Site survey

Danang, May 2017


Agenda
1. Overview about site survey
2. Equipment information
3. TSSR and Layout
4. Site survey summary table
5. Notes
6. DO
7. Cooperated procedure
1. Overview about site survey

Collect existing site information


Propose location for new equipment
Propose site design: Antenna height, Tilt, Azimuth

ZTE Corporation. All rights reserved


3
1. Overview about site survey-Site survey tools

GPS
Compass
Digital Camera
Metter
Tool for check downtilt

ZTE Corporation. All rights reserved


4
2. Equipment information Main equipment

Equipments Dimension (W*D*H) Weight (kg) Q'ty Remark

B8200 (BBU) 482.6*197*88.4mm 7 1

DCPD7 482.6*197*44mm 2 1

R8862A 422 * 218 * 133 mm 15 3

R8854 415 * 296 * 104mm 15 3

Small Cell R8922 290 * 270 * 90mm 7 1


OCPD1 0.5 1
Antenna 4 ports
1500 * 325 * 110 15 3
(1710-2690)MHz
Antenna 6 ports
1500 * 480 * 110 22 3
(1710-2690)MHz

ZTE Corporation. All rights reserved


5
2. Equipment information Cable information
No. Cable Type Size From To
1 Grounding cable 16mm2 RRU Grounding Bar on the top of Tower

2 Grounding cable 35mm2 Grounding Bar on the top of Tower Outdoor Grounding Bar (OGB)

3 Grounding cable 16mm2 Indoor cable tray Intdoor Grounding Bar (IGB)

4 Grounding cable 16mm2 BBU/DCPD7 Intdoor Grounding Bar (IGB)

5 BBU Power Cable BBU Power Rack


2x4mm2
6 RRU Power Cable 2x6mm2 DCPD7 OCPD
2x10mm2
50m, 100m,
7 Optical fiber BBU-RRU BBU RRU
150m
8 Optical fiber LC-SC 20m BBU ODF/ Switch L2

9 1/2" feeder jumper 1/2" RRU Antenna

RRU DC Cable size & length


Item 2x4mm2 2x6mm2 2x10mm2 Remark
R8862A 50m 80m 140m OCPD1 only use for
R8854 45m 70m 125m 2x10mm2

ZTE Corporation. All rights reserved


6
3. TSSR and Layout

Collect enough information and Fill enough and exactly information in


TSSR report
Make layout for indoor and outdoor equipment

TSSR Report Layout

ZTE Corporation. All rights reserved


7
4. Site survey summary table

After finished site survey at sites, surveyor need completed


TSSR&Layout and full fill Site survey summary table.
Base on site survey summary table, ZTE/TST will make DO and send
materials to sites for installation.

Site survey summary table:

ZTE Corporation. All rights reserved


8
5. Notes

During site survey, the Surveyor need pay high attention to:

Must print out TSSR&layout and take to site together


Collect enough and exactly existing information at sites, such as:
Antenna parameters (tilt, Azimuth, height,)
The cable length must be exactly

ZTE Corporation. All rights reserved


9
6. DO

Base on Site survey summary table, ZTE will make DO to delivery


equipments to sites for installation.

Local VNPT must arrange engineer go to sites to check DO


and sign, make sure lacking no any materials.
After receiver materials, must keep materials safety.

DO template:

ZTE Corporation. All rights reserved


10
7. Cooperated procedures

Local VNPT do site survey, send TSSR and Layout to TST for checking
TST will check and modify if any
TST submit TSSR and Layout to VNPT-Net for approval
VNPT-Net will check and approve
TST will inform approved result to local VNPT
TST send delivery information to warehouse for delivery
Local VNPT install equipment follow TSST and Layout already approved.

ZTE Corporation. All rights reserved


11
8. Discussion

ZTE Corporation. All rights reserved


12
Thank you!