You are on page 1of 9

17/9/2017 When things go wrong: identifying combined cycle problem areas - Modern Power Systems

O&M REVIEW: COMBINED CYCLE PROBLEMS

When things go wrong: identifying


combined cycle problem areas
1 November 2007
14

In many combined cycle plants around the world the benefits of advanced gas turbine
technology have not been fully realised due to problems with compressors, combustors,
transition pieces, blades and vanes. Meherwan P Boyce, who has been in the
turbomachinery business for 44 years, reviews the problem areas.

The new generation of combined cycle power plants operates at thermal


efficiencies in the range 53-58%, with some incorporating innovative variations
on the conventional technology, using concepts such as solar power for
preheat, water flashing for inter-cooling in between gas turbine compression
stages, reheating, and steam for gas turbine hot component cooling. The high
efficiencies now being achieved are due, in no small measure, to the
introduction of new gas turbine technologies with thermal efficiencies in the
region of 40 to 48%). Among the factors contributing to elevated efficiencies are
high pressure ratios and high firing temperatures (2400F, 1315C).
However, the advantages of advanced gas turbines have to some extent been
eclipsed by the following major problems experienced during operation:
lower availability (up to 10% less than that averaged by earlier (ie less-than-
175-MW machines));
reduced life of nozzles and blades (averaging 15000 hours);
higher degradation rate (5-7% in first 10 000 hours of operation); and
instability of low NOx combustors.
Firing temperature significantly affects the performance and life of the
components in the hot section of the turbine. Turbines are also very sensitive to
backpressure exerted on them by heat recovery steam generators. In addition,
the pressure drop through the air filter also results in a major deterioration of
turbine performance.
The issues are exacerbated by the increasing need for cycling. Large combined
cycle power plants were originally developed as baseload units (one start in
every 1000 hours of operation). The reality has been very different and most
combined cycle power plants are operating under cyclic conditions where the
load at off prime time could be as low as 40-50% of the baseload. Many of
these plants now shutdown for the weekends.
1
Figure 1. Gas turbine compressor showing the bleed holes (Note: the decrease of the
casing thickness near the bleed flow ports)
2
Figure 2. Compressor blade with squealer tip
3
Figure 3. Damage to fuel nozzles due to flash back
Compressor developments
The axial flow compressor used in advanced gas turbines typically has 17-22
stages, with very high pressure ratios (17:1 to 20:1 for industrial gas turbines,
30:1 for frame and 40:1 for aero engines). The more stages, and the higher the
pressure ratio the smaller the operational margin between the surge and choke
regions of the compressor. Such a narrow operation margin makes operation of
the turbine very susceptible to compressor fouling. The high pressure ratios
http://www.modernpowersystems.com/features/featurewhen-things-go-wrong-identifying-combined-cycle-problem-areas/ 1/9
17/9/2017 When things go wrong: identifying combined cycle problem areas - Modern Power Systems

also result in high compressor exit temperatures, making the bleed air from the
compressor unsuitable for cooling the turbine vanes and blades without being
cooled first. This requires that the bleed air be sent to an external cooler, which
can introduce the problem of contamination. Potential sources of contamination
are corrosion due to condensation in the bleed lines and weld slag or other
debris not properly cleaned out before start-up. Several failures have occurred
due to the clogging up of cooling holes in vanes and blades, resulting in
overheating of components.
Table 1 summarises recent changes in compressor design and the associated
risk.
The trend in advanced axial flow compressors is towards fewer, thinner, larger,
3D and controlled diffusion shaped airfoils (3D/CDA), with smaller clearances
and higher loading per stage. There is also increased use of water injection at
the inlet or between compressor sections, which affects airfoil erosion.
Tip rubs are also major problems in the compressor section of advanced gas
turbines. The smaller clearances (20-50 mils) and high pressure ratios tend to
increase the probability of encountering rubs. These tip rubs usually occur near
the bleed flow sections of the compressor where there are inner diameter
changes, and the compressor casing tends to deform slightly (Figure 1). Such
rubs, if severe can lead to tip fractures and overall destruction of the
downstream blades and diffuser vanes due to domestic object damage (DOD).
To get round the problem of blade rub, many advanced compressor blades
have squealer sections on the blade tips (Figure 2), which are designed to wear
in a safe manner if the blades are in contact with the casing.
4
Figure 4. A DLE combustor showing damage to the combustor due to flash back
5
Figure 5. Transition components from an annular combustor
Combustion systems
Combustion systems typically consist of three major components: fuel nozzles;
combustor cans; and transition pieces.
The majority of problems in the combustion system occur in the combustor cans
and transition pieces. Fuel nozzles do not seem to suffer failures but do get
clogged and the tips can have heavy carbon build-ups, especially when
operating with fuel oil.
The new large gas turbines have two types of combustors:
Can annular (GE, Mitsubishi, Siemens (Westinghouse), Hitachi).
Annular (Alstom, Siemens (Germany)).
The advanced gas turbines all have dry low NOx combustors. The stable,
simple, diffusion flame combustor has been replaced with a barely stable,
staged-combustion system with multiple injection locations which vary with gas
turbine load.
The dry low NOx combustor system has to be monitored and tuned precisely for
stability from starting to full load while maintaining low emissions and avoiding
"flashback" and "high pressure pulsations", which usually damage the
combustor and turbine components.
The principal features of such a combustion system are the premixing of the
fuel and air before the mixture enters the combustion chamber and leanness of
the mixture strength in order to lower the flame temperature and reduce NOx
emissions.
The management of air in the combustion process and for cooling of the
combustor is particularly critical. Dry low NOx combustors require more
complex fuel nozzle designs and cooling arrangements, as well as thermal
barrier coatings (TBC) to achieve adequate life for both the can-annular and
annular combustion systems.

