Renewable and Sustainable Energy Reviews 52 (2015) 14131423

Contents lists available at ScienceDirect

Renewable and Sustainable Energy Reviews


journal homepage: www.elsevier.com/locate/rser

Hydroelectric plants environmental viability: Strategic environmental


assessment application in Brazil
Andr de Lima Andrade a,c, Marco Aurlio dos Santos b,c,n
a
IBAMA, Brazil
b
CNPq, Brazil
c
Energy Planning Program (COPPE/UFRJ), Brazil

art ic l e i nf o a b s t r a c t

Article history: Brazil has a predominantly renewable origin electricity generation matrix, with hydro generation
Received 14 November 2014 accounting for about 69% of the supply. This paper promotes hydropower projects in Brazil environ-
Received in revised form mental licensing procedure critical assessment, with the aim of identifying and assessing possible
22 May 2015
solutions to enhance the process, especially through Strategic Environmental Assessment (SEA)
Accepted 29 July 2015
application to hydroelectric generation expansion planning processes. It was concluded that impact
assessment has led to signicant environmental improvements, as it is capable of preventing, controlling
Keywords: and compensating signicant and very often irreversible environmental impacts, especially through
Hydropower projects optimization and environmental programs that were not initially foreseen in the EIA inclusion.
Environment
However, as has been expounded throughout this study, there are still several gaps and limitations in the
Brazil
current process, both in power generation expansion planning aspect and project environmental impact
Impact
assessment aspect. SEA application in the planning phase could contribute to facilitate and simplify
hydroelectric plants licensing. Many currently compulsory stages that are carried out after the request
for a prior license, such as the consultation made to involved entities and the area environmental
diagnosis could already be commenced in the planning phase.
& 2015 Elsevier Ltd. All rights reserved.

Contents

1. Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1413
2. Material and methods . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1415
3. Recent advances in hydroelectric plants environmental licensing process. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1415
4. Present environmental licensing model limitations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1417
4.1. EIA carried out in the planning phase low efcacy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1417
4.2. Lack of objective parameters to determine environmental viability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1417
4.3. Limited alternative analysis. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1418
4.4. Difculty to integrate EIA with other environmental instruments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1419
4.5. Presented information sluggishness and low quality. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1419
4.6. Limited public participation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1420
5. SEA application in hydropower energy expansion planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1420
6. Conclusion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1421

Annex 1.
Table with laws and regulations related to Hydroelectric Power Plants in Brazil environmental impact assessment. . . . . . . . . . . . . . . . . . . . . . . . . . 1422
References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1423

n
Corresponding author at: Energy Planning Program COPPE/UFRJ, Centro de Tecnologia, Bloco C, sala 211, Cidade Universitaria, Rio de Janeiro, Brazil.
Tel.: 55 21 39388763.
E-mail addresses: andreandrade02@hotmail.com (A.d.L. Andrade), aurelio@ppe.ufrj.br (M.A. dos Santos).

http://dx.doi.org/10.1016/j.rser.2015.07.152
1364-0321/& 2015 Elsevier Ltd. All rights reserved.
1414 A.d.L. Andrade, M.A. dos Santos / Renewable and Sustainable Energy Reviews 52 (2015) 14131423

1. Introduction to Hydroelectric Power Plants environmental impact assessment in


Brazil were detailed in Table A1, included in Annex A.
Brazil has a predominantly renewable origin electricity genera- In Brazil, EIA is carried out in order to provide elements for the
tion matrix, with hydro generation accounting for about 69% of the environmental licensing instrument, provided by Law no. 6.938/
supply [27]. This source is considered the best option for electric 1981. To put it simply, Brazil's EIA procedure is characterized by
power generation, because it is cheaper [47] emits a lower green- the following elements, which distinguish it from effected pro-
house gases quantity [35] and Santos et al. [40]. cesses in most countries:
However, if on the one hand hydro energy has several advantages,
building hydroelectric plants can cause highly signicant environ- i. It focuses on projects environmental impacts assessment, and
mental impacts, which are very often irreversible [51], such as is not mandatory or regulated in the planning phase.
biodiversity loss and species extinction due to native vegetation and ii. It is effected in 3 (three) stages, and in each of which it is
planted forest areas ooding, habitats destruction, farmland loss, the necessary to obtain specic licenses: (i) prior license, when the
need to move a large number of people, interference in indigenous project environmental viability is discussed, as detailed below;
territories or traditional populations, alterations in the water regime (ii) installation license, when the work is authorized to start;
and water bodies morphology, sh fauna impact, etc. and (iii) operating license, when the enterprise is authorized to
The most signicant impacts occur during reservoir construc- operate, which, in the case of hydroelectric plants, includes
tion, but long-term impacts, especially on aquatic ecosystems and lling the reservoir and power generation start-up (Law no.
on rivers water regime should also be considered [23]. 6.938/1981).
An important aspect to be observed is that negative environ- iii. In the 1st stage, or prior licensing stage, the project is assessed
mental impacts resulting from a hydroelectric project are even in terms of location and concept, based on EIR (Environmental
more substantial if the reservoir is situated in environmentally Impact Assessment Report) analysis. If the environmental body
signicant or sensitive areas [22]. certies the project environmental viability, the Prior License is
Thus, the fact that hydroelectric generation expansion in Brazil issued and requirements to be fullled in the process next
will be highly concentrated (86% in terms of installed capacity) in phases are established (CONAMA Resolution no. 237/97).
the Amazon region makes it even more relevant, as it is considered iv. The assessment should cover not only natural environment,
a very sensitive area from the ecological viewpoint, representing but also anthropic environment. Cumulative impacts should be
the planet's largest biodiversity reserve [19]. assessed, as well as alternative technologies and project loca-
The ten-year Energy Plan [26] provides for new hydroelectric tions, comparing them to the hypothesis that the project is not
plants installation until 2022, in addition to the plants that are carried out.
being already built. Fig. 1 shows the geographical localization of v. The process is conducted by the environmental institution
planed hydroelectric plants until 2022. (federal or state) that is responsible for taking decisions
It is fundamental, therefore, that activities related to new regarding licenses issuing. The federal agency (IBAMA) is
hydroelectric plants planning and construction should take responsible for hydroelectric processes located in more than
place within a broad and robust process of Environmental Impact one state, in protected areas by the union, on indigenous lands
Assessment (EIA). The most important laws and regulations related in the Brazilian border, and in plants with capacity exceeding

Fig. 1. Planned Hydroelectric Power Plants. .


