Professional Documents
Culture Documents
Owns
the
“Float?”
to the contractor for the resulting addi- the “float” by the contractor is at his is that the contractor had the right to
tional expense of performance or for own peril since it would belong to the delay those items to the extent of their
additional contract time. Any use of owner. If neither party has exclusive “float:’ and thus that the float was his.
use of the “float:’ then either could The other principle is the rule that
consume all or part of the slack on a a contractor has the right to finish a
first come first served basis without project early, and may recover dam-
responsibility for delay to the other. ages if the owner delays his planned
However, should the contractor own early completion date — even if the
the float, then he can control the time project still meets the contractual com-
and sequencing of work items not on pletion date.
the critical path. Any delay or disrup- An analogy can be drawn between
tion of that activity by the owner could an individual work item in a CPM
entitle the contractor to compensation project schedule and its float time, and
for any additional costs of delaying an entire project, with its total float
performance of that event even though time being the period between the con-
it does not delay completion of the tractor’s early completion date and the
project. contract completion date.
At least one Board of Contract Ap- If a contractor can recover damages
peals has implicitly recognized that for delay of an entire project which still
“float” is a resource best utilized by meets the contract date, he should be
the contractor, stating: able to recover damages for delay of
[Float] allows the manager lati- a work item which still meets its late
tude in the scheduling of non-criti- finish time. In both cases, the owner
cal activities that originate or has taken from the contractor a valu-
terminate at that event, and to able resource—time.
effect trade-offs of resources to As with many construction issues,
shorten or control his project. the ownership of the float is a matter
Joseph E. Bennett Co., 72-1 BCA which can be clearly settled by a
¶9364 (GSBCA 1972) at 43,467 n. 7. specific contract provision. Obviously,
However, the courts have not yet the discretion to use float time is some-
fashioned a satisfactory answer to the thing a contractor should consider bar-
question of whether the contractor or gaining for in the contract. However,
the owner “owns” the float—i.e., has failing a clear allocation of this
the discretion to use up that time. resource or even worse facing a con-
Where the contract is silent, however, tract document allocating float to the
established legal principles suggest that owner, the contractor should consider
the discretion to use the float lies with preparing his schedule to show
the contractor. One such principle minimal float so that he can exercise
comes from the “concurrent delay” greater control over his work activities.
cases.
The general rule there is that a con-
tractor cannot recover delay damages
where he and the owner are jointly This article presents timely ideas
responsible for the delay. In other and information on legal matters of
words, any contractor-caused delay interest to the construction industry.
will bar his claim. However, the courts The text of these articles is necessarily
have refused to apply this rule where generalized, and we recommend that
the contractor caused delays occurred you consult legal counsel as to the legal
on items which did not lie on the implications of any given actual
critical path. The necessary implication circumstances.