You are on page 1of 8

Pork Solar Tesla

resistance flares p7
p3 p4-5
Published by Megger
February 2016

ELECTRICAL
TESTER The industrys recognised information tool

Never mind the noise!


The majority of CTs have ratios of 3000:5, but there


are also some with ratios of 30,000:5. Tests were
carried out with the latest Megger MRCT relay and
current transformer tester , working in atrocious
conditions it was raining heavily and all work had
to be carried out under a tent.

Standard practice was followed when setting up


the test, with insulated wires from the top of the
bushings brought down to ground level for easier
connections. When testing was not underway, the
bushings were grounded through these wires.

The first tests were carried out on the H1 bushing


CTs. During the insulation resistance test, however,
the test set gave a warning that live voltage was
present on one of the bushings. Similar problems
were encountered when attempts were made to
test other CTs.

After carrying out further investigations, which


were hampered at all stages by the constant rain,
the engineers discovered that the root cause of the
measurement problems was that the H1 bushing was
acting as an antenna for electrical noise. To address
this problem, a directly connected grounding wire
was installed on the H1 bushing, even though this
bushing is also grounded via the test set.
in 765 kV substations. Engineers from Megger, results. Measurements falsely showing ratio errors Table 1 shows the connections made to test H1
Dinesh Chhajer working on site in conjunction with their utility of 100% and more were by no means unusual. bushing CTs. It is to be noted that H2 test lead of
- Manager, technical support group
counterparts, have now developed a complete and Having been made aware of the problem, the MRCT instrument was connected to X0 bushing
Jill Duplessis
effective solution to this challenging problem. The Megger engineers visited a substation where instead of X1 for the return path. Since the height of
- Technical Marketing Manager
subject utility, one of the largest in the USA with tests needed to be performed urgently in X0 bushing is smaller than X1 bushing, the electric
rainy weather on a single-phase 765 kV noise interference could be reduced by using X0
Electrical noise is an ever-present issue when trying over five million customers in 11 states, operates
autotransformer prior to energization. The bushing for return path.
to make reliable and accurate measurements in numerous 765 kV substations. A crucial part of transformer is a 750 MVA 765/528 kV unit
high-voltage substation environments and its an the commissioning process for power transformers with a 13.8 kV tertiary winding. It is sited With this arrangement, it was made possible to
at these substations is the testing of CTs. Despite adjacent to 765 kV transmission lines that were make accurate measurements on all six CTs on the
issue that was proving especially problematic for
in operation and energised during testing. H1 bushing. The worst-case error was just 0.029%,
one very large investor owned utility (IOU) in North having tried instruments from several different
and in most cases the error was well below 0.02%.
America. In particular, the company was finding manufacturers, this IOU had been unable to find The transformer has 17 CTs six on H1, four on
it impossible to test bushing CTs on transformers equipment that would give reliable and repeatable X1, two on H0-X0, three on Y1 and two on Y2. Continued on page 3

Bushing H1 X1 H0- Xo Y1 Y2 Bushing H1 X1 H0- Xo Y1 Y2


MRCT leads H1and Grounded Floating H2 Grounded Grounded MRCT leads H2 and grounded H1 Floating Grounded Grounded

Table 1 - Standard connections for H1 bushing CTs Table 2 - standard connections for testing X1 bushing CTs

New 800 kv test and development facility


Within weeks of opening, Meggers new Radeburg equipment, not least by extending the companys
Dr Sacha Markalous - General manager,
Hagenuk KMT
facility was used to present a seminar on HV DAC in-house capabilities up to 800 kV. Initially, the
(damped AC) testing, which offers a convenient
primary focus will be on the development and
In response to the rapidly evolving test requirements and cost-effective alternative to conventional
evaluation of HV DAC test equipment. The overall
of utilities and other organisations that operate power frequency testing of cables. It also hosted
HV and EHV power cables, Megger has opened a acceptance testing of a VLF (very low frequency) goal, however, is to develop practical equipment for
major new test, development and manufacturing burn unit supplied to Con Edison, and an R30 use where no satisfactory test solution is currently
facility in Radeburg, near Dresden in Germany. cable test van supplied to RTE-France. available, such as on the long undersea HV and
This became operational in October 2014 and
is equipped to work on test and diagnostic The new facility significantly expands the scope EHV cables that are being used increasingly for
equipment for cables operating at up to 800 kV. of Meggers operations in relation to cable test transmission links between regions and countries.

www.megger.com ELECTRICAL TESTER - February 2016 1


ELECTRICAL
The industrys recognised information tool TESTER
Contents Current transformers in electrical
Never mind the noise!......................................p1,3
Dinesh Chhajer - Manager, technical
diagnostics
support group &
Jill Duplessis - Technical Marketing Manager

New 800 kv test and development facility.........p1


Dr Sacha Markalous - General manager,
Hagenuk KMT

Current transformers in electrical diagnostics....p2 Fig 4 - An electrical installation with multiple


Dr Stan Zurek, MSc, PhD, SMIEEE - Manager of earthing points
magnetic development