A.d.L. Andrade, M.A. dos Santos / Renewable and Sustainable Energy Reviews 52 (2015) 14131423 1415

300 MW (Complementary Law no. 140/2011 and Federal a) The obligation to pay environmental compensation in order to
Decree no. 8.437/2015). The remaining dams are licensed by support preservation units setting up and maintenance (Law
states. 9985/2000) and to offset impacts that cannot be minimized,
vi. It provides for the participation of affected communities and caused by the installation of projects with a signicant envir-
other institutions involved in indigenous people and quilom- onmental impact.
bola populations protection, the National Institute of Historic b) Entrepreneur's obligation to acquire, to protect and to very
and Artistic Heritage, and preserved areas. often reforest permanent preservation areas created around
reservoirs (Federal Provisional Measure 2166/2001).
According to this context, this study sought to evaluate the c) The Energy Research Company (Empresa de Pesquisa Energtica
present hydroelectric plants impact assessment model, focusing EPE) creation, under Law 10847/2004, which determined the
on the procedure prior licensing stage adopted by the Brazilian company responsibility to carry out studies on electric power
Federal Environmental Agency (IBAMA), with the aim of identify- plants social impacts, technical-economic and socio-environ-
ing and assessing possible solutions to enhance the process, mental viability; to draw up necessary studies for electric
especially the possibility of Strategic Environment Assessment power generation expansion plans development (10-year and
(SEA) application to the planning process, for hydroelectric gen- national energy plans); and to develop studies to determine
eration expansion in Brazil. river basins optimal use (Hydroelectric Inventories and IEAs, or
Integrated Environmental Assessments).
d) The need, from 2004 on, to obtain a prior license for holding a
2. Material and methods power auction (Decree no. 5.163/2004). According to the new
model, the Brazilian government will be only able to hold a
The environmental licensing procedure critical evaluation was hydroelectric plant concession auction after a prior license is
carried out by means of a bibliographical review of already obtained.
published studies in the area: ROHDE [33]; Bursztyn et al. [9]; e) The obligation to carry out a prior socioeconomic register of the
Oliveira and Bursztyn [30]; Glasson and Salvador [16]; MPF [29]; population that will be affected (Federal Decree no. 7.342/
TCU [45]; Banco Mundial [6]; Unger [49]; Acende Brasil [2]; Abema 2010).
[1]; and CNI [12]; and also by reviewing 24 (twenty-four)1 out of f) The regulation of the authority for environmental licensing
all the 29 (twenty-nine) federal environmental licensing processes (Complementary Law no. 140/2011 and Federal Decree no.
for hydroelectric plants that had been through the prior licensing 8.437/2015).
phase.2 g) The regulation of the way in which federal public administra-
When reviewing hydroelectric plants federal environmental tion bodies and entities involved in environmental licensing
licensing processes, this study looked for: the time length it took should operate (Inter-ministry Administrative Order no. 60/
for the processes to be carried out, the frequency with which 2015).
complementary information was requested, which complemen-
tary information items were usually requested, the most impor- In this period, several advances have also occurred in the
tant criteria adopted in the EIA when discussing viability, the most federal environmental licensing process. Currently, pre-implem-
signicant aspects or impacts taken into account on IBAMA entation actions, aimed to prepare the region that will be affected
viability opinion, the reasons to declare a project environme- by large hydroelectric plants installation social impacts, may be
ntally unviable, and environmental improvements or signicant executed.
improvements in the project resulting from impact assessment A signicant improvement has been observed in impact pre-
process. diction models, such as reservoir water quality modeling studies,
what has already helped environmental institutions in determin-
ing corresponding mitigation measures. Other important advances
3. Recent advances in hydroelectric plants environmental resulted from sh transfer systems (stairs, elevators and channels)
licensing process installation in new projects and dening clear rules for carrying
out expropriations and people and communities that are directly
Up to the seventies, Brazilian electric power concessionaires affected relocation.
concerns regarding environmental impacts were practically lim- There has also been a strong trend towards building run-of-
ited to the relocation of the infrastructure that would be ooded, the-river plants, using ever-smaller reservoirs with a good ratio
new access roads construction and towns' relocation [34]. In 1972, between installed capacity and the area to be ooded. If, on the
the rst environmental assessment was carried out for Sobradinho one hand, such plants generate lower environmental impacts, on
dam (1050 MW) in Northeastern Brazil, due to a demand from the the other hand they lead to a lower energy storage capacity, which
World Bank [18]. is necessary for critical drought periods, and to a lower oodwater
Since then, hydroelectric plants construction impact assess- storage capacity in ooding periods [41].
ment has greatly evolved, with the creation of various prov- At present, platform style plants construction in the Amazon
isions and laws that enhanced dams planning and building region is being studied. This proposal means a signicant change
process. The main identied advances regarding planning and from the concept of hydroelectric plants as a factor for affected
environmental viability assessment, starting in the last decade, are regions development to the concept of such plants as a factor for
listed below: preserving areas that are considered to be of ecological interest.
Inspired by oil platforms, this model foresees plant construction
1
In 5 (ve) processes the information was not available for research. almost exclusively based on provisional structures for building
2
It is important to explain that the great majority of hydroelectric plants that work support, with workers taking turns in shifts. When the
IBAMA currently grants licenses for and that are operating have not gone through construction work is concluded, the building site is expected to be
the prior environmental licensing process, since they started being built before the removed and the area to be reforested, leaving the plant to be
National Policy for the Environment (Law no. 6938/1981) was adopted, and before
the authority for the federal environmental licensing process was regulated by
operated almost entirely by remote means [32].
means of CONAMA Resolution no. 237/97. Currently, there are 93 (ninety-three) There has also been an increase in transparency during the period.
processes for hydroelectric plants undergoing federal licensing. At present, all technical opinions and environmental licenses issued by
1416 A.d.L. Andrade, M.A. dos Santos / Renewable and Sustainable Energy Reviews 52 (2015) 14131423

