )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
thick, 1:2:4 for one pipe Cft. 100

Cement Lbs. 244


Triangular meah rif style no.245 Sft. 29
Binding wire Lbs. 0.2
Ballast 1/4" to 3/4" gauge Cft. 10.8
Sand Cft. 5.4
Special shuttering for pipe L.s

Masons No. 1.5


Workers No. 3

9 3" R.C.C ( 1:2:4 ) using fine stone or river


shingle aggregate and B.R.C no. 10 includi-
ng use and waste of forms and shuttering. Sft. 100

R.C.C 1:2:4 Cft. 25


B.R.C no.10 fabric fixed Sft. 110
Shuttering formwork ( rate reduce to 1/6 for Sft. 100
reason of repeated use )

Masons No. 0.75


Workers No. 4
Reinforced concrete work 1:2:4 1000
112
cft. 100

Cement 23 cft. lbs. 2070 184.8214 Bag


Corse aggreagate 1/4" to 3/4" gauge cft. 92 9.2 Sud
Sand cft. 46 4.6 Sud

Masons no. 2 20 no
Workers no. 15 150 no
ANALYSIS OF RATES ( Iron and Steel work )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

1 Hoisting and fixing R.S. girder ( over 1/2 ton


weight ). Cwt. 1

R.S. girder Cwt. 1


Carriage to site Cwt. 1
Hoisting and fixing Cwt. 1

2 Hoisting and fixing R.S. girders or joists


( below 1/2 ton weight ). Cwt. 1

R.S joist Cwt. 1


Cariage to site Cwt. 1
Hoisting and fixing Cwt. 1

3 W.I work in tees, bars, angles, round,etc. Cwt. 1

Tees, bars, angles, etc. Cwt. 1


Carriage to site Cwt. 1

Smiths No. 2
Workers No. 2

4 W.I straps for trusses, posts, etc.with bolts


and nuts,etc. Lbs. 1

Straps, bolts and nuts Lbs. 1


Carriage to site L-s

Smiths No. 0.033

5 Mild steel bars reinforcement 1/2" cut,


bent, and fixed in floors, roofs and beams. Cwt. 1

1/2" bars Lbs. 117.6 5%Wastage


14 S.W.G binding wire Lbs. 1

Smiths No. 1
Workers No. 1

6 Mild steel bars reinforcement 1/2" cut,


bent, and fixed in columns and braces. Cwt. 1

1/2" bars Lbs. 117.6 5%Wastage


14 S.W.G binding wire Lbs. 1

Smiths No. 1.5


Workers No. 1.5

7 Mild steel bars reinforcement 5/8"to 1"cut,


bent, and fixed in floors, roofs and beams. Cwt. 1
ANALYSIS OF RATES ( Iron and Steel work )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
5/8" to 1" bars Lbs. 117.6 5%Wastage
14 S.W.G binding wire Lbs. 1

Smiths No. 0.75


Workers No. 0.75

8 Mild steel bars reinforcement 5/8"to 1"cut,


bent, and fixed in columns and braces. Cwt. 1

5/8" to 1" bars Lbs. 117.6 5%Wastage


14 S.W.G binding wire Lbs. 1

Smiths No. 1
Workers No. 1

9 Mild steel bars reinforcement 1/2" cut,


bent, and fixed in walls. Cwt. 1

1/2" bars Lbs. 117.6 5%Wastage


14 S.W.G binding wire Lbs. 1

Smiths No. 1.25


Workers No. 1.25 14 S.W.

10 Mild steel bars reinforcement 5/8"to1" cut,


bent, and fixed in walls. Cwt. 1

5/8" to 1" bars Lbs. 117.6 5%Wastage


14 S.W.G binding wire Lbs. 1

Smiths No. 1
Workers No. 1

11 Mild steel bars reinforcement 1"to1.5"cut,


bent, and fixed in columns and bracing. Cwt. 1

1" to 1" bars Lbs. 117.6 5%Wastage


14 S.W.G binding wire Lbs. 1

Smiths No. 0.75


Workers No. 0.75

12 Mild steel bar reinforcement 1/4" stirrups


and spacers cut, bent and fixed in floors,
roofs and beams. Cwt. 1

1/4" bars Lbs. 117.6 5%Wastage


14 S.W.G binding wire Lbs. 1

Smiths No. 2 1.5 no.for 3/8"


ANALYSIS OF RATES ( Iron and Steel work )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Workers No. 2 1.5 no.for 3/8"

13 Mild steel bars reinforcement 1"to1.5"cut,


bent, and fixed in floors,roofs and beams. Cwt. 1

1" to 1-1/2" bars Lbs. 117.6 5%Wastage


14 S.W.G binding wire Lbs. 1

Smiths No. 0.625


Workers No. 0.625

FIXING ONLY STEEL FABRIC

14 Fixing steel fabric or mesh reinforcement in


beams, floors, and walls, B.R.C expanded
metal or other types, including all straight
cutting and the supply of wiring as
necessary with 14-G. wire, measured nett
no allowance for lap. Sft. 100

Sheet weighting under 4 lbs.per yard super.

14 S.W.G binding wire L-s


Smiths No. 0.5

Sheet from 4 lbs to 8 lbs.per yard super.

14 S.W.G binding wire L-s


Smiths No. 0.5714

Sheet over 8 lbs and under17 lbs.per yard super.

14 S.W.G binding wire L-s


Smiths No. 1

15 Fixing steel fabric or mesh reinforcement in


girders,columns & stanchions B.R.C
expanded metal or other straight cutting
and wiring as necessary with 14-G.
wire, measured nett no allowance for lap. Sft. 100

Sheet weighting under 4 lbs.per yard super.

14 S.W.G binding wire L-s


Smiths No. 0.75

Sheet from 4 llbs to 8 lbs.per yard super.

14 S.W.G binding wire L-s


Smiths No. 0.8571
ANALYSIS OF RATES ( Iron and Steel work )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

Sheet over 8 lbs and under17 lbs.per yard super.

14 S.W.G binding wire L-s


Smiths No. 1.5

16 Hinges butt stout pressed steel 3" to 4"


fixed complete with screws. No. 1

3" to 4" Butt hinge No. 1


1" wood screws Gross. 0.056

Carpenters No. 0.04

17 Hasp and staple 4" to 6" fixed complete


with screws. No. 1

4" to 6" Butt hinge No. 1


3/4" wood screws Gross. 0.056

Carpenters No. 0.02

18 Tower bolts japanned plate with bright sheet


6" to 9" fixed complete with wood screws. No. 1

6" to 9" Tower bolts No. 1


3/4" wood screws Gross. 0.056

Carpenters No. 0.04

19 Hook and eye 6" fixed complete. No. 1

6" Hook and eye No. 1

Carpenters No. 0.02

20 Provide 2" x 1/4" W.I hold fast 12" over all


length and fixed to chowkets with bolts and
nuts and washers complete and including
tarring 2 coats. No. 1

M-S Flat iron 2" x 1/4' x 12" Lbs. 1.7


Carriage to site L-s
3/8" 3" long bolts and nuts Lbs. 0.167
Coal tarring 2 coats Sft. 0.375

Smiths No. 0.02


Carpentes No. 0.02
Workers No. 0.02
112 2240

2399.56 2.67

25mm
5/8" to 1" bars lbs. 117.6 lbs. 3.003199 T
14 S.W.G binding wire lbs. 1 lbs. 57.2038 lb
Smiths no. 0.75 no. 45.04799 N
Workers no. 0.75 no. 45.04799 N
22mm
480 2.044
0.4599 T
8.76 lb
6.57 N
6.57 N

18mm
750 1.502 10.05804
0.528047 T
10.05804 Lb
2240 7.543527 N
7.543527 N

1/2" bars 10mm


lbs. 117.6 4058.2 0.376 13.62396
14 S.W.G binding wire lbs. 1 0.715258 T
13.62396 Lb
Smiths no. 1.25 17.02995 N
Workers no. 1.25 17.02995 N
57.2038
8.76
10.05804
13.62396
89.64579
ANALYSIS OF RATES ( Ceiling )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

1 4x 1/2" T & G plank ceiling with 4"x 2" joist


at 2' centers. Sft. 100

4"x 1/2" T & G planks 331 Rft. Cft. 5.29 15%Wastage


Joists 5x 10'x 4"x 2" Cft. 3.36 10%Wastage
Nails & spikes Lbs. 2.5

Carpenters No. 2.25

2 1/2"T & G ceiling without ceiling joists. Sft. 100

4"x 1/2" T & G planks Cft. 5.29 15%Wastage


Nails Lbs. 1.5

Carpenters No. 1.5

3 4"x 1/2"Butt joint plank ceiling with 2"x 1/2"


splines and 4"x 2" joist at 2' ceatres. Sft. 100

4"x 1/2" Planks 10'x 10'x 1/2"


Cft. 7.19 15%Wastage
Splines 30x 10'x 2"x 1/2"
Joists 5-1/2x 10'x 4"x 2" Cft. 3.36 15%Wastage
Nails & spikes Lbs. 2.5

Carpenters No. 2.5

4 Asbestos cement ceiling with 4"x 2" joists


at 2' centers for ( 16'x 16' ) Sft. 256

4'x 4' Asbestos cement sheet Sft. 282 10%Wastage


Beading 1"x 1/2" Cft. 0.96 15%Wastage
Joists 4"x 2" Cft. 8.8 10%Wastage
1" wood screws No. 216
Nails Lbs. 1.5

Carpenters No. 7.5

5 Asbestos sheet ceiling with 3"x 2" joists at


2' center and 1"x1/2" beading for 16'x16' Sft. 256

A-C plain sheets Sft. 282 10%Wastage


ANALYSIS OF RATES ( Ceiling )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
3"x 2" joists Cft. 6.6 Do
1"x 1/2" beadings Cft. 0.96 15%Wastage
1" wood screws Gross. 1.5
Nails Lbs. 1.5

Carpenters No. 6.5

6 Asbestos sheet ceiling with 4"x 2" joist at


4' centers and 2"x 2" cross joists at 2'
centers complete with 1"x 1/2" Teak
beadings for 16'x 16' Sft. 256

A.C plain sheets Sft. 282 10%Wastage


Joists 4"x 2" Cft. 4.89 10%Wastage
Joists 2"x 2" Cft. 4.6 10%Wastage
Teak beading 1-1/2"x 1/2" Cft. 0.96 10%Wastage
1-1/2" Wood screws Gross. 1.5
Nails Lbs. 1.5

Carpenters No. 7.5

7 A.C plain sheet ceiling 3"x 2" joists at 4'


centers and 2"x 2" cross joists at 2' centers
complete with 2"x 1/2" Teak beadings for
( 16'x 16' ) Sft. 256

4'x 4' A.C plain sheets Sft. 282 10%Wastage


Joists 4"x 2" Cft. 3.67 Do
Joists 2"x 2" Cft. 4.6 10%Wastage
Beading 1-1/2"x 1/2" Cft. 1.28 Do
1-1/2" Wood screws Gross. 1.5
Nails Lbs. 1.5

Carpenters No. 7

8 A.C plain sheet ceiling with 1"x 1/2"


Teak beadings but without ceiling joists
for ( 16'x 16' ) Sft. 256

4'x 4' A.C plain sheets Sft. 282 10%Wastage


Beading 1"x 1/2" Cft. 0.96 15%Wastage
1-1/2" Wood screws Gross. 1.5
ANALYSIS OF RATES ( Ceiling )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Nails Lbs. 0.5

Carpenters No. 3.5

9 Bamboo mat ceiling with covering strips but


without joists. Sft. 100

Bamboo mat single layer Sft. 115


Covering strips 4"x 1/2" Cft. 1.28 15%Wastage
Nails Lbs 2

Carpenters No. 1

10 Single fine bamboo mat ceiling with 3"x 2"


joists at 4' centers and 2"x 2" cross joists
at 2' centers with 2"x 1/2" beading. Sft. 256

Fine mat ( bamboo ) Sft. 295 15%Wastage


Scantling 3"x 2" Cft. 3.67 10%Wastage
Scantling 2"x 2" Cft. 4.6 15%Wastage
Beading 2"x 1/2" Cft. 1.28
Nails Lbs 5

Carpenters No. 5
Workers No. 1.5

11 X.P.M ceiling with 3"x 1/2" beading without


ceiling joists Sft. 100

X.P.M Sft. 110 10%Wastage


3"x 1/2" Beadings Cft. 0.96 15%Wastage
Nails Lbs. 1.5

Carpenters No. 2

12 X.P.M 3/4"mesh 1/4" thick ceiling with 3"x


1/2" beadings. Sft. 100

X.P.M 3/4" Mesh 1/4"thick Sft. 110 10%Wastage


1/2" Beadings Cft. 0.96 15%Wastage
Nails Lbs 1.5
ANALYSIS OF RATES ( Ceiling )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Carpenters No 2

13 Square mesh ceiling with 4"x 2" joists at 2'


centers and 2"x 1/2" beadings. Sft. 100

4"x 2" Scantling Cft. 3.67 10%Wastage


2"x 1/2" Beadings Cft. 0.48 15%Wastage
Sq.meah Sft. 110 10%Wastage
Nails Lbs 1.5

Carpenters No. 2.5

14 Providing plywood ceiling with 3"x 2" ceiling


joists at 2' centers for 16'x 16' Sft. 256

Plywood Sft. 295


3"x 2" Scantlings Cft. 6.6
Nails Lbs 2
Wood screws Gross. 2

Carpenters No. 6.5

15 Providing 3plywood complete with 3"x1-1/2"


ceiling joists at 2' centers ( both ways ) and
2"x 1/2" beading for ( 16'x 16' ) Sft. 256

Plywood( 3 ply) Sft. 295 10%Wastage


3"x 1-1/2" Scantlings Cft. 10.35 Do
1/2"Beadings Cft. 2.3 Do
Nails Lbs. 3
Wood screws Gross. 2
Carpenters No. 7.5
4 Asbestos cement ceiling with 4"x 2" joists 100.000 Sft
at 2' centers for ( 16'x 16' ) Sft. 256

Beading 1-1/2"x 1/2" Cft. 0.96 0.375 Cft.


Joists 4"x 2" Cft. 8.8 3.438 Cft. 0.07625
1-1/2" wood screws no. 216 84.375 no.
Nails lbs. 1.5 0.586 lbs. 0.16276
Carpenters no. 7.5 2.930 no.

100 Sft
5 Asbestos sheet ceiling with 3"x 2" joists at
2' center and 1-1/2"x1/2" beadingSft. 256

A-C plain sheets Sft. 282 110.156 Sft.


3"x 2" joists Cft. 6.6 2.578 Cft. 0.059
1-1/2"x 1/2" beadings Cft. 0.96 0.375 Cft.
1-1/2" wood screws Gross. 1.5 0.586 no.
Nails lbs. 1.5 0.586 lbs.
Carpenters no. 6.5 2.539 no.

6 Asbestos sheet ceiling with 4"x 2" joist at


4' centers and 2"x 2" cross joists at 2' 100 Sft
centers complete with 1-1/2"x 1/2" Teak
beadings for 16'x 16' Sft. 256

A.C plain sheets Sft. 282 110.156 Sft. 6.884766


Joists 4"x 2" Cft. 4.89 1.910 Cft. 0.082
Joists 2"x 2" Cft. 4.6 1.797 Cft.
Teak beading 1-1/2"x 1/2" Cft. 0.96 0.375 Cft.
1-1/2" Wood screws Gross. 1.5 0.586 no.
Nails lbs. 1.5 0.586 lbs.
Carpenters no. 7.5 2.930 no.

14 Providing plywood ceiling with 3"x 2" ceiling


joists at 2' ce Sft. 256 1000.000
4 Asbestos cement ceiling with 4"x 2" joists 100.000 Sft
at 2' centers for ( 16'x 16' ) Sft. 256

Plywood Sft. 295 115.234 3.601074 Sht


3"x 2" Scantl Cft. 6.6 2.578 0.051563 Ton
Nails Lbs 2 0.781 0.217 Viss
Wood screws Gross. 2 0.781 0.781

Carpenters No. 6.5 2.539 2.539


ANALYSIS OF RATES ( Doors & Windows )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

1 1-1/2"Thick Teak panelled door 1st class


for 7'x 3-1/2' ( Double leaf ) Sft. 24.5

Styles 4x 7'x 4"x 1-1/2"


Top & Bottom rails 4x 1-5/6'x 4"x 1-1/2" Cft. 2.4 15% wastage
Lock rails 4x 1-5/6'x 8"x 1-1/2"
Panels 6x 1-5/6'x 1-1/4"x 1" Cft. 1.32 15% wastage
Nails & Glue L-s
Carpenters No. 5

2 1-1/2" Thick 1/3 panelled 2/3 glazed door,


1st class for 6-1/2'x 3-1/2' ( Double leaf ) Sft. 22.75

21 Oz sheet glass pane Sft. 11 50% wastage


Styles 4x 6-1/2'x 4"x 1-1/2"
Top & Bottom rails 4x 1-5/6'x 4"x 1-1/2" Cft. 1.95 15% wastage
Lock rails 2x 1-5/6'x 8"x 1-1/2"
Sash bars 2x 3-1/3'x 1-1/2"x 1-1/2"
Cft. 0.25 15% wastage
Sash bars 6x 1-1/4'x 1-1/2"x 1-1/2"
Panels 2x 1-1/3'x 2-1/6"x 1" Cft. 0.56 15% wastage
Nails & Glue Lbs 0.5
Carpenters No. 4.75

3 1-1/2" Thick Teak panelled door for 6'-9-1/2"


x 2'-10" single leaf Sft. 19.3

Styles 2x 6-7/8'x 4-1/2"x 1-1/2"


Top & middle rails 2x 2-7/8'x 4-1/2"x 1-1/2"
Cft. 1.79 15% wastage
Bottom & lock rails 2x 2-7/8'x 9"x 1-1/2"
Verticals rails 1x 2-1/2"x 4"x1-1/2"
Panels 2x 2-1/4'x 1-5/8"x 3/4"
Panels 1x 2-1/4'x 1'x 1/2" Cft. 0.59 15% wastage
Panels 1x 2-1/4'x 1-1/24'x 1/2"
Nails & Glue L-s
Carpenters No. 5

4 1-1/2" Thick Teak ledged and battened door


for 6-1/2'x 3' Sft. 19.5

Styles 4x 6-1/2'x 4"x 1-1/2"


Rails 4x 1-7/12'x 6"x 1-1/2" Cft. 1.93 15% wastage
Lock rails 2x 1-7/12'x 6"x 1-1/2"
T & G planking 40'x 4"x 1/2" Cft. 0.65 15% wastage
Nails & Glue L-s

Carpenters No. 3.5

5 Corrugated iron doors and windows for 7'x


3-1/2' double leaf Sft. 24.5
ANALYSIS OF RATES ( Doors & Windows )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

Corrugated iron 2x 7'x 1-3/4' Sht 2


Styles 4x 7-1/2'x 3-3/4"x 1-1/2"
Top & bottom rails 4x 1-1/2'x 3-3/4"x 1-1/2"
Cft. 2.26 15% wastage
Diagonal rails 4x 3-1/4'x 3-3/4"x 1-1/2"
Lock rails 2x 1-1/2'x 3-3/4"x 1-1/2"
Nails Lbs. 0.5

Carpenters No. 1.5

6 Single coarse mat doors and windows with


1" thick battens double leaf for 3'-1"x 7'-1/2" Sft. 21.71

Styles 4x 7'-1/2"x 3"x 1"


Top rails 2x 1'-6-1/2"x 3"x 1"
Bracings 6x 2-9"x 3"x 1" Cft. 1.44 15% wastage
Bottom rails 2x 1'-6-1/2"x 4"x 1"
Lock rails 2x2'x 1'-6-1/2"x 4"x 1"
Covering strips 1/2" ( 1/2 of above ) Cft. 0.72 15% wastage
Bamboo mats Sft. 21
Nails Lb. 0.5

Carpenters No. 1

7 Mat door double leaf 3'-1"x 7'-1/2" Sft. 21.71

Styles 4x 7-1/2'x 3"x 1"


Top rails 2x 1'-6-1/2"x 3"x 1"
Bracings 6x 2-9"x 3"x 1" Cft. 1.44 15% wastage
Bottom rails 2x 1'-6-1/2"x 4"x 1"
Lock rails 2x2'x 1'-6-1/2"x 4"x 1"
Covering strips 1/2" ( 1/2 of above ) Cft. 0.72 15% wastage
Double mats best quality Sft. 42
Nails Lb. 0.5

Carpenters No. 1

8 Mat window double leaf 3'-1"x 4'-1" Sft. 12.57

Styles 4x 4'-1"x 3"x 1"


Top and bottom rails 4x 1'-6-1/2"x 3"x 1"
Cft. 0.88 15% wastage
Lock rails 2x 1'-6-1/2"x 4"x 1"
Brace 4x 2'-6"x 3"x 1"
Covering strips 1/2" ( 1/2 of above ) Cft. 0.44 15% wastage
Double mats best quality Sft. 24
Nails Lb. 0.375
Carpenters No. 0.625

9 1-1/2" Thick Teak glazed window 1st class


4'x 3' ( Double leaf ) Sft. 12
ANALYSIS OF RATES ( Doors & Windows )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

21 Oz sheet window glass panes Sft. 9.05 50% wastage


Styles 4x 4'x 4"x 1-1/2"
Top & bottom rails 4x 1-1/2'x 4"x 1-1/2" Cft. 1.16 15% wastage
Sash bars 6x 1'x 1-1/2"x 1-1/2"
Nails and glue Lbs. 0.25

Carpenters No. 3

10 1-1/2" Thick Teak glazed fanlights supplied


and fixed complated and including 18 Oz
glass and glazing 5'-6"x 1'-8" Sft. 9.16

Teak scantling Cft. 0.69 15% wastage


Teak planks ( sash ) Cft. 0.08 15% wastage
Nails & glue L-s
Pivot hinges 2-1/4"x 7/8" brass pairs. 2
Safety catch brass self closhing No. 1
18 Oz glass sheet Sft. 7.72 50% wastage

Carpenters No. 2

11 1-1/2" Thick Teak movable venetain window


1st class double leaf 4' x 3' Sft. 12

Styles 4 x 4-1/2"x 4"x 1-1/2"


Top & bottom rails 4x 1-1/2'x 4"x 1-1/2" Cft. 1.76 15% wastage
Venetian flaps 40x 1-1/12'x 4"x 2"
Venetian rods 4,x 3-5/12'x 2"x 1" Cft. 0.22 15% wastage
Venetian beadings 4,x 3-7/12'x 1"x 1"
Cft. 0.17 15% wastage
Venetian bars 6,x 1-1/6'x 1"x 1"
Nails & glue Lbs. 0.5

Carpenters No. 6

12 1-1/2" Thick Teak panelled venetianed and


glazed door 7'-7-1/2"x 3'-7" double leaf Sft. 27.32

21 Oz. Sheet window glass panes Sft. 5.63 50% wastage


Styles 4x 7-2/3'x 4"x 1-1/2"
Top rails 2x 1-5/6'x 4-1/2"x 1-1/2"
Cft. 2.64 15% wastage
Middle rails 2x 1-5/6'x 4"x 1-1/2"
Bottom & lock rails 4x 1-5/6'x 9"x 1-1/2"
Panels 2x 1-3/4'x 1-2/3'x 3/4"
Sash bars 2x (1-5/8'+1-3/8' )x 1-1/2"x 1-1/4"
Sash beads 22'x 1/2"x 1/2"
Cft. 1.08 15% wastage
Venetian flaps 18x 1-1/3'x 4"x 1/2"
Venetian rods 4-1/2'x 2"x 1"
Venetian beadings 4,x 2-1/4'x 1"x 1"
Nails & glue Lbs. 0.5
ANALYSIS OF RATES ( Doors & Windows )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

Carpenters No. 8.5

13 1-1/2" Thick Teak venetianed and glazed


windows 5'-1"x 4'-1" ( double leaf ) Sft. 20.75

21 Oz. Sheet window glass panes Sft. 6.6 50% wastage


Styles 4x 5'-2"x 3-1/2"x 1-1/2"
Top rails 2x 2'-1"x 4-1/2"x 1-1/2"
Bottom rails 2x 2'-1"x 5"x 1-1/2"
Middle rails 2x 2'-1"x 4"x 1-1/2"
Sash bars 2x 3'-1-1/2"x 1-1/2"x 1-1/4" Cft. 2.6 15% wastage
Sash beads 2x 12'x 1/2"x 1/2"
Venetian flaps 20x 1-5/8'x 4"x 3/4"
Venetian rods 2, 2-1/2'x 2"x 3/4"
Venetian beadings 4,x 2-1/2'x 1"x 1"
Nails & glue L-s

Carpenters No. 7

14 Palisading door Pyingado or Engin 7'x 4' Sft. 28

Quartering 6x 2'x 5"x 3"


Palisading 8x 7'x 4"x 2" Cft. 4.92 10% wastage
Filling pieces for bolts 1x 2'x 4"x 2"
M.S bolts 6"x 1/2" No. 24

Carpenters No. 1.5

15 1" Thick Inn C.G.I doors and windows 32 G.


fixed complated with iron fitting 3'-6"x 7' Sft. 24.5 Double leaf.

Inn 1" plank Cft. 1.34 15% wastage


C.G.I sheets 32 G. 7' No. 2
Roofing nails Lb 0.5
4" butt hinges no. 6
6" Hook and eye no. 2
6" Tower bolts no. 2
6" Hasp and staple no. 1

Carpenters no. 1

16 1' Thick jungle wood battened doors and


windows fixed complete with iron fitting 19.5
6-1/2'x3'
Jungle wood 1"plank Cft. 1.22
15% wastage
J-W 1/2" T & G Cft. 0.61
Nails & glue L-s
4" butt hinges No. 6
6" Hook and eye No. 2
ANALYSIS OF RATES ( Doors & Windows )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
6" Tower bolts No. 2
6" Hasp and staple No. 1

Carpenters No. 4

17 Jungle wood Verandah gate with 3"x 1-1/2"


frame and 2"x 1/2" batten fixed complete
double leaf 4'x 3' Sft. 12

J-wood scantling Cft. 0.86 15% wastage


1/2" J-wood plank Cft. 0.28 15% wastage
1/16" hoop iron catch No. 1
4" butt hinges No. 4
Nails Lb 0.25

Carpenters No. 1

18 C.I door for garage with 5"x 2" frames and


bracings 8'x 8' ( double leaf ) Cft. 64

C.G.I sheet 8'x 10/3 No. 4


Styles, 4x 8'x 5"x 2"
Rails 6, 4'x 5"x 2" Cft. 6.23 15% wastage
Diagonals,4,5'-6"x 5"x 2"
Nails Lbs. 1.5

Carpenters No. 4

19 1-1/2" Thick X-P.M door or sq,mesh doors Sft. 17.88


( 2'-9"x 6'x 6" )
X.P.M or sq, mesh 1x 2'-6"x 6'-3" Sft. 17.19 10% wastage
Styles 2x 6'x 3"x 1-1/2"
Rails 3x 2'-9"x 3"x 1-1/2"
Cft. 1.02 15% wastage
Beadings 2x 6'-6"x 3"x 1/2"
Beadings 3x 2'-9"x 3"x 1/2"
Nails Lbs. 1

Carpenters No. 2.5

20 1" Thick panelled swing door ( double leaf )


( 3'-3"x 3' ) Sft. 9.75
Styles 4x 3'-9"x 3"x 1"
Cft. 0.5 15% wastage
Rails 4x 1'-6"x 3"x 1"

Carpenters No. 2

21 1-1/2" Thick panelled swing door ( double leaf ) 9.75


( 3'-3"x 3' )
Styles 4x 3'-9"x 3"x 1-1/2"
Cft. 0.75 15% wastage
Rails 4x 1'-6"x 3"x 1-1/2"
ANALYSIS OF RATES ( Doors & Windows )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Panels Sft. 10

Carpenters no. 2

22 1"Thick trellis door with 3"x 1" frame( single


leaf ) 2'-9"x 6'-3" Sft. 17.19

Styles 2x 6'-3"x 3"x 1"


Cft. 0.5 15% wastage
Rails 3x 2'-9"x 3"x 1"
Zallies 2x 6'-3"x 3"x 1/2"
Zallies 3x 2'-9"x 3"x 1/2" Cft. 1.07 Do
Diagonals 17.19/100x 600'x 2"x1/2"
Nails Lbs. 3

Carpenters No. 2

23 Trellies door 4"x 1-1/2" teak styles rails and


braces covered with including 2"x 1/2" teak
battens fixed complete 7'x 3' (double leaf ) Sft. 21

Teak scantling Cft. 1.92


15% wastage
Teak 1/2" plank Cft. 1.01
Nails & screws Lbs 0.5
4"Steel butt hinges No. 6
6"Hook and eye No. 2
6"Tower bolts No. 1
9"Tower bolts No. 1
4"Brass bow handle No. 1
6"Hasp and staples No. 1

Carpenters No. 3

24 Collapsable iron door with 3/4"x 3/8"


channels and 3/4"x 1/8" flats ( one leaf ) Sft. 28.69
( 4'-3"x 6'-9" )
3/4"x 3/8" Vertical channels
22x 6'-9" @ 0.532 lbs./Rft.
2"x 1" Bottom channel
1x 4'-9" @ 6.8 lbs./Rft.
3/4"x 1/8" Flatiron
3x 4x 1'-0 @ 0.314 lbs./Rft.
3x 18x 2'-0 @ 0.314 lbs./Rft. Lbs. 185.13 5% wastage
2"x 1/2" Flat iron top rails
1x 4'-9" @ 3.4 lbs./Rft.
3/4"x 1/2" Bottom guide rail
1x 4'-9" @ 1.28 lbs./Rft.
Flat iron for lock ring
1x 3'-0 x 2"x 1/4" @ 1.7 lbs./Rft.
Rivets 3/16" 2-1/2" No. 44
Rivets 1/4" 2-1/2" No. 33
ANALYSIS OF RATES ( Doors & Windows )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Rivets 1/4" 3/4" No. 10
3/8" steel pipe Rft. 5.5
1/4" M.S pin 1-1/2" long No. 66
3/4" Outside 1/16" washers No. 505
Door handle No. 2
Roller with pin, 1-3/4"x 1/2" bottom No. 2
Roller with pin, 2"x 1/2" top No. 3

Smiths no. 6
Workers no. 5

25 1"Thick flyproof door complate with flyproof


mesh double leaf 7'x 3' Sft. 21

Teak plank 3"x 1" Cft. 0.96


15% wastage
Teak beading 3"x 1/2" Cft. 0.48
Flyproof mesh Sft. 23 10% wastage
Nails Lbs. 0.25
Screws Gross. 0.25

Carpenters No. 3

26 1-1/2"Thick door with ply wood on one side


of teakstyles and rails ( 4' x 6'-6" ) Sft. 26

Teak 4"x 1-1/2" Styles and rails Cft. 2.01


15% wastage
Plywood Sft. 30
Wood screws Gross. 0.5

Carpenters No. 3.5

27 Providing Teak plywood ( 3 ply ) flush door


with 1-1/2"thick teak style and rails
including cost of and labour for fixing iron
fittings 7'x 3'x 2-1/2" Sft. 22.46

Teak scantling Cft. 2.04


15% wastage
Teak plywood ( 3 ply ) Sft. 54
Wood screws & nails L-s
4"Steel butt hinges No. 3
6"Hook and eye No. 1
6"Tower bolts No. 2
4"Brass bow handle No. 1

Carpenters No. 3.75

28 Teak doors and windows chowkets planed


and ond side rebated includiing fixing hold
fast, etc. Rft. 100
ANALYSIS OF RATES ( Doors & Windows )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
( A ) 3"x 3" Cft. 7.19 15% wastage
Nails Lbs. 2
Carpenters No. 4

