You are on page 1of 7

Modelling and Simulation of an Adaptive Differential Current

Protection Scheme for a Solar PV Microgrid


C. Louw*; C. Buque; Dr S Chowdhury#

*Electrical Engineering Department, University of Cape Town, South Africa, chrislouw@hotmail.com,



Thermal and Renewable Energy Division, Mott MacDonald, South Africa, claudiobuque@yahoo.com.br,
#
Electrical Engineering Department, University of Cape Town, South Africa, sunetra.chowdhury@uct.ac.za

Keywords: Microgrid, Solar PV Array, Adaptive island mode. Optimal DG sizing techniques have been
Differential Current, Relay Model, Protection Coordination developed and can be used to efficiently size the microgrids
[8].
Abstract
The microgrid network is supplied by three 100kW
This paper presents modelling and simulation of an adaptive photovoltaic arrays designated as PV-DG1 feeding Bus 1,
differential current protection scheme for a solar PV-DG2 feeding Bus 2 and PV-DG3 feeding Bus 3. The PV
photovoltaic microgrid which is capable of operating in both array output is controlled depending on the mode of
grid-connected and islanded modes. The microgridtest operation. The PV Arrays voltage is stepped up to 22kV
model comprises three photovoltaic generators, each through a 100kVA 3- phase 2-winding transformer. Authors
connected to a load. The entire microgrid is connected to the in [7] suggest the use of smart PV inverters with active and
main utility network through a static switch (SS). The reactive power capabilities, to assist in grid code compliance
protection system contains differential relays which monitor during operation. These capabilities were included during
current parameters at specific points within the microgrid to the modelling of the PV inverters for this paper.
detect the fault. The settings of the relays are changed
through the relay operating algorithm to suit the current
Utility Grid
mode of operation. The relays are effectively coordinated
through a central controller which uses differential current
to detect and isolate faults occurring in various zones.

1. Introduction
5
The integration of renewable energy generation to existing
SS
power networks started through the use of distributed
generation. Once distributed generation became established R1_2 R1_1 R1_3
4
the concept of microgrids became more appealing. Globally, CB 2 CB 6 CB 10

the installed capacity of photovoltaic systems has increased


at a higher rate than what the development of grid codes was ZONE 1 FEEDER 2 ZONE 1 FEEDER 1 ZONE 1 FEEDER 3
able to cope with [7]. Theincreased popularityis due its
capability of acting in grid-connected mode, in which it can CB 3 CB 7 CB 11
R2_2 1 R2_1 R2_3 3
support the utility or island mode in which the islanded 2

microgrid can support itself. The microgrid concept, with CB 5


ZONE 2 CB 9
ZONE 2 CB 13
ZONE 2
distributed generators, is a great advancement for the power R3_2 R3_1 R3_3
industry but its use is limited due to the dynamic nature of
the current within the microgrid. It is for this reason that CB 4 CB 8 CB 12