Ill have a 100 bacon sandwich, please!..........p3


Keith Wilson, electrical engineer

Fig 8 - The double-clamp method in use


Megger host transformer and switchyard event in
Pennsylvania.........................................................p3 difficulty lies in the application of a known voltage
Greg Valdez - Marketing communications Dr Stan Zurek, MSc, PhD, SMIEEE
to a continuous circuit. However, this can be
manager - Manager of magnetic development
achieved by using a voltage transformer (VT).
Karen Becerril - CSA marketing specialist
A CT without anything connected to its output is
In the first part of this article, which appeared in an
The impact of GIC on electric power systems..p4-5 in fact a step-up VT. So if the secondary winding of Fig 5 - Equivalent circuit of installation with
earlier issue of Electrical Tester, we looked at the multiple earthing points (a) and simplified
Jill Duplessis - Global technical marketing manager such a transformer is driven with AC voltage, then
use of CTs in evaluating the condition of electrical equivalent circuit (b)
& Editor the device becomes a step-down VT.
insulation, particular in relation to portable
Need an update fast? Grab a power webinar!..P5
appliance testing (PAT testing). In this second and The CT shown in Fig. 6 has a ratio of 1000:1 so an
Yier Toh - Marketing engineer concluding part, we consider the role of CTs in AC current of 1 A in the primary cable produces 1
earth resistance measurement. Note that Figures mA of the output current. But the same device can
Pushing past the limitations of power factor testing 1 to 3 appeared with and relate to the first part be used as a VT, and if driven from the secondary
(part 2)...............................................................P6-7 of the article, which can still be accessed on line. side the ratio is still 1000:1, so 1 V applied to
Robert Breazeal - Southern California Edison
Earth Resistance the secondary winding will induce 1 mV in the
Jill Duplessis - Global technical marketing
primary cable. Combining VT and CT allows the
manager & Editor CTs are very useful in the diagnostics of earth or
measurement of resistance value in the loop.
ground resistance. A large building or installation
The principle is shown in Fig. 7 and a practical
Questions and Answers - Circuit breaker ...........p8 can have multiple earthing points (Fig. 4). Each
instrument in Fig. 8.
earthing electrode needs regular inspection. The
Five lesser-known facts about Tesla....................p8 equivalent electric circuit is such that all the earth For this particular instrument the voltage applied
Keith Wilson, electrical engineer resistances are connected in parallel. If there are is 30 V at 128 Hz. If the loop resistance is 1 ,
sufficiently many branches, the circuit simplifies to this will generate a loop current of 30 mA, which Fig 6 - An example of a clamp-on CT
a single resistance in a loop (Fig. 5), and just three will be stepped down to 30 A by the CT. The test
branches allow good indication of problematic instrument can measure the voltage applied to the
earth point. VT and the output current of the CT, and the ratios
For instance, let us assume that a good electrode of the VT and CT are constant. Hence, in this case
When you have finished with
this magazine please recycle it. has a resistance of 1 and a faulty value is the loop resistance can be calculated as:
10 . There are two good electrodes and one
Rx = VVT (ICT 10001000)
faulty electrode. Then measurement at a good
electrode will give Rx = 1 + 1||10 = 1.9 , but where: VVT = voltage applied by the instrument
The rights of the individuals attributed in Electrical Tester to be
measurement at the faulty electrode will give Rx = to the VT and ICT = output current from the CT as
identified as authors of their respective articles has been asserted
by them in accordance with the Copyright, Designs and Patents
10 + 1||1 = 10.5 . Therefore, the faulty electrode measured by the instrument.
Act 1988. Copyright Megger. All rights reserved. No part is easily identified. The values are more accurate Fig 7 - Principle of the double-clamp method
It is also possible to integrate both transformers (VT
of Electrical Tester may be reproduced in a retrieval system, or with more parallel branches.
transmitted in any form or by any means, electronic, mechanical, and CT) into a single device (Fig 9). This instrument
photo-copying, recording or otherwise without the prior written The measurement would be very simple (applying operates on the same principle as that discussed
permission of Megger. Ohms law) if it could be carried out directly. above, with two small differences: a higher
However, direct measurement is not possible operating frequency is used because the cross-
To request a licence to use an article in Electrical Tester, please
because this would mean introducing a break section area of the cores is smaller, and there is an
email electricaltester@Megger.com, with a brief outline of the in the loop shown in Fig. 5b. This is undesirable additional magnetic shielding between the internal
reasons for your request. for safety reasons, because if a fault occurred in VT and CT to improve measurement of small
the installation while the loop was broken, large currents in the proximity of the energised VT core.
potential could appear and could endanger the
All trademarks used herein are the property of their respective
operator or any other personnel in the vicinity of The resistance range is from 0.05 to 1500 .
owners. The use of any trademark in this text does not imply
the equipment. Moreover, after re-connection there Thus, the CT has to be able to detect currents from Fig 9 - An integrated double-clamp instrument,
trademark ownership rights in such trademarks, nor does use
less than 20 A to 1 A, because the induced loop and a close up of the jaws
of such trademarks imply any affiliation with or endorsement of
could be still doubt about the quality of connection.
Electrical Tester by such owners. voltage is at the level of 30 mV. Such measurement
A method is therefore needed where the
must be performed in the presence of much greater The other application is a contactless measurement
measurement can be carried out in a non-
leakage currents, which might be present due to of earth resistance with multiple grounding
invasive way. This can be achieved with clamp-on
A printed newsletter is not as interactive as its email equivalent the connection to the 50 Hz (or 60 Hz) network. electrodes. A current transformer in normal mode
current transformers (Fig. 6). One of the greatest
so to help you find items quickly on www.megger.com, we have
advantages of these devices is that they can be Summary is used for current detection. Voltage is injected
underlined key search words in blue.
clamped around a conductor without breaking the by driving a current transformer from its secondary
Current transformers are used for precise
current path and accurate measurements of AC side so that it behaves like a voltage transformer.
measurements relevant to safety and reliability in
Views expressed in Electrical Tester are not necessarily currents can be made. The loop resistance can be thus calculated from
the views of Megger. electrical installations.
Even contactless resistance measurement the known voltage and measured current. The
The word Megger is a registered trademark
simplifies to the application of Ohms law. Under Two examples were discussed in this series two transformers (voltage and current) can be
normal conditions the resistive component of of articles. The first shows the use of current integrated into a single instrument, to produce an
Editor Jill Duplessis impedance is dominant; capacitive and inductive transformers in portable appliance testing where easy-to-use handheld device.
E electricaltester@megger.com contributions can be neglected. Therefore, the leakage current in non-isolated devices needs to
Megger Limited be detected differentially at the level of 0.0001% In essence, the versatility and performance of current
voltage applied to the circuit generates a
Archcliffe Road Dover Kent CT17 9EN current that is inversely proportional to the or 1 ppm (10 A in 10 A). Only current transformers transformers mean that many of the instruments
T +44 (0)1304 502100 resistance. Measuring AC current with a clamp- are capable of performing such measurement with used for testing and diagnostics of electrical
E electricaltester@megger.com on CT is fairly easy. It requires only the CT and sufficient accuracy without using very expensive insulation and earthing can be made smaller, lighter,
www.megger.com an ammeter connected to its output. The instrumentation or components. safer, more reliable and less expensive.

2 ELECTRICAL TESTER - February 2016 www.megger.com


ELECTRICAL
The industrys recognised information tool TESTER
Never mind the noise! Bushing
MRCT leads
H1
H1 and grounded
X1
H2
H0- Xo
Floating
Y1
Grounded
Y2
Grounded

Continued from page 1 Table 3 - Modified connections for testing X1 bushing CTs
The results for the X1 bushing CTs showed slightly
Testing the CTs on the X1 bushing created an were shorted and grounded together. In all cases, and CT demagnetization) were completed on
higher errors worst case 0.24% than those for
additional challenge, since the ground connection accurate and repeatable results were obtained easily all 17 CTs in less than three hours, despite the
the H1 CTs. This was because the height of the X1 difficult working conditions. Based on their previous
from H1 could not be removed because of the level and quickly.
bushings made the measurements more susceptible experience, these IOU engineers had expected these
of electrical noise. The standard connections for the
to the effects of electrical noise induced by the The IOU engineers who witnessed the CT testing tests to take between one and two full days.
test set, shown in Table 2, could not be used as this
nearby live transmission lines. Nevertheless, the in the 765 kV transmission substation were very
would have created a ground loop (since H1 test This experience has demonstrated conclusively that
accuracy was still very good, and the utility engineers favourably impressed not only by the performance
lead is grounded at the test set). A slightly modified the Megger MRCT current transformer analyser
were completely satisfied with the measurements.
connection arrangement, shown in Table 3, was of Meggers MRCT test set, but also by its speed of is capable of delivering dependable and accurate
adopted. This has the effect of giving test results that A similar approach was used for measurements operation. Once the initial noise-related issues had results in high voltage substations where the high
have incorrect polarity, with 180 phase angle, but it on the X0 bushing CTs, while for tests on the Y1 been addressed, all the IEEE C57.13.1 recommended levels of electrical noise make it impossible for other
is easy to allow a fix for this. and Y2 bushing CTs all H1, X1 and X0 bushings tests (saturation, ratio, polarity, winding resistance instruments to operate correctly.