( B ) 4"x 2" Cft. 6.39 15% wastage


Nails Lbs. 2
Carpenters No. 4

( C ) 4"x 3" Cft. 9.58 15% wastage


Nails Lbs. 2.5
Carpenters No. 6

( D ) 5"x 3" Cft. 11.98 15% wastage


Nails Lbs. 3
Carpenters No. 7

( E ) 6"x 3" Cft. 14.38 15% wastage


Nails Lbs. 3.5
Carpenters No. 7

( F ) 5"x 2" Cft. 8 15% wastage


Nails Lbs. 2
Carpenters No. 6

29 1-1/2" Thick teak flush door with 3"x 1"


frame and plywood on both sides including
cost of and labours for fixing iron fitting7'x 3'
single leaf. Sft. 21

Teak 3"x 1-1/2" ( rails and styles ) Cft. 0.72


15% wastage
3"x 1"Bracings Cft. 0.24
Plywood Sft. 42 7'x3' = 2 Nos
Wood screws Gross. 0.5

Carpenters No. 4.25

30 C.G.I Door with 1-1/2" 4"Teak styles and


rails and braces covered with 32 G. C.G.I
sheet size 7'x 3-1/2' double leaf. Sft. 24.5

Corr. Iron sheet 32 G. 7' No. 2


Teak scantling Cft. 2.01 15% wastage
Nails.etc. L-s
4"Steel butt hinges No. 6
6"Hook and eye No. 2
6"Tower bolts No. 2 6"- 1No & 9" - 1 No
4"door bow handle No. 1
6"Hasp and staple No. 1

Carpenters No. 2
ANALYSIS OF RATES ( Doors & Windows )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
31 C.G.I Windows of 1-1/2"x 4" Teak styles
rails and braces and covered with 32,G. C.
G.I Sheet shingle leaf ( 3-1/2'x 2-1/2' ) Sft. 8.75

Teak scantling Cft. 0.7 15% wastage


32,G. C.G.I sheet 7' No. 0.5
Screw and nails L-s
3"Steel butt hinges No. 4
6"Hook and eye No. 2
6"Tower bolts No. 1
4"Tower bolts 1
4"Brass bow handle No. 1

Carpenters No. 1

32 Teak swing door of 1-1/2" thick styles,rails


and braces including 1/2" P.T.G teak plank Sft. 10.5

Teak scantling Cft. 1.1


15% wastage
Teak 1/2" P.T.G Cft. 0.34
Nails & screws L-s
4" Spring hinges No. 4

Carpenters No. 1.75

33 Fixed louvres of 1/4" thick opaque glass


blades set in and including 5"x 2" wrought
teak frame and 1-1/2"x 1/2" teak beadings,
supplied and fixed complete side 5'x 2'-6" Sft. 12.5

Teak scantlings Cft. 1.4


15% wastage
Teak 1" planks Cft. 0.05
1/4" Thick opaque glass Sft. 17.5 50% wastage
Nails L-s

Carpenters no. 2
Glaziers no. 0.5

34 Fixing doors and windows of anydescription


including easing ( labour only ) side of door Sft. 21
7' x 3'

Carpenters no. 0.5


26 1-1/2"Thick door with ply wood on one side
of teakstyles and rails Sft. 26

Teak 4"x 1-1/2" Styles Ton 0.0402


Plywood Sft. 30
Wood screws Gross. 0.5

3.72 Carpenters No. 3.5

27 Providing Teak plywood ( 3 ply ) flush door


with 1-1/2"thick teak style and rails
including cost of and labour for fixing iron
fittings 7'x 3'x 2-1/2" Sft. 22.46

Teak scantling Cft. 2.04


Teak plywood ( 3 ply Sft. 54
Wood screws & nails L-s
4"Steel butt hinges No. 3
6"Hook and eye No. 1
6"Tower bolts No. 2
4"Brass bow handle No. 1

Carpenters No. 3.75

2.38
26 1-1/2"Thick door with ply wood on one side
of teakstyles and rails Sft. 26

1.16

0.77

3.72
26 1-1/2"Thick door with ply wood on one side
of teakstyles and rails Sft. 26

1-1/2" Thick panelled swing door 9.75 Sft.


( 3'-3"x 3' ) 4258 327.5385
Styles 4x 3'-9"x 3"x 1-1/2"" Cft. 0.75 Cft.
Rails 4x 1'-6"x 3"x 1-1/2"
Panels Sft. 10 Sft. 4367.179
26 1-1/2"Thick door with ply wood on one side
of teakstyles and rails Sft. 26

Carpenters no. 2 no.


26 1-1/2"Thick door with ply wood on one side
of teakstyles and rails Sft. 26

#REF! #REF! #REF!

100

0.4314 3472 14.97821


3.5 121.52

7 #REF!
#REF!
3.6
Weight of Rond & Square M.S Rods.
or Sides in inches Round(Lb) Square (Lb)
" (6.5 mm- 8 mm) 0.167 0.213
" (10 mm) 0.376 0.478
" (12 mm) 0.668 0.849
" (16 mm) 1.043 1.328
" (18 mm- 20 mm) 1.502 1.912
" ( 22 mm) 2.044 2.603
1" (25.4 mm) 2.67 3.4
1" 4.172 5.312
1" 6.008 7.65
ANALYSIS OF RATES ( Painting & Washing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

1 Coal tarring one coat ( new work ). Sft. 100

Coal tar Gal. 0.25

Workers No. 0.375


Sundries including brushes,fuel,etc. L-s

2 Coal tarring two coats ( new work ). Sft. 100

Coal tar Gal. 1.25

Workers No. 0.75


Sundries including brushes,fuel,etc. L-s

3 Oiling with boiled linseed oil. Sft. 100

Linseed oil,Boiled Gal. 0.25

Workers No. 0.25


Sundries including brushes,etc. L-s

4 Oiling with boiled linseed oil. ( Two coats ) Sft. 100

Linseed oil,Boiled Gal. 0.4375

Workers No. 0.5


Sundries including brushes,etc. L-s

5 Earth oiling to roof with red ochre. Sft. 100

Red ochre Lbs. 1.5


Earth oil Gal. 0.5

Workers No. 0.375


Sundries including brushes,etc. L-s

6 Earth oiling with 5% coal tar. Sft. 100

Coal tar Lbs. 0.175


Earth oil Gal. 0.35
ANALYSIS OF RATES ( Painting & Washing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Workers No. 0.375
Sundries including brushes,etc. L-s

7 Earth oiling plain one coat. Sft. 100

Earth oil Gal. 0.35

Workers No. 0.375


Sundries including brushes,etc. L-s

8 Earth oiling plain two coat. Sft. 100


Earth oil Gal. 0.6

Workers No. 0.625


Sundries including brushes,etc. L-s

9 Distemper one coat. Sft. 100

Distemper Lbs. 3

Painters No. 0.25


Workers No. 0.125
Sundries including brushes,etc. L-s

10 Distemper two coats. Sft. 100

Distemper Lbs. 5

Painters No. 0.375


Workers No. 0.25
Sundries including brushes,etc. L-s

11 Distemper three coats. Sft. 100

Distemper Lbs. 7

Painters No. 0.5


Workers No. 0.375
Sundries including brushes,etc. L-s

12 Painting with solignum one coat. Sft. 100


ANALYSIS OF RATES ( Painting & Washing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Solignum Gal. 0.375

Painters No. 0.375


Sundries including brushes,etc. L-s

13 Painting with solignum two coats. Sft. 100

Solignum Gal. 0.625

Painters No. 0.625


Sundries including brushes,etc. L-s

14 White washing one coat. Sft. 100


* Use liquid
Straine lime Cft. 0.5 glue instead
Rice* Lbs. 0.125 rice.

Workers No. 0.125


Sundries including brushes,etc. L-s

15 White washing two coats. Sft. 100


* Use liquid
Straine lime Cft. 0.75 glue instead
Rice* Lbs. 0.25 rice.

Workers No. 0.25


Sundries including brushes,etc. L-s

16 White washing three coats. Sft. 100

Strained lime Cft. 1


Rice* Lbs. 0.375 * Use liquid of
glue instead
Workers No. 0.375 rice.
Sundries including brushes,etc. L-s

17 Colour washing one coat. Sft. 100

Strained lime Cft. 0.5


Yellow powder Lbs. 0.125
Liquid glue Lbs. 0.125
ANALYSIS OF RATES ( Painting & Washing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Painters No. 0.125

18 Colour washing two coats. Sft. 100

Strained lime Cft. 0.75


Yellow powder Lbs. 0.25
Liquid glue Lbs. 0.25

Painters No. 0.25

19 Colour washing three coats. Sft. 100

Strained lime Cft. 1


Yellow powder Lbs. 0.375
Liquid glue Lbs. 0.375

Painters No. 0.375

20 Cement washing one coat. Sft. 100

Cement 1.73 Cft Lbs. 156

Maistry No. 1
Workers No. 2
Sundries including brushes,etc. L-s

21 White lead painting three coats including Sft. 900


priming coat puttying.

priming coat ( inside )


Read lead Lbs. 1.5
White lead Lbs. 16
Raw linseed oil Pint. 6
Turpentine Pint. 0.25
Drier Lbs. 0.125
Putty Lbs. 2
Second coat
White lead Lbs. 15 Allow extra for
Raw linseed oil Pint. 3.5 works to be carried
Turpentine Pint. 1.5 out in the 2nd &
Drier Lbs. 0.5 3rd storeys.
Third coat.
ANALYSIS OF RATES ( Painting & Washing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
White lead Lbs. 15
Raw linseed oil Pint. 3.5
Turpentine Pint. 1.5
Drier Lbs. 0.25
Pinters No. 10
Workers No. 18
Sundries including brushes L-s

22 Painting one coat with red lead ready mixed


( new works ). Sft. 1000

* Red lead paint ( ready mixed ) Lbs. 30 *For renewal 20lb


Putty Lbs. 4 only.

Pinters No. 2.5


Workers No. 2.5
Sundries including brushes L-s

23 Painting one coat with white zinc in renewal Sft. 100

White zinc paint Lbs. 2


Drier Lbs. 0.015
Linseed oil Pint. 0.25
Turpentine Pint. 0.007
Putty Lbs. 0.5

Painters No. 1
Workers No. 1
Sundries including brushes L-s

24 Painting two coat with white zinc in renewal Sft. 100

White zinc paint Lbs. 3.5


Drier Lbs. 0.03
Linseed oil Pint. 0.5
Turpentine Pint. 0.014
Putty Lbs. 0.5

Painters No. 2
Workers No. 2
Sundries including brushes L-s
ANALYSIS OF RATES ( Painting & Washing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
25 Painting three coats with white zinc ready Sft. 1000
mixed.
Priming coat red lead Lbs. 30
White zinc paint for 2nd & 3rd coats Lbs. 45
Putty Lbs. 4

Painters No. 10
Workers No. 10
Sundries including brushes L-s

26 Painting two coats with white zinc ready


mixed ( Renewal ). Sft. 1000

White zinc ready mixed for two coats Lbs. 48


Putty Lbs. 2

Painters No. 5
Workers No. 5
Sundries including brushes L-s

27 Painting one coat with white zinc ready


mixed ( Renewal ). Sft. 1000

White zinc ready mixed Lbs. 28


Putty Lbs. 2

Painters No. 2.5


Workers No. 2.5
Sundries including brushes L-s

28 Painting two coats with white zinc (New


work). Sft. 1000

White zinc ready mixed for two coats Lbs. 55


Putty Lbs. 2

Painters No. 5
Workers No. 5
Sundries including brushes L-s

29 Painting one coat in renewal any paint


ready mixed red oxide, corrugal, chocolate,
ANALYSIS OF RATES ( Painting & Washing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
green, black,etc. Sft. 1000

Ready mixed paint Lbs. 20


Putty Lbs. 2

Painters No. 2.5


Workers No. 2.5
Sundries including brushes L-s

30 Painting two coats in renewal any paint


ready mixed red oxide, corrugal, chocolate,
green, black,etc. Sft. 1000

Ready mixed paint Lbs. 50


Putty Lbs. 2

Painters No. 5
Workers No. 5
Sundries including brushes L-s

31 Painting ripolin enamel ready mixed one


coat. Sft. 1000

Ripolin enamel paint Gal. 1.667

Painters No. 2.5


Workers No. 2.5
Sundries including brushes L-s

32 Painting three coats ( new work ) with ready


mixed paint of any approved colour. Sft. 1000

Ready mixed paint Lbs. 75


Putty Lbs. 4

Painters No. 10
Workers No. 10
Sundries including brushes L-s

33 Painting three coats to wood work in posts,


chowkets, facia boards, eaves boards and
stringers. Sft. 1000
ANALYSIS OF RATES ( Painting & Washing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

Ready mixed paint Lbs. 75


Putty Lbs. 4

Painters No. 12.5


Workers No. 10

34 Painting iron work with collins mixture one


coats. Sft. 225

Coal taer Gal. 1


Cement 1/50 Cft. Lbs. 1.8
Kerosene oil Gal. 0.125
Fire wood L-s

Painters No. 0.5


Workers No. 0.5
Sundries including brushes L-s

35 Painting with bitumastic solution one coat. Sft. 100

Bitumastc solution ready mixed Gal. 0.25

Workers No. 0.5


Sundries includng brushes L-s

36 Varnishing ( copal ) one coat. Sft. 100

Copal varnish Gal. 0.25

Painters No. 0.375


Sundries includng brushes L-s

37 Varnishing ( copal ) two coats. Sft. 100

Copal varnish Gal. 0.5

Painters No. 0.5


Sundries includng brushes L-s

38 Varnishing ( copal ) three coats. Sft. 100


ANALYSIS OF RATES ( Painting & Washing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Copal varnish Gal. 0.625

Painters No. 0.75


Sundries includng brushes L-s

39 Wood oiling one coat. Sft. 100

Wood oil Lbs. 2

Workers No. 0.5


Sundries including brushes L-s

40 Wood oiling two coats. Sft. 100

Wood oil Lbs. 3

Workers No. 0.75


Sundries including brushes L-s

41 Bee's waxing. Sft. 100

Bee wax Lbs. 0.25

Painters No. 0.125


Sundries including labour for wood No. 1
Dust topping cloth L-s

42 Removing old paint entirely with caustic


soda. Sft. 100

Caustic soda Lbs. 3


Paint remover brushes L-s

Carpenters* No. 0.25 * For Taking down


Painters No. 0.5 and rehanging
Workers No. 0.25 doors & windows.

43 Snowcem one coat. Sft. 100

Snowcem Lbs. 3.5

Painters No. 0.25


ANALYSIS OF RATES ( Painting & Washing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Workers No. 0.125

44 Snowcem two coats. Sft. 100

Snowcem Lbs. 6

Painters No. 0.375


Workers No. 0.25

45 Plastic emulsion paint one coat. Sft. 100

Emulsion paint Gal. 0.2

Painters No. 0.25

46 Plastic emulsion paint two coats. Sft. 100

Emulsion paint Gal. 0.333

Painters No. 0.25

47 Plastic emulsion paint three coats. Sft. 100

Emulsion paint Gal. 0.5

Painters No. 0.75

48 Bengal polishing three coats to wooden wall Sft. 100

Methylated spirit Gal. 1.25


Shellac Lbs. 1.25
Sand paper, cotton waste, etc L-s

Polishers No. 7

49 Bengal polishing three coats to wooden


furniture. Sft. 100

Methylated spirit Gal. 1.375


Shellac Lbs. 1.375
Sand paper, cotton waste, etc L-s
ANALYSIS OF RATES ( Painting & Washing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Polishers No. 10.5 windows.
25 Painting three coats with white zinc
Sft. 1000 1000.000 Sft

Priming coat red lead lbs. 300 300.000 lbs.


White zinc paint for 2nd & lbs. 45 45.000 lbs.
Putty lbs. 4 4.000 lbs.

Painters no. 10 10.000 no.


Workers no. 10 10.000 no.
Sundries including brushesL-s

32 Painting three coats ( new work ) with ready


mixed paint of any approved colour.
Sft. 1000 6923.000 Sft

Ready mixed paint lbs. 75 519.225 lbs.


Putty lbs. 4 27.692 lbs.

Painters no. 10 69.230 no.


Workers no. 10 69.230 no.
Sundries including brushesL-s

46 Plastic emulsion paint two coats.


Sft. 100 1000.000 Sft

Emulsion paint Gal. 0.333 3.333 Gal.

