TABLE OF CONTENTS
1. PURPOSE
2. SCOPE
3. RESPONSIBILITY
4. MANPOWER
6. METHODS / PROCEDURES
A. TRIAL HOLE
B. EXCAVATION
C. CABLE LAYING
D. BACKFILLING
E. FIXING LIGHT FITTINGS AND TERMINATION WORKS
7. SAFETY PROCEDURES
2
1. PURPOSE
This method statement provides minimum guidelines to carry out trial hole,
excavation, cable laying, fixing of light fitting and termination works in
accordance with drawings
2. SCOPE
This method statement covers the procedure to be followed for trial hole,
excavation works, cable laying, fixing of light fitting and termination works.
3. RESPONSIBILITY
Foreman is responsible for the direct work at site and ensures. That
performance in accordance with the approved drawing.
Project manager will responsible for monitoring the safety aspects work
environment and will ensure the quality of work as per the approved
drawing
4. MANPOWER
3
5. TOOLS AND EQUIPMENTS
Shovel
Pick axe
Winch machine
Excavator
Lifting equipment
Tools of skilled staff
Safety helmet
PPE safety
6. METHODS / PROCEDURES
A. TRIAL HOLES
B. EXCAVATION
After trial holes as per the coordinates marking from main contractor we
will mark the route of excavation with gypsum powder and confirm the
route with main contractor and consultant.
4
After getting confirmation we will start excavation with labors using shovel,
pick axe and small excavators and it will supervised by our foreman as per
EDD standard width of 0.350 meter for one cable/two cable, 0.5 meter for
three cables height of .550 meter.
Proper barrier will be provided to cover the trial holes for safety and proper
warning tape will be wrapped.
Proper PPE will be provided to all working staff in order to confirm the
safety at site
C. CABLE LAYING
D. BACK FILLING
After cable laying complete we will be back filling our layed cable as per
EDD standard for LV cable and caution tape will be provided on the top of
the layed cable 0.25 meter from the floor level
Proper PPE will be provided to all working staff in order to confirm the
safety at site
After back filling we will install the area lighting, garden light, bollard, wall
recessed light using hiab and man power. Skilled technical staff will do the
termination work using technical tools like crimping, glanding.
For installing Area light, garden light we will use Hiab with proper safety
belt and termination work will be carried out by our skilled staff using
5
crimping tool, srew drivers, spanners, cable cleaning knife, insulation tape,
cable cleaning fluids, rachets of different sizes and glanding with monkey
pliers
Proper PPE will be provided to all working staff in order to confirm the
safety at site
7. SAFETY PROCEDURES
All working personnel involved in the activity are trained and experienced