the federal body may be seen in its internet page, and environmental about its environmental viability, and strong criticism from the
studies return or license applications refusal are made public, what Brazilian and world communities led to a very signicant improve-
makes it easier for the nation to follow what is being done. ment in the project, and resulted in several environmental improve-
As pointed out by Kumar et al. [22] and Snchez and Morrison- ments, among which the following will be mentioned: alteration in
Saunders [37], another aspect that has helped making the process the reservoir maximum elevation and conguration, with a reduction
more effective is the experience acquired by entrepreneurs, con- in the ooded area from 1.225 km2 to 516 km2 (excluding Indian
sulting companies and environmental institutions in already territories from the area to be ooded); pre-implementation actions
installed enterprises environmental licensing processes. This being taken in order to adapt the infrastructure; detour channel
experience has been reected in improvements when drawing construction, in order to enable sh migration; some of the reservoir
up environmental studies, holding public consultations, carrying and channel inlets reshaping, in order to reduce eutrophication risk;
out mitigating measures, and establishing environmental licensing and an ecological hydrograph adoption, with a 8.000 m3/s ood ow
norms and procedures. release in the reduced ow stretch, which is sufcient to achieve
These advances and learning were the result of efforts on the hydrological pulses maintenance, rock shoals total ooding and
part of society different sectors, the federal government and also alluvial forests partial ooding [21]. Fig. 3 enables to compare the
other licensing bodies, which, over the years, have greatly original project with the one that was approved.
improved environmental impacts assessment and control tools When analyzing the processes that were evaluated for environ-
(Fig. 2). mental viability by the federal licensing body, it was found that in
In the case of Belo Monte Hydroelectric Plant, with planned 85% of hydroelectric plant processes in which the prior license was
installation capacity of 11.233 MW, for example, decades of discussion granted, signicant environmental improvements were identied

Fig. 2. Flow Chart of the procedure to assess hydroelectric projects environment viability. .

Fig. 3. Belo Monte Hydroelectric Plant original and approved project. .


A.d.L. Andrade, M.A. dos Santos / Renewable and Sustainable Energy Reviews 52 (2015) 14131423 1417

9
8
8

Number of Processes
7
6 6
6
5 5
5
4
3
2
2
1
0
Maximum Anticipatory Fishermen Instream Flow Fish Negotiation
reservoir level actions or support increase populations forums
change, in programs program restocking establishment
order to reduce inclusion, in program with the
the flooded order to community
area support local
infrastructure
Fig. 4. Environmental improvements identied in hydroelectric plants licensing processes. .

due to environmental viability discussion. Such improvements enterprises installation, lack of transparency and lack of a robust
resulted in project alterations or in the inclusion of mitigating evaluation of alternatives for hydroelectricity expansion in Brazil.
programs or measures that were not initially present. The most There are also conicts in hydroelectric plants planning and
frequently identied environmental improvements are shown in construction vis--vis priority areas for biodiversity preservation,
Fig. 4. preservation units and indigenous territories. In the carried out
Environmental improvements do not exclusively occur due to Ten-year Plans review, several cases were found in which enter-
environmental bodies participation, but are very often proposed in prises considered suitable in the planning phase have not obtained
response to pressure exerted by society in general (local commu- a prior license and had to be abandoned in project phase.
nities, NGOs and Public Prosecution Service). In many cases, there As recommended by the World Commission of Dams WCD
were project alterations even before the process was led at the [51], the Brazilian government should identify river basins with a
environmental body or as a consequence of an initial refusal by the vocation and aptitude for hydroelectric potential development,
federal licensing body to issue the respective license. and rivers and basins that should be protected.
All these factors cause new projects to be increasingly in tune
with environmental issues. However, despite all the advances
4.2. Lack of objective parameters to determine environmental
listed above, even if all the mitigating and compensating measures
viability
currently envisaged are introduced, the environmental impact
resulting from these enterprises installation and operation is still
There is a great deal of discussion about environmental
very high, what signicantly increases the planning process
viability concept in Brazil. From the legal viewpoint, at present, a
complexity and makes it more difcult to arrive at a decision as
hydroelectric plant cannot be built if
to whether or not a project is environmentally viable.
 it directly affects indigenous territories that have been
4. Present environmental licensing model limitations marked out, going against Art. 231 of the Federal Constitution,
until the respective regulations are issued e.g., Marab
Next, the main limitations identied in hydroelectric plant Hydropower Plant;
licensing processes diagnosis that included environmental viabi-
 it directly affects Full Protection Preservation Units, going
lity discussion are presented. The aim was to assess the way these against Law 9985/2000 e.g., Itumirim Hydro Power Plant3;
limitations are reected, from a practical viewpoint, in the licen-
 it causes irreversible impacts to highest importance caves;
sing processes, and how strategic environmental assessment could
 it causes the elimination of primary vegetation, or vegetation in
make a positive contribution to overcome or minimize the advanced and medium recovery stages, of the Atlantic Rain-
deciencies found. forest biome, with characteristics detailed in Art. 11 of Law
11428/2006 Atlantic Rainforest Law;
 it causes irreversible losses to a historical, cultural or scenic
4.1. EIA carried out in the planning phase low efcacy
nature beauty protected heritage;
At present, it is possible to say that the environmental variable
is considered in some way in new hydroelectric projects planning Environmental viability analysis should involve evaluating the
process initial stages, as the National Energy Plans (PNEs), the Ten- effects caused by anthropic actions, in order to verify their
year Energy Plans (PDEEs), the River Basins Hydroelectric Inven- compatibility with the environment capacity to assimilate such
tories, and the River Basins Integrated Environmental Analyzes effects without detriment to environmental system productivity,
(IEAs) are drawn up. However, despite the positive aspects, several that is, to assess whether the environment is able to withstand the
gaps and limitations prevent these studies from decisively con-
tributing to EIA carried out in the project phase [50]. 3
In some cases, the Brazilian government has altered protection preservation
Some limitations mentioned above are due to the lack of unit borders, in an attempt to make hydroelectric projects viable (e.g., So Luiz do
participation and integration of the different agents involved in Tapajs and Tabajara hydroelectric plants).
1418 A.d.L. Andrade, M.A. dos Santos / Renewable and Sustainable Energy Reviews 52 (2015) 14131423

Unidentified 8

Pressure on the infrastructure of the region 4

Impact on indigenous population 3

Low relative installed power / flooded area 3


Damage to migratory fish and affectation of marginal
9
lagoons
Affectation of protected areas or priority areas for
3
biodiversity conservation
Impact on fishing activity 2

Flooding of fertile lands 2

Concern about future water quality 3

Loss of wildlife habitats 3


Reduced flow instream flow passage insufficient to allow
4
maintenance of aquatic ecosystems
Low lifetime of the project 2

Increase in the risk of species extinction 3

Deforestation 2

0 1 2 3 4 5 6 7 8 9 10
Number of Processes

Fig. 5. Most signicant negative impacts types considered in IBAMA's technical opinions. .