Painters no. 0.25 2.500 no.

47 Plastic emulsion paint three coats.


Sft. 100 1000.000 Sft

Emulsion paint Gal. 0.5 5.000 Gal.

Painters no. 0.75 7.500 no.


25 Painting three coats with white zinc
Sft. 1000 1000.000 Sft

1.25
ANALYSIS OF RATES ( Roofing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

1 Danyingon ( mangalore pattern ) clay tile


roofing with 2"x 1" battens and 4"x 2"
common rafters. Sft. 100

Mangalore pattern clay tiles No. 156 20%Wastage


2"x 1"Battens at 13" centres Cft. 1.76 15%Wastage
4"x 2"Common rafters 2' centers Cft. 3.42 10%Wastage
Wire nails & spikes Lbs. 2
Binding wire L-s

Carpenters No. 2
Workers No. 2

2 Danyingon ( mangalore pattern ) clay tile


roofing with 2"x 1" close battens and 4"x 2"
common rafters. Sft. 100

Manglore or marseilles tiles No. 156 20%Wastage


2"x 1"Close battens Cft. 9.58 15%Wastage
1"x 1"Ordinary batterns above Cft. 1.32 15%Wastage
close above
4"x 2"Common rafters 2'centers Cft. 3.42 10%Wastage
Wire nails & spikes Lbs. 5

Carpenters No. 3
Workers No. 3

3 Danyingon ( mangalore pattern ) clay tile


roofing with 2"x 1" battens but without rafter. Sft. 100

Manglore or marseilles tiles No. 156 20%Wastage


2"x 1"Battens at 13" centres Cft. 1.76 15%Wastage
Wire nails & spikes Lbs. 1.5
Binding wire Lbs. 0.5

Carpenters No. 1.5


Workers No. 2

4 Danyingon ( mangalore pattern ) clay tile


roofing without frames. Sft. 100

Mangalore tiles No. 156 20%Wastage


Wire nails & spikes Lbs. 1.5
Binding wire Lbs. 0.5

Carpenters No. 1.25


Workers No. 1.5

5 Galvd. C.I.roofing 24 or 30 B.W.G 7'x10/3 Sft. 100

Galvd.C.I.sheet 7'x 10/3 No. 7


G.I.roofing nails Lbs. 1.5
ANALYSIS OF RATES ( Roofing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

Carpenters No. 1.5


Workers No. 1

6 Galvd.C.I.roofing laind on 1" planking Sft. 100

Galvd.C.I.sheet 7'x 10/3 No. 7


G.I.roofing nails Lbs. 1.5
1"Thick planking Cft. 9.58 15%Wastage
Nails Lbs. 2

Carpenters No. 3
Workers No. 1

7 Roofing of 32 G. C.G.I sheets supplied and


fixed. Sft. 100

32 G. C.G.I sheets No. 9 15%wegs


G.I roofing nails Lbs. 1.5

Carpenters No. 1.5


Workers No. 1

8 Wind ties for corrugated iron roofing Sft. 100

Flat iron 1"x "with nessary bolts hole Lbs. 128


3/8"Hook bolts 12" long with heads & nuts No. 25

Carpenters No. 1
Smith No. 3
Workers No. 1

9 Teak shingle roofing with 2"x 1" battens and


3"x 2" common rafters at 2' centers. Sft. 100

Teak shingles 15"x 5" No. 600 15%Wastage


2"x 1"Battens at 5"centers Cft. 4 10%Wastage
3"x 2"Common rafters 2' centers Cft. 2.52
Nails & spikes Lbs. 5
Earth oil Gal. 4
Fuel L-s

Carpenters No. 2.5


Workers No. 4

10 Teak shingle roofing with 2"x1"close batten Sft. 100

Teak shingles 15"x 5" No. 600


2"x 1"Battens Cft. 9.58 15%Wastage
Nails & spikes Lbs. 9
Earth oil Gal. 4
Fuel L-s

Carpenters No. 3
ANALYSIS OF RATES ( Roofing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Workers No. 4

11 Thatch roofing with bamboo rafters & purlins Sft. 100

Bamboo rafters 9"centers 10' long No. 14


Bamboo purlins 18"centers 10' long No. 7
Bamboo small size for lattice work 10' long No. 20
Thatch ( 6 no.to 1' ) No. 120
Cane ties L-s

Thatch layers No. 1


Workers No. 1

12 Wagat roofing with bamboo rafters & purlins Sft. 100

Bamboo rafters 2'centers 10' long No. 6


Bamboo purlins 18"centers 10' long No. 7
Bamboo small size for lattice work 10' long No. 20
Wagat ( 6 no.to 1' ) No. 120
Cane ties L-s
Earth oil Gal. 1
Fuel L-s

Wagat layers No. 1


Workers No. 1.25

13 Wagat roofing with bamboo common rafters


1' centers and whole wind ties complete. Sft. 100

1" to 2" Bamboo No. 20 * Wind ties at


Hnee ( fine bamboo ) Viss. 1 2' centers
Wagat ( 6 no. to 1' ) No. 120
Binding wire Lbs. 0.25
Earth oil Gal. 1
Fuel L-s

Wagat layer No. 1


Workers No. 1.25

14 Wagat roofing with 2"x 1" rafters 1' centers


and bamboo wind ties fixed at 2' centers
complete including earth oiling 2 coats to
timber & impregnating wagat with earth oil Sft. 100

2"x 1"Common rafters Cft. 1.75


1" to 2" Bamboo No. 8
Wagat ( 6 no. to 1' ) No. 120
Nails Lbs. 1
Binding wire Lbs. 0.25
Earth oil Gal. 1.333
Fuel L-s
ANALYSIS OF RATES ( Roofing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

Wagat layer No. 1


Carpenters No. 0.333
Workers No. 1.25

15 Dhani, Thetke or Thatch roofing laid 6 byits


to 1' with 6" side laps and including 1"
bamboo common rafters at 12" centers and
including a covering of bamboo lattice frame
and 1" wind ties at 4' centers Sft. 100

1" Bamboo rafters at 12" centers No. 11


1" Bamboo for lattice and wind ties No. 15
Dhani, Thetke or Thatch ( 6 no.to 1' ) No. 120
Hnee Viss. 1
G.I binding wire Lbs. 0.5

Dhani or Thetke layers No. 1


Workers No. 1

16 Corrugated A.C sheet roofing with 1/4"


hook bolts and washers. Sft. 100

Trafford or corrugated A.C sheet 7' long No. 5 * Tilex 10no.


Hook bolts and washers Lbs. 5 (30"x5') *burdex
15 no. 22"x 5'
Carpenters No. 2
Workers No. 1

17 Galvd iron ridge and hip covers with 6" lap. Rft. 7.5 When G.I ridg-
ing & hip cove-
Galvd iron ridge with G.I screws Rft. 8 ring is to be
used for A-C
Carpenters No. 0.25 sheet roofing
allow 1 more
18 Ridging of G.I plain sheet 24" girth with 9" carpentes for
end laps fixed complete. Rft. 100 every 7'.

G.I plain sheet Rft. 112


G.I roofing nails & washers Lbs. 1.5

Carpenters No. 3.333

19 No 24G.GI plain sheet ridging 2'-6" girth 3"


roll 9" end laps complete. Rft. 100

7' G.I plain sheet 24 G. Rft. 112


G.I roofing nails with washers Lbs. 1.5
Carpenters No. 3.333
20 Danyingon ( mangalore pattern ) clay ties
ANALYSIS OF RATES ( Roofing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
ridge and hip covering set in cement
mortar 1:2 Rft. 100

Mangalore or marseilles ridge tiles No. 90


Cement mortar Cft. 2

Masons No. 2
Workers No. 2

21 Wooden ridge and hip covers. Rft. 100

Ridge roll 1x 10'x 4"x 3" Cft. 0.92 10%Wastage


Boards 2x 10'x 9"x 1" Cft. 1.44 15%Wastage
Nails Lbs. 0.25

Carpenters No. 0.25

22 20 B.W.G. 8'x 3' Zinc valley guttering 3'


wide laid on 12" x 1" planks & 2"x 1"fillets. Rft. 22

20.B.W.G 8'x 3' zinc sheet 9" lap Sht. 3


Planks 2x 25'x 2"x 1" Cft. 4.79 15%Wastage
Fillets 2x 23'x 2"x 1" Cft. 0.73 Do
Nails Lbs. 0.5

Carpenters No. 1.5

23 G.I valley guttering 3' wide without planks. Rft. 22.5

G.I plain sheets Sft. 72


Nails Lbs. 0.25

Carpenters No. 1

24 Valley gutter with G.I plain sheet 36" girth


with 9" end laps, supported on 1" valley
boards and 2"x 1" fillets including earth
oiling 2 coats. Rft. 22.5

G.I plain sheet Rft. 24 15%Wastage


Planks 6"x 1" Cft. 6.47 Do
Fillets 2"x 1" Cft. 0.73
Earth oil Gal. 0.5
Nails Lbs. 0.75

Carpenters No. 1.75


Workers No. 0.25

25 Valley gutter of 32 G. G.I plain sheet 24"


girth with 9" end laps on 1/2" thick valley
ANALYSIS OF RATES ( Roofing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
boards fixed complete with 2"x 1" fillets
including earth oiling 2 coats. Rft. 100

G.I plain sheet Rft. 112


Plank 6"x 1/2" Cft. 9.58 15%Wastage
Fillets 2"x 1" Cft. 3.19 Do
Nails Lbs. 2.5
Earth oil Gal. 1.5

Carpenters No. 5
Workers No. 1.5

26 5 lbs.per set flashing 18" wide for 150 set. Rft. 100

7' x 3' Lead sheet 5 lbs./Sft. Sht. 9


Composite motar Cft. 2.5

Masons No. 2
Smiths No. 2
Workers No. 4

27 Lead flashing 18" wide. Rft. 100

Lead sheet ( 7' x 3' ) Sht. 9


Cement Lb 75
Sand Cft 2.5

Masons No. 2
Tin smiths No. 2
Workers No. 4

28 5 lbs.per.Sft. Lead flashing 20" wide for


( 167 Sft. ) Rft. 100

5 lbs./Sft. Lead sheet Sft. 189


Cement motar ( 1: 3 ) Cft. 2.5

Masons No. 2
Smiths No. 2
Workers No. 4

29 G.I plain sheet flashing 18" witdh. Rft. 100

G.I Plain sheet 7' x 3' Sht. 8


Cement Lbs. 75
Sand Cft. 2.5

Masons No. 2
Smiths No. 2
Workers No. 4
30 Zinc flashing 18" wide with 6" lap. Rft. 13.5
ANALYSIS OF RATES ( Roofing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

Zinc sheet 7' x 3' No. 1


Nails & screws Lbs. 1

Carpenters No. 1

31 G.I / C.I Ring water pipe. Rft. 100

G.I / C.I Pipe Rft. 100


Offsets and bends L-s

Plumbers No. 3
Mate No. 3

32 Corrugated A.C or Trafford ridging with 1/4"


hook bolts and nuts and washers. Sft. 100

A.C Ridging tile No. 66


1/4" Bolts & nuts and washers Lbs. 22 *To be included
only if the ridging
Carpenters No. 3.33 is carried out
Workers No. 1 separately

33 Diamond shape cement tile roofing with 2"x Note: To cover


1" battens but without rafters. Sft, 100 edges the following
are available.
Diamond shape tile No. 220 1.Horizontal Top
Half-Tile.
2"x 1"Battens at 6" centers Cft. 3.52 2.Horizontal bottom
Half-Tile.
Wire nails Lbs. 3 3.R.H.S Half-Tile.

Carpenters No. 2 4.L.H.S Half-Tile.


Workers No. 2

34 Cement tile ridging for diamond shape Note: To cover


cement tile roofing, set in cement motar 1:2 Rft. 100 ends the following
are available.
Cement tile ridge piece No. 74 1.R.H.S end ridge
Cement motar Cft. 2 piece and
2.L.H.S end ridge
Masons No. 2 piece
Workers No. 2
7 Roofing of 32 G. C.G.I sheets supplied and
fixed. Sft. 100 1000

32 G. C.G.I sheets no. 9 11.5 Sft 15%wegs


G.I roofing nails lbs. 1.5 15 lbs.

Carpenters no. 1.5 15 no.


Workers no. 1 10 no.

17 Galvd iron ridge and hip covers with 6" lap.


Rft. 100 1000

Galvd iron ridge with G.I screws Rft. 8 80 Rft.

Carpenters no. 0.25 2.5 no.


7 Roofing of 32 G. C.G.I sheets supplied and
ANALYSIS OF RATES ( Walling )

9/27/2017 11:30
No. Particular Unit
QuantityRate PerAmount Remark

1 1/2"Thick teak or pyingado T & G plank Reinforceme


walling without frames. Sft. 100

T & G plank 4" x 1/2" Cft. 5.29 15% Wastage


Nails Lbs. 2

Carpenters No. 2

2 6"x 1/2" Weather boarded walling without


frames. Sft. 100

6"x 1/2"Planks allowing 1" Cft. 6.48 15% Wastage


Vertical strips 1"x 3" Cft. 0.72
Nails Lbs. 1

Carpenters No. 2.5

3 1/2"Butt jointed plank walling without frame


but with 2"x 1/2" splines. Sft. 100

6"x 1/2"Planks 200'


2"x 1/2" Planks 200' Cft. 6.39 15% Wastage
Nails Lbs. 2

Carpenters No. 2.5

4 Trellis work 2" mesh with 2"x 1/2" batting &


zallies without frames. Sft. 100

Filling pieces 20'x 2"x 1/2"


Zallies 40'x 2"x 1/2" Cft. 5.27 15% Wastage
Diagonals 600'x 2"x 1/2"
Nails & spikes Lbs. 6

Carpenters No. 2

5 Galvanized C.I sheet 8/3 corrugation walling


4" lap without frames. Sft. 100

Gal. C.I sheet 8/3 corrugationNo. 9


G.I roofing nails with washerLbs. 1.5
ANALYSIS OF RATES ( Walling )

9/27/2017 11:30
No. Particular Unit
QuantityRate PerAmount Remark

Carpenters No. 0.75


Workers No. 0.5

6 Galvanized C.I sheet walling 4" lap


without frames. Sft. 100

Gal. C.I sheet 10/3 corrugatioNo. 6


G.I roofing nails with washerLbs. 1.5
Carpenters No. 0.75
Workers No. 0.5

7 3"Thick reinforced brick wall in cement


mortar 1:3 reinforced at everySft.
3rd course.
100

Reinforcement ( X-met 2-1/2"Rft. 105


Bricks 9"x 4-3/8"x 2-3/4" No. 350
Cement Lbs. 118
Sand Cft. 4

Masons No. 1.5


Workers No. 2

8 4"Thick reinforced brick wall in cement


mortar 1:3 reinforced at every
Sft.
4th course.
100

Reinforcement ( X-met 2" wRft. 115


Bricks 9"x 4-3/8"x 2-3/4" No. 550
Cement Lbs. 297
Sand Cft. 10

Masons No. 2
Workers No. 3

8(a) 4"Thick reinforced brick wall in cement


mortar 1:3 with 6"x 3" frameSft. 100

Reinforcement ( X-met 2" wRft. 115


Bricks 9"x 4-3/8"x 2-3/4" No. 550
Cement Lbs. 297
Sand Cft. 10
Frames 4x 10'x 6"x 3" Cft. 5.5 10% Wastage
ANALYSIS OF RATES ( Walling )

9/27/2017 11:30
No. Particular UnitQuantityRate PerAmount Remark
Beadings 3/4"x 3/4"x 4x 4x 1Cft. 0.81 15% Wastage
Screws Gross. 0.75
Coal tar Lbs. 1
Nails & spikes Lbs. 1

Masons No. 2
Carpenters No. 1.25
Workers No. 3

9 3"Thick reinforced brick wall in cement


mortar 1:2 reinforced at everySft.
3rd course.
100

Reinforcement ( X-met 2" wRft. 105


Bricks 9"x 4-3/8"x 2-3/4" No. 350
Cement mortar ( 1:2 ) Cft. 4

Masons No. 1.5


Workers No. 2
10 4-1/2"Thick reinforced brick wall in lime mo-
rtar 1:1:1 and with reinforcement at every
4th course set in cement mortar
Sft.1:2100

