You are on page 1of 3

Technology Triumphs

By Dorian L. Adams, P.E.


Courtesy Intermountain Health Care.

Buckling restrained braces (BRBs) will help limit non-structural


earthquake damage at this Utah medical facility near the Wasatch Fault.

T
he Intermountain Medical Cen- Buckling Restrained Braced Frames cles of large inelastic deformations while
ter (IMC), located in Murray, The high strength-to-weight ratio of maintaining strength and absorbing en-
Utah, is the agship hospital structural steel made it ideal for seismic ergy in excess of that produced by major
for Intermountain Health Care, design by limiting building mass. Buck- seismic events. BRBs are situated to work
one of the leading health care ling restrained braced frames (BRBFs) with the architects layout of corridors,
providers in the nation. Approximately and eccentrically braced frames were windows, stairs, and elevators. In many
ve miles east of the hospital campus considered as potential seismic force re- cases, corridors and doorways pass be-
lies the Wasatch Faultan active fault sisting systems for this project because tween the braced frame diagonals.
capable of producing magnitude 7.3 of their ability to absorb seismic energy IMC is the largest project to date in
earthquakes. while limiting inter-story drift. BRBFs the United States constructed with BRB
In the event of a large earthquake, were chosen because they were deemed technology. There are 648 BRBs on the
the eight buildings on the 1.3 million more reliable and better performing than Intermountain Medical Center project,
sq. ft campus have to be able to serve eccentrically braced frames. all manufactured by Core Brace of West
the community immediately and with In recent years, there has been a large Jordan, Utah. Six large-scale BRB quali-
minimal interruption. The structural amount of full-scale testing of buckling fying tests were successfully completed
frame therefore needed to limit damage restrained braces (BRBs). These tests at the University of Utah structures lab-
to non-structural building components show that BRBs can withstand many cy- oratory consisting of two 184 kip braces,
and medical equipment by controlling two 414 kip braces, and two 920 kip
seismic drift while absorbing seismic braces. Testing followed the guidelines
energy. It also needed to be able to found in the AISC-SEAOC Recommended
withstand large seismic accelerations Provisions for Buckling-Restrained Braced
without the need for extensive repairs. Frames. Two of the test braces experi-
Structural steel was selected for its enced cyclical loading at forces above
superior seismic performance, economy, 1.3 million lb.
and its effect on design exibility and
construction duration. Beyond its seis- Foundation and Steel Frames
mic advantages, a steel frame would be Approximately 12,350 tons of struc-
fabricated and erected quickly, meet- tural steel were used throughout the
ing the extremely tight schedule, and hospital campus, which includes a heart
would be easily modied during fu- Dorian Adams is a project manager for center, tertiary hospital, patient care tow-
ture revisions as the hospitals needs Reaveley Engineering and Associates, er, oncology center, ambulatory surgery
changed. Inc. center, and a womens and newborn cen-

