CALCULATION
DOCUMENT NO. REV : 0
THERMAL SAFETY VALVE (TSV) PAGES :
-
1 of 7
REVISION SHEET
DOCUMENT NO.
THERMAL SAFETY VALVE (TSV) REV : 3
-
3 of 7
Revision
LOCATION :
SUMMARY
BALIKPAPAN
4 SUMMARY
5 Min Firewater Shell's Roof top Actual Firewater Total
Ring Application Rate
8 No. Description Demand Nozzle Nozzle Demand Nozzle
Quantity (L/min.m2)
m3/h lpm Quantity Quantity m3/h gpm Quantity
1 ADO Tank (D-20-04D) 3 0.00 0.00 0.00 0 0 0.00 0.00 0
2 FAME Tank 3 10.20 1222.67 20377.80 124 86 1223.34 5386.20 210
3 RFO Tank 3 10.20 527.74 8795.71 62 30 535.94 2359.67 92
9 3 Premium Tank 3 10.20 1127.41 18790.19 122 72 1130.13 4975.82 194
10 TOTAL 2877.82 47963.69 308 188 2889.42 12721.70 496
11
13
14
15
17
18
19
20
21
32
33
33
33
33
33
33
PROCESS SAFETY CALCULATION
DOCUMENT NO.
THERMAL SAFETY VALVE (TSV) REV : 0
-
4 of 7
CLIENT : Rev Date Made by Checked by Page
PT. PERTAMINA 1 6-Jul-15 HRS ARF
LOCATION :
BALIKPAPAN 3 of 4
B. Design Data
10
11
13
14
15 C. Calculation :
17 1. Calculate Heat Absorption to Liquid
18 (API STD 521, 6th Ed, 4.4.13.2.4.2)
19
20 C1 = 43200
21 F = 0.03
32 AWS = 333
33 Q = 151708.28 Watt
33
33 2. Calculate
33
E. Reference:
33 1. NFPA 15, Standard for Water Spray Fixed Systems for Fire Protection, 2012 edition
33 2. To be confirmed by VENDOR
Page
Revision
3 of 4
PROCESS SAFETY CALCULATION
DOCUMENT NO.
THERMAL SAFETY VALVE (TSV) REV : 3
-
5 of 7
11 B. Fire Scenario :
13 1. HVGO Tank on fire
14 In case of HVGO Tank is on fire, then ADO Tank will be exposed by heat radiation from HVGO Tank. Hence, the shell area and
roof top surface area of ADO Tank which are facing HVGO Tank is cooled by water spray.
15 C. Calculation :
17 I. Surface Area to be Protected
18 Surface Area for Tank's Shell = 131 x 14.98 = 1962 m2
19 Surface Area for Tank's Roof (Cone) = rs = 1367.73 m2
20 Total Surface Area = 3329.71 m2
21
0 = 86.0 nozzle
Actual Firewater Demand = 5386.2 gpm
33
E. Reference:
33 1. NFPA 15, Standard for Water Spray Fixed Systems for Fire Protection, 2012 edition
33 2. To be confirmed by VENDOR
Page
Revision
3 of 4
PROCESS SAFETY CALCULATION
DOCUMENT NO.
THERMAL SAFETY VALVE (TSV) REV : 3
-
6 of 7
11 B. Fire Scenario :
13 1. RFO U.13 on fire
14 In case of RFO U.13 Tank is on fire, then RFO Tank U.14 Tank will be exposed by heat radiation from RFO U.13 Tank. Hence, the shell area and
roof top surface area of RFO U.14 Tank which are facing RFO U.13 Tank is cooled by water spray.
15 C. Calculation :
17 I. Surface Area to be Protected
18 Surface Area for Tank's Shell = 75 x 12.8 = 965.097 m2
19 Surface Area for Tank's Roof (Dome) = 2rh = 472.11 m2
20 Total Surface Area = 1437.21 m2
21
0 = 30 nozzle
Actual Firewater Demand = 2360 gpm
E. Reference:
33 1. NFPA 15, Standard for Water Spray Fixed Systems for Fire Protection, 2012 edition
33 2. To be confirmed by VENDOR
Page
Revision
3 of 4
DOCUMENT NO.
THERMAL SAFETY VALVE (TSV) REV : 3
-
7 of 7
11 B. Fire Scenario :
13 1. HVGO Tank on fire
14 In case of HVGO Tank is on fire, then ADO Tank will be exposed by heat radiation from HVGO Tank. Hence, the shell area and
roof top surface area of ADO Tank which are facing HVGO Tank is cooled by water spray.
15 C. Calculation :
17 I. Surface Area to be Protected
18 Surface Area for Tank's Shell = 119 x 16.2 = 1934 m2
19 Surface Area for Tank's Roof (Cone) = rs = 1136.33 m2
20 Total Surface Area = 3070.29 m2
21
33 Minimum nozzle required for top surface area of Tank (1 ring) = 72 nozzle
Actual Firewater Demand = 4976 gpm
E. Reference:
33 1. NFPA 15, Standard for Water Spray Fixed Systems for Fire Protection, 2012 edition
33 2. To be confirmed by VENDOR
Page
Revision
3 of 4
ADO
r = 26 m
t = 1.625 m
r2 = 676
t2 = 2.640625
s2 = 678.6406
s = 26.05073
FAME
r = 20.845 m
t = 1.302813 m
r2 = 434.514
t2 = 1.69732
s2 = 436.2113
s = 20.88567
Premium
r = 19 m
t = 1.1875 m
r2 = 361
t2 = 1.410156
s2 = 362.4102
s = 19.03707