Reinforcement ( X-met 2-1/2"Rft. 115


Bricks 9"x 4-3/8"x 2-3/4" No. 550
Lime mortar ( 1:2 ) Cft. 7.5
Cement mortar ( 1:1:1 ) Cft. 2.5

Masons No. 2
Workers No. 3

11 Palisading walling for prisoners cage inclu-


ding rivets. Sft. 100

3/8" rivets 6-1/2" long No. 88


Frames 4x 10'x 5"x 4"
Verticles 20x 10'x 4"x 2" Cft. 18.34 10% Wastage

Carpenters No. 3

12 1" Thick expaned metal lath ( No.26 )


walling in cement mortar 1:2Sft. 100
ANALYSIS OF RATES ( Walling )

9/27/2017 11:30
No. Particular UnitQuantityRate PerAmount Remark
Expaned metal lathing ( No. Sft. 110 10% Wastage
Cement mortar Cft. 12

Masons No. 2
Workers No. 2

13 X.P.M or square mesh walling without frame


but with 2"x 1/2"covering strips and secured
with screws. Sft. 100

X.P.M or sq,mesh Sft. 110 10% Wastage


Covering strips 8x 10'x 2"x 1Cft. 0.64 15% Wastage
Scerws Gross. 0.5
Nails Lbs. 1

Carpenters No. 1

14 1/4"Thick 2" sq.mesh walling with and


including 2"x 1/2" teak wrought beading and
including 4"x 2" teak wroughSft. 100

2"sq.mesh 2"x 2"x 7 S.W.G Sft. 110 10% Wastage


2"x 1/2" Teak beadings Cft. 0.48 15% Wastage
Teak wall frames Cft. 3.7 10% Wastage
Nails & wood screws Lbs. 1.5

Carpenters No. 2
15 Squre mesh window guard with and
including 2"x 1/2" thick teak Sft. 25.18

2" Squre mesh 2"x 2"x 3/16 Sft. 27.7 10% Wastage
2"x 1/2" Teak beading Cft. 0.2 15% Wastage
Nails & wood screws L-s

Carpenters No. 0.625

16 1/2"Mesh galved iron wire netting with


battens and zallies. Sft. 100

1/2"Mesh galved wire nettingRft. 42


Battens, horizontal 1x 80'x 2
Battens verticals 24x 1-1/4"x
Cft. 3.28 15% Wastage
ANALYSIS OF RATES ( Walling )

9/27/2017 11:30
No. Particular UnitQuantityRate PerAmount Remark
Covering strips 2x 80'x 2'x 1 Cft. 3.28 15% Wastage
Covering strips 24x 1-1/4'x 2
Nails Lbs. 1

Carpenters No. 1.5

17 Flyproof mesh fixed with 2"x 1' teak fillets


and 1-1/2"x 1/2" teak beadinSft. 100

1"Teak beadings Cft. 0.72 15% Wastage


2"x 1"Teak fillets Cft. 1.92 Do
Flyproof mesh ( wire ) Sft. 110
Nails Lbs. 1

Carpenters No. 1.5

18 Bird proof wire mesh fixed with 2"x 1"teak


fillets & 1"x1/2"teak beadi Sft. 100

1/2"Teak planks Cft. 0.72 15% Wastage


1"Teak planks Cft. 1.92 15% Wastage
Bird proof mesh ( wire ) Sft. 110
Nails Lbs. 1

Carpenters No. 2.5

19 4"x 1/2"Fixed venetian walling with 4"x 2"


Frames. Sft. 100

Frames 7x 10'x 4"x 2" Cft. 4.28 15% Wastage


Venetian 74x 10'x 4"x 1/2" Cft. 11.82 15% Wastage
Nails Lbs. 1

Carpenters No. 16

20 4"x 1/2"Movable venetian walling with 4"x 2"


frames. Sft. 100

Frames 7x 10'x 4"x 2" Cft. 4.28 10% Wastage


Venetian flaps 74x 10'x 4"x 1Cft. 11.82 15% Wastage
Venetian bars Cft. 1.28 15% Wastage
Venetian hooks No. 150
ANALYSIS OF RATES ( Walling )

9/27/2017 11:30
No. Particular Unit
QuantityRate PerAmount Remark

Carpentares No. 19

21 Asbestos sheet walling without frames but


with 1"x 1/2" moulded beadings
complete with screws on fra Sft. 144

Asbestos sheet Sft. 158 10% Wastage


Beading 1-1/2"x 1/2"x 110' Cft. 0.66 15% Wastage
Nails Lbs. 0.25
Screws No. 104

Carpenters No. 1
Workers No. 2

22 Single rough bamboo mat walling without


frames but with 3"x1/2" cover
Sft. 100

Covering strips, 4x 10'x 3"x Cft. 0.48 15% Wastage


Banboo mat Sft. 115
Nails Lbs. 1.5

Carpenters No. 1

23 Double bamboo mat wall ( coarse outside


and fine inside ) with 2"x 1/2" zallies but
without frames. Sft. 100

1/2"Planks Cft. 0.32 15% Wastage


Mat ( coarse bamboo ) Sft. 115
Mat ( fine bamboo ) Sft. 115
Wire nails Lbs. 1.5

Carpenters No. 1

24 Single bamboo mat walling without frames


but with 3"x 1/2" covering strSft. 100

Covering strips 4x 10'x 4"x 1Cft. 0.64 15% Wastage


Bamboo mat Sft. 115
Wire nails 2" Lbs. 1.5
ANALYSIS OF RATES ( Walling )

9/27/2017 11:30
No. Particular Unit
QuantityRate PerAmount Remark
Carpenters No. 1
25 Double bamboo mat walling without frames
but with covering strips. Sft. 100

Covering strips, 4x 10'x 4"x Cft. 0.64 15% Wastage


Bamboo mat ( course ) Sft. 115
Bamboo mat ( fine ) Sft. 115
Wire nails Lbs. 1.5

Carpenters No. 1

26 Providing movable plywood partition wall


fixed on both sides and including 2"x 1"
frames and runners. Sft. 100

Scantlings Cft. 5.5 10% Wastage


Planks Cft. 1.92 15% Wastage
Plywood Sft. 230 15% Wastage
4"Brass handle No. 4
Nails & wood screws Lbs. 2

Carpenters No. 10

27 Providing of plywood walling Sft. 100

Plywood Sft. 115 15% Wastage


Nails & spikes Lbs. 1.5

Carpenters No. 2

28 Providing of plywood ( 5 ply ) walling with


and including 4"x 2" frames. Sft. 100

Plywoood ( 5 ply ) Sft. 115 15% Wastage


Wall frames Cft. 2.44
Nails & spikes Lbs. 2

Carpenters No. 2

29 Bamboo scaffolding Sft. 100

Bamboo ( wahya 1-1/2" to 2No. 48


ANALYSIS OF RATES ( Walling )

9/27/2017 11:30
No. Particular Unit
QuantityRate PerAmount Remark
Coinyan Viss. 2.44 15% Wastage

Carpenters No. 4
Workers No. 4
8 4-1/2"Thick reinforced brick wall in cement
mortar 1:3 reinforcSft. 100 1000 112

Reinforcement ( X-met 2-1/2" wide ) Rft. 115 1150 Rft. 10


Bricks 9"x 4-3/8"x 2-3/4" no. 550 5500 no.
Cement lbs. 297 26.518 Bag
astage Sand Cft. 10 1 Sud

Workers no. 3 30 no.

27 Providing of plywood walling Sft. 7853

astage Plywood Sft. 9031 282.2 ###


Nails & spikes Lbs. 117.8 235590

Carpenters No. 157.06 314120


###

8(a) 4"Thick reinforced brick wall in cement


mortar 1:3 with 6"x 3" frame Sft. 100 100

Reinforcement ( X-met 2" w Rft. 115


Bricks 9"x 4-3/8"x 2-3/4" No. 550
Cement Lbs. 297 2.652
Sand Cft. 10 0.1
Frames 4x 10'x 6"x 3" Cft. 5.5 0.055
Beadings 3/4"x 3/4"x 4x 4x Cft. 0.81 0.016
Screws Gross. 0.75
Coal tar Lbs. 1
Nails & spikes Lbs. 1 0.278

Masons No. 2
Carpenters No. 1.25
Workers No. 3
8 4-1/2"Thick reinforced brick wall in cement
mortar 1:3 reinforcSft. 100 1000 112

astage
8 4-1/2"Thick reinforced brick wall in cement
mortar 1:3 reinforcSft. 100 1000 112
astage
8 4-1/2"Thick reinforced brick wall in cement
mortar 1:3 reinforcSft. 100 1000 112
astage

astage
astage

astage
astage
astage

astage
astage
8 4-1/2"Thick reinforced brick wall in cement
mortar 1:3 reinforcSft. 100 1000 112

astage

astage
astage

astage
astage

astage
astage
astage
8 4-1/2"Thick reinforced brick wall in cement
mortar 1:3 reinforcSft. 100 1000 112

astage
astage

astage

astage

astage
8 4-1/2"Thick reinforced brick wall in cement
mortar 1:3 reinforcSft. 100 1000 112

astage

astage
astage
astage

astage

astage
8 4-1/2"Thick reinforced brick wall in cement
mortar 1:3 reinforcSft. 100 1000 112
astage
ANALYSIS OF RATES ( Fencing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

1 Wooden fencing with posts 8' centers


and two longitudinal rails. Rft. 100

Coal tar, two coats Gal. 4.25


Corner post, 1x 6-1/2'x 5"x 5"
Cross feet, 2x 2'x 5"x 3"
Inter posts, 11x 6'x 5"x 3" Cft. 24 10%Wastege
Cross feet, 22x 1-1/2'x 5"x 2" For 24Cft. 4
Longitudional rails, 2x 100'x 4"x 2" carpenters. &
Nails and spikes Lbs. 7 coal tatring
350 Sft.worker
Carpenters No. 4 for 12 posts
Workers No. 4 holes.

2 Wooden fencing with posts 8' centers


and three longitudinal rails. Rft. 100

Coal tar, two coats Gal. 5.5


Corner post, 1x 6-1/2'x 5"x 5"
Cross feet, 2x 2'x 5"x 3"
Inter posts, 11x 6'x 5"x 3" Cft. 30.11 10%Wastege
Cross feet, 22x 1-1/2'x 5"x 2" For 30Cft. 5
Longitudional rails, 2x 100'x 4"x 2" carpenters. &
Nails and spikes Lbs. 8 coal tatring
450 Sft.worker
Carpenters No. 5 for 12 posts
Workers No. 4 holes.

3 5 Strand wire ( No. 5 seven ply ) fencing


with wooden posts 14' apart. Rft. 98

Coal tar, two coats Gal. 1


No. 5 seven ply wire Lbs. 49
Straining bolts, 18"x 1/2" No. 5
Corner posts, 7'x 5"x 5"
Cross feet, 2x 2'x 5"x 5"
Cft. 6.47 10%Wastage
Inter posts, 6x 6-1/2'x 4"x 3"
Cross feet, 12x 1-1/2'x 4"x 2"
Staples Lbs. 0.5

Carpenters No. 2
Workers No. 1.5

4 5 Strand wire fencing ( no. 5 seven ply )


with R.C posts 14' apart. Rft. 98

R.C corner posts at 196' apart No. 0.5


R.C inter posts and one strut No. 7
No. 5 seven ply wire Lbs. 49
Straining bolts 18"x 1/2" No. 5
Lime concrete foundation for corner posts
ANALYSIS OF RATES ( Fencing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
1/2x 2'x 2'x 2-1/2' Cft. 5
Binding wire staples Lbs. 1

Caarpenters No. 1
Workers No. 2

5 American woven wire fencing with R.C post


12' apart. Rft. 100

American woven wire Rft. 100


R.C corner posts 200' apart No. 0.5
R.C inter posts and one strut No. 8
Lime concrete foundation for corner posts Cft. 5
1/2x 2'x 2'x 2-1/2'
Straining bolts 18"x 1/2" No. 5
Binding wire staples Lbs. 1

Carpenters No. 2
Workers No. 2

6 Bamboo fancing with wooden posts 10'apart Rft. 100

Post corner 1x 6'x 5"x 5"


Cross feet, 2x 2'x 5"x 3"
Cft. 9.95 10%Wastage
Inter posts, 9x 6'x 5"x 3"
Cross feet, 18x 1-1/2'x 5"x 3"
Bamboo ( half split ) for horizontal 10' long No. 15
Bamboo for split verticals ( 3" ) 10' long No. 75
Nails Lbs. 2

Carpenters No. 1.5


Workers No. 3

7 Barbed wire Fencing with 4"x 4" timber post


8' apart embedded in 1:2:6 lime concrete. Rft. 96

5"x 5" Corner posts, 1x 8'x 5"x 5"


4"x 4" posts, 11x 8'x 4"x 4", struts Cft. 17.17 10%Wastage
8 x 10' x 4" x 2"
Barbed wire
Rft. 1200
Diagonals, 2x 12x 10'
Lime Cft. 4.55
Sand Cft. 9.1
Brick aggregate Cft. 27
Nails Lbs. 1
Carpenters No. 2
Workers No. 4
8 Chain link fencing with 4"x 4" timber posts
8' apart embedded in 1:2:6 lime concrete. Rft. 96

5"x 5" Corner posts, 1x 8'x 5"x 5"


Cft. 18.38 10%Wastage
4"x 4" posts, 11x 4"x 2"
ANALYSIS OF RATES ( Fencing )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Battens, 13x 6'x 2" 1/2"
Straining wire, 3/8", 3x 96' Rft. 288
Chain link 6 x 96' Sft. 576
Lime Cft. 4.55
Sand Cft. 9.1
Brick aggregate Cft. 27
Nails Lbs. 1

Carpenters No. 2
Workers No. 4
7 Barbed wire Fencing with 4"x 4" timber post
8' apart embedded in 1:2:6 lime concrete.
Sft. 96 1000.000
5"x 5" Corner posts, 1x 8'x 5"x 5"
4"x 4" posts, 11x 8'x 4"x 4", struts Cft. 17.17 178.854 Cft. 3.577083 ton 10%Wastage
8 x 10' x 4" x 2"
Barbed wire Rft. 1200 12500.000 Rft.
Diagonals, 2x 12x 10'
Lime Cft. 4.55 47.396 Cft.
Sand Cft. 9.1 94.792 Cft.
Brick aggregate Cft. 27 281.250 Cft.
Nails lbs. 1 10.417 lbs.

Carpenters no. 2 20.833 no.


