Trabajos Preliminares
DEMOLICION DE PISO INCLUYENDO F.P. E=15 cm m 8.00 8.0
DEMOLICION DE MURO K.K SOGA m 4.00 4.0
TRAZO Y REPLANTEO PRELIMINAR m 218.8 48.6 46.9 314.3
0.0
Movimiento de Tierras 0.0
EXCAV.ZANJAS Y ZAPATAS Rt<2 kg/cm H=2.30 m m 160.0 160.0
EXCAV.ZANJAS Y ZAPATAS Rt<2 kg/cm H=1.20 m m 26.1 26.1
RELLENO MANUAL CON MATERIAL PROPIO m 38.4 8.5 46.9
ACARREO INTERNO, MATERIAL PROCEDENTE DE EXCAVA. m 160.4 22.9 183.3
ELIMINACION MATERIAL EXCEDENTE ACARREADO m 160.4 22.9 183.3
NIVELACION INTERIOR Y APISONADO ARA F.P. m 149.3 28.4 46.9 224.5
0.0
Obras de Concreto Simple 0.0
ZUB-ZAPATAS Y SUB-CIMIENTOS: CONCRETO C:H 1:12+30% P.G. m 69.55 4.1 73.6
CIMIENTO CORRIDO: CONCRETO C:H 1:10+30 % P.G. m 29.4 10.6 40.0
CIMIENTO CORRIDO: ENCOFRADO Y DESENCOFRADO m 83.0 30.8 113.8
SOBRECIMIENTO, CONCRETO C:H 1:8 + 25% P.M. m 2.9 1.7 4.6
SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO m 36.9 19.8 56.7
FALSO PISO MEZCLA 1:8 e=4" m 133.7 45.8 179.5
GRADAS EN RELLENO.- f'c=140kg/cm +25% P.M. m 0.7 0.7
GRADAS EN RELLENO.- ENCOFRADO Y DESENCOFRADO m 4.8 4.8
0.0
Obras de Concreto Armado 0.0
ZAPATAS.- CONCRETO f'c=175 kg/cm m 20.02 20.0
ZAPATAS- ENCOFRADO Y DESENCOFRADO m 61.76 61.8
ZAPATAS.- ACERO Fy=4200 kg/cm kg 235.01 235.0
VIGA DE CIMENTACION.- CONCRETO f'c=175 kg/cm m 10.1 2.7 12.8
VIGA DE CIMENTACION.- ENCOFRADO Y DESENCOFRADO m 86.8 29.8 116.5
VIGA DE CIMENTACION.- ACERO Fy=4200 kg/cm kg 1009.9 165.3 1175.3
COLUMNAS.- CONCRETO f'c=210 kg/cm m 6.1 6.1
COLUMNAS.- CONCRETO f'c=175 kg/cm m 1.0 2.0 3.1
COLUMNAS.- ENCOFRADO Y DESENCOFRADO m 86.3 20.7 107.0
COLUMNAS.- ACERO Fy=4200 kg/cm kg 1828.9 257.9 2086.8
VIGAS.- CONCRETO f'c=210 kg/cm m 12.3 12.3
VIGAS.- CONCRETO f'c=175 kg/cm m 0.6 1.7 2.3
VIGAS.- ENCOFRADO Y DESENCOFRADO m 97.3 17.0 114.2
VIGAS.- ACERO Fy=4200 kg/cm kg 1851.7 135.0 1986.8
LOSA ALIGERADA .- CONCRETO f'c= 210 kg/cm m 14.5 14.5
LOSA ALIGERADA.- ENCOFRADO Y DESENCOFRADO m 163.9 163.9
LOSA ALIGERADA.- ACERO Fy=4200 kg/cm kg 1016.1 1016.1
LOSA ALIGERADA.- LADRILLO DE TECHO DE 15 x 30 x 30 und 1366 1366
0.0
Estructuras de Madera y Coberturas 0.0
VIGA Y CORREAS DE MADERA TORNILLO SEC. VARIABLE m 71.5 71.5
COBERTURA CON GRAN ONDA DE 1.097 x 3.05m ANDINA m 52.9 52.9
CUMBRERA MOVIL CON GRAN ONDA m 6.5 6.5
0.0
Muros y Tabiques de Albailera 0.0
MURO DE LADRILLO KK TIPO IV CABEZA M:1:1:4 E=1.5 CM m 53.0 36.7 89.7
MURO DE LADRILLO KK TIPO IV SOGA M:1:1:4 E=1.5 CM m 38.0 42.7 80.7
ACERO DE REFUERZO HORIZONTAL kg 38.3 24.9 63.2
0.0
Pgina 1 de 18
R E S U M E N D E METRADOS ING. ROLANDO ROMERO DELGADO
OBRA : MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO " SAN GABRIEL " DE 3 SS.HH. O. EXTER.