Ill have a 100 bacon sandwich, please!


Keith Wilson, electrical engineer measuring the resistance of the meat would
provide a reliable indication of salt penetration
and hence the progress of the curing process. His
When you next power up your trusty ohmmeter, first experiments were carried out with a supply
its unlikely that your intention will be to measure derived from the AC mains and rectified with a
the resistance of a lump of pork or bacon. Things thermionic valve. The current in the meat was
were rather different back in 1935, however, when measured with a milliammeter and the resistance
Evershed and Vignoles, one of the predecessor calculated using ohms law.
companies of Megger, sponsored the publication
The results were less than satisfactory, as
of a paper with the somewhat surprising title The
electrolysis meant that chlorine was liberated at
Electrical Resistance of Pork and Bacon. the test probes and this discoloured the meat. For
So what was it all about? A bored development subsequent experiments, a valve oscillator running
at 1 kHz (1,000 c/s in those days!) was used, and
engineer who just happened to plunge his test
the resistance measurements were carried out
probes into his breakfast sandwich and then
with a modified version of a Wheatstone bridge.
decided to share the results with the world?
No! As you might expect, there was a very good Now the results were encouraging, showing
reason for writing the paper and for carrying out a definite and repeatable, albeit non-linear,
the research that underpinned it. relationship between the resistance of the meat
and the salt content of the pork. So far, so good,
In an effort to justify this not inconsiderable effort, but using a valve oscillator and a Wheatstone
the paper points out that meat had been preserved bridge with headphones as null detector was quite
by curing for many years, but that back in 1935 clearly not exactly an optimum solution in a busy
at least there were few scientific controls over the meat processing plant.
curing process. In essence, the meat was pumped
Evershed and Vignoles therefore designed a much
with a suitable pickling fluid, then placed on a
more practical method of measuring the resistance
dry-salt stack or placed in a pickling tank. The only
of the meat and, with startling originality dubbed
guide to when the curing process was complete was
this the Meg Salinity Tester. It probably wont
experience or to cut off a small piece of meat and come as much of a surprise that this was based
taste it, which gave a very rough guide to the salt on the popular hand-cranked Megger insulation
content. tester of the period.

Neither of these options was particularly To quote the official description, The instrument
satisfactory, but it was important to ensure that consists of a hand generator and ohmmeter
the meat was properly cured otherwise it would combined in a one case. It is used in conjunction Unfortunately, the paper gives no indication of inspector at a pork processing plant wandering
spoil and quickly become unfit for consumption. with a special probe, the principle of operation the commercial success or otherwise of the Meg around and occasionally probing a piece of meat
Bear in mind that few homes at this time had being shown in the diagram. The deflection of the Salinity tester so its impossible to say whether while cranking an instrument that must have looked
refrigerators, so domestic purchasers at least were ohmmeter movement, which depends on the ratio these instruments were produced in quantity and
for all the world like a Megger insulation tester!
heavily dependent on the proper processing of of the currents in the current and potential coils, widely used, or whether they remained little more
meats to guard against the risk of food poisoning. gives the resistance directly. The rotary converter than a curiosity. (Grateful thanks to the Archive Department of the
and the rectifier enable alternating currents to
To address this issue, the author of the paper, be used in the testing circuit, thus eliminating The whole concept of the tester does, however, IET, which provided access to the paper on which
F H Banfield, decided to investigate whether electrolytic action at the electrodes. conjure up a rather appealing visual image of an this article is based.)

Megger hosts workshop for EPRI TSUG in Pennsylvania


afternoon factory tours and live demonstrations. produces world-class portable instruments for
Greg Valdez - Marketing communications
Attendees first appreciated a preview of Meggers transformer, cable fault, battery, and power quality
manager
deep technical competencies in the morning, diagnostics, comfortably accommodated the
Karen Becerril - CSA marketing specialist
delivered through a series of presentations at guests and demonstrations.
the meetings venue, the Hilton Philadelphia at
On July 20, 2015, which brought near record-setting Penns Landing. A variety of subjects were covered, Attendees were offered the opportunity to try the
high temperatures in the greater Philadelphia PA including substation safety, battery maintenance DELTA4000 variable frequency insulation power
area, Megger hosted a one-day workshop for and testing, MV cable VLF testing and diagnostics, factor/dissipation factor (tan delta) test set, the
personnel knowledge and capabilities related
the Electrical Power Research Institutes (EPRI) winding resistance measurements and frequency MTO250 portable transformer ohmmeter (winding
to large power transformers and associated
Transformer and Switchyard Users Group (TSUG) at response techniques. resistance test instrument with demagnetizing
switchyard equipment. The group is involved in
the Megger facilities in Norristown, Pennsylvania. The capability) and the groundbreaking TRAX multi-
From the hotel, attendees were bused to Meggers the collection, dissemination, and development of
event kicked off the organizations meetings which functional substation test instrument, amongst
Valley Forge facility where they split into groups maintenance and troubleshooting processes and
convened the following day. Meggers initiative to many others. The event gathered over 50 attendees
according to preferred application interests, other activities related to large power transformers
share their electrical testing expertise and the latest and created many opportunities for networking
including transformers, relay, circuit breaker and and associated switchyard equipment. EPRI
development of electrical testing technologies was and to set the foundation for future business
high current injection applications, and enjoyed conveyed their enthusiasm for Meggers support,
enthusiastically welcomed by the group. relationships.
hands-on demonstrations. Meggers relatively perceived to be instrumental to the success of the
The Megger workshop was divided into two parts new (2001) and expansive 60,000 square foot EPRIs TSUGs primary goals are to support and event and expressed their desires to collaborate
a morning substation best practices seminar and manufacturing and engineering facility, which promote activities that will increase power plant again with Megger in the future.

www.megger.com ELECTRICAL TESTER - February 2016 3


ELECTRICAL
The industrys recognised information tool TESTER
The impact of GIC on electric power