impact caused by the activity [28]. Along the same lines, in order species extinction) and when there are uncertainties related to
to reach a conclusion about environmental viability, it is necessary impacts foreseeability and magnitude, which occurs especially in
to check whether the foreseen impact from the actions in a certain the case of biotic medium impacts [17].
plant would result in thresholds stipulated in the legislation or in In diagnosing hydroelectric plants licensing processes where
established quality standards breach. environmental viability was discussed, it was found, in practice,
This procedure is well applied in the case of impacts expected to that there is lack of objective criteria both in the EIA and in the
occur mostly on the physical medium. In such cases, the task is made licensing body technical opinion to determine an enterprise
easier by established quality standards (quality of air, water, soil, etc.) environmental viability and to evaluate EIA quality.
existence, and when impacts are easy to foresee in several cases they In none of the cases it was found that a quantitative balance
can be forecast and measured using mathematical models. between positive and negative impacts had been carried out, nor a
Another way to assess environmental viability is through a cost/benet evaluation, which is not demanded by the federal
comparison between positive and negative environmental impa- environmental body either.
cts. This view is better applied in cases of complex activities that In the Terms of Reference,4 it is normally required that
affect not only the physical medium, but also the biotic and the conclusion regarding environmental viability should be
socioeconomic media (as in hydroelectric plants). In this case, it based on a comparative evaluation between future scenarios
is necessary to nd a way to compare or to add up the impacts, in for the region where the project would be carried out cons-
order to conclude whether gains exceed environmental costs. idering hypotheses of the project being or not being imple-
Several techniques have been developed to work out this mented.
balance: intuitive methods, weighted matrixes and multi-criteria Therefore, the nal decision, even if based on information and
analyses. However, despite all this evolution, all techniques are prognoses evaluated in the EIA, is qualitative, subjective and
invariably based on subjective assessments [7] and depend on a discretionary. A method including objective criteria to determine
value judgment [39]. At some point, it is necessary for one or more a project environmental viability has yet to be created.
participants to attribute weights to the impacts, comparing them In the analyzed EIRs, emphasis was given to the possibility of
to each other; and as a result of the same impact assessment, minimizing negative impacts forecast by adopting environmental
different conclusions may be reached about impacts importance, programs and mitigating measures, followed by the possibility of
and consequently, about the project environmental viability. generating income and boosting the region's economy.
It is also necessary to compare impacts with totally distinct
characteristics and scopes: positive and negative; short, medium
and long-term; reversible or irreversible; that may or may not be 4.3. Limited alternative analysis
mitigated. This makes it very difcult to take decisions regarding a
project development. Fig. 5 depicts the most important negative Alternative technologies and locations for enterprises evalua-
impacts considered by the technical licensing body to determine tion should be included in EIRs. This is a fundamental element in
hydroelectric dams' environmental viability. drawing up a creative and proactive impact assessment that is
As it can be seen, impacts have very different nature. Therefore, relevant for decision-making [52].
it is difcult to compare negative impacts, like the migratory sh As identied in this study, there are several examples where
damaging possibility and impacts on indigenous people, with discussing alternatives enabled alterations and improvements in
positive impacts, like employments raise and income generation. the project (alterations in ooding elevation, project congurations,
The decision regarding environmental viability is even more
complex when the activity affects assets with existence values 4
Term of Reference is a document issued by the environmental agency that
(e.g., cultural assets), when there are ethical issues involved (e.g., details all EIR requirements and scope.
A.d.L. Andrade, M.A. dos Santos / Renewable and Sustainable Energy Reviews 52 (2015) 14131423 1419

building site location, etc.). However, these changes are limited to The integration between project planning, soil use and occupa-
one project context. Alternative analyzes are limited to the river tion policies is also very weak. People migration to areas that are
basin and are partial, because each company is interested in making affected by projects can lead to many social hazards if not well
its own project viable. managed. Another example refers to the conict generated by
In a survey carried out by the Federal Public Prosecution large hydroelectric plants installation in regions that are tradi-
Service(MPU, 2004), where dozens of EIRs were analyzed, no tionally inhabited by indigenous peoples whose land has not yet
situation was found in which the team responsible for drawing been marked out. At present, this conict is making several plants
up the EIR had concluded that the alternative proposed by the installation, such as So Manuel (700 MW), Teles Pires (1820 MW)
entrepreneur was not the most suitable. and So Luiz do Tapajs (8040 MW) unfeasible or difcult. In order
According to Sanches [38,39], it is not realistic to demand the to reduce such conicts, prior action by the government would be
environmental impact study to consider other alternatives with a needed, marking out Indian territories and improving the existing
similar detail degree. Normally, EIAs are carried out when the tribes' social structure.
engineering project is sufciently outlined (which is usually a Huge projects installation in regions without an adequate social
basic project) and when economic evaluations already indicate its structure requires pre-implementation actions execution. How-
viability. This means that funds have already been spent in ever, in order to adjust the timing between pre-implementation
preparing the project and in its economic evaluation, so going measures execution and the beginning of the construction work, it
back to a strategic condition of analyzing alternatives means is necessary to dene these actions as early as the planning phase,
questioning decisions that have already been taken. in order to enable the government to prepare the region.
Broader alternatives are not compared within an EIA or a Technical In the Belo Monte process, for example, there was a great impact
and Economic Feasibility Study (TEFS) as to identify the most attractive on the region directly affected by the dam caused by the fact that
ones from the environmental and economic viewpoint. It is not foreseen pre-implementation measures (construction of schools,
possible to evaluate, for example, whether it is more attractive, from water and sewerage systems, etc.), which were to be executed before
the environmental and economic viewpoint, to build hydroelectric the construction work began, were not carried out [20].
plants on Tapajs River or on Tocantins River. It is also hard to establish effective mitigating actions that can
According to Brazil's federal water management body, ANA [3], be carried out by a specic entrepreneur, because such measures
hydroelectric generation planning in sensitive areas requires two are long-termed and broader or more strategic in nature, and are
additional analysis levels: the rst, considering a river basin as the normally dependent on the State or are under its responsibility. An
analysis unit, and comparing different uses (electricity generation example is sewage treatment to prevent a future dam water
or water supply); and the second, analyzing all the proposed eutrophication.
projects in the basin in relation to the other basins, and the In the opinion of Abema [1], without other instruments provided in
possible trade-offs between basins, considering each one's poten- the Environmental Policy support, licensing loses its purpose as an
tial and vulnerabilities. instrument to measure impacts, increasingly becoming a bureaucratic
However, alternatives evaluation within an EIA occurs after the practice, in detriment to environment protection. Higher integration
decision to build was taken by the institutions that execute the energy between economic and social development sectorial policies and
policy. Therefore, the environmental damage caused by hydroelectric environmental policy is necessary [48].
plants construction is often diagnosed when it is no longer possible to
signicantly alter the paths taken by the country's energy policy. In 4.5. Presented information sluggishness and low quality
the project phase, it is even more difcult to alter decisions related to
projects linked to policies or plans that were formerly approved A recurrent criticism made about hydroelectric plants environ-
without the necessary analyses. mental licensing process is how long it takes. In the environmental
It is therefore necessary for alternatives analysis to occur also in licensing processes diagnosis in which environmental viability was
the planning phase. Without alternatives evaluation in the plan- discussed, it was found that the time taken to complete the
ning phase, the environmental licensing processes established in processes in the federal licensing body, from the initial opening
EIAs are based on the principle of adapting nature preservation to request to the decision regarding the project's viability, was on
the existing economic logic [8], and thus aim to reconcile power average of 5 years and 4 months, divided according to Fig. 6.
plants installation with the local environment, what is not always Many factors contribute to this delay. It can be partly justied by
possible. the process democratic nature, which should provide for the public
and all other involved entities participation, as well as the information
4.4. Difculty to integrate EIA with other environmental instruments complexity that has to be gathered and analyzed in the EIA, which
requires, in the case of hydroelectric plants, carrying out detailed
A large project installation, especially in regions with poor seasonal studies regarding the local environment conditions.
infrastructure, requires other environmental instruments (envir- The federal licensing body and other entities involved in
onmental zoning, protected spaces creation, land ownership the process decient structure, and the absence of a stand-
legalization, legal reserves, water usage grants, etc.) to be also ard Reference Term for drawing up the EIRs highly increase the
effective, as they are complementary. This allows environmental response delay. Anyway, in the carried out processes diagnosis,
impacts to be absorbed and mitigated. However, the current model the main factor responsible for the process sluggishness was identied
makes it difcult for the environmental licensing instrument to be as the need for EIR and complementary information resubmission.
integrated with other instruments provided by the legislation. In 67% of the cases (16 out of 24 projects), the licensing body
Many of these instruments require long-term actions on the part of returned the EIR due to absence of the minimum content set out in
the government in order to become effective. However, at present, the the Reference Terms. Some cases were found in which as many as
dialog among the various ministries occurs at a later phase than four EIR versions had been submitted, which contributed to the
planning, when conicts have already been created, what makes the time required for EIR acceptance being of months to on average
process of integrating development policies and plans with environ- 2 years and 9 months.
mental preservation policy even more difcult. Because of this lack of It is worth pointing out that it is determined, under the licensing
dialogue, national parks and indigenous reserves have been created in body's internal regulations, that public hearings can be held only after
planned areas to be affected by reservoirs. EIR acceptance. After public participation, the EIR is sent to other
1420 A.d.L. Andrade, M.A. dos Santos / Renewable and Sustainable Energy Reviews 52 (2015) 14131423