http://www.modernpowersystems.com/features/featurewhen-things-go-wrong-identifying-combined-cycle-problem-areas/ 2/9
17/9/2017 When things go wrong: identifying combined cycle problem areas - Modern Power Systems

The fuel nozzles are more complicated and larger in number due to the multiple
injection locations.
When dual fuel is involved or water injection is used to further reduce
emissions, the purge systems for the multiple injection points are complex and
can be a significant source of problems such as fuel nozzle plugging and
localised hot section damage. As with new compressor and turbine designs, the
costs and the risks associated with these complex combustion systems are
high, see Table 2.
6
Figures 6a and 6b. Can annular combustor transition piece
7
Figure 7. Typical failure in gas turbine expander section (note missing tip shrouds in
stages 3 and 4)
8
Figure 8. HP first stage nozzle vanes
9
Figure 9. First stage nozzle vanes (note cooling holes on the vane shroud area)
The majority of the NOx produced in the combustion chamber is called 'thermal
NOx'. It is produced by a series of chemical reactions between the nitrogen (N2)
and the oxygen (O2) in the air that occur at the elevated temperatures and
pressures in gas turbine combustors. The reaction rates are highly temperature
dependent, and the NOx production rate becomes significant above flame
temperatures of about 3300F (1815C).
The important factors in the reduction of NOx are the temperature of the flame,
the nitrogen and oxygen content and the residence time of the gases in the
combustor.
The DLE approach is to burn most (at least 75%) of the fuel at cool, fuel-lean
conditions to avoid any significant production of NOx.
However, controlling CO emissions can be difficult (they increase as flame
temperature is reduced) and rapid engine off-loads bring the problem of
potential flame extinction. If extinction occurs the flame cannot be safely re-
established without bringing the engine to rest and going through the restart
procedure.
The DLE injector has two fuel circuits. The main fuel, approximately 97% of the
total, is injected into the air stream immediately downstream of the swirler at the
inlet to the premixing chamber. The pilot fuel is injected directly into the
combustion chamber with little if any premixing.
With the flame temperature being much closer to the lean limit than in a
conventional combustion system, some action to prevent flame out has to be
taken when the engine load is reduced. If no action is taken flame out can occur
because the mixture strength becomes too lean to burn. A small proportion of
the fuel is always burned richer to provide a stable 'piloting' zone, while the
remainder is burned lean. In both cases the swirler is used to create the
required flow conditions in the combustion chamber to stabilise the flame.

The major problem with DLE combustors is the flash back problem in which the
flame moves from the main combustor region to the pre-mix chambers. This
causes the combustion to occur in the fuel nozzle section instead of the primary
combustion zone, damaging the nozzle (see Figure 3). This also leads to
uneven combustion and causes damage in the primary and secondary zones of
the combustor can (Figure 4).
Operators must take great care to avoid flash back by ensuring that the fuel is
dry. It should be injected at a minimum of 60F (33C) above the fuel's dew
point. The dew point should be measured by analysing the fuel, including the
high hydrocarbons (C5-C16) . Most fuel analysis ignores the higher
hydrocarbons, which may lead to an error of 50-60F (28-33C) in the
measured dew point.

http://www.modernpowersystems.com/features/featurewhen-things-go-wrong-identifying-combined-cycle-problem-areas/ 3/9
17/9/2017 When things go wrong: identifying combined cycle problem areas - Modern Power Systems

