Project Name Product Release

Project Manager Alex B.


Project Deliverable

Start Date 2-Sep


End Date 9-Oct
Overall Progress 20%

Tasks Responsible Start End Days

3/16/2016
Set kick-off meeting Alex B. 9/2 9/2 0
Agree on objectives Frank C. 3-Sep 7-Sep 4
Initiation
Detailed Reqs. Jacob S. 7-Sep 9-Sep 2
Hardward Reqs. Jacob S. 9-Sep 11-Sep 2
Final Resource Plan Jacob S. 11-Sep 15-Sep 4
Staffing Alex B. 15-Sep 17-Sep 2
Development
Techincal Reqs. Frank C. 17-Sep 21-Sep 4
DB Development Shari W. 21-Sep 23-Sep 2
API Development Shari W. 23-Sep 25-Sep 2
UI Client Alex B. 25-Sep 29-Sep 4
Testing Kennedy K. 29-Sep 2-Oct 3
Dev. Complete Jacob S. 2-Oct 5-Oct 3
Operations
Hardware Config. Alex B. 5-Oct 7-Oct 2
System Testing Kennedy K. 7-Oct 9-Oct 2
Launch 9-Oct 9-Oct
Or
Status
9/2 9/3 9/4 9/5 9/6 9/7 9/8 9/9 9/10 9/11 9/12 9/13 9/14 9/15 9/16

Complete

Complete

Complete

Overdue

In progress

In progress

Not started

Not started
Not started

Not started

Not started
Not started

Not started

Not started
Or, Click Here to Create Your Work Plan in Smartsh
9/17 9/18 9/19 9/20 9/21 9/22 9/23 9/24 9/25 9/26 9/27 9/28 9/29 9/30 10/1 10/2 10/3 10/4
an in Smartsheet
10/5 10/6 10/7 10/8 10/9

You might also like