Reference Term definition 10

EIR delivery after Reference Term definition 6

Time length for IBAMA to accept EIR 33

Prior License application final answer after EIR and after


14
IBAMA acceptance

Prior license application final answer time length 64

0 10 20 30 40 50 60 70

Fig. 6. Average term to complete processes.

involved institutions involved for analysis, and then the period of people who are affected, as well as the participation
commences for the technical team to evaluate the study content of entities involved in the licensing process that defend the interests
and give their response regarding the presented information. Even so, of indigenous populations, protected areas, African slaves
even after environmental studies acceptance, in 79% of the cases (19 descendants, etc.
out of 24 projects), complementary information was requested, what Other participation forms frequently take place during the period
contributes to the delay in the entity's nal position announcement when the EIR itself is drawn up, when the participative diagnoses are
regarding the enterprise's prior license issuing. carried out, when environmental studies Reference Terms are drafted,
According to this research, it takes, on average, 5 years and and throughout the process, especially with the intent of providing
4 months to the federal agency to give the nal answer to the prior elements for environmental programs execution.
license request.5 Participation in public hearings aims at showing to the inter-
In the processes in which environmental viability was dis- ested parties the report content, clarifying questions and gathering
cussed in the licensing institution diagnosis, it was found that criticism, as well as suggestions.
certain information types are very often requested, among which However, public participation can be considered limited, given that
the need for information resubmission related to water quality it takes place mostly in only one process phase, and it is based on a
diagnosis and prognosis, sh species impacts prognosis, and fauna format that does not allow much freedom to alter important decisions
and ora inventory, can be highlighted. This is depicted in Fig. 7. that have already been made. Little or no participation takes place in
In only one case (Santo Antnio do Jari Hydropower Plant the initial planning phases, when the inventory is made, or during the
373 MW) was the Prior License issued without the need of EIR return National or Ten-year Energy Plans drawing up, when energy genera-
and additional information submission. In this case, the total time tion several alternatives are discussed in a broad context [5].
taken for carrying out the process in the Prior License phase was of In general, public consultation occurs at a stage that is too late to
2 years and 1 month. The Prior License was issued four months after allow it to inuence best alternatives selection [44], and it is much
EIR approval. more a mean of informing the community than of considering the
With the aid of well-constructed diagnoses, it is possible to opinions of the various interest groups in the decision-making process.
predict the effects of actions resulting from these projects plan- According to Rovere [36], society as a whole should debate the
ning, installation and operation. The diagnosis and prognosis are alternatives for the hydroelectric sector's global planning, this is,
very often non-conclusive, so the licensing institution frequently however, a closed planning process. As CANTER [10] reminded, it is
resorts to the precautionary principle as a justication for an not enough for people to be heard; it is necessary to incorporate the
environmental license request rejection, or the need for additional opinions gathered from them into the decision-making process.
information to complement the study. IBAMA reasons to reject or
suspend the Prior License were listed in Table A2 (Annex A).
5. SEA application in hydropower energy expansion planning
4.6. Limited public participation
Recognized limitations in the present Brazilian environmental
licensing process caused several institutions and researchers to suggest
Public participation is a fundamental requirement in an Envir-
that the Strategic Environmental Assessment (SEA) should be gener-
onmental Impact Assessment process. It is one of the most
ally applied in Brazil to assess the impacts of Programs, Plans and
important environmental principles, according to which citizens
Policies TCU [45], Teixeira [46], Ayres [5], Unger [49] and Assis et al.
should participate in the proceedings and in the environmental
[4]; or more specically, to provide information for planning hydro-
decisions, not only because they are directly affected by them, but
electricity expansion in Brazil Pires [31], MMA [24], MMA [25],
also because of the commitment that everyone should have to the
Burian [8], and Westin [50].
environment defense and protection [43].
In global terms, SEA application is also seen as an alternative to
In the project phase, public participation occurs in a regulated
promote higher sustainability in policies related to the energy
manner, by means of Public Hearings, which provide the participation
sector [15]. In Portugal, for example, the SEA was employed in
2007 in the National Program for Dams, with a High Hydroelectric
5
Time necessary to elaborate the EIR is included in this period. Potential (PNBEPH). Using this tool, energy, socioeconomic and
A.d.L. Andrade, M.A. dos Santos / Renewable and Sustainable Energy Reviews 52 (2015) 14131423 1421