special protection schemes are required to ensure safe L2 L1 L3


operation in both modes of operation and to reduce the
possibility of damaging electrical equipment. PV-DG 2 PV-DG 1 PV-DG 3
Fig.1 Schematic Diagram of Microgrid Model
2. Microgrid Test System
The microgrid network is connected to the utility through
2.1 Microgrid Model the static switch (SS), between Bus 4 and Bus 5 as shown in
A model of the 22kV test microgridsimulated in Matlabcan Fig. 1. The microgrid can operate in grid-connected mode if
be seen in Fig. 1. The utility generator produces electrical SS is closed and in island mode if SS is open. The
power at a voltage of 120kV [1]. This voltage is then respective PV arrays each supply the demand required by
stepped down by a 3-phase 2-winding transformer to the the load connected to their own dedicated bus. This scheme
distribution voltage level of 22kV at Bus 5. The holds for both grid-connected and islanded mode.
22kVdistribution voltage from the utility is then supplied to
the microgrid section through three distribution feeders of Zones of protection are set up along each line within the
varying lengths, with the default Matlab parameters being microgrid. Protection Zone 1 and Zone 2for all the feeders
used for simulation. are shown in Fig.1. These zones are protected from faults by
coordinating the relays along each line to trip the circuit
The loads connected to the microgrid network were chosen breakers (CBs) only within the faulted zone. Relays R1_1,
to be purely resistive and less than the PV array capacity to R2_1 and R3_1 along line 1, as well as all the other relays
allow for there to be adequate capacity once operating in along line 2 and line 3, each with their own current
1
transformerare also shown in Fig.1. The same zones and The relay takes in the 3-phase current from each end of the
relays are applied along each line within the microgrid. feeder. The 3-phase current is then converted into its RMS
Only 3-phase faults aresimulated within the zones because value, and then its magnitude extracted. The two
they are the most severe and destructive faults that can magnitudes are then subtracted and the absolute value of the
occur in a power network. subtracted values is then set as the differential current of the
feeder.
The grid-connected operation assumes that any excess
capacity produced by the PV arrays is fed back to the utility, The varying levels of fault current and changes in network
as would be the case for selling back capacity to the utility configuration, produced during faults in both modes of
or peak-shaving support for the utility. The utility supplies operation, as discussed in [4], implies that it is hard to
the extra capacity needed if the PV arrays do not produce discriminate the differential current for certain feeders and
enough capacity to supply the load in grid-connected mode. areas in the network. The low currents also mean that
This could happen due to insufficient irradiance. opening or closing of circuit breakers could present
differential current whilst there is no fault, therefore it is
important to have efficient relay coordination in place.The
2.2 Protection System Model
coordination methods presented in this paper are novel and
Differential current protection is a popular technique allow the differential protection system to adapt its settings
proposed for microgrids and small transmission systems. according to the modes of operation in microgrids.
The technique uses the principle that under normal
conditions, the same current that enters a feeder will leave 2.3 Relay Coordination
the feeder; hence the differential current (defined as the
difference between the currents entering the feeder and In order to coordinate the relays, the level of fault current at
leaving the same) should be zero. However, this will not be each relay within the microgrid is needed during both
the case when a fault occurs, and a non-zero differential operating modes. This is done by performing a fault study
current is used to detect a fault condition. Similar protection which involved simulating a 3-phase fault within Zone 1
systems are used in [2] and [3]. and Zone 2 along Feeder 1.Once thelevel of fault current at
each relay is obtained, the differential fault current between
The technique measures the magnitude of the current each of the relays is calculated for Zone 1 and Zone 2 on
between two relays at each end of a feeder. The magnitude Feeder 1.The differential fault current between each relay is
of the currents are measured and subtracted from each other. then used to find a unique differential fault current between
The absolute value of the subtracted value is used as an specific relays which only occur when there is a fault in
indicator of a fault condition. The differential current will be Zone 1 or a fault in Zone 2 on Feeder 1. This unique
close to or equal to zero if all the current entering the feeder differential fault current between specific relays is then set
leaves the feeder. Under fault conditions various sources as a differential fault current limit within the relays. This
contribute to the fault from different paths thus increasing unique limit or condition means relays will now only trip
the absolute value of the differential current to greater than the faulted zone on Feeder 1, because each zone on Feeder 1
zero. The level of the differential current must be has its own unique differential fault current limit.This
predetermined to allow for the proper tripping of circuit method is developed to ensure the relays would be able to
breakers. This is particularly effective in short transmission distinguish between normal operating currents and fault
lines where the line losses are minimal. The relay reaction currents in both operating modes and false tripping would
times are ideal for the simulated cases in this paper, be avoided. The differential fault current for Zone 1 on
however an additional reaction delay would be included in Feeder 1 in both modes of operation is shown below.
practical applications, to prevent tripping from false fault
Table 1: Differential Current Relay Coordination - Island Mode
detection and to comply with the industry standards. RELAY NO FAULT OPERATION FAULT OPERATION
POSITION (A) (A)
The relay model designed to implement the differential R2_1 & R2_2 0.1 1.17
current protection is shown in Fig .2. R2_1 & R2_3 0.1 1.17
R2_1 & R1_1 0.2 6
R2_1 & R3_1 2 0
Table 2: Differential Current Relay Coordination Grid-connected Mode
RELAY NO FAULT OPERATION FAULT OPERATION
POSITION (A) (A)
R2_1 & R2_2 0.25 0
R2_1 & R2_3 0.25 0
R2_1 & R1_1 0 6400
R2_1 & R3_1 2 0

