I. HSE Matters
Item. 11867C
Replacement corroded and leaking 3 diesel fuel distribution line at CEB
Status:
Completed
NOTE:
Based on result of CPA/INS inspection on 29 June 2012, 3 header line of diesel fuel will
be replaced, waiting for drawing approved by CPA/PRD. Presently, supply of diesel fuel to
each TEG and DEB, supplied by new line. Existing line was blind spaded.
Item. 11172H
Replacement of 12 reducer tee and bar tee installation at HQA gathering
line
Status:
Completed
Item. 12490H
Spading and de-spading activity for piping modification 12 LP line HI to
CPA
Status:
Completed
Item. 12467H
Replacement of 6 #600 RTJ ball valve at HQA gathering line, due to passing
and seepage at body valve.
Status:
Completed
Item. 12507C
Replacement diesel fuel distribution line from T-6020, CEB
Status:
Sheet 2 of 3
- Stringing material
- Install scaffolding
- Double joint activity
Remaining:
- Repair welding, 1 joint
- Tie ins activity, waiting for brief procedure
Sheet 3 of 3
- Tie ins activity, waiting for TOP.
Item. 12535H
Install operating access for 2 SDV gas lift line at HDA
Status:
Completed
Item. 112522C
Replacement of exhaust stack TEG-105 and modification at CEB area
Status:
Completed
NIL