It is also suggested that large knockout drums and coalescing filters be


positioned next to each turbine to ensure the gas has no liquids entrained.
10
Figure 10. The trailing and leading edge of these nozzle vanes, which experience the
highest temperatures due to their relative thinness, are badly burnt
11
Figure 11. First stage expander section blade with excessive rub
12
Figure 12. First stage shroud ring assembled from a number of shroud blocks
Transition pieces
The transition piece brings the combustion gases from the combustor section to
the first stage turbine nozzle vanes (Figures 5 and 6). The transition pieces
require substantial cooling, as well as thermal barrier coatings (TBC), because
of the high gas temperatures close to 2300F (1260F). In some advanced gas
turbines steam is used for cooling the transition pieces. Steam cooling is done
by routing the steam exiting from the HP section of the combined cycle plant
steam turbine to the transition piece thus providing cooling and reheat of the
steam. The GE H series gas turbine also uses the steam for cooling the nozzle
vanes and blades. When steam is used for cooling in the gas turbine the water
specifications for the steam must be very closely monitored to ensure its purity.
Both conventional and steam cooled transition pieces have experienced
cracking.
Gas turbine expander section
The development of new materials as well as cooling schemes has seen rapid
growth in turbine firing temperatures leading to high turbine efficiencies. The
stage 1 blade of the turbine expander section must withstand the most severe
combination of temperature, stress and environment; it is generally the limiting
component in the machine. Since 1950, expander section turbine blade (or
bucket, the GE term) material temperature capability has advanced about
850F (472C), about 20F (10C) per year. The importance of this increase can
be appreciated by noting that an increase of 100F (56C) in turbine firing
temperature can provide a corresponding increase of 8% to 13% in output and
a 2% to 4% improvement in simple-cycle efficiency. Advances in alloys and
processing, while expensive and time-consuming, provide attractive returns
through increased power density and improved efficiency.
Typically the first and second stages of the turbine expander section use
complex multi-path serpentine cooling schemes inside the blades. Higher
strength single crystal (SC) blade materials coupled with oxidation resistant
coatings and/or thermal barrier coatings are used in the first stage blades, and
directionally solidified (DS) blade materials with TBC are used in the second
and third stage blades to meet turbine life requirements.
Design margins are set by FEM at the element level, but the long-term creep
strength characteristics of the turbine materials are not well-defined. In addition,
the turbine materials now being used typically have reduced temperature
margin to melting compared with earlier materials. As with compressors, the
smaller clearances and higher expansion ratios employed in the newer designs
of turbine tend to increase the probability of encountering rubs. The costs of
these larger airfoils, with complex cooling schemes, more twisted shapes, and
using more sophisticated materials and coatings, are substantially higher per
airfoil stage than earlier designs.
The trends in the turbine expander section are similar to those in the
compressor section, with use of fewer but larger 3D airfoils with smaller
clearances and higher expansion ratios (Re). As with compressors, the smaller
clearances and higher expansion ratios associated with the newer turbines tend
to increase the probability of encountering rubs.
Table 3 summarises points of difference between older and newer designs in
the turbine expander section.

http://www.modernpowersystems.com/features/featurewhen-things-go-wrong-identifying-combined-cycle-problem-areas/ 4/9
17/9/2017 When things go wrong: identifying combined cycle problem areas - Modern Power Systems

The high temperatures encountered in advanced gas turbines have been


contributing to failures in turbine nozzle vanes and blades, with the failures
occurring at blade tips (Figure 7) and at the bases of the turbine nozzle vanes.
First stage nozzle vanes (Figure 8) are encountering air temperatures in the
range 2100F to 2350F (1150C to 1288C) so cooling of these vanes is very
important. In particular, the nozzle vanes are encountering problems at the
platform and shroud region, necessitating cooling for these regions (Figure 9).
All the OEMs have introduced modifications, including new cooling patterns for
the nozzle vane platforms and shroud regions, further cooling of the
compressor bleed air with external heat exchangers, and the use of steam for
cooling.
The highest temperatures are encountered at the leading and trailing edges of
the nozzle vanes and even with extensive new cooling schemes vanes are
being badly damaged (Figure 10).
First stage blades in the expander section also suffer from excessive tip rubs
(Figure 11) due to the very small clearances now being used in the interests of
high efficiency, coupled with high temperatures, which cause the blades to
grow. Most damage is mainly at the blade trailing edges. These are very thin
and tend to fail when they come into contact with the casing, causing massive
damage to the vanes and blades that follow.
The tip rubs create problems on the tip shroud blocks of the turbine. Shroud
blocks, formed into a shroud ring (Figure 12), are used so that the casing itself
is not damaged. The shroud blocks are also thermal barrier coated and
extensively cooled due to the high temperatures they experience.
The first stage turbine expander section blades are usually impulse turbines,
and the second to third and fourth stages are reaction type (30-60%) and
normally have shroud tips, see Figure 13. These shroud tips are there to give
the blade more support so that the blades do not suffer from blade resonance
problems. If the locks on these shroud tips do not fit flush that means the blade
has been stretched and may be close to failure.
13
Figure 13. Shroud tips with cooling holes
14
Figure 14. Failure of expansion joint
Expansion joints, exhaust manifolds and HRSGs
There is usually an expansion joint between the gas turbine and the HRSG.
There have been many failures of these expansion joints (Figure 14). Some of
these failures are due to the joints experiencing large temperature excursions
due to cycling of the turbine.
In some cases external heat sources cause damage to the expansion joint and
insulation alone does not prevent damage. Often a heat shield is required to
prevent heat from the exhaust transition ducting radiating directly on to the
expansion joint. In other cases the insulation between the exhaust transition
piece and the expansion joint is poorly installed and allows excessive heat to
reach the expansion joint.
Also prone to cracks are the struts (Figure 15) which support the exhaust
manifold connecting the gas turbine to the HRSG. These struts are exposed to
hot exhaust gas flows. The more the plant is cycled the greater the stresses,
leading to failures in the material. Most of these cracks can be repaired by
welding, but recurrence of cracks in repaired areas is not uncommon.
It is recommended that the exhaust manifold and expansion joints are inspected
regularly.
In the case of the HRSG itself the main problems are usually encountered in the
superheaters of the HP and IP sections. The heating coils of the superheaters
experience the highest temperatures and failures have occurred due to exhaust
temperature increases of 25F-50F (14C-28C) following gas turbine