Modern Steel Construction September 2005


ter. The largest building in the project is
composed of a four-story base that sup-
ports the eight-story heart center and the
16-story patient care tower.
The BRBFs from the towers are sup-
ported on reinforced concrete shear walls
in the lowest two levels. The largest net
uplift force on the columns of the 16-story
BRBF was 8,000 kips. This magnitude of
force is created by the BRBF design proce-
dure that requires the column to have the
strength to resist the vertical component
of the expected yield strength of each
brace in the frame. This design philoso-
phy guarantees the column will remain
elastic during a seismic event while the
BRBs are yielding and absorbing seismic
energy. The BRBF columns were taken
through the reinforced concrete shear
walls and connected directly to the foun-
dation with up to 20 3-diameter ASTM
F1554 grade 105 anchor rods through
base plates up to 9 thick to resist the
high net uplift force.
The interface between concrete shear
walls and structural steel created a con-
struction and sequencing challenge. The
rst tier of BRBF steel columns needed
to be erected before the concrete shear
walls could be placed. Originally, in-
dividual boxes were to be erected
consisting of the braced frame columns
connected to adjacent columns with tie
beams. Once steel erection began, it be-
came clear that the building could not be
plumbed properly using this method. To
solve this problem, additional tie-in steel
was shipped for erection to connect the Above: Many of the BRBF columns were jumbo shapes. The BRBF design procedure requires
braced frames together and lock the em- the column to have the strength to resist the vertical component of the expected yield strength of
each brace in the frame. Photo courtesy Reaveley Engineers & Associates, Inc.
bedded columns into place prior to pour-
ing concrete. Subsequent plumbing prob-
Below: Threaded anchor rods for a BRBF column prior to concrete placement. BRBF columns
lems were eliminated or substantially were taken through the reinforced concrete shear walls and connected directly to the foundation
reduced. This allowed for structural steel with up to 20 3-diameter ASTM F1554 grade 105 anchor rods through base plates up to 9 thick.
erection to continue while concrete work Photo courtesy Reaveley Engineers & Associates, Inc.
was performed.

Material Procurement and Delivery


The structural steel fabricator was
challenged with material procurement
and delivery of large steel sections
needed for the braced frame columns.
Jumbo shapes were purchased from Ar-
celor International in Luxemburg. Many
of these sections needed to be erected
a month before the main portion of
structural steel erection commenced so
they could be cast into concrete shear
walls. The early erection schedule con-
icted with the delayed rolling of some
of the sections, making it necessary to
purchase a few of them from Arcelors
warehouse in the U.S. Some of these

September 2005 Modern Steel Construction


sections also required cover plating. would be completed in time to start con- The 16-story tower topped out in July
To make the early deliveries and still struction of foundations and the prima- 2005 and the remaining buildings will be
be ready for the primary start of erec- ry structure in August 2004. Construc- topped out by October 2005. Substantial
tion, the fabricator found it necessary tion of the steel structure was underway completion for the largest building is
to sublet the fabrication of the majority while architectural, mechanical, and expected for the summer of 2007, while
of these sections. electrical contract documents were be- the smaller buildings will be nished
Some of the remaining sections that ing completed. The architectural and en- sooner.
were being rolled to meet the later erec- gineering designs were developed and
tion schedule were set back to a later coordinated on a critical path format to
Owner
date, challenging the schedule once meet the schedules of each bid package.
Intermountain Health Care
again. Rolling progress, dock delivery, Structural steel allowed for modica-
ship loading in Luxemburg, arrival at tions in the event of planning changes Architect
one of three ports in California, unload- and shortened the construction dura- Anshen + Allen, San Francisco
ing, and delivery for fabrication in Cali- tion. Structural steel detailing began
Structural Engineers
fornia and Utah was monitored by inter- August 2004 and the rst of the steel fab-
Reaveley Engineers & Associates, Salt
nal expediters to ensure that deliveries rication began in November for erection
Lake City (executive)
were not postponed. in December. Detailing was completed
ARUP, San Francisco (associate)
in May 2005 and fabrication wrapped
Fast-Track Schedule up in July. Engineering Software
After more than a year of careful A weekly structural steel detailing ETABS
programming, the architect turned the coordination meeting was implemented RAM Structural System
design over to the structural engineers to solve structural steel challenges in a
Fabricator and Erector
in August of 2003, with the structural timely manner and to meet the aggres-
SME Steel Contractors, Inc., West Jor-
contract documents put out to bid seven sive construction schedule. The con-
dan, Utah, AISC member
months later in June 2004. A fast-track struction manager, engineer, architect,
construction method was implemented and steel fabricator attended these meet- General Contractor
by bidding the project in several phases. ings and were very successful in solving Okland Construction Company, Salt
Earthwork and site utility construction issues before the shop drawings were Lake City
documents were bid so that the work submitted for approval.

Modern Steel Construction September 2005

You might also like