Fig.2 Differential Current Relay Model Table 1 shows the values of the differential current between
specific relay positions during the simulated fault in Zone 1

2
on Feeder 1for island mode. The position of Zone 1 fault is specifically for this test microgrid. The conditions for a fault
shown in Fig.3. The differential current between relay R2_1 in Zone 1 and Zone 2 for Feeder 1 are shown in Table 3
and all the other relay positions is the difference between below.
the fault current contributions leaving each of the PV-DGs.
The fault current contribution of PV-DG2 and PV-DG3 is Table 3: Primary Protection Fault Conditions for Feeder 1
greater than PV-DG1 because their loads are smaller. The
significant or uniquedifferential current, in island mode, is Zone Island (A) Grid (A)
the one between relaysR2_1 and R1_1. This indicates that a Zone 1 (R2_1)(R1_1)>1 (R2_1)(R1_1)>15
fault is occurring between those two relays. The flow of [(R2_1)(R2_2)>3]&& [(R2_1)(R2_2)>15] &&
fault current for this case can be seen in Fig. 3below. Zone 2 [(R2_1) (R2_3) >3] && [(R2_1) (R2_3) >15] &&
[(R2_1)(R3_1)< 1] [(R2_1)(R3_1)< 1]
5
SS = OPEN For Zone 1 fault in island mode, current through R2_1 is
R1_1
4 differentiated with the current through R1_1. In this specific
CB 6
test microgrid, the current through R1_1 will always be
greater than the current through R2_1 during a fault because
ZONE 1 FEEDER 1
FAULT the other PV-DGs will combine their fault current and this
CB 7 combined current passes through R1_1.This means a
1 R2_1 2 3
differential current will always be present during a fault in
CB 9
ZONE 2
Zone 1 on Feeder 1, as seen in Fig. 3. This is not a typical
R3_1 characteristic of microgrids and is only identified through
CB 8
detailed analysis of the power network design. The limit of
L2 L1 L3
greater than 1A is chosen for the island condition because
PV-DG 2 PV-DG 1 PV-DG 3
the normal operating current or no fault differential current
Fig. 3 Fault Current flow for a Zone 1 fault in island mode is 0.1A, and the differential fault current exceeds 1A, as
seen in Table 1. This will ensure a trip signal is sent only if
Fig. 3 clearly shows how the fault current contribution from the differential fault current is greater than the no fault
PV-DG 2 and PV-DG 3 combines and moves down Feeder differential current and that the trip signal is sustained while
1 to contribute to the fault current which is measured at the fault occurs. The grid-connected condition for Zone 1 is
R1_1. The fault current caused by PV-DG1 passes through the same except the limit on the differential current is set to
R2_1 which is why the differential current between these 15A, three times the normal rated current. This is done to
two relay positions shows a visible difference. This unique ensure no unnecessary tripping would take place. It also
differential current can be seen in the grid-connected mode limits the amount of fault currentallowed in the network
as well, except the differential current is much higher, as from the utility which improves the protection on network
shown in Table 2, due to the fault current contribution from equipment.If the differential current is less than 15A during
the utility side.For a fault in Zone 1, the same relays are a fault in grid connected mode the relays will not pick-up
used to measure the differential fault current, however the the fault. The differential current limit of 15A for grid
magnitude of the differential fault current limit must differ connected mode can be adjusted if a more sensitive setting
during each operating mode to avoid nuisance tripping. is required. However, the differential currents caused during
the initial stages of switching between operating modes or
The differential current can determine if a fault occurs on a the time it takes those differential currents to settle to a
specific line by monitoring the current at both ends of the steady state, will determine by how much the limit can be
line as shown in Table 1. The magnitude of the current from adjusted.The higher the setting the less the likelihood of a
a single source, or lack thereof, does not matter because of nuisance trip. To eliminate this non-detection zone, a
the multiple sources present which will cause a difference in voltage based protection system could be included as a
fault current. This is crucial for inverter-based generation back-up protection system.
where fault current is limited [5]. This is the reason for
using differential current as the primary protection system. The conditions for a fault in Zone2 on Feeder 1 differentiate
the currents through R2_1 and R3_1 as well as the currents
The limited fault current contribution and the knowledge of through R2_1, R2_2 and R2_3. The fault currents through
the fault direction from each source allow for appropriate R2_1 and R3_1 will flow toward the Zone 2 fault and will
conditions to be set which would indicate a fault on any be the same which means the differential current will be
feeder and any zone on that feeder. These conditions can be zero between them, as seen in Fig 4. This condition however
programmed into a central controller using combinational is not sufficient for a trip signal because for a fault in Zone 1
logic. The specific relays and the magnitude of the all the fault current from the PV-DG1 flows towards the
differential fault current between those relays, caused by a 3 fault, as seen in Fig. 3, which means the current through
phase fault, are found in Table 1 and Table 2. These values R2_1 and R3_1 will be the same, hence the differential
set the differential fault current limit for each condition current will also be zero. This means that if the condition for

