You are on page 1of 8

completion incuding binding wire from Km 82.300 Km to Km 112.

500 of KBC, Package


No.1

Sl No Item Unit Qty Rate Amount


1
Labour Charges for Reinforcement Cutting,Bending,
tying & Transportation up to completion incuding
binding wire below 16Dia
MT 1.832 3650.00 6688.26
2 Labour Charges for Reinforcement Cutting, Bending,
tying & Transportation up to completion incuding
binding wire 16Dia & Above

MT 8.756 3350.00 29333.74


3 Labour Charges for Shifting of Steel from yard to
required Site Location
MT 10.589 400.00 4235.50
4 Labour charges for shuttering & De shuttering for
Raft & foottings
Sqmt 0.000 100.00 0.00
5 Labour charges for shuttering & De shuttering for
Walls Sqmt 48.686 250.00 12171.53
6 Labour charges for shuttering & De shuttering for
Piers Sqmt 0.000 150.00 0.00
7 Labour charges for shuttering & De shuttering for
Piers -(2ND Lift) Sqmt 0.000 165.00 0.00
8 Labour charges for shuttering & De shuttering for
slab above 3.5 Mtr. Sqmt 0.000 250.00 0.00
9 Labour charges for shuttering & De shuttering for
Haunch Portion Sqmt 0.000 40.00 0.00
Labour charges for shuttering & De shuttering for
10 Slab up to 3.5 m height Sqmt 0.00 200.00 0.00

Labour charges for Stagging, de-stagging including


11 all tools and tackles.
Cum 0.00 25.00 0.00

12
Labour charges for fixing of Water Stopper Rmt 0.000 25.00 0.00
13
Labour charges for fixing of Bituminious Sqmt 0.000 40.00 0.00
14
Pouring of concrete for Slab with boomplacer cum 0.000 40.00 0.00

15 Pouring of concrete for Piers with boomplacer Cum 38.821 70.00 2717.46

16 Labour charges for Ply wood Shutter making Sqmt 0.000 50.00 0.00
Total : 55146.48
or Say : 55146.00

Prepared by Checked by Approved by


ABSTRACT for Steel Qty

Discription Unit Below 16mm


Steel Qty of CR/FALL @ 82.300Vide P.No Ref. P -20 to23/4A
MT 1.832
Total: 1.832

ABSTRACT for Shuttering Qty

Discription Unit Qty

Wall Shuttering Qty of CR/FALL 82.300 Qty vide P.No Ref. P -24/4A Sqm 49

ABSTRACT for Concreting Qty


Discription Unit Qty
Wall concreting Qty of CR/FALL 82.300 Qty vide P -24/4A cum 38.82

Prepared by Checked by
16mm & above

8.756
8.756
Steel Qty for CR/FALL@82.300

Bar Description Dia No's Length Wt /Rmt


Total
Length
CR Portion /sec 1-1
wall verticals 25 35 9.30 325.50 3.854
wall verticals 25 39 8.13 317.07 3.854
wall verticals 25 70 9.30 651.00 3.854
wall verticals 25 78 8.13 634.14 3.854
CR Portion /concrete wall 0.00
wall verticals 25 70 9.30 651.00 3.854
wall verticals 25 78 8.13 634.14 3.854
wall verticals 12 184 3.50 644.00 0.888
wall binders 12 17 18.85 320.45 0.888
wall binders 12 17 0.60 10.20 0.888
wall binders 12 17 22.45 381.65 0.888
wall binders 12 17 0.60 10.20 0.888
LHS /CF2 Stem wall(1 to 12 mt) 0.00 0.000
wall binders(inner) 16 10 25.90 259.00 1.579
wall binders(inner) 16 12 25.90 310.80 1.579
6th wall to 14 th wall vertical laping 25 84 2.20 184.80 3.854
6th wall to 14 th stem wall vertical laping 25 28 2.20 61.60 3.854
LHS /CF2 6th wall to 14 th wall distribution
laping 12 140 1.10 154.00 0.888
LHS /CF2 1 st wall to 6 th wall /stem wall
laping(outer face) 20 7 12.80 89.60 2.467
LHS /CF2 1 st wall to 6 th wall /stem wall
laping(3.6 to 4.8 ) 16 7 12.80 89.60 1.579

stem wall verticals over laping 12 103 3.00 309.00 0.888


stem wall verticals over laping(outer) 12 103 4.00 412.00 0.888
CF2 1 st wall to 6 th wall distribution
laping(3.6 to 4.8 ) 12 50 1.60 80.00 0.888
LHS /CF3 stem wall distribution laping 12 30 13.98 419.40 0.888
12 128 4.00 512.00 0.888
12 64 2.92 186.56 0.888
Total :

Description Total Qty in Kgs

Below 16mm 3054.00


16mm & above 14593.90
Total 17647.90
Prepared by Checked by
Ref. P -20 to23/4A
Now
Total wt Release Total wt (Kgs )
(Kgs ) Pecentage
%

1254.47 60% 752.68


1221.98 60% 733.19
2508.94 60% 1505.36
2443.96 60% 1466.38
0.00 60% 0.00
2508.94 60% 1505.36
2443.96 60% 1466.38
571.84 60% 343.11
284.55 60% 170.73
9.06 60% 5.43
338.89 60% 203.33
9.06 60% 5.43
0.00 60% 0.00
408.85 60% 245.31
490.63 60% 294.38
712.22 60% 427.33
237.41 60% 142.44

136.75 60% 82.05

221.00 60% 132.60

141.44 60% 84.87

274.38 60% 164.63


365.84 60% 219.50

71.04 60% 42.62


372.41 60% 223.45
454.63 60% 272.78
165.66 60% 99.39
17647.90 10588.74

Now to be
Released Qty Qty in MT'S
in Kgs

1832.40 1.832
8756.34 8.756
10588.74 10.589
Shuttering Qty for CR/FALL@82.00
1 Shuttering Work P -24/4A
S.No Description of work No's Length width Depth Qty ( Sqm)

1
CR Portion/LHS-1st wall (0.4 to 2.75)

a
outer&inner shuttering 2 18.36 2.35 86.269
b stopper 2 1.00 2.35 4.700
c stop log groove portion 1 1.68 2.35 3.936
d radail gate groove 1 1.05 2.35 2.468
Total Qty : 97.4
Now Release 90 % of Qty
97.372 50% 48.7

Prepared by Checked by
Concrete Qty for CR/FALL@82.00
1 Pouring of Concrete MB- P -24/4A
S.No Description of work No's Length width Depth Qty ( Cum)
1 CR Portion/1 st wall/04 to 2.75 m 1 18.36 1 2.35 43.134

Total Qty : 43.1


Now Release 90% of Qty
43.134 90% 38.821

Prepared by Checked by