You are on page 1of 2

Who

Owns
the
“Float?”

Be Cautious on Who Controls the “Float” Time on Some


of Those Critical Path Jobs

By Peter Spanos, Esq.

I t is becoming commonplace now


for projects to be controlled by a
“critical path” method of scheduling,
tion and then plotted onto a matrix
which establishes which activities are
on the critical path to permit timely
the latest possible finish, less the dura-
tion of the activity itself is called
“float!’
in which all activities are identified and completion of the project. Such items If completion of an activity is
broken down into sequence and dura- must be started and finished on fixed delayed beyond its available “float”
dates or the completion of the project time, then it becomes a critical path
will be delayed. Items which are not item on which further delay shall delay
(Editor’s Note: Peter R. Spanos is on the critical path are assigned a cer- the project completion. Thus, it
a partner in the law firm of Hendrick, tain time period longer than the dura- becomes important who has a right to
Spanos & Phillips and has wide tion actually required for the activity, control this “float?
experience in construction industry during which the work activity may be If the owner retains control of the
law. He has written before for completed without delaying the entire float, then he would have the right to
Construction Dimensions and other project. For such activities, the period delay any work item and consume the
construction related publications.) between the earliest possible start and “float” without incurring any liability
Continued on page 30
26 Construction Dimensions/January 1984
“If completion . . . is delayed beyond its available ‘float’ time,
then it becomes a critical path item on which further delay shall
delay the project completion . . . (and) becomes important who
has a right to control this ‘float’?

to the contractor for the resulting addi- the “float” by the contractor is at his is that the contractor had the right to
tional expense of performance or for own peril since it would belong to the delay those items to the extent of their
additional contract time. Any use of owner. If neither party has exclusive “float:’ and thus that the float was his.
use of the “float:’ then either could The other principle is the rule that
consume all or part of the slack on a a contractor has the right to finish a
first come first served basis without project early, and may recover dam-
responsibility for delay to the other. ages if the owner delays his planned
However, should the contractor own early completion date — even if the
the float, then he can control the time project still meets the contractual com-
and sequencing of work items not on pletion date.
the critical path. Any delay or disrup- An analogy can be drawn between
tion of that activity by the owner could an individual work item in a CPM
entitle the contractor to compensation project schedule and its float time, and
for any additional costs of delaying an entire project, with its total float
performance of that event even though time being the period between the con-
it does not delay completion of the tractor’s early completion date and the
project. contract completion date.
At least one Board of Contract Ap- If a contractor can recover damages
peals has implicitly recognized that for delay of an entire project which still
“float” is a resource best utilized by meets the contract date, he should be
the contractor, stating: able to recover damages for delay of
[Float] allows the manager lati- a work item which still meets its late
tude in the scheduling of non-criti- finish time. In both cases, the owner
cal activities that originate or has taken from the contractor a valu-
terminate at that event, and to able resource—time.
effect trade-offs of resources to As with many construction issues,
shorten or control his project. the ownership of the float is a matter
Joseph E. Bennett Co., 72-1 BCA which can be clearly settled by a
¶9364 (GSBCA 1972) at 43,467 n. 7. specific contract provision. Obviously,
However, the courts have not yet the discretion to use float time is some-
fashioned a satisfactory answer to the thing a contractor should consider bar-
question of whether the contractor or gaining for in the contract. However,
the owner “owns” the float—i.e., has failing a clear allocation of this
the discretion to use up that time. resource or even worse facing a con-
Where the contract is silent, however, tract document allocating float to the
established legal principles suggest that owner, the contractor should consider
the discretion to use the float lies with preparing his schedule to show
the contractor. One such principle minimal float so that he can exercise
comes from the “concurrent delay” greater control over his work activities.
cases.
The general rule there is that a con-
tractor cannot recover delay damages
where he and the owner are jointly This article presents timely ideas
responsible for the delay. In other and information on legal matters of
words, any contractor-caused delay interest to the construction industry.
will bar his claim. However, the courts The text of these articles is necessarily
have refused to apply this rule where generalized, and we recommend that
the contractor caused delays occurred you consult legal counsel as to the legal
on items which did not lie on the implications of any given actual
critical path. The necessary implication circumstances.

30 Construction Dimensions/January 1984

You might also like