3
a fault in Zone 2 is kept as only the differential current 3 Testing Methodology and Case Studies
between R2_1 and R3_1, a fault in Zone 2 would send trip
signals toboth Zone 1and Zone 2 circuit breakers. This is 3.1 Test Case 1: Fault in Zone 1 on Feeder 1 - SS Open
not wanted so an additional condition is set for Zone 2
meaning only once both conditions are met a trip signal will A 3-phase fault is applied in Zone1 on Feeder 1 while SS is
be sent to the Zone 2 circuit breakers. The additional open, indicating island mode. The detection and isolation of
condition is that the differential current between R2_1 and this fault is crucial for microgrid operation in island mode.
R2_2 must be greater than 3A.Based on the results of 3- Before fault inception at the point shown in Fig.3, the
phase fault studies, the limit is chosen to be greater than the voltage at each bus during island mode is expected to be the
maximum differential fault current seen between R2_1 and nominal RMS voltage, while the currents at each bus are
R2_2 during a fault in Zone 1 but less than a differential expected to be close to zero since all the PV-DGs are set to
fault current of 5A seen for a fault in Zone 2. This ensures equal capacity as the load demand. The fault, however,
this condition will only be true for faults in Zone 2. The limits each PV-DG to supply twice their maximum current
value of 3A is only applicable to the network being rating, which is seen on each bus. The simulation is run for
investigated, however a similar methodology could apply to 1s, with predetermined islanding occurring at 0.3s, relay
other networks. This will be the case for a fault in Zone 2 thresholds switch to island mode, and the fault occurs from
because the current from PV-DG1 will not go past R2_1 so 0.5s to 0.6s.
the differential current between R2_2 and R2_1 will be
greater than the same measurement for a fault in Zone 1. The fault currents from PV-DG 2 and PV-DG3 combines to
feed the fault from above R1_1, while the fault current from
5 PV-DG1 is supplied from below R2_1. Once the fault is
SS = OPEN detected a trip signal is sent to CB6 and CB7 at the ends of
4
Feeder 1. This will isolate the faulted section, so no current
R1_1
CB 6 can be fed to the fault from either side of the feeder. PV-
DG 1 will now be islanded from the islanded microgrid but
ZONE 1 FEEDER 1 should still supply Load 1. Feeder 2 and Feeder 3 will still
be connected to each other and can share excess load.
CB 7
Frequency deviation is kept at a minimum in the microgrid
1 R2_1 2 3
by matching the respective PV-DGs with their loads [6].
CB 9
ZONE 2
FAULT
R3_1
CB 8

L2 L1 L3

PV-DG 2 PV-DG 1 PV-DG 3


Fig. 4 Fault current flow for a Zone 2 fault in island mode

The conditions set in Table 3allows for protection of each


zone on Feeder 1. Different relays positions can then be
used to set conditions and coordinate fault protection on any
of the feeders and in any of the zones.

The flow diagram in Fig.5 shows the operation procedure


for the protection system. In order to determine the
microgrid mode of operation during simulations, the 3-
phase current, Iabc_B5, through Bus 5 is measured.
However, in practice the state of the static switch, open or
closed, would be used to determine the mode of operation.
This means no current would flow to the microgrid during
island mode or when the PV-DGs fully supply the loads
requirements in either mode of operation. The protection
systems trip signal will finally pass through the sample and
hold block which holds the trip signal at 0, keeping the
circuit breaker open until the simulation ends.