Workers no. 4 41.667 no.
10%Wastage
ANALYSIS OF RATES ( Stone Work )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

1 Course rubble dry stone masonary Cft. 100

Rubble stone Cft. 125

Masons No. 2
Workers No. 2
Scaffolding and sundries L-s

2 Stone patching 12" or 18" stone Cft. 100

Rubble stone Cft. 110

Masons No. 2
Workers No. 2

3 6" spawls under stone pitching Cft. 100

Stone spawls Cft. 100

Masons No. 0.5


Workers No. 0.5

4 Coursed rubble stone masonry in cement


mortar 1:3 Cft. 100

Cement 10 cft. Lbs. 900


Rubble Stone ( selected ) Cft. 125
Sand Cft. 30

Masons No. 9
Workers No. 6
Scaffolding and sundries L-s

5 Coursed rubble stone masonry in cement


mortar 1:3 in arches Cft. 100

Cement 11 cft. Lbs 990


Rubble Stone ( selected ) Cft. 125
Sand Cft. 33

Masons No. 10
Workers No. 8
Scaffolding and sundries L-s

6 Random rubble stone in cement mortar 1:3


rough dressed Cft. 100

Cement Lbs. 1180


ANALYSIS OF RATES ( Stone Work )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Stone roughly dressed Cft. 150
Sand Cft. 40

Masons No. 4
Workers No. 5
Scaffolding and sundries L-s

7 Coursed rubble stone masonry in lime


mortar 1:1:1 Cft. 100

Lime mortar 1:1:1 Cft. 34


Rubble Stone ( selected ) Cft. 125

Masons No. 9
Workers No. 6
Scaffolding and sundries L-s

8 Random rubble stone masonry in lime


mortar 1:1:1 rough dressed Cft. 100

Lime mortar 1:1:1 Cft. 40


Stone roughly dressed Cft. 150

Masons No. 4
Workers No. 5
Scaffolding and sundries L-s

9 Coursed rubble stone masonry in lime


ortar 1:1:1 Cft. 100

Lime mortar 1:1:1 Cft. 34


Rubble Stone ( selected ) Cft. 125

Masons No. 10
Workers No. 8
Scaffolding centering and sundries L-s

10 Laterite blockwork with dressed 16"x 8"x 6"


block in cement mortar 1:4 Cft. 100

Cement 5 cft. Lbs 450


Laterite blocks Cft. 222
Sand Cft. 20

Masons No. 3
Workers No. 4
Scaffolding centering and sundries L-s
ANALYSIS OF RATES ( Stone Work )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
ANALYSIS OF RATES ( Road work by machine )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

1 Earth work excavation by machine for 100 ft


average haul in ordinary soil for level excav-
ation for 10,000 Cft. Cft. 10000
Labour
Worker for track cleaning, etc. Manday 1 (a) For 1:10 up
Operator Manday 1.333 grade dozing
Fitter Manday 0.667 allow 25% incre-
ase over level
Machine excavation
Bull dozer ( D-8 ) Hour. 5.333 (b) For 1:10down
P.O.L for operation grade dozing
H.S.D Gals 20 allow 25% deduc-
Engine oil Gals 0.333 tion over level
Gear Oil Gals 0.333 excavation
Hydraulic oil Gals 0.667
Grease Lbs. 0.333
Sundries L-s

2 Blasting hard rocks including removing


debris for 100 Cft. At quarry site (drilling by
manual labour) Cft 100

Labour

Miner Manday 0.1


Driller Manday 0.5
Drill helper Manday 0.5
Worker Manday 1

Tools

Hand drill Hour 8


Drill bit (10' boring) Hour 0.167 Life_ 60 Rft
Hammer (14 Lbs) Hour 0.008 Life_ 120 days

For Operation

Explosives Lbs 1.5


Safety fuse Ft 10
Detonator No 2
Sundries L-s

3 Blasting hard rocks including removing


debris for 100 Cft. At quarry site using
pneumatic drill Cft 100

Labour

Operator for air compressor Manday 0.14


Miner Manday 0.10
Driller Manday 0.14
Helper Manday 0.14
Worker for removing debris Manday 1.00

For Operation
ANALYSIS OF RATES ( Road work by machine )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

Explosives Lbs 1.50


Safety fuse Ft 10.00
H.S.D Gal 1.00
Engine oil Gal 0.50
Detonator No 2.00

Tools and Machine

Air compressor Hour 8


Pneumatic drill Hour 8
Drill bit(10' boring) No 0.05 Life - 200'
Sundries L-s boring

4 Crushing of 500 Cft of Boulders to different


sizes of road metals by stone crusher. Cft 500

Labour

Head workers Manday 1


Workers Manday 14
Operator Manday 1
Night durwan Manday 1

Materials
6"x9" boulders Cft 500

Machine
Stone crusher(600 Cft capacity) Hour] 8

For Operation

H.S.D Gals 3
Engine oil Gal 0.25
Grease Lb 0.125
Rosin Lb 0.25
Sundries L-s
Notes;
Different size of out turned road metals
depends on the size and adjustment of
crushing jaws.

5 Conversion of 4" to 6" Boulder by 450 Cft


Capacity granulator per day Cft 450

Labour
Operator Manday 1 Metal converted
Workers Manday 20 2"= 60 Cft
1"= 80 Cft
Materials Used Chips=410 Cft
4" to 6" boulders Cft 450 Total =550 Cft

For operation of Machine


H.S.D Gals 4
Engine oil Gal 0.125
Grease Lb 0.75
ANALYSIS OF RATES ( Road work by machine )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

Machine
Granulator No 1
Sindries L-s

6 Collection of sand within 1 Mile Lead Cft 1000

Labour
Worker for loading & unloading Manday 8

Machine
Tipper Hour 8
Sundries L-s

7 Consolodation of Sand 4" thick by diesel


roller Cft 2500 Whenever roller is
required over nig-
Labour ht one night is all-
Head workers Manday 1 owed in the con-
Workers Manday 25 solidation item.
Roller driver Manday 1

Materials
Sand Cft 2500

Machine
Roller Hour 8

P.O.L for operation


H.S.D Gals 6
Engine oil Gal 0.25
Gear oil Gal 0.125
Grease Lb 0.75
Cotton waste for cleaning, etc L-s
Sundries L-s

8 Laying and hand packing of soling stones


6"x9" and consolidated by road roller Cft 1000 Whenever roller is
required over nig-
Labour ht one night is all-
Head workers Manday 1 owed in the con-
Workers Manday 20 solidation item.
Roller driver Manday 1

Materials
6"x9" soling stone Cft 1000

Machine
Roller Hour 6

P.O.L for operation


H.S.D Gal 4.5
Engine oil Gal 0.188
Gear oil Gal 0.125
Grease Lb 0.5
Cotton waste for cleaning, etc L-s
ANALYSIS OF RATES ( Road work by machine )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Sundries L-s

9 Laying of 2" to 4" stone metal for 4" uncom;


pacted thickness and consolidated by road
roller Cft 1000

Labour
Head workers Manday 1
Workers Manday 14
Roller driver Manday 1

Materials
2"x4" soling stone Cft 1000

Machine
Roller Hour 8

P.O.L for operation


H.S.D Gal 6
Engine oil Gal 0.25
Gear oil Gal 0.125
Grease Lb 0.75
Cotton waste for cleaning, etc L-s
Sundries L-s

10 Laying of 1" to 2" metal for 4" uncom-


pacted thickness and consolidated by road Whenever roller is
roller Cft 1000 required over nig-
ht one night is all-
Labour owed in the con-
Head workers Manday 1 solidation item.
Workers Manday 12
Roller driver Manday 1

Materials
11/2"x2" soling stone Cft 1000

Machine
Roller Hour 8

P.O.L for operation


H.S.D Gal 6
Engine oil Gal 0.25
Gear oil Gal 0.125
Grease Lb 0.75
Cotton waste for cleaning, etc L-s
Sundries L-s

11 Laying of Kanker or Laterite for 6"uncompa-


cted thickness and consolidated by road
roller Cft 1000

Labour
Head workers Manday 1
Workers Manday 10
Roller driver Manday 1
ANALYSIS OF RATES ( Road work by machine )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

Materials
Kanker Cft 1000

Machine
Roller Hour 8 Whenever roller is
required over nig-
P.O.L for operation ht one night is all-
H.S.D Gal 6 owed in the con-
Engine oil Gal 0.25 solidation item.
Gear oil Gal 0.125
Grease Lb 0.75
Cotton waste for cleaning, etc L-s
Sundries L-s

12 Working expenses of diesel roller per day Day 1

Labour
Roller driver Manday 1 Employment of
Night durman Manday 1 mechanics for
maintenance
Machine & Tools mechanical equi-
Water cart No of 1 pments be inclu-
day ded the main
For Operation estimate.
H.S.D Gal 6
Engine oil Gal 0.25
Gear oil Gal 0.125
Grease Lb 0.75
Cotton waste for cleaning, etc L-s

13 Working expenses of diesel tipper per day Day 1

Labour
Driver Manday 1

For Operation
H.S.D Gal 8
Engine oil Gal 0.25
Gear oil Gal 0.125
Grease Lb 0.1

14 Working expenses of a petrol tipper per day Day 1

Labour
Driver Manday 1 Employment of
mechanics,etc;
For Operation for maintenance
H.S.D Gal 10 of mechanical
Engine oil Gal 0.25 equipments to be
Gear oil Gal 0.125 included in the
Grease Lb 0.1 main estimate.

15 Working expenses of diesel water bowzer


per day Day 1

Labour
Driver Manday 1 Employment of
ANALYSIS OF RATES ( Road work by machine )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
mechanics,etc;
For operation for maintenance
H.S.D Gal 8 of mechanical
Engine oil Gal 0.25 equipments to be
Gear oil Gal 0.125 included in the
Grease Lb 0.1 main estimate.

16 Working expenses of a petrol water bowzer


per day (Russian) Day 1

Labour
Driver Manday 1 Employment of
mechanics,etc;
For operation for maintenance
Petrol Gal 12 of mechanical
Engine oil Gal 0.5 equipments to be
Gear oil Gal 0.5 included in the
Grease Lb 1 main estimate.

17 Hot bitumen 1" depth grouting(Semigrout)


over stone metal surface with 1/4" to 3/4"
chipping for 1mile X 12' =63,360 Sft Sft 63360

Labour
Head worker Manday 15 Base on 3" comp-
Workers Manday 225 acted thickness
Boilers Manday 15

Materials
Bitumen Ton 23.96 13% wastage
Chippings Cft 4000

Machines Whenever roller is


Roller Days 15 required over nig-
Bitumen heater Days 12 ht, one night is
Thermometer Days 8 allowed in thecon-
solidation work.
For operation
Fire wood Ton 8.5
H.S.D Gal 90
Engine oil Gal 7.5
Gear oil Gal 1.875
Grease Lb 11.25
Cotton wastage for cleaning L-s
Sundries L-s

18 Hot bitumen 1" depth grouting (Semigrout)


over stone metal surface with 1/4" to 3/4"
chipping for 1mile X 12' =63,360 Sft Sft 63360

Labour
Head worker Manday 15 Base on 3" comp-
Workers Manday 225 acted thickness
Roller driver Manday 15

Materials
ANALYSIS OF RATES ( Road work by machine )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Bitumen Ton 15.82 13% wastage.
Chippings Cft 4000

Machines
Roller Days 15 Whenever a roller
Bitumen heater Days 12 is required over
Thermometer Days 8 night,one night
durwan per night
For operation is allowed for the
Fire wood Ton 6.4 consolidation
H.S.D Gal 90 work.
Engine oil Gal 3.75
Gear oil Gal 1.875
Grease Lb 11.25
Cotton wastage for cleaning L-s
Sundries L-s

19 Hot bitumen surface dressing over stone


metal surface with 1/4" to 3/4" chipping for Whenever a roller
1 mile X 12' =63,360 Sft Sft 63360 is required over
night,one night
Labour durwan per night
Head worker Manday 15 is allowed for the
Workers Manday 200 consolidation
Roller driver Manday 15 work.

Materials
Bitumen @ 40 lbs% Sft Ton 12.79 13% wastage.
Chippings Cft 3600

Machines
Roller Days 15
Bitumen heater Days 12
Thermometer Days 8

For operation
Fire wood Ton 5.12
H.S.D Gal 90
Engine oil Gal 3.75
Gear oil Gal 1.875
Grease Lb 11.25
Cotton wastage for cleaning L-s
Sundries L-s

20 Hot bitumen surface dressing over stone


metal surface with 1/4" to 3/4" chipping for
1 mile X 12' =63,360 Sft.(2nd coat) Sft 63360

Labour
Head worker Manday 15
Workers Manday 200
Roller driver Manday 15

Materials
Bitumen @ 25 lbs% Sft Ton 8 13% wastage.
Chippings Cft 3600
ANALYSIS OF RATES ( Road work by machine )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

Machines
Roller Days 15 Whenever a roller
Bitumen heater Days 12 is required over
Thermometer Days 8 night,one night
durwan per night
For operation is allowed for the
Fire wood Ton 3.2 consolidation
H.S.D Gal 90 work.
Engine oil Gal 3.75
Gear oil Gal 1.875
Grease Lb 11.25
Cotton wastage for cleaning L-s
Sundries L-s

21 Hot bitumen seal coat with chippings1/8" to


1/2" for 1mile X 12' =63,360 Sft Sft 63360

Labour
Head workers Manday 12
Workers for bitumen heating, spraying,stone
sperating, etc. Manday 180
Roller driver Manday 12

Materials
Bitumen Ton 8 13% wastage.
Chippings Cft 2800

Machines
Roller Days 12 Whenever a roller
Bitumen heater Days 12 is required over
Thermometer Days 8 night,one night
durwan per night
For operation is allowed for the
Fire wood Ton 3.2 consolidation
H.S.D Gal 72 work.
Engine oil Gal 3
Gear oil Gal 1.5
Grease Lb 9
Cotton wastage for cleaning L-s
Sundries L-s

22 Hot bitumen prime coat or track coat with


coarse sand for 1mile X 12' = 63,360 Sft. Sft 63360

Labour
Head workers Manday 12
Workers Manday 80

Materials
Bitumen Ton 6.4 13% wastage.
Sand Cft 1800

Machine & Tools


Bitumen heater Days 12
Thermometer Days 8
ANALYSIS OF RATES ( Road work by machine )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark

For operation
Fire wood Ton 2.6
Sundries L-s

23 Laying of 11/2" thick (consalidated) premix


carpet including priming coat
(660' x 12') = 7,920 Sft. Sft 7920

Labour
Head workers Manday 3 Whenever a roller
Workers Manday 54 is required over
Operators for mixer Manday 3 night,one night
Roller driver Manday 1 durwan per night
Tipper driver Manday 1 is allowed for the
consolidation
Materials item.
Bitumen 80/100 Ton 2.83 13% wastage.
H.S.D Gal 25
Chip 1/2" to 3/4" Cft 1000

Machines
4 cft capacity mixer (millers) 24 hrs 3
Roller 8 hrs 1
350 gals bitumen heater 8 hrs 3
Tipper 8 hrs 1
Sundries L-s

24 Laying only of hot mix asphalt concrete of


11/2" thickness. Cft 1200

Labour
Time keeper Manday 2 Whenever a roller
Foreman Manday 2 is required over
Traxcavator operator Manday 2 night,one night
Paver operator Manday 2 durwan per night
Mixer operator Manday 3 is allowed for the
Air compressor operator Manday 1 consolidation
work.
Head workers
For paver Manday 1
For mixer Manday 1
For general works Manday 1

Workers
For paver Manday 12
For mixer Manday 14
For general tar boiling & transporting Manday 11

Machines
Mixer (Hot) Millers 10cft capacity Days 1 Working expens-
Drier for chips Days 1 es to be included.
Tar boilers 5Nos Days 5 Cost of materials
12' wide barber green paver 1 No Days 1 ie, coarse aggre-
Taden roller 2 (6 Tons) Days 3 gate fillers and
Tippers 5 Nos Days 1 bitumen in the
ANALYSIS OF RATES ( Road work by machine )

9/27/2017 11:30
No. Particular Unit Quantity Rate Per Amount Remark
Water bowzer 1 No Days 1 varying mixes is
Traxcavator or grader 1 No Days 1 to be included in
Air compressor Days 1 the main estimate

For operation
H.S.D for machines Gals 200
Engine oil Gals 4
Grease Lb 1
Sundries L-s

25 Scarifying old metal 2" deep 12' wide includ-


ing screening, respreading, and rolling with
a road roller for 1 furlong. furlong 1

Labour
Head workers Manday 3
Workers Manday 30
Working expenses of roller Days 3
Sundries L-s

26 Dressing of subgrade to required camber by


manual labour for laying of soiling stones.
(12' X 660' ) = 7,920 Sft Sft 7920

Labour
Head workers Manday 3
Workers Manday 20
Sundries L-s
ANALYSIS OF RATES ( Road Work )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount Remark

1 Earth work in excavation in ordinary soil


either in embarkment of in cutting with an
initial lead of 100 ft and lift on 5 ft. Cft 1000

Maistry No 0.5
Digger No 7 Tasks = 140 cft
Workers for carrying No 7 for 1 digger.
Sundries L-s

2 Earth work in excavation in soft latritic,


gravelly or kanker soil either in embarkment
or in cutting with an initial lead of 100 ft &
lift of 5 feet. Cft 1000

Maistry No 0.5
Digger No 10 Tasks = 100 cft
Workers for carrying No 7 for 1 digger.
Sundries L-s