DISEO. : ING. ROLANDO ROMERO DELGADO AULAS TOTAL
FECHA : 30 DE SETIEMBRE DE 2003
ARQUITECTURA 0.0
0.0
Revoques, Enlucidos y Molduras 0.0
TARRAJEO PRIMARIO PARA C/ZOCALOS Y ENCHAPES m 26.5 89.7 116.2
TARRAJEO EN MURO: INTERIOR Y EXTERIOR m 190.3 87.7 278.0
TARRAJEO DE COLUMNAS m 66.2 18.1 84.3
TARRAJEO DE VIGAS m 97.3 17.0 114.2
VESTIDURA DE DERRAMRES m 42.8 22.5 65.3
BRUAS SEGUN DETALLE m 383.6 115.1 498.7
0.0
Cielo Rasos 0.0
CIELO RASO CON MEZCLA m 163.9 163.9
0.0
Pisos y Pavimentos 0.0
ACABADO DE PISO CEMENTO PULIDO Y BRUADO e=2" m 138.8 24.1 162.9
VEREDA; CONCRETO f'c=140 kg/cm m 37.5 9.4 46.9 93.8
0.0
Contrazcalos 0.0
CONTR.S/COLOREAR H=10 cm MZ 1:2 e=1.5 cm m 86.2 86.2
CONTR. S/COLOREAR H=30 cm MZ 1:2 e=1.5 cm m 59.7 20.5 80.2
0.0
Zocalos 0.0
ENCHAPE CON MAYOLICA COLOR DE 20 x 20 - PRIMERA m 83.5 83.5
0.0
Cubiertas 0.0
IMPERMEABILIZANTE CON ASFALTO LIQUIDO EN TECHO m 193.8 193.8
0.0
Carpintera de Madera 0.0
PUERTA DE MADERA TORNILLO CON TABLEROS m 7.2 4.8 12.1
TICERO DE MADERA TORNILLO DE L=5.0m - BARNIZADO und 3.0 3.0
PUERTA DE TORNILLO C/TRAPLACADA DE TRIPLAY e=10 mm m 9.0 9.0
0.0
Carpinteria Metlica y Herrera 0.0
VENTANA C/SEG PERFILES DE 1" x 1" x 1/8" m 58.8 6.5 65.4
0.0
Cerrajera 0.0
BISAGRAS DE 4" x 4" PESADA EN PUERTAS pza 12.0 8.0 20.0
BISAGRAS DE 3" PARA CUBICULOS DE SS.HH. pza 30.0 30.0
CERRADURA TIPO FORTE 2 GOLPES, INCLUYE MANIJA pza 3.0 2.0 5.0
MANIJA DE BRONCE DE 4" PARA PUERTAS pza 3.0 12.0 15.0
CERROJO DE 3" PARA PUERTA DE SS.HH. pza 10.0 10.0
0.0
Vidrios, Cristales y Similares 0.0
VIDRIOS TRANSPARENTES SEMIDOBLES e=5 mm p 632.4 632.4
0.0
Pintura 0.0
PINTURA LATEX EN CIELO RASO, VIGAS, DERRAMES Y BRUAS m 279.5 24.0 303.6
PINTURA LATEX 2 MANOS EN MUROS Y COLUMNAS m 256.5 105.8 362.4
PINTURA ANTICOR.Y ESMALTE 2 MANOS EN CARPIN. METALICA m 58.8 6.5 65.4
PINTURA BARNIZ EN CARPINTERIA DE MADERA m 14.5 55.2 69.7
PINTURA ESMALTE EN CONTRAZOCALO DE CEMENTO m 145.8 20.5 166.4
0.0
Varios 0.0
PIZARRA MURAL DE 4.0 x 1.2 m und 3.0 3.0
JUNTA DE DILATACION C/TECNOPOR + CHEMA JUNTA NEGRA e=1 m 3.9 3.9
JUNTA DE DILATACION C/MORTERO ASFALTICO e=1" m 32.5 7.8 107.3 147.5
0.0
Pgina 2 de 18
R E S U M E N D E METRADOS ING. ROLANDO ROMERO DELGADO
OBRA : MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO " SAN GABRIEL " DE 3 SS.HH. O. EXTER.