Fig. 5 Relay Coordination Procedure

4
3.2 Test Case 2: Fault in Zone 1 on Feeder 1 - SS Closed 4 Results and Discussion
A 3-phase fault is applied in Zone1 on Feeder 1 while SS is 4.1 Test Case 1: Fault in Zone 1 on Feeder 1 - SS Open
closed, indicating grid-connected mode. Before fault
1.5
inception, the voltage at each bus during grid-connected
1
mode is expected to be the nominal RMS voltage,

Signal
0.5
maintained by the synchronous utility generators, while the
0
currents are expected to vary according to the irradiance.
-0.5
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Time (s)
Since SS is closed relay thresholds will not switch to island Fig. 5 Relay Trip Signals for Test Case 1
mode thresholds. The fault current of each PV-DG is limited
to approximately twice its max rating so it is expected that Current at Bus 1
most of the fault current will be supplied by the utility. The 4

amount of the fault current is expected to be higher. Fault

Current (A)
2

detection takes place according to the relay logic of Table 3 1

(Zone 1; grid-connected mode). 0


0 0.1 0.2 0.3 0.4 0.5
Time (s)
0.6 0.7 0.8 0.9 1

Current at Bus 2

The simulation is run for 1s with the fault occurring from


5

0.5s to 0.6s. The currents from Bus 1, Bus 2 and Bus 3 will

Current (A)
3

be shown to highlight the faults effect on the generators 1

before, during and after the fault event.


0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Time (s)

Current at Bus 3
5

3.3 Test Case 3: Fault in Zone 2 on Feeder 1 - SS Open 4

Current (A)
3

This case tests a fault on the PV-DG (Zone 2 fault as shown 1

in Fig.4) while in island mode. There will be a power 0


0 0.1 0.2 0.3 0.4 0.5
Time (s)
0.6 0.7 0.8 0.9 1

mismatch once the PV-DG is removed causing possible


network instability. The most important factor of this fault is Fig. 6 Currents for Bus 1, Bus 2 and Bus 3 for Test Case 1
the protection the PV-DG and to see how the protection
system operates under network instability. The fault occurring at Zone 1 on Feeder 1 is detected and
the trip signal sent to the circuit breakers, CB6 and CB7, as
The trip signals for this fault aretriggered by R2_1 and R3_1 shown in Fig. 5. This shows that once islanding takes place
and are sent to CB 7 and CB 8, respectively. CB 7 will the differential current thresholds was set to the island mode
disconnect Load 1 from the microgrid while CB 8 removes thresholds, otherwise it would not have detected the fault. It
the PV-DG. This test will be a successif the protection must also be noted that the trip signal for the same zone
scheme accurately detects the fault and isolates the fault. along the adjacent feedersdoes not trip. The relay takes
0.0047s to detect the fault and then sends the trip signal to
Islanding occurs at 0.3s, relay thresholds switch to island the correct CBs. This shows that the relay properly detected
mode, and the fault occurs from 0.5s to 0.6s. the fault and coordinated the correct CBs to isolate the
fault. Islanding takes place at 0.3s.The fault occurs at 0.5s.
3.4 Test Case 4: Fault in Zone 2 on Feeder 1 - SS Closed
The fault is detected and isolated by removing the faulted
In this case the protection scheme is tested against a fault on section withCB6 and CB7. PV-DG1 is now disconnected
a PV-DG while in grid connected mode. The trip signal in from the islanded microgrid but it still supplies Load1
grid connected mode will only be sent to CB 8 through Bus1.
disconnecting PV-DG 1. This is done by removing the CB 7 The current from each PV-DG is shown to be near zero, as
trip signal. In the island mode version of this fault, seen in seen in Fig. 6. This is because all the current from each PV-
Test Case 3, two trip signals are sent to avoid power DG is fed to its respective load. This means the bus shows
mismatches in the network. All power mismatches will be little or no current. The small current seen in the grid-
dealt with by the utility generators which will supply or connected mode is the excess power which is fed back into
absorb any excess power. This test will be a success if the the utility. Also the near zero current in island mode shows
protection scheme accurately detects the fault and isolates that the PV-DGs and their loads are correctly matched
only the faulted area. The fault occurs from 0.5s to 0.6s. which maintains the frequency while in island mode.