3 Earth work in excavation in average latritic


gravelly or kanker soil either in embank-
ment or in cutting with an initial lead of
100 feet & lift of 5 feet. Cft 1000

Maistry No 0.625
Digger No 14
Workers for carrying No 8
Sundries L-s

4 Earth work in excavation in hard latritic,


gravelly or kanker soil either in embankment
or in cutting with an initial lead of 100 feet
& lift of 5 feet. Cft 1000

Maistry No 0.75
Digger No 21
Workers for carrying No 10
Sundries L-s

5 Excavation in soft rock including carriage


of stone for 50 feet. Cft 100

Miner No 1
Worker for carring No 4.5
Smith No 0.25
Bellow boy No 0.25
Sundries L-s

6 Excavation in hard rock by blasting includ-


ing removing stones. Cft 100

Blasting powder Lb 3
ANALYSIS OF RATES ( Road Work )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount Remark
Charcoal Lb 10
Miners No 5
Workers No 5.5
Black smith No 0.25
Bellow boy No 0.5
Hammer man No 0.5
Sundries L-s

7 Collection of soiling stones ( Local ) at the


quarry site. Cft 100

Hammer man No 1
Workers (collection & staking ) No 5
Sundries L-s

8 Collection of soiling stones ( Kankar ) at the


quarry site. Cft 100

Hammer man No 1
Workers (collection & staking ) No 4
Sundries L-s

9 Collection of soiling stones(Laterite Boulder)


at the quarry site. Cft 100

Hammer man No 1
Workers No 4
Sundries L-s

10 Breaking metal from boulders (1"to 2")


at quarry site. Cft 100

Hammer man No 1
Workers for getting out boulder No 2 Male workers.
Workers for breaking No 7
Sundries L-s

11 Collection and conversion of blasted debris


to 6" to 9" soilding stones at quarry site. Cft 100

Labour
Hammer man Manday 1
Workers (collection & staking ) Manday 2
Sundries L-s

12 Collection and conversion of blasted debris


to metal at quarry site. Cft 100

Labour
Hammer man Manday 1.5
Workers for collection & stacking Manday 3
Sundries L-s
ANALYSIS OF RATES ( Road Work )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount Remark
13 Breaking metal (2"- 4") from boulders at
quarry site including boxing. Cft 100

Labour
Hammer man Manday 2
Worker for boxing Manday 1
Sundries L-s

14 Breaking and boxing 1"to2" from 2" to 4"


metal at quarry site. Cft 100

Labour
Workers for breaking and boxing Manday 2
Sundries L-s

15 Breaking and boxing "to"chipping from


1 to 2" metal at quarry site. Cft 100

Labour
Workers for breaking and boxing,etc Manday 15
Sundries L-s

16 Breaking "to " chipping from 2" to 4"


metal at quarry site. Cft 100

Labour
Workers for breaking and boxing Manday 17
Sundries L-s

17 Collection of kanker or laterite gravel at


quarry site. Cft 100

Labour
Workers for digging,boxing etc. Manday 3 Plain section
Sundries L-s only (Outturn in
hill section=70cft
18 Collection of Hill gravel at quarry site.
(Screened) Cft 100

Labour
Workers Manday 4
Sundries L-s

19 Extraction of 1 "to 2" stone metal including


blasting and breaking to size at quarry site. Cft 100

Blasting powder Lb 3
Charcoal Lb 10
Miners No 5
Black smith No 0.25
Bellow boy No 0.25
Hammer man No 1
ANALYSIS OF RATES ( Road Work )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount Remark
Workers for breaking and stacking No 8

20 Laterite metal 2 " guage at quarry site. Cft 100

Worker for quarring No 2


Hammer man No 1
Worker for breaking and stacking No 5

21 Extraction of " to 1" gauge stone metal


including blasting and breaking to size at
quarry site. Cft 100

Blasting powder Lb 3
Charcoal Lb 10
Miners No 5
Black smith No 0.25
Bellow boy No 0.25
Hammer man No 1
Workers for breaking and stacking No 11

22 Extraction of stone chipping " to "


gauge including blasting and breaking
to size at quarry site. Cft 100

Blasting powder Lb 3
Charcoal Lb 10
Miners No 5
Black smith No 0.25
Bellow boy No 0.25
Hammer man No 1
Workers for breaking and stacking No 16

23 Collection of boulders from river bed for


soling within 2 furlons. Cft 100

Workers for collection and stacking No 6

24 Breaking metal 1" to 2"gauge rivershingle


with 2 furlons. Cft 100

Workers for collection No 3


Workers for breaking and stacking No 4
Sundries L-s

25 Collection of river shingle chippings ( " to


" ) within 2 furlons lead. Cft 100

Workers for collection No 4


Workers for breaking and stacking,etc No 6
Sundries L-s
26 Breaking brick into1" to 2"aggregate Cft 100

Jama bricks No 1000


ANALYSIS OF RATES ( Road Work )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount Remark
Workers for breaking and stacking No 5
Sundries L-s

27 Collection of sand within one mile lead Cft 100

Bullock cart with driver No 1


Workers for loading and unloading No 2
Sundries L-s

28 Collection of gravel within a mile lead. Cft 100

Bullock cart with driver No 1


Workers for digging,carrying,loading No 4
and unloading
Sundries L-s

29 Working expenses for a steam roller per Day 1


day.

Lubricating oil,cotton waste,kerosene,soap, L-s Wood fuel requir-


asbestos packing, etc. ed for a steam
Fire wood Cft 36 roller for 1 day
Driver No 1 work is 1/6 fathom
Fireman No 1 or 36cft=10cwt,or
Night durman No 1 1,120lb.If coal is
Cart for carrying fuel and water No 2 used 5cwt or 560
Repairs to chain and roller L-s lb is necessary.
Washing out roller and cleaning engine L-s
Sundries L-s

30 Working expenses for a motor roller per Day 1


day.

Petrol Gal 0.167


Kerosene oil Gal 6
Lubricating oil,cotton waste L-s
Engine driver No 1
Cleaning and rest L-s
Night durman No 1
Water cart No 1
Sundries L-s

31 Consolidation of 6" soilding stone by steam


roller after hand packing. Cft 1000

Steam roller charges Day 1


Maistry No 1
Workers No 21
Sundries L-s
32 Consolidation of stone metal with steam
roller including sand blinding ( 4" coat ). Cft 1200
ANALYSIS OF RATES ( Road Work )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount Remark
Steam roller charges Day 1
Sand for blinding Cft 133
Maistry No 1
Workers No 14
Sundries L-s

33 Scarifying old metal 2"deep,12' wide,scree-


ning,respreading and rolling with a steam
roller including sand blinding. Sft 3300

Steam roller charges Day 1


Sand for blinding Cft 137
Maistry No 1
Workers No 19
Sundries L-s

34 2" thick hot bitumen grouting blinded with


1/4" to 1/2" stone chipping. NB_1.A roller can
(For 1 mile X 12' = 63,360 Sft) Sft 63360 deal with 4,000
sft/day.
Bitumen at 100lb, per % sft Ton 32 2.One ton of coal
Rainway freight on above Ton 32 or 2 ton of fire
Carriage to site Ton 32 wood reqd to heat
1/2" to 3/4" chipping at site Cft 4000 up 5 tons or1,000
Wood fuel Cft 922 gal, of bitumen.
Labour for brushing old surface,spraying No 380 3.One fathom of
spreading, etc. fire wood weighs
Rolling charge steam roller Day 16 3 tons.
Hire for boiler sprayer,etc. Day 12 *Normal wastage
Wire and bristne brushes L-s 3% + leakage
Miscellancous camber board L-s 10%.

35 Hot bitumen surface dressing (1st coat )


blinded with 1/4" to 1/2" stone chipping
(For 1 mile X 12' = 63,360 Sft) Sft 63360

Bitumen at 40lb, per % sft Ton 12.79 13% wastage


Rainway freight on above Ton 12.79
Carriage to site Ton 12.79
1/2" to 3/4" chipping at site Cft 4000
Wood fuel Cft 369
Labour for brushing old surface,spraying No 380
spreading, etc.
Rolling charge steam roller Day 16
Hire for boiler sprayer,etc. Day 12
Wire and bristle brushes L-s
Miscellancous camber board,etc L-s

36 Hot bitumen surface dressing (2nd coat)


blinded with 1/4" to 3/4" stone chipping
(For 1 mile X 12' = 63,360 Sft) Sft 63360
ANALYSIS OF RATES ( Road Work )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount Remark

Bitumen at 25lb, per % sft Ton 8 13% wastage


Rainway freight on above Ton 8
Carriage to site Ton 8
Grit 1/4"" to 1/2" Cft 2650
Wood fuel Cft 230
Labour for brushing old surface,spraying No 320
spreading, etc.
Rolling charge steam roller Day 16
Hire for boiler sprayer,etc. Day 12
Wire and bristne brushes L-s
Miscellancous camber board ,etc L-s

37 1"(Consolidated thickness) Premix carpet.


(For 1 mile X 12' = 63,360 Sft) Sft 63360

Labour for brushing road surface No 330


Priming coat
Bitumen at 20 lbs.per 100 Sft Ton 6.4 13% wastage
Main Carpet
1/2" to 3/4" stone 3,400 Cft
Cft 5200
3/8" to 1/2" stone 1700 Cft
Bitumen at 4 lbs.per cft Ton 10.29 13% wastage
Sand at 5% of stone Cft 255
Bitumen for sand at 0.25 lb per cft Ton 0.03 13% wastage

Wearing course
1/4" to 1/2" chips, at 3cft per 100 sft
Cft 1900
1/8" to 1/4" chips,
Bitumen at 35 lb. per % sft Ton 11.19 13% wastage
Sand for final coat at 2 cft .per % sft Cft 1300
Rly freight for bitumen Ton 27.91
Carriage to site Ton 27.91
Wood fuel Cft 804
Labour for spreading,spraying,etc. No 500
Road roller charges M - coat Day 16
Road roller charges W - coat Day 4
Hire for boiler sprayer,etc. Day 16
Wire and bristle brushes L-s
Miscellancous, tools & plant, camber L-s
board, etc.

38 2"(Consolidated thickness) Premix carpet.


(For 1 mile X 12' = 63,360 Sft) Sft 63360

Labour for brushing road surface No 300

Main Coat
1" to 11/4" stone 7,670 Cft
Cft 11500
1/4" to 3/4" stone 3,8300 Cft
ANALYSIS OF RATES ( Road Work )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount Remark
Bitumen at 3 lbs.per cft Ton 20.31 13% wastage
Sand at 5% of stone Cft 575
Bitumen for sand at 0.25 lb per cft Ton 0.07 13% wastage

Topping Course
1/2" to 3/4" chipping at 5cft per 100 sft
Cft 3200
1/4" to1/2"chipping
Bitumen at 4 lb. per cft Ton 6.45 13% wastage

Wearing course
1/4" to 1/2" chipping at 4.5cft per % sft
Cft 2900
1/8" to 1/4" chipping
Bitumen at 25 lb. per % sft Ton 8 13% wastage
Sand for final coat at 2 cft .per % sft Cft 1300
Rly freight for bitumen Ton 34.83
Carriage to site Ton 34.83
Wood fuel Cft 1066
Labour for spreading,spraying,etc. No 1000
Road roller charges M - coat Day 25
Road roller charges, Topping course Day 4
Road roller charges W - course Day 25
Wire and bristne brushes L-s
Miscellancous,tools & plant, camber L-s
board, etc.

39 Liquid seal coat 1 mile X 12' =63,360 sft Sft 63360


Bitumen for liquid seal coat at 1/4 Gal
per sq yard at 215 gallons a ton 1760 gal-
lons and wastage. Ton 9.25

Gallons a ton 1,760 gallons & wastage. 13% wastage


Freight on bitumen Ton 9.25
Cartage on bitumen Ton 9.25
Wood fuel for heating bitumen Cft 267
Labour for spraying No 90
3/8" grit or coarse sand for blinding Cft 1800
Labour for spreading sand No 40
Steam road roller charges Day 10
Hire for boiler for heating bitumen Day 6
Incidental charges such as brushes, pour-
ing can,oil etc. L-s
ANALYSIS OF RATES ( Wood Work )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount Remark

1 Thitya,Ingin,Pyingado work wrought and


fixed. Cft 50

Thitya,ingin,pyingado Cft 55 10% wastage


Nails & Spikes Lb 14
Carpenters No 12

2 Jungle wood work wrought and fixed. Cft 50

Jungle wood scantling Cft 55 10% wastage


Nails & Spikes Lb 14
Carpenters No 10

3 Wood work wrought and fixed in fencing


and bridges. Cft 50

Scantling Cft 55 10% wastage


Nails & Spikes Lb 14
Carpenters No 7

4 Teak hand railing 1st class plain. Rft 8

Horizontal top 1X 7' X 4"X 3"


Horizontal bottom
Cft 2.61 10% wastage
Horizontal inter 2 X 7' X 3" X2"
Post, 1 X 3' X 4"X 4"
Verticals 5 X 2' X 2"X 2"
Cft 1.31 15% wastage
Diagonals 10 X 2' X 2" X 2"
Nails Lb 1
Carpenters No 2

5 Hand railing 2nd class plain (other than


teak) Cft 8

Post, 1 X 3' X 4"X 4"


Cft 1.18 10% wastage
Horizontal 2 X 7' X 3" X2"
Verticals 3 X 2' X 2"X 3"
Cft 0.78 15% wastage
Diagonals 6 X 4' X 2" X 1"
Nails Lb 0.5
Carpenters No 1.5

6 Teak stair case without hand railing for


45 Sft.(10' X 4' clear width). Sft 45

Stringers 2 X 10' X 12" X 3" Cft 5.5 10% wastage


Treads, 9 X 4' X1" X 1"
Cft 8.22 15% wastage
Risers, 9 X 4' X 7" X "
Nails Lb 2
Carpenters No 8
ANALYSIS OF RATES ( Wood Work )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount Remark
7 Stair case 2nd class without hand rail-
ing.(other than teak) for 30 Sft.(10' X 3') Sft 30

Stringers 2 X 10' X 10" X 3" Cft 4.59 10% wastage


Treads, 9 X 2' X 9" X 1"
Cft 2.47 15% wastage
Risers, 6 X 3' X 9" X "
Nails Lb 2
Carpenters No 4

8 Hard wood steps for out houses without


hand railing.for 15 Sft ( 5' X 3' ) Sft 15

Stringers 2 X 5' X 10" X 2" Cft 1.53 10% wastage


Treads, 4 X 3' X 8" X 1" Cft 0.77 15% wastage
Nails Lb 0.5
Carpenters No 1.5

9 Providing wrought jungle wood steps


with 10" X 2" stringers and 9" X 1"
treads. Sft 15

Jungle wood,stringers Cft 1.53


Treads Cft 1.3
Nails Lb 0.5
Carpenters No 1.5

10 Teak gate 1st class for 12' wide. Rft 12


W.I hinges 2 X 4" & 2 X 4' X 2" X " Lb 28.9
1" pintels,4 Nos Lb 12.6
" bolts for hinges and hasps 17Nos, Lb 3.72
4" long
Head & nuts for bolts Lb 0.29
Locking hasp 1 X 1' No 1
Top bar 2 X 6' X 8" X 3"
Bottom & center rails 4 X 6' X 5" X 3"
Diagonals,2 X 6' X 5" X 3" Cft 8.79 10% wastage
Outer stanchions, 2 X 5 X 5" X 3"
Inter stanchions, 2 X 4 X 5" X 3"
2" X 1" battens Cft 1.3 15% wastage
Nails Lb 2
Carpenters No 5

11 Gate 2nd class (other than teak). Rft 12

W.I as above item 10 Lb 45.5


Locking hasp 1 X 1' No 1
Stanchions, 2 X 4' X 4" X 2"
Stanchions, 2 X 4' X 4" X 2"
Cft 4.03 10% wastage
Horizontals,6X 6' X 4" X 2"
Diagonals, 2 X 6 X 4" X 2"
ANALYSIS OF RATES ( Wood Work )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount Remark
2" X 1" battens Cft 2.04 15% wastage
Nails Lb 2
Carpenters No 3

12 Eaves & Facia boards 12" X 1" plank. Rft 100

Planks 100' X 12" X 1" Cft 9.58 15% wastage


Nails & screws Lb 2
Carpenters No 4

13 Eaves & Facia boards 10" X 1" plank. Rft 100

Planks 100' X 10" X 1" Cft 7.98


Nails & screws Lb 2
Carpenters No 3.5

14 6" X 1" Teak facia & eaves boards. Rft 100

Teak 1" plank Cft 4.8 15% wastage


Nails & screws Lb 2
Carpenters No 2

15 8" X1" Thitya,Ingin, Pyingado eaves


boards wrought & fixed including earth
oiling 2 coats. Rft 100

Thitya,ingin,pyingado 8"X 1" planks Cft 6.4 15% wastage


Nails & Spikes Lb 2
Carpenters No 3
Earth oiling 2 coats Sft 150

16 9" X1" Thitya,Ingin, Pyingado eaves


boards wrought & fixed including earth
oiling 2 coats. Rft 100

Thitya,ingin,pyingado 9"X 1" planks Cft 7.19 15% wastage


Nails & Spikes Lb 2
Carpenters No 3.25
Earth oiling 2 coats Sft 167

17 6" X1" Pyingado eaves boards wrought


& fixed complete including earth oiling
2 coats. Rft 100

Pyingado 6"X 1" planks Cft 4.8


Nails & Spikes Lb 2
Carpenters No 2
Earth oiling 2 coats Sft 117

18 3" X 1" Facia boards planed and earth


ANALYSIS OF RATES ( Wood Work )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount Remark
oiling 2 coats and fixed complete. Rft 100

3" X 1" plank Cft 2.4 15% wastage


Nails & Screws Lb 1
Carpenters No 1.5
Earth oiling 2 coats Sft 42

19 3" X 1" Wrought inn facia boards fixed


completed including earth oiling 2 coats. Rft 100

3" X 1" Inn plank Cft 1.2 15% wastage


Nails & Screws Lb 1
Carpenters No 1.25
Earth oiling 2 coats Sft 33.5

20 18" Wide shelves with brackets. Rft 18

Planks 1 X 18' X 18" X 1" Cft 2.59 15% wastage


Brackets Cft 0.45
Nails & Spikes Lb 0.5
Carpenters No 0.75

21 12" Wide shelves with brackets. Rft 20

Planks 1 X 20' X 12" X 3" Cft 1.92 15% wastage


Brackets Cft 0.22
Nails & Spikes Lb 0.5
Carpenters No 0.75
ANALYSIS OF RATES ( Bridges )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount

1 Labour for driving 10" diameter timber pile in


oridinary soil.(With Ton drop hammer from
puttey winch and local trestle and manually
operated ) penetrarion average 20 feet. Ft 20

Labour
Foreman Manday 0.25
Carpenter(1st grade) Manday 0.5
Carpenter(2st grade) Manday 0.5
Workers Manday 3

Plants
Pile driving frame 1 No Hrs 4
Sundries L-s

2 Labour for driving 10" diameter timber piles in


oridinary soil (With pile driving machine)
penteration average 20 feet. Ft 20

Labour
Operators Manday 0.125
Foreman Manday 0.125
Carpenter(1st grade) Manday 0.5
Carpenter(2st grade) Manday 0.5
Workers Manday 3

For Operation
H.S.D Gal 0.667
Grease Lb 0.083

Plants
Pile driving frame 1 No Hrs 2.667
Sundries L-s

3 Labour for pile driving reinforced cement con-


cretr pile 14" X 14"X 40"in oridinary soil (with
40' disel hammer ) peneration average 40'. Ft 40

Labour
Foreman Manday 0.25
Pile driving machine operator Manday 0.25
Pile driving machine asst Manday 0.25
Crane operator Manday 0.25
Workers Manday 6

Tools Required
40' rail line trollies for transport of precast pile
One crane for loading, unloading, erecting &
pitching of precast pile Hrs 2
ANALYSIS OF RATES ( Bridges )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount
Pile driving machine No.1 Hrs 2

For Operation
H.S.D for pile driving machine Gal 1
H.S.D for crane Gal 1.125
Engine oil Gal 1.083
Sundries L-s

4 Labor for driving R.C.C pile 14" X14" X 40' in


oridinary soil (using drop hammer with winch
operated by machine ) penetration average Ft 40
40 feet.

Labour
Foreman Manday 0.5
Operator Manday 0.5
Workers Manday 8

Machine
Pile driving machine 1 No Hrs 4

For Operation
Diesel oil Gal 4
Grease oil,etc Gal 0.25
Sundries L-s

5 Labour for launching of R.S.J.S over bridge


supports (Using two pulleys and winch from
the other side) 5Nos X 44' X 24" X 7" at 95
lbs per rft.(Total 9.3 Tons) Tons 9.3

Labour
Bridge Foreman 3
Workers 45
Sundries

6 Labour for assembling and launching of


balley bridge 100' span.D/S. Tons 24.9
(Total weight =24.9 Ton)

Tools required
Bailey rollers = 6 Nos _ _
Bailey jacks = 2 Nos _ _
Jumpers 6 Nos. _ _
Sleepers or bailey clps 12 Nos _ _
One hammer _ _

Labour
Bridge foreman Manday 8
Workers Manday 80
ANALYSIS OF RATES ( Bridges )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount
Sundries L-s

7 Labour for assembling of C.H bridge (18' road


way) on scaffolding and fixing bolts and nuts
for all steel works complete 60' span single
depth total weight 23.45 Tons. Tons 23.45

Tools Required
Tools kit one _ _
One hammer _ _
Coir rope 1" 200 Rft _ _
25 Ton jacks 2 Nos _ _

Labour
Bridge foreman Manday 10
Workers Manday 80
Sundries L-s

8 Labour for assembling and launching of C.H


bridge (22' road way) bolts and nuts for all
steel work complete 160' span double depth.
Total weight = 150 Tons. Tons 150

Labour
Bridge foreman Manday 45
Skilled workers Manday 315
Unskilled workers Manday 2385

Tools Required
Total kit 1 No _ _
One hammer _ _
Coir rope 1" 200' _ _
4 Tons hand winch 2 Nos _ _
Bailey roller 6 Nos _ _
Jumpers 10 Nos _ _
Wire rope 750' _ _
One local lib _ _
Double pully 2 Nos _ _
Single pully 1 No _ _
50 Ton jacks 2 Nos _ _
Sundries L-s

9 Labour for assembling of german bridge ( 11'


road way ) on scaffoldings and lowering down
on supports or launching 60' span.
Total weight = 17.87 Tons. Tons 17.87

Labour
Bridge foreman Manday 8
Workers Manday 80
ANALYSIS OF RATES ( Bridges )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount

Tools Required
Bailey jacks 2 Nos _ _
Bailey rollers 6 Nos _ _
One spanner _ _
One hammer _ _
Sundries L-s

10 Labour for assembling of R.P.T bridge on sca-


ffoldings including rivetting and lowering down
on supports complete 100' span and 16' road
way.
Total weight = 64.2 Tons. Tons 64.2

Labour
Bridge foreman Manday 36
Skilled workers Manday 126
Unskilled workers Manday 414

Tools Required
4 Tons hand winch _ _
Wire rope " = 1500' _ _
Wire rope " = 750' _ _
Coir rope 1" = 500' _ _
Service bolts _ _
Double pulley 2 Nos _ _
Single pulley 1 No _ _
One bellow _ _
Two dollys _ _
Two riveting guns _ _
One compressor with two Nos hose pipes500' _ _
Local jib 1 No _ _
One hammer _ _
75 Tons jacks 2 Nos _ _
Sundries L-s

11 Labour for assembling & launching of R.P.T.


bridge after rivetting complete for all steelwork
100' span 16' road way.
Total weight = 64.2 Tons. Tons 64.2

Labour
Bridge foreman Manday 41
Skilled workers Manday 138
Unskilled workers Manday 447

Tools Required
4 Tons hand winch _ _
Wire rope " = 1500' _ _
Wire rope " = 750' _ _
ANALYSIS OF RATES ( Bridges )

9/27/2017 11:30
No Particular Unit Quantity Rate Per Amount
Coir rope 1" = 500' _ _
Service bolts _ _
Double pulley 2 Nos _ _
Single pulley 1 No _ _
One bellow _ _
Two dollys _ _
Two riveting guns _ _
One compressor with two Nos hose pipes500' _ _
Local jib 1 No _ _
One hammer _ _
75 Tons jacks 2 Nos _ _
Sundries L-s
Remark

Cost of timber piles


according to varying
dia, with of necess-
ary fittings is to be
included in the main
estimate.

Cost of timber piles


according to varying
dia, with of necess-
ary fittings is to be
included in the main
estimate.

Cost of RCpile to be
calculated accord-
ing to the reqd size
Remark
& included in the
main estimate.

Cost of R.C piles to


be calculated accor-
ding to the reqd
size & included in
the main estimate.
Remark
Remark
Remark
MISCELLANEOUS NOTES
No Particular Unit Quantity Rate Per Amount Remark

Allowing Wastage of building Materials

1 The quantities of material given allow for oridi-


nary Breakages,Wastage,Carriage,Etc,Viz.

(a) Scantlings( all timbers) 10%


(b) Small timber 2" X 2" cross section and below 15%
(c) For door and windows 15%
(d) X.P.M wire netting 10%
(e) Glass 50%
(f) Roofing tiles
(1)Mangalore pattern 20%
(2)Cement roof tiles 10%
(3)Asbestos cement sheets 10%
( g ) Floor tiles 5%
( h ) Marble slabs 7%
( i ) Plywood 15%
( j ) Steel Rods 5%
Task for an average artisan per (8 hrs) day.
1 Ballast
( a ) Breaking brick ballast 1" gauge. 20 Cft perday
( b ) Breaking brick ballast 1" gauge. 25 Cft perday
( c ) Breaking stone ballast 1" gauge. 12.5Cft perday
( d ) Breaking stone ballast 1" gauge. 10 Cft perday
2 Brick Work
( a ) Brick Work in lime mortor up to plith 25 Cft perday
( b ) Brick Work in superstructure 25 Cft perday
( c ) Brick Work in arches in buildings 20 Cft perday
( d ) Brick Work in bridges 20 Cft perday
( e ) Brick on edge in lime mortar 50 Sft perday
3 Stone Work
( a ) Coursed rubble masonary ( dressing ) 20 Cft each
( b ) Coursed rubble masonary laying 25 Cft each
( c ) Random rubble stone masonary ( dressing & laying ) 25 Cft each
( d ) Random rubble stone dry as in retaining walls 50 Cft each
( e ) Coursed stone arched work _
4 Wood Work
( a ) Sawing hard wood ( Pyingado or Engyin) 40 Sft (one pair of sawyers)
( b ) Sawing soft wood 60 Sft (one pair of sawyers)
( c ) Chowkets hard wood 1 Cft each
( d ) Chowkets soft wood 1.5 Cft each
( e ) Door battened & planed (Teak) 6 Sft each
( f ) Door battened & planed (Engyin) 6 Sft each
( g ) Door panelled & Glazed (Teak) 5 Sft each
( h ) Door panelled & Glazed ( Other Timber ) 6 Sft each
( i ) Window fully glazed (Teak) 4 Sft each
5 Roofing
( a ) Mangalore tiles 50 Sft each
( b ) C.I sheets 70 Sft each
( c ) Wagut 100 Sft each
( d ) Thatch 100 Sft each
( e ) Shingles 40 Sft each
6 Plastering & Painting
( a ) Plastering " one coat 100 Sft each
( b ) Plastering fine coat 100 Sft each
( c ) Painting 100 Sft each
( d ) White washing one coat 803 Sft each
( e ) Distempering one coat 400 Sft each
( f ) Painting doors & windows 200 Sft each
( g ) Painting plain surfaces 400 Sft each
( h ) Painting sheet iron roof 200 Sft each
( i ) Varnishing door & window 500 Sft each
( j ) Coal tarring one coat 250 Sft each
Weight Load table for various building materials
double bu- Lorries Tipping wa Lorry
No Materials Unit Weight
llock cart 15Cwt 30Cwt 3Cwt gon 27Cft Tippers
1 Asphalte paving Ton Ton 0.6 0.6 1.25 2.5 0.7 2
2 Asphalte socony Ton Ton 0.6 0.6 1.25 2.5 0.7 2
3 Brick 9" X 4 3/8" X 2 3/4" Each 7.5 Lbs 200 200 425 850 250 650
4 Brick ballast Cft 60 Lbs 25 25 50 100 27 80
5 Broken stone metal Cft 110 Lbs 18 15 30 60 20 50
6 Cement Ton Ton 0.75 0.75 1.5 3 0.9 2.5
7 Surkhi Cft 80 Lbs 25 20 40 80 27 60
8 Exp.metal (Av:) 8' X 4' Sft 40 Lbs 40 40 80 160 50 125
9 Fencing style No 949 220 Yd 415 Lbs 4 4 8 16 5 12
roll
10 Gravel Cft 110 Lbs 20 15 30 60 23 50
11 Kanker Cft 72 Lbs 25 22 45 90 27 70
12 Lime ordinary quick Cft 53 Lbs 25 30 60 120 27 95
13 Riding G.I 22G,7' Each 22 Lbs 75 75 150 300 100 240
14 Sand Cft 110 Lbs 20 15 30 60 23 50
15 Sheet C.I 24G,7' 100 Sht Ton 75 75 150 300 80 240
16 Sheet zinc 22G, 8' X 3' Each 25 Lbs 60 60 120 240 80 190
17 Shingles 15" X 5" Each 1.25 Lbs 1,500 1,250 2,500 5,000 1,600 4,000
18 Stone( building ) Cft 110 Lbs 18 18 37 75 20 60
19 Coal tar (5 gals drum) Each 63 Lbs 25 25 50 100 30 80
20 Tiles,mangalore roofing Each 5.5 Lbs 275 275 550 1,100 300 900
21 Tiles,mangalore ridging Each 6 Lbs 250 250 500 1,000 300 800
22 Timber scantling( average ) Ton Ton 0.6 0.6 1.2 2.4 _ 1.9
23 Wire netting " mesh 50 Yds 87 Lbs 17 17 35 70 20 55
roll
24 Wire barbed 448 Yds 112 Lbs 12 12 25 50 16 40
roll
25 Wire standard 7 ply 6 gauge 481 Yds 112 Lbs 12 12 25 50 16 40
26 6" thatch ( covering capacity ) Sft _ 120 120 240 480 _ 380
27 Bamboo large Nos _ 60 15 30 60 _ 50
28 Bamboo mouil Nos _ 120 120 240 480 _ 380
29 Bullies ( average ) Nos _ 9 9 18 36 _ 30
30 Chattai ( matting ) Sft _ 900 900 1,800 3,600 _ 2,900
31 4" piping Rft _ 120 120 240 480 _ 380

Means of Transport
(a)Mortor Transport
One military 3 ton (chev) lorry should do the equivalent work of 100 miles daily and efficient loading will give the following equivalents:

Loading sand ..4 Miles,unloading sand .. 3 Miles


Loading shingles .. 6 Miles unloading shingles . 4 Miles
Loading bricks 12 Miles unloading brick 8 Miles
Loading stores . 12 Miles unloading stores .. 8 Miles
Loading bamboos .. 18 Miles unloading bamboos 4 Miles
eg.Distance from shingle bed to job .. Say 12 Miles.

Distance .. 24 Miles
One Trip Loading ... 6 Miles
Unloading .. 4 Miles
34 Miles
3 trips = 102 Miles
(b)Bullock Cart
One bullock cart load is equivalent to one quarter of the load carried by the average 3 Tons(chev.) lorry .
( c )Railway Wagon
Approximate capacity of 10 Tons metre gauge Railway wagon.
2500 Nos bricks
10 Tons coal dust
10 Tons cement
160 Nos bullies
250 Cft swan timber or logs
400 Nos bamboo large
200 Cft boulder & stones ballast
10 Tons steel
35 Tons bitumen or tar
(35 Gals each)