SAUDI ARAMCO ID/PID FORM REV 1 - 010109 Rev 6 COS 03/31/2012

SATIP No. APPROVED DATE DISCIPLINE:


SAUDI ARAMCO TYPICAL INSPECTION PLAN
Chilled Water System SATIP-K-001-05 30-Apr-13 HVAC
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
QUALITY ASSIGNMENTS
ITEM PROJECT PHASE QUALITY
TASK / ACTIVITY PROCEDUR REMARKS
NO. & ACTIVITY CODE RECORD
E CNTRCTR
SAUDI
ARAMCO

1.0 DOCUMENT REVIEW

Review of HVAC System Testing See See See SATIP-K-001-12 Testing, Adjusting and Balancing
1.1
Organization Qualifications Remarks Remarks (TAB) of the HVAC System
Review of HVAC System Testing, See See See SATIP-K-001-12 Testing, Adjusting and Balancing
1.2
Adjusting and Balancing Procedures Remarks Remarks (TAB) of the HVAC System

Chilled Water System does not require NDT nor


Radiography Testing.
See See
1.3 Review of Hydro Test Packages Hydrostatic Testing of On-Plot Piping - SATIP-A-004-
Remarks Remarks
02
Hydrostatic Testing of Pipelines - SATIP-A-004-03

Review of Chilled Water System See See Treatment Procedure shall be reviewed and approved
1.4
Treatment Remarks Remarks by Environmental Protection Department.

2.0 MATERIAL RECEIVING

Chilled Water System Components include but are not


Chilled Water System Components SAIC- SAIC- necessarily limited to: Air Cooled Chillers, Pumps
2.1
Receiving Inspection K-4022 K-4022 H W Expansion Tanks, Air Separator and Chemical Dosing
Systems

Chilled Water System Components


SAIC- SAIC-
2.2 Handling, Storage and Preservation
K-4022 K-4022 W S Weekly Inspection by QA/QC Contractor
Inspection

See See
2.3 Chilled Water Piping See SATIP-K-001-04 Chilled Water Piping
Remarks Remarks

See SATIP-G-005-01 Centrifugal Pump for 50 hp and


larger. For less than 50 hp refer to manufacturers
See See recommendation, however contractor shall develop
2.4 Chilled Water Pumps
Remarks Remarks the inspection checklist in accordance with the
manufacturer recommendation subject to PID
approval.

3.0 INSTALLATION

Page 1 of 3
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 Rev 6 COS 03/31/2012
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Chilled Water System SATIP-K-001-05 30-Apr-13 HVAC
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
QUALITY ASSIGNMENTS
ITEM PROJECT PHASE QUALITY
TASK / ACTIVITY PROCEDUR REMARKS
NO. & ACTIVITY CODE RECORD
E CNTRCTR
SAUDI
ARAMCO

Chilled Water System Components include but are not


Chilled Water System Components SAIC- SAIC-
3.1
Inspection K-4023 K-4023 H W necessarily limited to: Air cooled chillers, Expansion
Tanks, Air Separator and Chemical Dosing Systems

Air Moving/Cooling Equipment


SAIC- SAIC- Saudi Aramco shall be notified on start of this activity
3.2 Duct/Pipe Connection
K-4003 K-4003 H W for each location by type or manufacturer
Inspection

See SATIP-G-005-01 Centrifugal Pump for 50 hp and


larger. For less than 50 hp refer to manufacturers
See See recommendation, however contractor shall develop
3.3 Chilled Water Pumps
Remarks Remarks the inspection checklist in accordance with the
manufacturer recommendation subject to PID
approval.

See See
3.4 Chilled Water Piping See SATIP-K-001-04 Chilled Water Piping
Remarks Remarks

See See
3.5 Air Handling Unit See SATIP-K-001-02 Air Handling Units
Remarks Remarks

SAIC-K- Saudi Aramco shall be notified on the start of this


3.6 Fan Coil Units (FCU) SAIC-K-4040
4040 H W activity for each location by type or manufacturer

4.0 PRE-COMMISSIONING

SATR- SATR-
4.1 Chilled Water System Treatment
K-4002 K-4002 RH RH

System Testing, Adjusting and See See See SATIP-K-001-12 Testing, Adjusting and Balancing
4.2
Balancing Report Remarks Remarks (TAB) of the HVAC System

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may
1 adjust the levels of Saudi Aramco participation based upon the Contractors performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization

Page 2 of 3
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 Rev 6 COS 03/31/2012
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Chilled Water System SATIP-K-001-05 30-Apr-13 HVAC
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
QUALITY ASSIGNMENTS
ITEM PROJECT PHASE QUALITY
TASK / ACTIVITY PROCEDUR REMARKS
NO. & ACTIVITY CODE RECORD
E CNTRCTR
SAUDI
ARAMCO

Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4 attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H 100% Hold Point for QC Inspection or Test. R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 3 of 3