5
4.2 Test Case 2: Fault in Zone 1 on Feeder 1 - SS Closed shown in Fig. 9. This shows that once islanding takes place
1.5
the differential current thresholds was set to the island mode
1
thresholds, otherwise it would not have detected the fault.
The relay takes 0.0146s to detect the fault and sends the trip
Signal

0.5
0 signal to the correct CBs. This shows that the relay detected
-0.5
the fault and coordinated the correct CBs in order to isolate
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Time (s)
the fault.
Fig. 7 Relay Trip Signals for Test Case 2
The fault which occurs on PV-DG1 is removed from the
Current at Bus 1
network by CB 8 opening. CB 7 disconnects Load 1 from
3
the microgrid. This was done to avoid power mismatch in
the microgrid. The expected rise and fall in fault current
Current (A)

1
once the fault occurs and is isolated can be seen in Fig. 10.
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Time (s)

Current at Bus 2
20 Current at Bus 1
15
15
Current (A)

Current (A)
10
10

5 5

0 0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Time (s) Time (s)
Current at Bus 3 Current at Bus 2
20 6

15

Current (A)
Current (A)

4
10
2
5

0 0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Time (s)
Time (s)
Current at Bus 3
6

Fig. 8 Currents for Bus 1, Bus 2 and Bus 3 for Test Case 2
Current (A)

The fault occurring at Zone 1 on Feeder 1, while in grid 0


0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1

connected mode, is detected and the trip signal sent to the Time (s)

circuit breakers, CB6 and CB7, as shown in Fig. 7. It must


Fig. 10Currents for Bus 1, Bus 2 and Bus 3 for Test Case 3
be noted that the trip signal for the same zone along the
adjacent feeders does not trip. This shows that the grid-
connected thresholds are adequate. The relay takes 0.0006s The power for PV-DG1 reduces to zero after the fault
to detect the fault and then sends the trip signal to the occurs but this is due to it supplying the fault. The rest of
correct CBs. the microgrid network is stable but the quality of the supply
is slightly reduced.
The fault current seems like it is exclusively supplied by the
utility because fault currents are extremely large but the 4.4 Test Case 4: Fault in Zone 2 on Feeder 1 - SS Closed
inverter-based PV-DGs are supplying the fault as well. Feeder 1: Zone 4 Trip Signals
ThePV-DGs fault current is limited to twice their rated 1.5
1
current which is insignificant compared to the utility fault
Signals

0.5

current but it is still being supplied. Fig. 8 shows the twice 0

limited fault current supplied by PV-DG 2 and PV-DG 3 -0.5


0 0.1 0.2 0.3 0.4 0.5
Time (s)
0.6 0.7 0.8 0.9 1

during the fault and it shows currents are equal before and Fig. 11 Relay Trip Signal for Test Case 4
after the fault. This is the excess power being supplied to the
utility. The current at Bus 1 remains almost zero indicating The fault occurring at Zone 2 on Feeder 1 is detected and
PV-DG 1 is only supplying its load. the trip signal sent to the CB8 as shown in Fig. 11. This
indicates that the grid-connected thresholds are adequate.
4.3 Test Case 3: Fault in Zone 2 on Feeder 1 - SS Open The relay takes 0.0009s to detect the fault and then sends
1.5
p g
the trip signal to the correct CBs. This shows that the relay
1
properly detected the fault and coordinated the correct CBs
Signal

in order to isolate the fault.


0.5

-0.5
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Time (s)
The fault which occurs on PV-DG 1 is removed by CB 8
Fig. 9 Relay Trip Signals for Test Case 3
opening. Load 1 is still connected to the microgrid. Load 1
is now supplied by the utility since PV-DG1 was removed
The fault occurring at Zone 2 on Feeder 1 is detected and
once CB 8 opened. The fault occurs at 0.5s which leads to
the trip signal sent to the circuit breakers, CB8 and CB7, as
the expected initial current increases shown in Fig. 12.

