HANDOVER NOTES

Site / Place of Handover : Handil


Department / Service : CST/OPB/HDL
From :I Gede Andi Dipayadnya
Date / Time :11 July 2012
To : Agus D.L
CC : Mr. Sentot H./ Mr. Sri Widadi

I. HSE Matters

ALWAYS REMINDER ALL OF THE CREW ABOUT ZERO TOLERANCE CAMPIGN

II. Work In progress and Today Activities


Item. 12299C
Repair by doubler corroded section of platform leg and bracing at BSB area
Status:
- Install scaffolding
- Stringing material
- Doubler 10 bracing at row B, completed
Remaining:
- Continue install scaffolding at 30 platform leg.
- Continue doubler corroded section, 8 and 10 bracing and 30 platform leg, row. 1 and 2
(see drawing)
- NDT (penetrant)
- Touch up painting
- Dismantle scaffolding
Progress Reported: 20 %

III. Main Events on the Period.

Item. 11867C
Replacement corroded and leaking 3 diesel fuel distribution line at CEB
Status:
Completed
NOTE:
Based on result of CPA/INS inspection on 29 June 2012, 3 header line of diesel fuel will
be replaced, waiting for drawing approved by CPA/PRD. Presently, supply of diesel fuel to
each TEG and DEB, supplied by new line. Existing line was blind spaded.
Item. 11172H
Replacement of 12 reducer tee and bar tee installation at HQA gathering
line
Status:
Completed

Item. 12490H
Spading and de-spading activity for piping modification 12 LP line HI to
CPA
Status:
Completed

Item. 12467H
Replacement of 6 #600 RTJ ball valve at HQA gathering line, due to passing
and seepage at body valve.
Status:
Completed

Item. 12507C
Replacement diesel fuel distribution line from T-6020, CEB
Status:
Sheet 2 of 3
- Stringing material
- Install scaffolding
- Double joint activity
Remaining:
- Repair welding, 1 joint
- Tie ins activity, waiting for brief procedure
Sheet 3 of 3
- Tie ins activity, waiting for TOP.

Item. 12535H
Install operating access for 2 SDV gas lift line at HDA
Status:
Completed
Item. 112522C
Replacement of exhaust stack TEG-105 and modification at CEB area
Status:
Completed

IV. High Priority Job to be done in forthcoming days


Item. 12666C
Modification beam at TEG-225
Item. 11632C
Replace 3 diesel fuel line
Item. 12337C
Replacement 4 sprinkler line D/S XDV. 8802, LEX

V. Pending Job and to be solved

NIL

VI. Miscellaneous Items

- Contractors team under PT. Meindo, Foreman: Afrizal


- MOP LCT. Logindo Pelican will be valid until 12 July 2012

VII. Signature of Leaving Personnel Signature of Incoming Personnel

( I Gede Andi Dipayadnya ) ( Agus DL )