16 15

NUMBER OF PROCESSES
14

12

10
8
8 7 7

6 5 5 5
4 4
4 3 3
2
2

Fig. 7. Usually requested complementation.

environmental criteria were considered in order to select 10 out of hydroelectric expansion planning process is carried out in a
a universe of 25 dams under study, so as to achieve the previously transparent manner, with the participation of the various inter-
chosen goal of increasing the country's potential to 7.000 MW by ested agents, including environmental entities.
2020 [11]. Similar study was conducted in Vietnam [42]. Strong resistance can be observed on the part of the productive
In recent years, strategic environmental assessment implementa- sector against a SEA formal execution for the National and Ten-year
tion voluntary initiatives have multiplied in Brazil. These initiatives Energy Plans; there is the fear that the time required for obtaining
have not occurred to meet any legal requirement, but in many cases licenses for hydroelectric plants would increase. On the contrary, it is
due to the difculties encountered in large projects environmental believed that the fact that the impact assessment tool is carried out in
licensing (Sanches [38,39]). As an example, in 2004, Madeira River a regulated manner only in the project phase makes the process more
Complex hydropower plants SEA was held to enable the environ- sluggish.
mental licensing of Santo Antnio (3.150 MW) and Jirau (3.450 MW) It is suggested that SEA should be applied in the process of
hydroelectric power stations. formulating the National Energy Plan (PNE 2050), which is
In this study opinion, a SEA with the purpose of improving the currently in the initial drafting phase, and whose purpose is to
hydropower generation expansion process could: (a) promote underpin the formulation of public policies and the energy supply
various public entities and other stakeholders integration; (b) expansion national strategy [13,14]. The SEA could be applied at
discuss strategic alternatives for the expansion of the country's least in the chapter related to hydroelectric generation, which
hydroelectric generation; (c) identify river basins to be protected does not exclude the possibility of applying this tool to the other
or to be prioritized for projects installation; (d) identify conicts energy sources.
that may arise in the event of hydroelectric plants construction; (e) As has already been discussed and detailed in this paper, SEA
establish guidelines and actions that can facilitate the project application in the planning phase could contribute to facilitate and
licensing process; (f) identify pre-implementation actions that are simplify hydroelectric plants licensing. Many currently compulsory
needed for the projects installation; (g) integrate the impact stages that are carried out after the request for a prior license, such
assessment tool with other instruments; and (h) increase the as the consultation made to the entities involved and the environ-
sector's decision-making process transparency. mental diagnosis of the area, could already be commenced in the
In this respect, carrying out an SEA in the planning phase for power planning phase.
generation capacity expansion would be important in order to include
the various points of view in the decision-making process. It would
not be possible, however, to effectively enable the participation of 6. Conclusion
people and communities that could be directly affected by hydro-
electric plants installation. Hence, public participation in the planning Brazil's hydroelectric plants environmental viability assessment
phase should not be a substitute for the participation of local agents, represents a formidable challenge, and overcoming this challenge is
which takes place during the project phase. fundamental to the pursuit of more sustainable development in the
SEA application would not exclude the subjectivity and discre- related ght against global warming. Though imperfect and sluggish,
tionary aspect of the decision-making process relative to hydro- it is considered that impacts assessment has led to signicant
electric plants environmental viability. Even so, this tool would environmental gains, as it is able to prevent, control and compensate
contribute to the process by causing the plants that are considered signicant and very often irreversible environmental impacts,
most appropriate in the planning phase to advance to the project especially through projects improvement and the inclusion of envir-
EIA phase. This projects directing would only be effective if the onmental programs that are not initially foreseen in the EIA.
1422 A.d.L. Andrade, M.A. dos Santos / Renewable and Sustainable Energy Reviews 52 (2015) 14131423

However, as has been expounded throughout this paper, there strategy for the expansion of the country's hydro energy genera-
are still several gaps and limitations in the current process, both in tion. It would reduce the number of conicts and bring more
the aspect of power generation expansion planning, as in the speed, credibility and efciency to hydroelectric plants environ-
aspect of project environmental impact assessment. These gaps mental viability assessment phase.
and limitations make hydroelectric plants environmental viability
assessment processes even more difcult; and their complexity
tends to increase with the prospects of increasing exploitation of
the Amazon Region's hydroelectric potential. Annex 1. Table with laws and regulations related to
It is believed that a SEA applied in the process of formulating Hydroelectric Power Plants in Brazil environmental impact
the National Energy Plan (PNE 2050) could be useful for the assessment
incorporation of the environmental variable, in a systematic,
transparent and democratic manner, in the selection of the best See Annex Tables A1 and A2.

Table A1
Main laws and regulations related to Hydroelectric Power Plants in Brazil environmental impact assessment.

Main laws and regulations Objectives

Law no. 6.938/1981 Creates and denes elements for the environmental licensing instrument.
CONAMA Resolution no. 01/86 Details the characteristics and dene the requirements of the Environmental Impact Assessment Report EIR.
CONAMA Resolution no. 237/97 Details the characteristics of the environmental licensing instrument.
Law no. 9985/2000 Creates and denes projects with the obligation to pay environmental compensation, in order to support the setting up and
maintenance of preservation units.
Law no. 10847/2004 Denes hydroelectric power plants power auction procedure.
IBAMAs Administrative Order no. Details the federal environmental licensing process implemented by IBAMA
184/2008
Federal Decree no. 7.342/2010 Denes the obligation to carry out a prior socioeconomic register of the population that will be affected by Hydroelectric Power
Plants
Complementary Law no. 140/2011 Denes the main characteristics of projects that should be licensed by the federal agency or state agencies
Federal Decree no. 8.437/2015 Details activities and projects that should be licensed by the federal agency
Inter-ministry Administrative Order Denes the participation of institutions involved in the protection of indigenous people and quilombola populations, the national
no. 60/2015 historical and artistic heritage, and preserved areas in the federal licensing process

Table A2
Power plants with suspended or refused Prior License application.