Figure 1:Part Cycle, Semi Saturation of Transformer Cores

I
Zp = Rp + jXp Ip Zs = Rs + jXs
one side (see the top black dashed line in Figure 0 0I
Jill Duplessis - Global technical marketing
1). This bias causes the transformer to enter the Ip Is
manager & Editor I I
saturation region in the half cycle in which the ac
causes a flux in the same direction as the bias. This Ep Ih ZM Im E p Es Es
In the last issue of Electrical Tester, we examined effect is known as half - cycle saturation. When the
what GIC (Geomagnetically Induced Current) is core saturates, it has reached the limit of its ability
and why it occurs. In this article, we look at the to carry a magnetic field; any field beyond the limit
potential impact of GIC on power systems and, in leaks out of the core and passes through the
particular, on transformers. space around the core (air/oil) as leakage flux.
Magnetisation Magnetisation
The source of nearly all of the operating and While the magnetic reluctance of the core is still (Core) loss (Core) inductance
equipment problems attributed to a geomagnetic low, the reluctance of the portion of the magnetic
Figure 2: Transformer Equivalent Circuit
disturbance is the reaction of susceptible circuit outside the core is high. This results in a
transformers to the presence of GIC. The first order much - reduced value of shunt inductance and
a large shunt current (Im) flows through the In summary, a saturated transformer becomes a Capacitive reactance is expressed by XC =
effects of GIC are those on the transformer and
magnetizing branch. The inductive volt - amperes - reactive energy sink, an unexpected inductive load 1/(2fC). From this, it is easy to see that a
the second order effects of GIC are those on the
reactive (VAR) requirements of the transformer can on the system, and behaves more like a shunt capacitor presents as an open circuit (infinite
power system.
become very high (see the red excitation current reactor. Transformer differential protective relays impedance) to DC current; this underpins the
First Order Effects of GIC pulse given a DC offset on the bottom vertical axis may trip and take the transformer out of service. effectiveness of series capacitor blocking in
The excitation current of a transformer represents in Figure 1). With saturated core magnetization, Excessive leakage flux can result in detrimental very long transmission lines as a GIC mitigation
the continuous energy required to force the transformer voltage and current waveforms overheating, or in some designs, winding damage strategy. In contrast, as frequency goes up,
transformer action, in other words, to make the contain very high harmonic content. due to resulting high winding circulating currents. capacitive reactance drops so capacitor banks
transformer behave as a transformer. It is largely a Separately, the magnetizing current pulse of a GIC have lower impedances to harmonics and draw
Problems can occur with differential protective
reactive current (usually dominated by an inductive inflicted transformer injects significant harmonics larger currents when harmonics are present.
relays that are looking to see balanced primary
contribution known as the magnetizing current) into the power system. The resultant impact of
and secondary currents. The transformer While saturated transformers draw large
and it is typically very small usually less than 1% these changes in the transformer(s) constitutes the
protection may trip as the primary current becomes currents, forcing system voltage down and
of the transformers rated operating current as second order effects of GIC.
disproportionately large (drawing increasingly more
transformers are very efficient devices. Under normal potentially overloading long transmission lines,
reactive current) compared to the secondary current. Second Order Effects of GIC
steady-state conditions, the excitation current of a capacitor banks also draw large currents due to
transformer is symmetrical (balanced between the Leakage flux is always present in a transformer that Many agree that the more concerning impacts of the presence of harmonics, partially offsetting
positive and negative peaks of its waveform) as is carrying load. Because of the problems that it GIC are its indirect effects on the power system the inductive effects. Essentially, the saturated
shown in Figure 1 where the excitation current is can otherwise cause, transformer manufacturers and its components. The effect of a transformer transformers are in a tug - of - war with the
shown in blue on the bottom vertical axis. design and build their transformers such that the morphing into a shunt reactor on the power system capacitors on the system. Modern shunt
anticipated leakage flux is managed and has is best understood after a review of shunt reactors capacitors have very low loss and are therefore
For economic reasons, the peak ac flux in the minimal impact on the long-term operation and and capacitors. less susceptible to transient heating damage
power transformer (given by the blue waveform on life of the transformer. Leakage flux, however, due to excess current. However, large currents
the left side of Figure 1) is designed to be close is never anticipated from the excitation of the Shunt capacitor banks are used to offset
may affect other components in capacitor bank
to the knee (or magnetic saturation point) of the transformer. The high peak magnetizing current inductive effects on the power system (to
installations, resulting in damage and unwanted
magnetization curve (shown by the black curve in pulse (red in Figure 1) produces correspondingly support voltage) while shunt reactors are used to
tripping. Voltage imbalance and overvoltage
Figure 1) so that nearly the full magnetic capabilities higher magnitudes of leakage flux (as given by the offset the effects of capacitance on the system
protection may also be fooled by harmonic
of the transformers core is used during operation. red waveform on the left side of Figure 1) that is (to reduce voltage). Typically, shunt capacitors
When a core operates below its saturation point, voltage spikes and cause unwanted trips.
also rich in harmonics. are switched in during periods of high load, and
practically all of the magnetic flux created by the Finally, overcurrent protection may also operate
shunt reactors are switched in during periods of
excitation current is contained in the core. The The influence of excessive leakage flux on the spuriously in the face of harmonic currents.
light load. The same effects can be achieved,
magnetic reluctance of the core is low because the transformer is generally thermal. Leakage flux in Similar issues may apply to SVCs. Harmonic
within rating limits, by varying the excitation of
core steel is an excellent conduit for magnetic flux. transformers that links any conductive material filters for SVC banks create parallel resonances,
generators, i.e., operating them as synchronous
(including transformer windings and structural which can exacerbate voltage disturbance issues
Accordingly, the magnetization losses are low (i.e., condensers. Static VAR compensators (SVCs),
parts) will cause induced currents that result in and result in tripping of the protection devices.
a small Ih in Figure 2) and the (shunt) magnetizing which combine capacitor banks and reactors,
almost immediate localized, unexpected, and
inductance is high, resulting in a very small provide similar compensation and voltage Rotating machines have fairly high thermal
severe heating due to resistive losses. Paint burning
magnetizing current, Im. The excitation current support, with very fast automated controls. inertia, so generators operated as synchronous
off transformer tank walls might be considered an
is the vector sum of these current contributions, Many power systems once had dedicated condensers have a higher probability of
asset owners best-case example!
Ih and Im. The inductive volt - amperes - reactive synchronous condensers (rotating machines). staying on line. However, generators can also
(VAR) requirements of the transformer are Transformer designs that include core bolts are a However, capacitor banks are cheaper and as be affected by GIC currents. These effects
very low. Moreover, with non - saturated core concern because, should the stray flux link such capacitor technology advanced to the point include additional heating, damage to rotor
magnetization, the transformer voltage and bolts located at the bottom of the windings and where reliability became excellent, synchronous components, increased mechanical vibrations
cause the surrounding oil to heat to 140C, this condensers were retired.
current waveforms contain very low harmonic and torsional stress due to oscillating rotor flux
could result in bubble evolution that ultimately
content. caused by increased negative sequence harmonic
leads to transformer failure. For any given design, Inductive reactance, which is expressed by XL
During a GIC event, a quasi - dc current enters the a finite element analysis will reveal the leakage = 2fL, indicates that as inductance, L, goes currents. The harmonic content of negative
ground-connected neutral of the transformer and flux paths and weaknesses, if any, in the design. down, inductive reactance drops. Saturated sequence currents can also cause relay alarming,
splits equally between phase windings (on multiple If a transformer is lightly loaded, and therefore its transformers have low shunt magnetizing erratic behaviour or generator tripping. If VAR
phase winding transformers). If the zero-sequence operating leakage flux is light compared to its full inductance so they draw high currents; they resources are exhausted during a GMD event,
reluctance of the transformer is low, the GIC biases load rated flux, the unit may be able to handle the look like shunt reactors on the system, dragging specifically capacitive voltage support, voltage
the operating point on the magnetization curve to additional leakage flux introduced by GIC. down the system voltage. collapse can occur.

