Construction Cost Breakdown

Loan Number Job Address:


Owner
Builder Lip Amount: $

Cost Items Description Budget Pre-Paid


GENERAL CONDITIONS
1 Engineering & Survey
2 Excavation & Grading
3 Plans/Blueprints
4 Permits
5 Soil Testing
6 Temporary Facilities
7 Temporary Utilities
8 Water Meter
9 School Fees
10
OFFSITE WORK
11 Civil
12 Geology
13 Blasting
14 Compaction
15 Sewer
16 Backfill-Sand
17 Water Mains
18 Utilities
19 Electric/'Phone
20 Paving
20.1 Concrete
20.2 Asphalt
21 Curb & Gutter
22 Driveway Apron
23 Side walk
24 Sub drains
25 Slope & Erosion Control
26 Fencing
27 Equipment Rental
28 Fire Hydrants
29 Street Lights
30 Misc. Labor
31
32
ONSITE WORK
33 Gas Line
34 Sewer / Septic
35 Sanitary
36 Storm
37 Cleaning, Trash Disposal
38 Flatwork & Driveway
39 Patio and Walks
40 Sprinklers
41 Landscaping
42 Fence

Date

Date
Cost Items Description Budget Pre-Paid

Concrete
43 Pool/Spa/Solar
44 Finish Grading
45
46
47
48
CONCRETE
49 Foundation / Footing
50 Retaining walls
51
52
ELECTRICAL
53 Underground
54 Rough
55 Finish
56 Fixtures
MASONRY
57 Fireplace & Chimney
58 Walls
59 Brick Front
60 Brick Veneer
61
62
PLUMBING
63 Ground
64 Rough
65 Finish
66
METALS
67 Hardware - Rough
68 Hardware - Finish
69 Sheet Metal / Heating / Duct Work
70 Rebar
71 Stairs
72 Railings
73
74
WOOD CARPENTRY
75 Lumber Rough
76 Carpentry - Rough
77 Lumber -Finish
78 Carpentry - finish
79 Trusses
80 Siding
81 Cabinets
82 Garage Doors
83
84
ROOFING
85 Comp / Shingle / tile
86 Roofing Labor
WINDOWS / GLASSES
87 Enclosures, Tub & Shower
88 Skylight
89 Mirrors
90 Sliding Glass Door
91 Windows
92
93

Date

Date
Cost Items Description Budget Pre-Paid

FINISHES
94 Insulation
95 Luminous Ceiling
96 Suspended Ceiling
97 Drywall Installed
98 Stucco
99 Painting Interior
100 Painting Exterior
101 Wallpaper
102 Carpet installed
FINISHES
103 Linoleum Flooring
104 Tile Flooring
105 Counter Tops / Pullmans
106
107
APPLIANCES
108 Hood & Fan
109 Range & Oven
110 Microwave
111 Washer / Dryer
112 Dishwasher / Refrigerator
113 Garbage disposal
114
115
MISCELLANEOUS
116 Furnace / Air Conditioning
117 Contingency
118 Water Heater
119 Smoke Detector
120 Security System
121
122
123
CONTRACTOR
124 Overhead
125 Supervision
126 Profit
127
TRACT / APTS ONLY
128 Interest Reserve
129 Insurance
130 Advertising
131 Signs
132 Recreation Room
133 Laundry Room
134 Sales Office / Model
135 Carports
136 Parking Lot Striping
137
138
COMMERCIAL ONLY
139 Interest Reserve
140 Insurance
141 Advertising
142
143
144
145
146
147

SUB - TOTAL - -

Date
Date
Net

-
-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-
-
Net

-
-
-
-
-
-

-
-
-
-

-
-
-
-

-
-
-
-
-
-

-
-
-
-

-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-
-

-
-

-
-
-
-
-
-
-