DISEO. : ING. ROLANDO ROMERO DELGADO AULAS TOTAL
FECHA : 30 DE SETIEMBRE DE 2003
Pgina 3 de 18
SUSTENTO DE METRADOS
MEDIDAS
PARTIDA DESCRIPCIN UNID. CANT. PARCIAL TOTAL
LARGO ANCHO ALTO
Pgina 4 de 18
SUSTENTO DE METRADOS
MEDIDAS
PARTIDA DESCRIPCIN UNID. CANT. PARCIAL TOTAL
LARGO ANCHO ALTO
Corte 1 - 1 y 2 - 2 2 16.65 0.60 0.8 15.98
Pgina 5 de 18
SUSTENTO DE METRADOS
MEDIDAS
PARTIDA DESCRIPCIN UNID. CANT. PARCIAL TOTAL
LARGO ANCHO ALTO
C - A ( Anteriores ) 12 0.25 0.13 1.53 0.59
Encofrado y Desencofrado m 86.3
C-1 8 1.05 3.45 28.98
Pgina 6 de 18
SUSTENTO DE METRADOS
MEDIDAS
PARTIDA DESCRIPCIN UNID. CANT. PARCIAL TOTAL
LARGO ANCHO ALTO
1/2" 4 6.9 1.02 28.15
3/8" 4 36.0 1.34 0.58 111.92
3/8" 4 14.0 1.15 0.58 37.35
V-102 3/4" 3 9.8 2.26 66.44
5/8" 3 46.1 1.60 221.28
ARQUITECTURA
Pgina 7 de 18
SUSTENTO DE METRADOS
MEDIDAS
PARTIDA DESCRIPCIN UNID. CANT. PARCIAL TOTAL
LARGO ANCHO ALTO
C - A ( Posteriores ) 12 0.50 1.15 6.90
C - A ( Anteriores ) 9 0.50 1.525 6.86
C - A ( Anteriores ) 3 0.63 1.525 2.88
Vanos 12 1.50 0.160 2.88
Vanos 12 1.13 0.160 2.16
* Tarrajeo de Vigas m 97.3
V - 101 1 25.00 1.05 26.25
V - 101 1 25.00 0.85 21.25
VB 1 25.00 0.40 10.00
V - 102 2 5.75 0.60 6.90
V - 102 2 5.75 0.40 4.60
V - 102 ( Volado ) 2 1.30 0.64 1.66
V - 102 ( Volado ) 2 1.30 0.44 1.14
V - 103 3 5.75 0.85 14.66
V - 103 ( Volado ) 3 1.30 0.55 2.15
Viguetas Largas 9 3.875 0.20 6.98
Viguetas Cortas 3 2.775 0.20 1.67
* Vestidura de Derrames m 42.8
Ventanas 9 3.845 34.61
Ventanas 3 2.745 8.24
* Bruas segn diseo m 383.6
Pizarras 3 10.4 31.2
Elevacin Posterior 12 5.075 60.9
Elevacin Anterior 6 10.55 63.3
Vigas 2 5.45 10.9
Vigas 12 7.25 87.0
Vigas 3 23.25 69.8
Columnas Laterales 22 2.75 60.5
CIELO RASOS
* Cielo Raso con mezcla m 163.9
Losa 23.25 7.05
PISOS Y PAVIMENTOS
* Acabado de Cemento Pulido y bruado e=2" m 138.8
Interior 1 23.31 5.93 138.23
Puertas 3 1.1 0.16 0.53
* Vereda: Concreto f'c=140 kg/cm m 37.5
25.0 1.5
CONTRAZOCALOS
* Contrazocalo s/color h=10 cm e=1,5 cm m 86.2
Aulas 86.16
* Contrazocalo s/color h=30 cm e=1,5 cm m 59.7
Exterior 59.68
CUBIERTAS
* Impermeabilizante c/asfalto lquido en techo m 193.8
25.0 7.8
CARPINTERIA DE MADERA
* Puerta de Tornillo c/tableros de tornillo m 7.2
P-1 3 1.15 2.1
* Ticero de madera Tornillo de l=4.0m - Barnizado m 3.0
Pgina 8 de 18
SUSTENTO DE METRADOS
MEDIDAS
PARTIDA DESCRIPCIN UNID. CANT. PARCIAL TOTAL
LARGO ANCHO ALTO
Vent. Posteriores 6 3.85 1.5 34.6
Vent. Anteriores 3 3.85 1.125 13.0
Vent. Anteriores 3 2.75 1.125 9.3
Sobre luz 3 1.1 0.6 2.0
CERRAJERIA m 3.1
* Bisagras de 4" pesada en puertas und 12.0
ARTEFACTOS
Pgina 9 de 18
SUSTENTO DE METRADOS
MEDIDAS
PARTIDA DESCRIPCIN UNID. CANT. PARCIAL TOTAL
LARGO ANCHO ALTO
Artefacto fluorescente de 3x36, adosado und 12.0
Pgina 10 de 18
SUSTENTO DE METRADOS
OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO " SAN GABRIEL " DE CASCAS
DISEO: ING. ROLANDO ROMERO DELGADO
HECHO POR: Ing. ROLANDO ROMERO DELGADO FECHA: Trujillo, 30 de Setiembre de 2003
MEDIDAS
PARTID DESCRIPCION UND CANT PARCIAL TOTAL
LARGO ANCHO ALTO
Pgina 11 de 18
SUSTENTO DE METRADOS
OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO " SAN GABRIEL " DE CASCAS
DISEO: ING. ROLANDO ROMERO DELGADO
HECHO POR: Ing. ROLANDO ROMERO DELGADO FECHA: Trujillo, 30 de Setiembre de 2003
MEDIDAS
PARTID DESCRIPCION UND CANT PARCIAL TOTAL
LARGO ANCHO ALTO
Corte B - B 1 4.50 0.60 2.70
Corte C - C 1 8.30 0.60 4.98
Pgina 12 de 18
SUSTENTO DE METRADOS
OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO " SAN GABRIEL " DE CASCAS
DISEO: ING. ROLANDO ROMERO DELGADO
HECHO POR: Ing. ROLANDO ROMERO DELGADO FECHA: Trujillo, 30 de Setiembre de 2003
MEDIDAS
PARTID DESCRIPCION UND CANT PARCIAL TOTAL
LARGO ANCHO ALTO
1/4" 2 24.0 0.96 0.25 11.52
V-101 4 3/8" 4 4.0 5.49 0.58 50.95
1/4" 4 20.0 0.94 0.25 18.80
ESTRUCTURA DE MADERA Y COBERTURAS
Pgina 13 de 18
SUSTENTO DE METRADOS
OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO " SAN GABRIEL " DE CASCAS
DISEO: ING. ROLANDO ROMERO DELGADO
HECHO POR: Ing. ROLANDO ROMERO DELGADO FECHA: Trujillo, 30 de Setiembre de 2003
MEDIDAS
PARTID DESCRIPCION UND CANT PARCIAL TOTAL
LARGO ANCHO ALTO
Ventanas 1 8.70 8.70
Cubiculos 2 6.90 13.80
* Bruas segn diseo m 115.1
En Enchapes 1 60.91 60.9
Elevacin Posterior 2 7.75 15.5
Elevacin Anterior 2 3.85 7.7
Elecacion Lateral 2 15.5 31.0
PISOS Y PAVIMENTOS
Pgina 14 de 18
SUSTENTO DE METRADOS
OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO " SAN GABRIEL " DE CASCAS
DISEO: ING. ROLANDO ROMERO DELGADO
HECHO POR: Ing. ROLANDO ROMERO DELGADO FECHA: Trujillo, 30 de Setiembre de 2003
MEDIDAS
PARTID DESCRIPCION UND CANT PARCIAL TOTAL
LARGO ANCHO ALTO
Muros 87.74
Columnas 18.11
* Pintura anticorrosiva y esmalte en Ventanas m 6.5
INSTALACIONES SANITARIAS
* Salida de desague en PVC 2", 3" y 4" pto 12.0
Pgina 15 de 18
SUSTENTO DE METRADOS
OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO " SAN GABRIEL " DE CASCAS
DISEO: ING. ROLANDO ROMERO DELGADO
HECHO POR: Ing. ROLANDO ROMERO DELGADO FECHA: Trujillo, 30 de Setiembre de 2003
MEDIDAS
PARTID DESCRIPCION UND CANT PARCIAL TOTAL
LARGO ANCHO ALTO
INSTALACIONES ELECTRICAS
* Salida de techo ( Centro de luz ) pto 2.0
CONDUCTORES Y/O CABLES
* Caja de pase de F G liviano 200 x 200 x 100 und 1.0
TABLEROS Y CUCHILLAS (Llaves)
* Tablero Termomagnetico ( TD-SS.HH. ) und 1.0
1-2x30A y 1 - 2x15A
ARTEFACTOS
Artefacto florescente circular de 40 W und 2.0
Pgina 16 de 18
HOJA DE SUSTENTO DE METRADOS
OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO " SAN GABRIEL " DE CASCAS
DISEO: ING. ROLANDO ROMERO DELGADO
HECHO POR: ING. ROLANDO ROMERO DELGADO FECHA: Trujillo, 30 de Setiembre de 2003
MEDIDAS
PARTID DESCRIPCION UND CANT PARCIAL TOTAL
LARGO ANCHO ALTO
INSTALACIONES SANITARIAS
Pgina 17 de 18
HOJA DE SUSTENTO DE METRADOS
OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA DEL COLEGIO " SAN GABRIEL " DE CASCAS
DISEO: ING. ROLANDO ROMERO DELGADO
HECHO POR: ING. ROLANDO ROMERO DELGADO FECHA: Trujillo, 30 de Setiembre de 2003
MEDIDAS
PARTID DESCRIPCION UND CANT PARCIAL TOTAL
LARGO ANCHO ALTO
INSTALACIONES ELECTRICAS
INSTALACIONES ELECTRICAS
* Cable TW 3 x 4 mm + 1 x 6 mm m 9.0
* Cable TW 2 x 4 mm m 19.0
Pgina 18 de 18