4 ELECTRICAL TESTER - February 2016 www.megger.com


ELECTRICAL
The industrys recognised information tool TESTER
er systems Need an update fast?
GIC flows in lines
Grab a power webinar!
Transformer half-cycle saturation Reactive power loss

Harmonics Transformer heating

P&C incorrect Capacitor bank or SVC Voltage control, limits


operation tripping - loss or reactive contingency management
support

Generator overheating Voltage and angle


and tripping stability

including definitions
GIC Simulations Power system simulations of key terms and a
discussion of battery
Figure 3: Effects of GIC in a High Voltage Transmission Network (from NERC) types. It then covers
failure modes for
NERCs 2012 Special Reliability Interim Report: FERC/NERC Regulation various types of
Effects of Geomagnetic Disturbances on the Bulk batteries, such as sulphation and hard/soft shorts
Federal regulations designed to protect the electric
Power System provides a block diagram that in lead-acid batteries, and separator deterioration
illustrates the effects of GIC, culminating in a threat grid in the USA from the potentially severe and in nickel-cadmium types.
to system voltage and angle stability (Figure 3). widespread impact of a geomagnetic disturbance
This introductory section is followed by an
(GMD) are in the process of being adopted. Following
Special Dispensation about the examination of the importance of maintaining
several years of study, the Federal Energy Regulatory
Effects of GIC on CTs and protective Yier Toh - Marketing engineer batteries regularly, to ensure that conditions such
relays Commission (FERC) initiated a rulemaking in 2012,
as blocked ventilation systems and corrosion are
It is important to have accurate measurements of the first of its kind, directing NERC to develop and detected before they lead to a breakdown or, in
system state during abnormal operating conditions. submit for approval Reliability Standards to protect the worst cases, a catastrophic failure.
For these purposes, the industry has predominantly the grid from the impact of GMDs. Knowing how difficult it can be for professional
engineers and technicians to refresh their The IEEE standards applicable to various battery
relied upon conventional instrument transformers
In Order No. 779, FERC determined that the knowledge of testing techniques and to keep up- types are introduced before the second half of the
such as a current transformer (CT); a potential (or
to-date with the latest developments in the field, seminar moves on to consider the importance of
voltage) transformer, which may be inductive (PT/ risk posed by GMD events, and the absence of
Megger produces a series of monthly webinars compliance with mandatory NERC requirements.
VT) or capacitive (CCVT); or a combined current Reliability Standards to address GMD events,
and voltage instrument transformer. An instrument each year that provide concise information about
posed a risk to system reliability that justified its Test methods that will ensure compliance is
transformer (IT) is intended to reproduce in carefully chosen key topics. The 2015 series of live
precedent - setting order directive to NERC to achieved are explained in detail, with full coverage
its secondary circuit, in a definite and known webinars has concluded, but the good news is that
develop Reliability Standards to address the issue. given to the benefits and limitations of impedance
proportion, the current or voltage of its primary the recordings are available online. So, if youd
testing, as well as to the correct procedures for
circuit with the phase relations and waveforms To expedite the standards - setting process, FERC like a convenient way to enhance your testing
discharge testing, which is the only completely
substantially preserved. The electromagnetically ordered NERC to develop mandatory standards in knowhow without even leaving your desk, why
dependable way of measuring battery capacity.
induced current or voltage waveform(s) in the two stages, both of which are now underway. not take a look?
The webinar concludes with information about
secondary circuit(s) of the IT should then be of recording, analysing and trending test results.
In the first stage, FERC directed NERC to submit The topics in the 2015 webinar series are:
an easily measurable value for the metering or
protective devices that are connected as the load, Reliability Standards that required owners and Basics of recloser testing If all of this sounds interesting, but the topic you
or burden, on the IT. operators of the bulk-power system to develop particularly want to see isnt in the list, it may be
Applications of time-domain reflectometry coming up in 2016 because we listened to your
and implement operational procedures to mitigate
In as much as a traditional, ferromagnetic IT has a suggestions when planning the next series. Heres a
the effects of GMDs to ensure grid reliability. Medium and high voltage circuit breaker
magnetic core, ITs are influenced by GIC much like a sneak preview of some of the new topics:
These operational procedures were considered a testing
power transformers. If an IT is pushed to a non - linear
region of its saturation curve (i.e., its operating curve), first step to address the reliability gap and were Insulation diagnostic methods for
GPS/IRIG-B timing methods for end-to-end
due, for example, to a DC flux shift, the accuracy of approved by FERC in June 2014. These standards transformers and bushings
relay testing
the IT will significantly decline. While it is true that ITs became mandatory on January 1, 2015. Advanced end-to-end testing
typically operate at lower magnetization levels than Battery testing for compliance with NERC
power transformers because reading accuracy must In the second stage, FERC directed NERC to provide standards Partial discharge and tan delta
be maintained in the face of large fault currents (i.e., more comprehensive protection by requiring entities measurements for improving grid resiliency
Chasing medium voltage cable faults in
they have more built - in margin on the curve), there to perform vulnerability assessments against a branched networks Improving the efficiency of transformer
is no way of knowing whether the magnitude of GIC
benchmark GMD event and develop appropriate commissioning
in the system will saturate the core despite its margins, Detecting cable deterioration before the
mitigation strategies to protect their facilities against
or if remanence was pre - existing in the core and fault Advances in high-current injection testing
already compromising the ITs performance. In short, GMD events. These strategies include blocking GICs
from entering the grid, instituting specification The importance of demagnetising More topics will soon be added to the list, so
there will always be uncertainty about the reliability of
transformer cores check Meggers webinar landing page frequently
system state measurements provided by ferromagnetic requirements for new equipment, and isolating
instrument transformers during a GIC event. for details, especially if you want to participate
equipment that is not cost effective to retrofit. Guide to low resistance testing
in the live webinars to interact with Meggers
Moreover, when currents and voltages become rich The standard to implement the second phase of Improvements in transformer winding subject matter experts. Based on overwhelming
in harmonics, even if the IT is not operating in a resistance testing feedback from our webinar attendees, in 2016,
NERCs GMD program is known as TPL-007-1. As
saturated state, the accuracy of the measurements we will extend the Q&A segment by 30 min after
of November 2015, FERC continues to deliberate Each webinar lasts for around an hour, but five-
will decline. Unfortunately, there is no on - line the conclusion of the webinar. This way you can
method of validating whether the instrument over its approval. The initial Notice of Proposed minute samples of all of them are available on
stay online and chat with the presenter to get your
transformer is operating in a non - saturated state Rulemaking (NOPR) comment period, which closed YouTube, so its easy to try before you buy
questions answered.
and, therefore, within its window of accuracy (i.e., in May 2015, was extended until October 22, 2015 even though all webinars are absolutely free to
the pseudo - linear region of its saturation curve at view. To check out the YouTube clips, simply go For power professionals, Megger webinars are
to allow for additional commenters to submit their
50 or 60 Hz) or in a saturated state and, therefore, to Meggers YouTube channel at http://www. the fastest, most convenient, and most reliable
views regarding the GMD benchmark. FERC ordered
outside the realm in which it can accurately youtube.com/meggerUS. You can always find the way to keep up to date on trending technical
NERC to make changes to the proposed standard latest information on all previous and upcoming developments and best practices in the industry.
reproduce measurements.
including: refining its definition of the benchmark webinars on our webinar landing page at www. You dont even have to leave the comfort of your
It must also be remembered that protective relays event; requiring the installation of monitoring megger.com/webinars. office to participate!
operate based only on their inputs. If a CT, for
equipment wherever there are reliability gaps;
example, is supplying a distorted waveform due to As an example of the type of content youre likely Links:
and setting deadlines for completion of corrective to find in these webinars, lets take a look at the
the effects of harmonic saturation, the relay may www.youtube.com/meggerUS
respond in a different, and unwanted, way than it actions. FERC is also considering shortening NERCs battery testing and NERC standards webinar.
does to nearly sinusoidal inputs. proposed 5-year period for compliance. This starts with an overview of battery basics, www.megger.com/webinars

