CDM project activity prior consideration form


(Version 03.0)

This form is to be used by project participants in order to submit the notification of the commencement of the
project activity and the intention to seek CDM status. 1

Is this Initial Submission?


(tick only if applicable)

Is this Notification of progress?


(tick only if applicable)

SECTION 1: PROJECT DETAILS

.A Title of the proposed project activity

Malea Hydroelectric Power Plant Project

.B Location of the proposed project activity (Specify Town/City, Region, Country and precise
geographical location such as geo-coordinates or other adequate means to identify the project
location)

Project located at upstream of Sadang River, Tana Toraja Regency, South Sulawesi Province, Indonesia.
Geographical coordinate of project location between 0230'00"S - 380'00"S and 11920'00"E - 12001'00"E

.C Technology under consideration

The project will use hydro powered turbine engine from Toshiba, Japan.

.D Brief description of the proposed project activity

The project involves the construction and operating a 2x45 MW hydropower plant for first phase and 3x75
MW for the second phase at Sadang river. Power will be evacuated with a transmission line of about 12 KM
to Makale city. The electricity will be sold to Perusahaan Listrik Negara (PLN) under PPA. The project will
reduce greenhouse gas (GHG) emission by avoiding CO2 emissions from fossil fuel power plants.

1
The completed form should be sent to the Host Party DNA (find DNA contacts at: https://cdm.unfccc.int/DNA/index.html) and the
UNFCCC secretariat (P.O. Box 260124 D-53153 Bonn Germany, OR cdmregistration@unfccc.int)

Version 03.0 Page 1 of 3


CDM-PC-FORM
SECTION 2: NOTIFICATION OF PROGRESS MADE2

.A Brief description of progress made

Malea Energy has paid 5% LC for Turbine Engine on January 2017. Loan fund from Bank Negara Indonesia
and Bank Rakyat Indonesia partially disbursed starting from the end of June 2017.

.B Original title of the proposed project activity


(only if project title has changed since submission of initial Prior consideration form)

Malea Hydroelectric Power Plant Project

SECTION 3: CONTACT INFORMATION

Name of the project participant: PT. Malea Energy


(legal entity name)

Contact details of authorized representative: Mr. Ms.

Last name: Kalla Telephone:

First name: Suhaeli Fax:

Email: Address: JI. Amil No. 7, Warung Buncit, Jakarta


Selatan, Indonesia, 12740

Signature: Date: .

-----

2
This section shall be filled until the PDD of a project activity has been published in accordance with the relevant provisions of the
CDM project cycle procedure.

Version 03.0 Page 2 of 3


CDM-PC-FORM
Document information

Version Date Description

03.0 17 March 2015 Revision to:

Include a provision on the technology under consideration;

Clarify the specification of a provision on the location of the


proposed project activity;

Change the symbol from F-CDM-PC to CDM-PC-FORM and


minor editorial improvements;

Editorial improvement.
02.0 13 March 2012 EB 66.
Revision required to ensure consistency with the clean development
mechanism project cycle procedure as referenced in the
implementation plan for the clean development mechanism project
standard, validation and verification standard and project cycle
procedure (EB 65 report, annex 6, appendix 1).
01.0 17 July 2009 EB 48, Annex 62.
Initial adoption.
Decision Class: Regulatory
Document Type: Form
Business Function: Registration
Keywords: prior consideration, project activities

Version 03.0 Page 3 of 3