SGD SAIPEM CAMP ACCOMODATION AND BUILDING FACILITIES

JOB SAFETY ANALYSIS


JSA NO. 003 Page 1 of 2
PROJECT OPERATIONAL CAMP
Activity: Loading Unloading Date 07/01/2013

Steps Hazards Control Measures to be Enforced Remarks / Actions


Transportation Failure of lifting gears or Only approved plant will be used to transport heavy Site Supervisor.
lifting equipment loads.
/ Lifting of heavy Plant/Equipment used will be maintained in a good
Equipment. condition.
Licensed and experienced operators will be used to
carry out this activity.
The loading of equipment will be carried out in
accordance with approved documents.
Loading will be closely supervised with trained banks
men in attendance.
Rigging / Crane studies will be undertaken (if
required) to ensure the lifting operation is carried
out in a controlled and effective manner utilizing any
existing lifting points provided.
The weight of any such load will be determined to
ensure that overloading is prevented.
Only competent and approved operator shall be
deployed for lifting operations.
Equipment as well as lifting jacks to be certified by
competent persons before deployment.
Daily inspection of the equipment should be done by
the operator.
No overloading allowed follow procedures of safe
handling.
Training and assistance of banks man/ Rigger.
Coordination between operator & Banks man.
Adequate Rest breaks recommended.
SGD SAIPEM CAMP ACCOMODATION AND BUILDING FACILITIES
JOB SAFETY ANALYSIS
JSA NO. 003 Page 2 of 2
PROJECT OPERATIONAL CAMP
Activity: Loading Unloading Date 07/01/2013

Material Handling Back injury due to manual Whenever practicable, mechanical lifting aids e.g. Site Supervisor
( material handling. Cranes, forklifts trucks etc., will be used to alleviate
Individual Capability. the requirement for manual handling.
Manual Lifting/ Supervision will assess weight, centre of gravity etc.
Poor lighting conditions.
Lowering of Inadequate space. and determine the number of persons required to
Tripping/ Slipping. carry out the work safely.
Materials). Improper lifting load beyond Personnel will be trained in manual handling
the capacity of the individual. techniques.
Improper lifting techniques. Avoid manual load lifting if possible. If not then,
Lack of training, instruction & check and ensure that the load is below the
supervision. recognized permissible limit.
Slippery surface / Workers fit for the activity to be engaged.
overcrowded place. Area to be illuminated with adequate lighting.
Improper housekeeping. Good housekeeping standards to be maintained at all
times to avoid slip trips and falls.
Train the staff for good posture;
Use slip resistance shoe with toe protection and
hand gloves with sufficient grip to avoid insecure
hold.

Name Signature Date

Approved By: