Id Modo Nombre de tarea Duracin Comienzo Fin 14 may '17 21 may '17 28 may '17 04 jun '17 11 jun

zo Fin 14 may '17 21 may '17 28 may '17 04 jun '17 11 jun '17 18 jun '17 25 jun '17
de tarea L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L
1 ANTENA MINA MARIA 45 das lun 15/05/17lun 26/06/17
2 TRABAJOS PRELIMINARES 6 das lun 15/05/17 sb 20/05/17
3 TRASLADO DE HERRAMIENTAS Y EQUIPOS 3 das lun 15/05/17 mi 17/05/17
4 FLETE TERRESTRE Y ACARREO DE MATERIALES 3 das lun 15/05/17 jue 18/05/17
5 TRAZO Y REPLANTEO INICIAL 2 das jue 18/05/17 vie 19/05/17
6 CARTEL DE OBRA 1 da vie 19/05/17 sb 20/05/17
7 ZAPATAS Y PEDESTALES 14 das mi 17/05/17 mar 30/05/17
8 EXCAVACION A MANO EN TERRENO SEMIDURO 10 das vie 19/05/17 lun 29/05/17
9 SOLADO PARA ZAPATAS 2 das lun 22/05/17 mi 24/05/17
10 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 4 das mi 17/05/17 sb 20/05/17
11 Concreto F'c=210 kg/cm2 para ZAPATAS 4 das mi 24/05/17 dom 28/05/17
12 ENCOFRADO Y DESENCOFRADO DE PEDESTALES 4 das dom 21/05/17mi 24/05/17
13 Concreto F'c=210 kg/cm2 para PEDESTALES 2 das mi 24/05/17 vie 26/05/17
14 RELLENO COMPACTADO MANUAL CON MATERIAL PROPIO 2 das dom 28/05/17mar 30/05/17
15 CURADO CON ADITIVO QUIMICO EN CONCRETO 1 da dom 28/05/17lun 29/05/17
16 MONTAJE DE TORRES (h=21m, h=15, h=6m) 12 das lun 29/05/17 vie 09/06/17
17 TRASLADO DE TORRES METALICAS A PUNTOS DE MONTAJE 2 das lun 29/05/17 mi 31/05/17
18 MONTAJE DE ESTRUCTURAS METALICAS - ANTENAS 10 das mi 31/05/17 vie 09/06/17
19 CASETA DE PROTECCION DE EQUIPOS 14 das lun 29/05/17 dom 11/06/17
20 MOVIMIENTO DE TIERRAS 3 das lun 29/05/17 jue 01/06/17
21 EXCAVACION MANUAL PARA CIMIENTOS CORRIDOS 2 das lun 29/05/17 mi 31/05/17
22 ELIMINACION DE MATERIAL EXCEDENTE (manual) 1 da mi 31/05/17 jue 01/06/17
23 CIMIENTOS CORRIDOS 2 das mi 31/05/17 vie 02/06/17
24 CIMIENTOS CORRIDOS MEZCLA 1:10 C:H + 30% PIEDRA GRANDE 2 das mi 31/05/17 vie 02/06/17
25 SOBRECIMIENTOS 2 das vie 02/06/17 sb 03/06/17
26 CONCRETO SOBRECIMIENTOS MEZCLA 1:8 + 25% PIEDRA MEDIANA 1 da sb 03/06/17 sb 03/06/17

27 ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTOS 1 da vie 02/06/17 sb 03/06/17

28 MUROS Y TABIQUES 2 das dom 04/06/17lun 05/06/17


29 MURO DE LADRILLO KK DE SOGA MEZCLA C:A, 1:4 TIPO IV 2 das dom 04/06/17lun 05/06/17
30 COLUMNETAS 4 das vie 02/06/17 lun 05/06/17
31 ACERO Fy=4200 Kg/cm2. GRADO 60 PARA COLUMNAS 1 da vie 02/06/17 sb 03/06/17
32 ENCOFRADO Y DESENCOFRADO NORMAL PARA COLUMNAS 2 das sb 03/06/17 dom 04/06/17
33 Concreto F'c=210 kg/cm2 para COLUMNAS 1 da dom 04/06/17lun 05/06/17
34 LOSAS MACIZAS 6 das lun 05/06/17 dom 11/06/17
35 ACERO Fy=4200 Kg/cm2. GRADO 60 PARA LOSAS MACIZAS 2 das mi 07/06/17 vie 09/06/17
36 ENCOFRADO Y DESENCOFRADO NORMAL PARA LOSAS MACIZAS 2 das lun 05/06/17 mi 07/06/17
37 Concreto F'c=210 kg/cm2 para LOSAS MACIZAS 2 das vie 09/06/17 dom 11/06/17
38 PISOS 1 da mi 07/06/17 jue 08/06/17
39 FALSO PISO DE 4" CON MEZCLA 1:8, C:H 1 da mi 07/06/17 jue 08/06/17
40 CERCO DE PROTECCION 15 das dom 11/06/17dom 25/06/17
41 CERCO DE INSTALACIONES CON POSTES Y ALAMBRES DE PUAS 6 das vie 16/06/17 mi 21/06/17
42 CERCO CON MALLA GALVANIZADA DE 2"x2" TIPO COCADA N 12 15 das dom 11/06/17dom 25/06/17
43 SUMINISTRO E INSTALACION DE ACCESORIOS EN CASETA DE PROTECCION 18 das mi 07/06/17 sb 24/06/17

44 ACARREO Y SUMINISTRO DE ACCESORIOS Y EQUIPOS 2 das mi 07/06/17 vie 09/06/17


45 TRABAJOS DE MONTAJE E INSTALACIONES EN CASETA DE EQUIPOS 4 das vie 09/06/17 mar 13/06/17
46 SUMINISTRO E INSTALACION DE PANELES SOLARES 4 das mar 20/06/17 sb 24/06/17
47 ESTRUCTURAS METALICAS 4 das sb 17/06/17 mar 20/06/17
48 PUERTA METALICAS 2 das sb 17/06/17 lun 19/06/17
49 SOPORTE METALICO PARA PANELES SOLARES 2 das lun 19/06/17 mar 20/06/17
50 VARIOS 29 das jue 18/05/17 mi 14/06/17
51 LIMPIEZA FINAL DE OBRA 1 da mar 13/06/17 mi 14/06/17
52 POZO DE TIERRA (inc. excavacion) 6 das mi 07/06/17 mar 13/06/17
53 IMPACTO AMBIENTAL 15 das jue 18/05/17 jue 01/06/17
54 SEGURIDAD Y SALUD 42 das jue 18/05/17 lun 26/06/17
55 ELABORACION, IMPLEMENTACION Y ADMINIST DEL PLAN DE SEGURIDAD Y 42 das jue 18/05/17 lun 26/06/17
SALUD

56 EQUIPOS DE PROTECCION PERSONAL (individual) 30 das jue 18/05/17 jue 15/06/17


57 SEALIZACION TEMPORAL DE SEGURIDAD 15 das jue 18/05/17 jue 01/06/17
58 CAPACITACION EN SEGURIDAD Y SALUD 5 das vie 19/05/17 mi 24/05/17

Tarea Resumen Hito inactivo solo duracin solo el comienzo Hito externo Divisin crtica
Proyecto: GANTT
Fecha: mi 07/06/17 Divisin Resumen del proyecto Resumen inactivo Informe de resumen manual solo fin Fecha lmite Progreso
Hito Tarea inactiva Tarea manual Resumen manual Tareas externas Tareas crticas Progreso manual

Pgina 1

You might also like