www.megger.com ELECTRICAL TESTER - February 2016 5


ELECTRICAL
The industrys recognised information tool TESTER

Pushing past the limitations of po


should match the overall CH values. The GST per Open DETC UST (Table 3): DETC is placed at
Robert Breazeal - Southern California Edison phase may be performed at up to rated voltage a midway position between taps. Secondary
Jill Duplessis - Global technical marketing provided the guarded excitation current does not terminals are short-circuited and energized at the
manager & Editor exceed the output of the test equipment. The H1, same voltage as in the overall test. One primary
H2, H3 tests are designated as ICH1, ICH2, and terminal is measured while guarding the other
This is the second part of an article discussing how two terminals. The sums of the watts, milliamps,
ICH3 respectively.
Southern California Edison (SCE) has successfully and capacitances for all three tests should match
adopted methods based on electrically dividing UST Per Phase (CHL): One primary terminal is the overall CHL values. The tests are designated in
the insulation of power transformers into sections energized while guarding the other two terminals. terms of the primary terminal that is measured. H1,
H2 and H3 tests are designated as CHL1, CHL2,
to facilitate testing. The first part of this article Output from X0 terminal is measured. X1, X2 and
and CHL3 respectively.
appeared in the November 2015 edition of X3 bushings are floated. The DETC is left on tap.
Electrical Tester, which is available on the Megger The sums of the watts, milliamps, and capacitances
TRANSFORMER CONFIGURATIONS
website, and introduced cross-check tests and for all three tests should match the overall CHL AND LIMITATIONS
open DETC tests as methods to sectionalize the values. The UST crosscheck may be performed at
insulation beyond the typical segmentation (e.g., up to rated voltage provided the guarded excitation Delta-Wye Configuration: The ideal test subject is
CH, CHL and CL on a two-winding transformer). current does not exceed the output of the test a delta-wye configuration with a three-leg core.
This second part describes cross-check and open equipment. H1, H2 and H3 tests are designated as Delta-wye is the only configuration on which the
DETC test procedures, the transformer winding ICHL1, ICHL2, and ICHL3 respectively. entire set of supplemental tests may be performed
configurations for which these methods are most without geometry-induced errors. In distribution
effective, and provides a case study wherein OPEN DETC TESTS core configurations, the CH2 measurements for
these methods provided useful supplemental the centre phase are inaccurate because the core
information to help characterize the problem at In the cross-check tests above, the visibility of an configuration severely impedes current flow for CH
hand in a faulted transformer. anomaly is proportional to its proximity to the per phase tests.
voltage source. In the open DETC protocols, the however is not possible if the exciting current
Delta-Delta Configuration: If a cross-check,
CROSS-CHECK TESTS entire section of energized winding is at the same
per-phase test is performed on a three-phase required by the secondary winding is beyond the
potential since the low voltage winding terminals capacity of the test equipment.
winding with a delta secondary, the primary
Unlike the preparation required for traditional are short-circuited. This enables the detection of exciting current induces circulating currents in the
power factor testing, transformer windings are not anomalies in the centre of the winding, which may Wye-Wye Configuration: The wye secondary
secondary, which make it impossible to collect
short-circuited for Cross-check tests. Therefore, be difficult to pinpoint with the cross-check tests. configuration enables the cross-check, per-phase
accurate data. The open DETC tests (Table 3) are
when voltage is applied to a bushing terminal, (1) This sectionalisation of the primary also enables the CH and CHL tests to be performed as given in Table
the only supplemental tests that may be used on
the winding is now being excited and (2) voltage 4. With the wye primary configuration only one
technician to determine the location of an anomaly this configuration.
distributes non-uniformly across the winding. primary winding is energized per test when each
in relation to the DETC. If a fault in the centre of a
Highest voltage stress is placed upon the insulation Wye-Delta Configuration: The open DETC GST phase terminal is energized, making the protocol
primary winding radially propagates sufficiently to
closest to the energized terminal. In this way, the test is the only protocol guaranteed to yield usable a true per-phase test. While the CH0 and CHL0
involve numerous coil layers, it may be detectable
CH (for example) insulation system measured in data with this winding configuration. Open DETC
as seen from both sides of the open DETC. tests are not useful for localization of anomalies,
a traditional overall power factor test by shorting UST tests may not yield useable data because the
the data is used to compare the sums of watts,
all 3 phase windings together, can now be secondary winding interface is normally located
Open DETC GST (Table 3): DETC is placed at a mA, and capacitances to the overall values. For the
sectionalised into thirds. It is expected, therefore, between the DETC and neutral. When the cross-
midway position between taps. One primary reasons stated in the wye-delta section above, the
that the results (mA, Watts and capacitance) for check, per-phase protocol is performed on the
terminal is energized while guarding the other open DETC UST test may not yield useable data.
the 3 (segmented) cross-check tests should add to wye-delta configuration, the unit must be treated
two primary terminals and all secondary terminals as a delta-wye, meaning that the tests must be The open DETC GST test may be performed, as
equal the results measured in the traditional overall
(LV winding short-circuited). The sums of the performed by energizing the X winding. This table 5 shows.
power factor test. It is noted here that cross-check
watts, milliamps, and capacitances for all three
tests for the CL insulation system are not provided
tests should match the overall CH values. The Mode Energize Ground Guard UST Measurement
because in many cases, the current requirement to
DETC open GST crosscheck is performed at a
excite the low voltage winding is greater than most 1 GST HV LV ICH + ICHL
maximum of 500 volts. H1, H2 and H3 tests are
field portable test instruments can provide. 2 GST HV LV ICH
designated as CH1, CH2, and CH3 respectively. In
GST Per Phase (CH): One primary terminal is this configuration individual sections of the delta 3 UST HV LV ICHL
energized while guarding the other two terminals primary are isolated and energized. If an anomaly 4 GST LV HV ICL + ICLH
and X0. (X1, X2 and X3 bushings are floated.) is suspected to be located in the centre portion of 5 GST LV HV ICL
The DETC is left on tap. The sums of the watts, a winding, the open DETC test will determine the
6 UST LV HV ICLH
milliamps, and capacitances for all three tests location of the anomaly in relation to the DETC.
7 GST H1 H2,H3,X0 - X1,X2,X3 ICH1