Hydroelectric power plant Reasons for Prior License suspension or rejection

Couto Magalhes (150 MW) Reduced ow instream ow passage does not allow aquatic ecosystems maintenance.
Araguaia River
Ipueiras (460 MW) Tocantins Flooding of large areas of cerrado with signicant importance, ooding of marginal lagoons, unfavorable power/ooded area ratio,
River intention of establishing a protected area in the area to be ooded.
Itumirim (60 MW) Corrente Direct interference in Emas National Park.
River
Marab (2160 MW) Tocantins Flooding of indigenous land.
River
Pai Quer (292 MW) Pelotas Possibility of endemic species extinction, interference in the priority area for biodiversity. Conservation, intention of establishing a
River protected area in the area to be ooded, interference in archeological heritage area (Passo de Santa Vitria).
Santa Isabel (1087 MW) Araguaia Potential impact in a Conservation rea Serra dos Martirios State Park, interference in caves, areas of endemism and scenery of the
River Araguaia Guerrilla.
Serra Quebrada (1328 MW) Flooding of indigenous land.
Tocantins River
Tijuco Alto (144 MW) Ribeira Reason for the initial rejection: Interference in caves, quilombola communities, Atlantic Forest remnants, risk of species extinction,
River poor diagnosis of vegetation to be removed, sh populations to be affected. Possibility of lead contamination. Lack of integrated
impacts assessment.
Tupiratins (620 MW) Tocantis Affects indigenous land.
River
Uruui (134 MW) Parnaiba River Unfavorable installed capacity/ooded area ratio. Need for removal of riparian populations and ooding of large cerrado fragments
with importance to local wildlife. Interference area of great importance for Ichthyofauna breeding (ooding of marginal lagoons).
A.d.L. Andrade, M.A. dos Santos / Renewable and Sustainable Energy Reviews 52 (2015) 14131423 1423

References [27] MME/EPE. Minuta do Plano Decenal de Expanso de Energia 2023/Ministrio