http://www.modernpowersystems.com/features/featurewhen-things-go-wrong-identifying-combined-cycle-problem-areas/ 5/9
17/9/2017 When things go wrong: identifying combined cycle problem areas - Modern Power Systems

upgrades. Gas turbine upgrades in a combined cycle plant must be very


carefully evaluated because increases in exhaust temperatures and flows can
have a major negative impact in the HRSG.
Stress cracks are also encountered frequently in HRSG shells and in some
cases HRSG shells exposed to higher flow rates can bulge out and cause the
movement of steam coils. These problems have been encountered in many
installations as turbine upgrades are often sold by the gas turbine
manufacturers without a full assessment of the effects on the rest of the plant.
Figure 16 shows a typical rupture in steam tubing due to high temperatures.
Problems are also often encountered in feedwater pumps. These pumps should
be provided with 100% backup as a failure brings the entire plant down and the
extra cost for a full back-up system as a percentage of the entire plant cost is
minor. Most of the problems with these pumps are due to the bearings.
15
Figure 15. Strut failure in exhaust manifold
16
Figure 16. Typical rupture of steam tubing due to high temperature
Steam turbine and condensers
The steam turbine usually experiences problems in the LP section due to water
droplets in the last stages. The blades suffer erosion of the leading edge. The
last stage blades are also very long and thus may encounter resonance
problems if they are not properly damped. Usually the blades have mid-span
damping as well as tip damping.
The main purpose of the steam condenser is to convert the low pressure steam
from the exit of the LP steam turbine to condensate by reducing the exhaust
pressure of the LP steam turbine to a pressure below atmospheric and to
condense the steam so that the condensate is available for reuse as boiler
feedwater. This is accomplished with the lowest achievable backpressure.
Increase in the back pressure will reduce the power output from the LP steam
turbine.
The most common condenser is the water tube and shell type. The tubes
carrying the cooling water can foul and need to be cleaned otherwise the
effectiveness of the cooling is decreased. Poor cooling affects the exhaust
temperature of the steam turbine, increasing the back pressure on the LP
steam turbine section and reducing the output. The water pump system must
have a full back-up especially if the plant condenser cooling water comes from
the ocean and is subject to fouling.
The author is with the Boyce Consultancy Group, Houston Texas.
Tel +1 713 807 0888. email mpboyce@boycepower.com

http://www.modernpowersystems.com/features/featurewhen-things-go-wrong-identifying-combined-cycle-problem-areas/ 6/9
17/9/2017 When things go wrong: identifying combined cycle problem areas - Modern Power Systems

http://www.modernpowersystems.com/features/featurewhen-things-go-wrong-identifying-combined-cycle-problem-areas/ 7/9
17/9/2017 When things go wrong: identifying combined cycle problem areas - Modern Power Systems

10

11

12

13

14

15

http://www.modernpowersystems.com/features/featurewhen-things-go-wrong-identifying-combined-cycle-problem-areas/ 8/9
17/9/2017 When things go wrong: identifying combined cycle problem areas - Modern Power Systems

16

Follow Us: Linkedin


Modern Power Systems is a product of Global Trade Media, a trading division of Progressive Trade Media Limited. 2017, All Rights Reserved.

Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy
policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy
unless you have disabled them.

http://www.modernpowersystems.com/features/featurewhen-things-go-wrong-identifying-combined-cycle-problem-areas/ 9/9

You might also like