Overview of Supplementary Tests 8 GST H2 H1,H3,X0 - X1,X2,X3 ICH2


9 GST H3 H1,H2,X0 - X1,X2,X3 ICH3
10 UST H1 H2,H3 X0 X1,X2,X3 ICHL1
11 UST H2 H1,H3 X0 X1,X2,X3 ICHL2
12 UST H3 H2.H3 X0 X1,X2,X3 ICHL3
Table 2: Overall and Cross-Check Per-Phase Tests for Delta-Wye Transformer Configurations*

Test Mode Energize Guard UST Measurement


1 GST H1 H2,H3, X0,X1,X2,X3 - ICH1
2 GST H2 H1,H3, X0,X1,X2,X3 - ICH2
3 GST H3 H1,H2, X0,X1,X2,X3 - ICH3
4 UST X0,X1,X2,X3 H2,H3 H1 ICHL1
5 UST X0,X1,X2,X3 H1,H3 H2 ICHL2
6 UST X0,X1,X2,X3 H1,H2 H3 ICHL3
Table 3: Open DETC Tests

Test # Mode Energize Guard UST Measurement


1 GST H1 X0,H2,H3 ICH1
2 GST H2 X0,H1,H3 ICH2
3 GST H3 X0,H1,H2 ICH3
4 GST H0 X0,H1,H2,H3 ICH0
5 UST H1 H0 X0 ICHL1
6 UST H2 H0 X0 ICHL2
7 UST H3 H0 X0 ICHL3
8 UST H0 H1,H2,H3 X0 ICHL0
Table 4: Cross-Check, Per-Phase Tests for Wye-Wye Configurations (DETC on Tap)

6 ELECTRICAL TESTER - February 2016 www.megger.com


ELECTRICAL
The industrys recognised information tool TESTER

power factor testing (part 2)

Wye-Wye Autotransformer and 3 Phase Regulators: Ratio test results were within specification with no phase in which the fault originated. The standard The winding was untanked and a physical
The cross-check, per-phase method is used in indication of abnormalities. Insulation resistance tests supplementary tests were performed to obtain inspection was performed. As expected the
this configuration to investigate questionable CH yielded values of 605 M, 7.35 G, and 48 M for per phase power factor values for GST and UST C phase secondary winding had sustained a
values. As in the other configurations, the sum of CHL, CH, and CL respectively. Exciting current tests tests. The unit was constructed with a standard 3 ground fault in proximity to the interwinding
the watts, milliamps, and capacitances from the were successfully performed at 10kV. Overall power leg core configuration, which allowed for collection barrier, validating the CHL2 value. It was also
cross-check tests should equal the respective values factor test results are shown in Table 7. of accurate GST and UST cross-check data. discovered that the C phase static shield had
from the overall test. Cross-check, per phase tests Among other problems, it was noted that the CHL failed validating the CH3 value (which indicated
Elevation of CH3 in combination with depression
are performed as given in Table 6. power factors on lines 3 and 6 deviated by nearly CH damage in close proximity to the H3 lead).
of CHL2 values indicated conclusively that the CL
0.1%. The assumption was made that a voltage fault occurred in the C phase winding (H2-H3). Conclusion
CASE STUDY: Root cause failure dependent problem was present as a result of the Because the CHL fault for C phase was indicated
analysis of a 69 kV substation The strength of the per-phase protocol is the
failure. A power factor tip-up test was performed in CHL2, this verified that the H2 lead jumper
transformer with secondary for CHL, CH, and CL (Figure 1). localisation of incipient problems to their respective
enters the C phase primary winding at the inside
ground fault windings, but other methods such as dissolved gas
The test data revealed power factor tip-up edge of the primary winding adjacent to the
analysis and sweep frequency response analysis
The #2 South B Bank from Tulare Substation was values of approximately 0.16 and 0.4% for CHL inter-winding barrier. The CH fault was not detected
should also be employed in order to determine the
removed from service. Relay targets had indicated and CH respectively, most likely due to carbon to a significant degree in the CHL2 test, therefore
physical basis of the anomaly.
a differential fault on C phase. Substation contamination. CL power factor on the other hand it may be deduced that the location of the fault
personnel performed insulation resistance tests on increased dramatically as voltage was increased was in close proximity electrically to the end of the A thorough understanding of the winding
the transformer which indicated that the unit had to 10 kV. The tip-up test in conjunction with the C phase winding from which the H3 bushing arrangement and internal geometry is essential
failed. At this point the transformer was cut off the insulation resistance values indicated the CL as lead originates. for proper interpretation of the per-phase data.
pad and sent to the SCE Large Apparatus Repair the principle fault location. The exciting current Because the fault occurred in C phase, the CH1 Winding arrangements and internal connections
Facility for further testing. and ratio tests however did not indicate the and CHL1 per phase values accurately reflected the will vary significantly, depending on size and
condition of the primary windings away from the voltage class of unit.
fault zone. The H1 lead is not common to C phase, They may be performed in cases where the CH
making any C phase anomaly invisible as seen from or CHL are elevated above the baseline values
CH1 and CHL1 measurements. obtained in the commissioning tests. Another
For procedural reasons, the DETC could not be tool that SCE uses to investigate problems is a
operated. If the DETC could have been placed recommended routine screening test known as
between taps, the open DETC per phase protocol the Narrow-band dielectric frequency response test
would have been performed which negates the (DFR) test (also called variable frequency power
power factor shift as seen in the standard per factor). This will be the focus of the last part of this
phase protocol (resulting from the CL ground fault) series in the next issue of ET.
and yields accurate per phase power factor data. * Table 1 is in Part 1 of the series.

Measurement Test kV mA Watts %PF


ICH + ICHL 10.0 35.367 3.423 0.958
ICH 10.0 10.605 1.65 1.540
Figure 1 Power Factor Voltage Tip-up for failed 69 kV bank
ICHL 10.0 24.756 1.794 0.718
ICL + ICLH 5.0 69.377 10.759 1.535
Test # Mode Energize Guard Measurement ICL 5.0 44.615 9.300 2.064