de Minas e Energia. Empresa de Pesquisa. Available at http://www.epe.gov.
br; 2014.
[1] Abema. Novas propostas para o licenciamento ambiental no Brasil/Associao [28] Montano Marcelo, Ranieri Victor. Anlise de Viabilidade Ambiental in Engen-
Brasileira de Entidades Estaduais de Meio Ambiente; organizao Jos Carlos haria Ambiental Conceitos, Tecnologia e Gesto. Elsevier; 2013 p. 741765.
Carvalho Braslia. Available at www.abema.org.br; 2013. [29] MPF. Decincia em estudo de impacto ambiental. Sntese de uma experi-
[2] Acende Brasil. Aprimoramentos para o setor eltrico: propostas aos candidatos ncia. Ministrio Pblico Federal. 4 Cmara de Superviso e Coordenao.
(Mandato 20152018). Instituto Acende Brasil. Available at http://www. Braslia: Escola Superior do Ministrio Pblico da Unio; 2004.
acendebrasil.com.br/media/estudos/2014_WhitePaperAcendeBrasil_13_Pro [30] Oliveira, Bursztyn. Avaliao de impacto ambiental de polticas pblicas. Rev
postas_aos_Candidatos_Rev1.pdf; 2014. Int Desenvolv Local 2001(3):4556.
[3] ANA, 2010. Plano Estratgico de Recursos Hdricos da Bacia Amaznica [31] Pires. Planejamento ambiental da expanso da oferta de energia eltrica:
Auentes 16 da Margem Direita. Braslia DF, set. 2010. Avaiable at http://
Subsdios para a discusso de um modelo de desenvolvimento sustentvel
margemdireita.ana.gov.br/default.asp.
para 47 Amaznia. Parcerias Estratgicas Ibid 2001:16084.
[4] Assis, Raslan Alexandre, Siqueira Emerson. O Ministrio Pblico e o caso 20
[32] RIMA SLT. Relatrio de Impacto Ambiental da Hidreltrica So Luiz do Tapajs .
das PCHs da Bacia do Alto Paraguai (Pantanal) in Hidreltricas e a atuao do
CNEC e WorleyParsons. Available at: www.ibama.gov.br/licenciamento;
Ministrio Pblico na Amrica Latina/Maia, Leonardo Castro. Porto Alegre:
2014.
Letra & Vida: Red Latinoamericana de Ministrio Pblico Ambiental; 2013
[33] ROHDE Geraldo Mrio. Estudos de impacto ambiental: a situao brasileira. In:
Cappelli, Slvia; Pontes Jnio, Felcio (Org.), 225256.
Verdum, Roberto, Medeiros, Rosa Maria Vieira, editors. ampl. Porto Alegre:
[5] Ayres, Madalena Junqueira. O processo decisrio de implantao de projetos
Universidade/UFRGS; 1995. p. 2036.
hidreltricos no Brasil. Anlise dos Casos Referncia da Usina de Barra Grande
[34] ROSA Luis Pinguelli, et al. Impacto de grandes projetos hidreltricos e
e do Complexo Hidreltrico do Rio Madeira Luz da Avaliao Ambiental
nucleares. Rio de Janeiro: Marco Zero/CNPq, AIE/COPPE; 1988.
Estratgica. Master Degree Thesis, PUC-Rio. 2009.
[35] Rosa Luiz Pinguelli, Schaeffer Roberto. Global warming potentials the case of
[6] Mundial, Banco. Licenciamento Ambiental de Empreendimentos Hidreltricos
emissions from dams. Energy Policy 1995;23(2):14958.
no Brasil: Uma Contribuio para o Debate; 2008.
[36] Rovere ELL. A Sociedade Tecnolgica, o Planejamento e a Democracia. In:
[7] Bruce Christopher. Can contingent valuation resolve the adding-up problem
Goldemberg M, editor. Rio de Janeiro: Editora REVAN; 1992. p. 77104.
in environmental impact assessment? Environ Impact Assess Rev 2006;26:
[37] Snchez, Morrison-Saunders. Learning about knowledge management for
57085.
improving environmental impact assessment in a government agency: The
[8] Burian Paulo Procpio. Do estudo de impacto ambiental avaliao ambiental
Western Australian experience. Journal of Environmental Management
estratgica: ambivalncias do processo de licenciamento ambiental do setor
2011;92:226071 2011.
eltrico. Doctorate thesis. Campinas: Universidade Estadual de Campinas;
[38] Snchez. Avaliao Ambiental Estratgica e sua aplicao no Brasil. Texto
2006 SP : [s.n.],.
preparado como referncia para o debate Rumos da Avaliao Ambiental
[9] Bursztyn et al (2001). A politica sustentabilidade politica energtica e
Estratgica no Brasil realizado em 9 de dezembro de 2008 no Instituto de
conitos ambientais. Garamond Universitria.
Estudos Avanados da Universidade de So Paulo. Available at www.iea.usp.
[10] Canter Larry. Participacin pblica en la toma de decisiones ambiental.
Madrid: Mc Graw Hill; 1998. br; 2008.
[11] COBA & PROCESL (). Programa Nacional de Barragens com Elevado Potencial [39] Snchez Luis Henrique. Avaliao de Impacto ambiental: conceitos e mtodos.
Hidroeltrico: Available at http://pnbeph.inag.pt/np4/np4/?newsId=4& Ocina de Textos 2008:287311.
leName=PNBEPH_RA_Memoria.pdf; 2007. [40] Santos MA, Rosa LP, Sikard B, Sikar E, Oliveira Ednaldo. Gross greenhouse gas
[12] CNI, 2014. Licenciamento ambiental: propostas para aperfeioamento uxes from hydro-power reservoir compared to thermo-power plants. Energy
confederao Nacional da Industria. Available at http://www.portaldaindus Policy 2006;34:4818.
tria.com.br/. [41] Soito Joo Leonardo, Freitas Marcos Aurlio. Amazon and the expansion of
[13] EPE. Plano Nacional de Energia para 2030. Empresa de Pesquisa Energtica hydropower in Brazil: vulnerability, impacts and possibilities for adaptation to
EPE. Available at http://www.epe.gov.brhttps://ben.epe.gov.br/downloads/ global climate change. Renew Sustain Energy Rev 2011;15 316:316577.
Resultados_Pre_BEN_2012.pdf; 2006. [42] Soussan, John, Nilsson, Mans, 2009. Strategic Environmental Assessment of
[14] EPE. Termo de Referncia (TDR) para elaborao do PNE 2050. Empresa de 10 the Hydropower Master Plan in t Context of Development VI.
Pesquisa Energtica. Available at http://www.epe.gov.br; 2013. [43] Staffen, Marcio, Bodnar, Zenildo. Audincia judicial participativa como instru-
[15] Fischer T. Strategic environmental assessment in post-modern times. 74 mento de acesso 44 justia ambiental: dilogo com Elio Fazzalari. Planeta
Bedford Street South, Liverpool L69 7ZQ, UK: Department of Civic Design, Amaznia: Revista 45 Internacional de Direito Ambiental e Polticas Pblicas.
The University of Liverpool; 2003. Macap, n. 2, p. 89-104, 46 47 2010. Available at le:///C:/Users/03795809690/
[16] Glasson J, Salvador NNB. EIA in Brazil: a procedurespractice gap. A compara- Downloads/127-1460-1-PB.pdf.
tive 20 study with reference to the European Union, and especially the UK. [44] Steinemann Anne. Improving alternatives for environmental impact assess-
Environ Impact Assess Rev 2000;20:191225. ment. Elsevier Science Inc. Environ Impact Assess Rev 2001;21:321.
[17] Gontier M, Balfors B, Mortberg U. Biodiversity in environmental assessment [45] TCU, 2004. Tribunal de Contas da Unio. Acordo 464/2004. Disponvel em
current practice and tools for prediction. Environ Impact Assess Rev www.tcu.gov.br.
2006;26:26886. [46] Teixeira, Izabella Teixeira Mnica . O Uso da Avaliao Ambiental Estratgica
[18] IBAMA. Avaliao de impacto ambiental: agentes sociais, procedimentos e no Planejamento de Oferta de Blocos para Explorao e Produo de Petrleo
ferramentas. Braslia: IBAMA; 1995. p. 1995. e Gs Natural no Brasil: uma proposta. Tese de Doutorado. Available at http://
[19] IBAMA. GEO Brasil 2002. Perspectivas do Meio Ambiente no Brasil/Organizaed www.coppe.ufrj.br/; 2008.
by Thereza Christina Carvalho Santos e Joo Batista Drummond Cmara; 2002. [47] Tolmasquim, Mauricio. O modelo institucional do setor eltrico brasileiro e seus
[20] IBAMA. Parecer Tcnico no. 143/2011 Anlise do 1 Relatrio de Andamento resultados. Palestra realizada no seminrio internacional abce fepac sinaenco,
do Plano Bsico Ambiental da UHE Belo Monte. Avaiable at www.ibama.gov. Rio de Janeiro (RJ). Available at http://www.sinaenco.com.br/downloads/Tolmas
br/licenciamento; 2011. quim.pdf; 2012.
[21] IBAMA. Processo de Licenciamento Ambiental da Usina de Belo Monte [48] Tucci, Carlos E. M. e Mendes, Carlos A. Curso de Avaliao Ambiental Integrada
02001.001848/2006-75. Available at http://www.ibama.gov.br/licenciamento/; 10 de Bacia Ministrio do Meio Ambiente. Secretaria de Qualidade
2014. Ambiental; 2006.
[22] Kumar A, Schei T, Ahenkorah A, Caceres Rodriguez R, Devernay J-M, Freitas M, [49] Unger, Mangabeira. Licenciamento Ambiental Reformas Institucionais e
et al. Hydropower. Cambridge, United Kingdom and New York, NY, USA: Aes para a 13 Gerao de Oportunidades. Braslia, junho de 2009. Available
Cambridge University Press; 2011. at http://www.law.harvard.edu/faculty/unger/portuguese/pdfs/11_Licencia
[23] Manyary Waleska, Carvalho Osmar. Environmental considerations in energy mento_ambiental1.pdf.
planning for the amazon region: downstream effects of dams. Energy Policy [50] Westin, Fernanda Fortes. Anlise do uso da avaliao de impacto ambiental
2007;35:347382. estratgica e integrada no contexto da expanso da hidroeletricidade e da
[24] MMA. Manual de Avaliao Ambiental Estratgica. . Braslia: MMA/SQA; 2002. poltica nacional de recursos hdricos: proposta para a efetividade. Doctorate
p. 92. thesis, Energy Planning Program/COPPE/UFRJ. Rio de Janeiro; 2014.
[25] MMA. Caderno setorial de recursos hdricos. Braslia: gerao de energia [51] WCD. The World Commission on Dams. Dams and Development A new
hidreltrica/Ministrio do Meio Ambiente Secretaria de Recursos Hdricos; framework for decision-making. The report of the Word Commission of Dams.
2006. Earthscan Publications; 2000.
[26] MME/EPE. Plano Decenal de Expanso de Energia 2022/Ministrio de Minas e [52] Wood C. Environmental impact assessment: a comparative review. 2nd ed..
Energia. Empresa de Pesquisa. Available at http://www.epe.gov.br; 2013. London: Person Prentice Hall; 2003. p. 2003.