6
Once the fault zone is isolated the voltage across the fully protected. This proves that the technique is appropriate
microgrid is maintained by utilities synchronous generators. for use in medium voltage photovoltaic microgrid systems.
The current spikes at the start of the fault, all the PV-DGs
supply fault current, and then the currents reduce to the Acknowledgements
nominal currents value once the faulted zone is isolated.
However, current through Bus 1 is almost 10 times greater The authors gratefully acknowledge the support and
than that of Bus 2 and Bus 3 due to the utility supplying infrastructure for the research work that was provided by the
fault current, which is shown in Fig. 12. The loads are now Electrical Engineering Department, University of Cape
supplied by the power generated by PV-DG 2 and PV-DG 3 Town, South Africa.
while the utility supplies any remaining load.
Current at Bus 1
References
100

[1] P Giroux, G Sybille, C Osorio, and S Chandrachood. (2012, January)


Current (A)

50
MathWorks. [Online].
0
www.mathworks.com/matlabcentral/fileexchange
0 0.1 0.2 0.3 0.4 0.5
Time (s)
0.6 0.7 0.8 0.9 1
/34752-grid-connected-pv-array
20
Current at Bus 2
[2] A.N. Milioudis, G.T. Andreou, and D.P. Labridis, "High Impedance
15 Fault Evaluation Using Narrowband Power Line Communication
Current (A)

10 Techniques",IEEE Trondheim PowerTech, pp. 1 - 6, 2011.


5
[3] E. Sortomme, S.S. Venkata, and J. Mitra, "Microgrid Protection
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 Using Communication-Assisted Digital Relays", IEEE Transactions
on Power Delivery, vol. 25, no. 4, pp. 2789-2796, October 2010.
Time (s)

Current at Bus 3
20

15
[4] C. Buque, O. Ipinnimo, S. Chowdhury, S.P. Chowdhury, Modelling
Current (A)

10 and simulation of an Adaptive Relaying Scheme for a Microgrid,


5 IEEE PES General Meeting, San Diego, USA, pp. 1-8, 2012.
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 [5] C. Buque, S. Chowdhury, Adaptive Protection for a Microgrid with
Time (s)
PV Generation, 12th International Conference on Sustainable Energy
Technologies (SET-2013), Hong Kong, pp. 1550-1561, August 2013.
Fig. 12 Currents for Bus 1, Bus 2 and Bus 3 for Test Case 4
[6] C. Buque, S. Chowdhury, S.P. Chowdhury, Modelling and
simulation of reverse power relay for loss of mains protection of
5 Conclusion distributed generation in microgrids, 2013 IEEE Power and Energy
Society General Meeting (PES), Vancouver, Canada, pp. 1-5,July
2013
Test Cases 1 and3show that the primary protection system
[7] M. Braun, T Stetz, R Brundlinger, et al., Is the distribution grid
detects and isolates all the faults in Zone1 and Zone2 whilst ready to accept large-scale photovoltaic deployment? State of the art,
in Island mode. The total capacity supplied by the PV-DGs progress, and future prospects, 26th EU PSVEC, Hamburg,
are matched with the load demand to ensure there is little Germany, pp. 681 697, 2011
frequency deviation. The currents from the PV-DGs are [8] M. Di Silvestre, G. Graditi and E. Sanseverin, A Generalised
stable and only contribute to the fault current while a fault Framework for Optimal Sizing of Distributed Energy resources in
Microgrids Using an Indicator-Based Swarm Approach, IEEE
occurs. Once the fault is removed the current quickly Transactions on Industrial Informatics, vol. 10, No.1, pp. 152-162,
stabilizes to their nominal values. Test Case 3 indicates that February 2014
once a fault is detected on the PV-DG, the PV-DG must be
immediately disconnected and turned off to avoid damaging
the PV-DG.
The differential fault currents in the microgrid while in grid-
connected mode are almost 50 times larger than the fault
currents in island mode. Test Case 2and Test Case 4 show
that the primary protection system detects and isolates all
the faults in Zone1and Zone2 whilst in grid connected
mode. This shows that the grid-connected conditions and
limits are accurate in detecting faults. Test Case 4 shows
that once the fault on the PV-DG is isolated the load is
supplied by the utility. The PV-DG must be immediately
turned off to avoid damaging the PV-DG.The voltage in
grid-connected mode is maintained by the synchronous
generators of the utility.

Finally, the use of differential currents to detect faults is an


accurate and robust technique which is mostly indifferent to
the low currents in inverter-based generation. The protection
systems added ability to adapt its settings according to the
microgrids mode of operation means the microgrid will be

You might also like