1 GST H1 H2,H3,H0,X0,X1,X2,X3 ICH 1 ICLH 24.752 1.557 0.623

2 GST H2 H1,H3,H0,X0,X1,X2,X3 ICH2 Table 7 Overall Power Factor Results 69 kV Bank


3 GST H3 H1,H2,H0,X0,X1,X2,X3 ICH3
Measurement Test kV mA Watts %PF CAP (pF)
4 GST H0 H1,H2,H3,X0,X1,X2,X3 ICH0
ICH1 5.0 3.373 0.187 0.555 894.6
Table 5: Standard DETC Open Per-Phase Tests for Wye-Wye Configurations
ICH2 5.0 3.301 0.096 0.292 875.7
ICH3 5.0 3.898 1.128 2.894 1033.7
Tests Mode Energize Guard Float Measurement
10.572 1.411 2804.0
1 GST H1 H2,H3,H0XO X1,X2,X3 ICH1
ICHL1 5.0 8.109 0.185 0.228 2150.9
2 GST H2 H1, H3,H0XO X1,X2,X3 ICH2
ICHL2 5.0 8.535 1.119 1.311 2263.7
3 GST H3 H1,H2, H0XO X1,X2,X3 ICH3
ICHL3 5.0 8.101 0.207 0.256 2148.9
4 GST H0XO H1,H2,H3 X1,X2,X3 ICH0 24.745 1.511 6563.6
Table 6: Per Phase Tests for Wye-Wye Autotransformers and 3 Phase Regulators Table 8 Cross-Check, Per Phase Winding Power Factor Tests 69 kV Bank

www.megger.com ELECTRICAL TESTER - February 2016 7


ELECTRICAL
The industrys recognised information tool TESTER

Q&A
Circuit breakers are at the heart of every modern power system and, to ensure those
systems are properly protected, it is essential that the breakers should operate correctly
when called upon to do so. This means that regular testing is vital, so its unsurprising
that our technical support team often receives questions on topics relating to breaker
testing. These are a few of the things were asked most frequently.

Q: When measuring the resistance of current is unlikely to be suitable for measuring the proportion of the available current is typically this point all of the test current is carried by the
circuit breaker contacts, the results obtained resistance of circuit breaker contacts. shunted via the path provided by the two ground arcing contacts.
are often considerably higher than the figures
quoted by the manufacturer. Why is this and Q: Can contact resistance be measured connections. A short time later, the resistance will increase
with the safety earths still connected to the
what can be done about it? Q: What is dynamic resistance almost to infinity as the arcing contacts open.
breaker?
measurement (DRM) for circuit breaker By noting the time between the operation of the
A: By far the most common reason for main contacts and the arcing contacts, it is possible
A: Yes, if the test equipment used is contacts and what can it reveal about the
these unexpectedly high readings is that the test to deduce the remaining length of the arcing
confirmed by the manufacturer as being suitable condition of the contacts?
current used in making the measurement is too contacts something that could otherwise only
for dual-ground testing. It is important to check A: DRM essentially means measuring
low. To obtain dependable results, its essential to be determined by dismantling the breaker. This
this point carefully, however, as by no means all
use a test current of 50 A or more. The breaker the resistance of the circuit breaker contacts
circuit breaker test sets meet this requirement. This technique does, of course, rely on the availability
manufacturers literature, or the standard to throughout the opening and closing operations, of dependable information about the motion of
is because, as weve seen, the instrument must
which the breaker is being tested, will provide inject large currents into the breaker in order to and then plotting the resistance against time. The the breaker contacts during operation, but Megger
more detailed guidance. This need for high produce dependable results. For all but the best plot obtained during the opening operation is circuit breaker test sets like the TM1800 provide
current testing means that a general-purpose low- specified instruments this can be challenging in the particularly informative. It will show a step change facilities for accurate motion analysis as well as for
resistance ohmmeter that uses only a modest test case of dual-ground working, where a substantial in resistance as .the main contacts open, since at DRM and support for dual-ground testing.

Five lesser-known
facts about Tesla
using the Earths resources at an alarming
Keith Wilson, electrical engineer
rate. And, as agriculture and farming are the
greatest pollutants and destroyers of natural
Weve written about Nikola Tesla before in habitats today, Tesla was right in assuming
Electrical Tester, but this enigmatic figure,
that a vegetarian diet would be far less
who some regard as the true father of
burdening for mother Earth: There is no
todays electrical technology, continues to
doubt that some plant food, such as oatmeal,
hold a strange fascination, not least for
is more economical than meat, and superior
those who work in the electrical sector. We
to it in regard to both mechanical and mental
are, therefore, presenting some of the lesser-
performance. Such food, moreover, taxes
known facts about this doughty pioneer.
our digestive organs decidedly less, and, in
Nikola Tesla is famous for his inventions making us more contented and sociable,
as well as his quirks, typical for a genius of produces an amount of good difficult to
his stature. He was born during a lightning estimate.
storm, and the rest of his life was just as
extraordinary. He pursued science relentlessly 3. He would have been diagnosed
and envisaged a world where scientific with OCD by todays standards
research improved and enriched peoples
It is widely held that Tesla suffered from a
lives for generations to come.
form of obsessive-compulsive disorder (OCD).
Tesla is famous for his contributions to the He hated touching things that appeared to
design of the modern alternating current be dirty (even hair!), which may be linked to
electricity system, but there is much more
the health scares he experienced in his youth
that meets the eye for this eccentric figure!
So, without further ado, lets take a look at when he was bed-bound with cholera.
the top five lesser-known facts, myths and He also hated jewellery, pearls and anything
trivia about the great man. round! As a dapper young man himself, Tesla
1. Tesla might well have been the had very rigid aesthetic beliefs and somehow
actual inventor of the radio round items did not fit in his vision of beauty
and being well dressed. An anecdote says
A somewhat disputed and controversial fact,
Tesla is believed to have created one of the that he was so appalled by pearl jewellery
first practical applications for radio waves, that he refused to speak to women wearing
which had been predicted by Heinrich it. He even sent his secretary home once for
Hertz. His invention involved a remote- the same reason!
documents and experiments and, to He also considered gender equality to be a
controlled boat with an antenna. Tesla was Later in life he developed an obsession with this day, they remain classified. Which force for good in the world, and foresaw
able to change its direction by transmitting
the number three, which meant that he begs the question of what exciting new the increasing importance of women in the
radio waves to the boat, where they were
would circle a building three times before inventions has the world lost out on in the workforce and society. He postulated that:
translated into mechanical movements of
entering it. last seventy years?
its rudder. This invention coincided with the female sex [is] endowed with no less than
Marconis wireless transmissions over the 4. The US Government still keeps 5. He was a humanist and supported men. But the female mind has demonstrated
Atlantic, leaving many in doubt about who some of his inventions classified gender equality a capacity for all the mental acquirements
discovered radio waves first.
In the days of Oculus Rift and artificial Throughout his life, Tesla was simply and achievements of men, and as generations
2. He foresaw the ecological decline of intelligence, what could Tesla have possibly uninterested in capitalising on his inventions ensue, that capacity will be expanded; the
the planet invented that is so significant it has to be and unlike Edison, wasnt too troubled by the average woman will be as well educated as
A keen observer of the world around him, kept away from the public, decades after business aspect of scientific discoveries. He the average man, and then better educated,
Tesla understood early on that consumerist his death? After his passing in 1943, the believed in doing good things for mankind () Woman will ignore precedent and startle
society was on the up and that humans were Office ofAlien Propertyseized many of his and improving peoples lives above all else. civilization with their progress.

8 ELECTRICAL TESTER - February 2016 www.megger.com

You might also like