You are on page 1of 3

chemical plant design and construction

Modularization of LNG
liquefaction plants
the transition to a mainstream project strategy
by Richard Brookeld, Director, Global LNG & Midstream, in order to reduce the work required at the main construc-
Foster Wheeler, and Jeremy Cooke, Project Operations tion site by use of one or more pre-fabrication and pre-
Manager, Business Solutions Group, Foster Wheeler assembly sites in other locations. Pre-fabricated and pre-
assembled modules are then transported usually by ship
and then by land transportation to the main construction
site where they are installed, connected and completed.
Modules are complete pre-assemblies of equipment,
bulk materials and components which are fabricated in
an offsite facility into a steel structure which can be trans-
ported and installed at the main construction site. Mod-
ules will vary in size, typically ranging from a few tonnes
up to several thousand tonnes depending on design and
installation constraints.
At its most simplistic level, modularization
can be achieved by taking a stick-build
design and splitting it into modules.
Alternatively, and more effectively,
Richard Brookeld Jeremy Cooke modularization is based on a

M
thorough assessment of the project
odularization is a construction strategy that was drivers to determine the optimum
originally developed in the offshore oil industry extent of modularization and
to enable large amounts of fabrication work specic modular designs for
to be carried out on land in a safer environment and at the project, taking account
considerable cost saving. Modular strategies for onshore of all relevant drivers and
projects have subsequently emerged, particularly since constraints.
the mid-1980s, made possible by developments in heavy
lift craneage and other specialist land transportation
equipment.
The application of a modularization strategy to an
onshore LNG liquefaction plant is very recent the North
West Shelf Venture Phase V LNG Expansion in Western
Australia, completed in 2008, was the rst LNG plant to
be designed and constructed on a multiple module ba-
sis where the process train was divided into a number
of separate, pre-fabricated modules. Subsequently,
several other onshore LNG developments planned
in Australia and other locations have also adopted
similar modular strategies and modularization has
now become a key consideration for many prospec-
tive LNG plant projects worldwide.

The modular
approach to plant construction
The traditional approach to construction of
process plants is to stick-build the facilities
entirely at the main construction site using
basic materials and a large construction labour
workforce. Where this is not desirable or not
feasible, a modular approach may be adopted

Chemical Technology October 2011 7


chemical plant design and construction

Drivers for modularization Another key factor for every modular project is the
There are many aspects of a project that may drive a maximum module size that can be fabricated, shipped
modularization strategy and typical considerations are and transported to the main construction site. Onshore
summarized in Table 1 on page 9. The main positive modules typically range up to 5 000 tonnes although the
drivers are generally labour (differential rates, availability maximum practicable size and weight will vary from proj-
and productivity) and site attributes (climate and remote- ect to project, often depending on the physical limitations
ness). Schedule, safety and environmental issues may of the transportation route to the main site location.
also inuence modularization decisions. Module fabrication is generally carried out in low-cost
Scarcity of resources, particularly skilled labour, is a locations where labour rates and productivity levels are
key driver which leads to higher construction costs and favourable in comparison to the main construction site.
increases the risk of delay. This may be the case in areas However, an increased degree of modularization will not
of signicant construction activity, where there is a high necessarily translate into overall cost savings as these
demand for labour, as well as remote locations where in- will be offset to some extent against the cost of addition-
sufcient local labour is available or where it is expensive al steelwork, shipping and specialist land transportation.
to bring labour to the site.
The attributes of the main construction site are also Implications for project execution
key drivers, particularly for sites in remote locations and Adopting a high degree of modularization has implica-
where climatic conditions are extreme and will constrain tions for all aspects of project execution. The use of
construction works. These factors will have potentially large-scale module fabrication yards introduces multiple
signicant impacts on cost and feasibility of stick-build construction locations for the project and consequently
construction. increases the complexity of execution planning and the
requirement for experienced management resources to
Degree of modularization achieve safe and successful outcomes.
and module size Constructability issues for modular projects are com-
One of the key decisions to be made in the early stages plex and need to be considered from the outset as they
of design is the degree of modularization that is will inuence early strategic decisions taken
appropriate for the project based on a detailed during feasibility and conceptual
assessment of the various factors and drivers as phases. Modularization decisions
summarized in Table 1. For many projects, some made during later project phases
modularization will be desirable and in some can result in considerable re-
cases it will be advantageous to maximize the work, and potentially, signi-
amount of work that can be transferred from the cant impacts on schedule. A
main construction site. However, it is not key consideration is the plant
possible to achieve total modularization layout which should be cong-
as there will always be work at the main ured from the outset to suit
construction site such as site prepara- the degree of modulariza-
tion, excavation, tank erection and nal tion, site location and
installation of the modules themselves. constraints, opera-
tional and mainte-
Modules are complete pre-assemblies of equipment, nance requirements
bulk materials and components that are fabricated
and the strategy for
offsite into a steel structure that can be transported
and installed at another location. Image: Courtesy of module installation
Woodside Energy. Source: Foster Wheeler and sequencing.

8 Chemical Technology October 2011


chemical plant design and construction

Modularization can give added schedule security by Table 1: Summary of main considerations for modularization
moving work away from a constrained construction site,
but will not usually shorten schedule due to the addi- Main considerations for modularization
tional logistical steps required. Logistics are particularly Labour Is there a lack of labour available at the project site, or local
relevant for projects where signicant land transportation area, or is there a restriction on site labour due to access and/or
of modules is required to reach the construction site. available land?
What are the relative labour rates and productivities for site and
potential module yards?
Future opportunities
for LNG modularization Site How do the site climatic conditions impact the construction logistic
Modularization is a complex strategy with many variables Attributes requirements of the site?
For example, cyclonic conditions, weather windows for shipping,
to consider and specic drivers will be different for each
cold climate, warm climate, hours of daylight, wind loading, snow
individual project. It is not a silver bullet and, in many
and ice loading, etc.
cases, may not be an appropriate solution. However, in
some circumstances, modularization offers signicant Site Do the available routes and lifting paths allow use of modules with
benets and these can be maximized by early decisions Access the dimensions set by road, rail or sea transportation?
to embed the execution strategy throughout all project
phases. Schedule Are there any significant constraints or requirements for the
project schedule which would benefit from a modular approach?
The successful design and execution of the rst Is construction constrained by weather windows or periods of
modular LNG plants has prompted a signicant number restricted site access?
of further LNG liquefaction projects to adopt modulariza-
tion strategies. Many of these projects are being planned Safety Are there existing facility operations on the site, unusual site
for construction in Australia where scarce and high cost hazards, site risk contours and regulatory requirements?
What is the expected safety performance for stick-build
labour resources are key drivers for modularization. Other
construction compared to work in module yards?
international LNG projects planned for remote and ex-
treme environment locations are also following modular Local Are there any requirements for local content for the project?
strategies which have become an established alternative Content May reduce or eliminate any potential benefit of modularization.
to traditional stick-build construction techniques.

ADVERT

Chemical Technology October 2011 9

You might also like