Professional Documents
Culture Documents
Headquaters address: Phuc Tan village, Gia Tan commune, Gia Loc district, Hai
Duong province.
ID number: 141946236
Date of issue: July 4, 2013 Place of issue: Hai Duong provinces Police
agency.
Permanent address : Phuc Tan village, Gia Tan commune, Gia Loc district, Hai Duong
province, Viet Nam.
Curent address: Phuc Tan village, Gia Tan commune, Gia Loc district, Hai Duong
province, Viet Nam.
-The Governments Decree No. 118/2015/ND-CP issued on November 12, 2015 detaily
define and guide the implementation of some articles from the investment law;
- Decision No. 1173/2013/QD-BTC issued on May 21, 2013 of the Minister of Finance
on the amendment of the Circular 45/2013/TT-BTC issued on April 25,2013 of the
Ministry of Finance guide the management regime, usage and fixed assets depreciation;
- Decision No. 11/2010/QD-UBND issued on June 22, 2010 of Hai Duongs People
Committee on management decentralization in some fields: construction planning,
1.2.2. Area:
Area: 29.773 m2.
Detailed description:
1.4.2. Facilities :
33.801.800.00
I Production machinery 0
syste
1 IQF machine system Japan m 4 6.200.000.000 24.800.000.000
Fruits washing machine: 1.522.500.00 4.567.500.00
2 D3230xR1350xC1510 Japan piece 3 0 0
Peeling machine: D1900x 707.000.00 2.121.000.00
3 R700x C 800mm Japan piece 3 0 0
Slicing machine:
D597xR1180xC1490 555.500.00 1.111.000.00
4 mmm Japan piece 2 0 0
Square-cut machine: 505.000.00 505.000.00
5 D901xR756xC1329 Japan piece 1 0 0
348.650.00 697.300.00
Vacuums machine 2-95
6 Netherland piece 2 0 0
II Equipment 194.500.000
joint- 50.000.00 50.000.00
1 Testing equipment venture piece 1 0 0
Humidity measuring joint- 15.000.00 30.000.00
2 device venture piece 2 0 0
Cooling measuring 5.000.00 25.000.00
3 device Japan piece 5 0 0
8.700.00 43.500.00
4 Computer LG piece 5 0 0
Process explaination:
Production plan:
Planning team receives requests from customers, thus creates daily, weekly, monthly
plan; deploys production plan in the factorys display in order to implement the
production (Refer to the production planning process).
Material checking:
Manual checking.
Input materials are randomly taken out to check refer to the regulated standards.
Use normal eyes and personal experiences to choose and evaluate, thus calcutale
percentage of materials which are not up to standards.
Based on standard specifications, use visual method to compare then select standard
products, calculate non-standard materials level (which has been less than 15%).
Raw materials are gathered to the factory which can be placed outside from 4 to 5
hours under cool weather conditions, then put into production or cooling storage; from 2
to 3 hours under summer weather conditions (with 2 10 Celsius degree cooling storage).
Material cleaning: use technical machines
The selected materials will pass through the impurity separation system, then
through the vibration separator for the first unsuitable materials removal.
The materials are taken down to the aeration tank and the water will remove mud
and sand in their surfaces.
The hygene materials source was contracted by the company with producers from the
beginning of the growing seasons. Our nation is a agricultural country so the supply
source is relatively abundant.
The company has signed contracts with groups of producers and cooperatives in and
outside the province, specializing in providing clean vegetable products.
2. Output market:
The output markets of frozen vegatables are mainly Japan, Korea, Dubai, according
to the orders signed by partners. Currently, the company has signed a number of contracts
in pricinple with companies purchasing frozen vegetables.
1. Site planning:
Construction works are arranged in the rent land to ensure safety corridors,
construction boundaries, usage capacity, relationship between departments, harmony of
beauty.
Green space: Arrange green trees around the site to contribute a clean enviroment for
factory area, reduce dust and noise, create a clean space.
The internal road sections shall ensure the fire prevention and fighting regulations
for vehicles to transport safely.
- Operation house: a two- floor buiding with total area of 720m2 according to the
permanent style housing which has structural framework, concrete roof, heat resistant
roof, brick wall, yellow sand cement built and plastered. The floor is made of broken
concrete, ceramic tile, the main door is the hydraulic glasss door. Their fuctions are the
workplaces of the company departments.
- Products eshibition house (5 houses): a one-floor construction scale with total
area of 750m2 according to the permanent style housing which has structural framework,
concrete roof, heat resistant roof, brick wall, yellow sand cement built and plastered. The
floor is made of broken concrete, ceramic tile, the main door is the hydraulic glasss door.
Their fuctions are the workplaces of the company departments.
- Workers canteen : a two-floor construction scale with total area of 720m2
according to the permanent style housing which has structural framework, concrete roof,
heat resistant roof, brick wall, yellow sand cement built and plastered. The floor is made
of broken concrete, ceramic tile, the main door is the hydraulic glasss door. Their fuctions
are the workplaces of the company departments.
- Agricultural products primary processing factory (2 factories): a one-floor
construction scale with total area of 1400m2 which has zemin steel framework, steel
system roof and industrial roof, three-sided walls and one is opened space for vehicles
while production operation, to ensure the early vegetables processing, and the area,
corridors, fire fighting
Internal roads:
The internal courtyard is backfilled with K=0.9 ; the structural surface by concrete.
Details as follows :
- Concrete layer by stone 2x4, 15cm of thickness.
- The compacted layer of stone has 15cm of thickness.
- The compacted sand floor K = 0.9 and 30cm of thickness.
In the yard, the internal roads is designed sloping along a roof and two roofs to
ensure the best drainage.
Supported construction works:
b.Electricity supply:
Details as follows:
1. Construction cost:
33.801.800.00
I Production machinery 0
2. Other expenses:
Including:
Due to the large investment capital in the project and long-term payback period, in
order to safety invest, the company proposed to lease the land for 30 years from the date
of having investment decision.
1.7. Project implementation schedule:
1.7.1. Construction schedule:
Completed construction is put into operation synchronously after 24 months from
the date of land handover.
1.7.2. Capital mobilization schedule:
+ Paid-in capital: 35.000.000.000 vnd
+ Finance leasing capital: 84.091.000.000 vnd under the commitments with the
banks.
To increase efficiency, reduce indirect costs, use experienced staff, reduce service
cost, the company will arrange a light operation department, experienced staff, one person
can cum many tasks with direct management regime, regular report the business
operation, production process to ensure smooth command, disciplined and effective
operatiton.
Details as follows:
1 Director 1
2 Indirect department 8
3 Direct worker 300
4 Security 2
1. Director:
Director is the general manager of all production activities of the company; must
take full responsibility in front of Law for his/her rights and obligations implementation.
The companys director manages the production through the deputy directors and
departments such as the accouting department, planning and engineering department.
This unit implements the accounting regime in the whole company in accordance with
the financial regualations of the State; responsible for financial works in front of the
Director and functional agencies.
Manage products quality, production plan, process and labor safety. This department
is responsible for production planning, supplying and stockpiling plans; responsible for
labors in the company and propose recruiting and training workers plan in the future.
4. Production factories:
1. Labor salary:
- At the end of each business period, the company will evaluate and have a
satisfactory rewards for individuals with high contributions.
- Under Labor Law: 8 hours/ day and 48 hours/ week. In the case of overtime work,
all time and working regime are also in accordance with Labor Law. Employees will be
entitled to full holidays, New year holidays, leave as prescribed.
- Besides, workers are ensured other rights such as: social and health insurance...
well-prepared clothes and safety equipments while working; receive medical
examinations and treatment; entitle to allowances as prescribed.
Employees usage under the Labor Law of the Government and the regulations of the
company.
Workers will be recruited locally and trained necessary skills to meet their assigned
work requirements.
To ensure the effective business operation, all post-recruitment workers must have a
vocational training, occupational health, safety working management. While operation, it
is necessary that factory managers and supervisors, technicians must be experts,
instructors for the workers to understand skills clearly, thus put into the production line.
The company will sign a contract with each employees. All their responsibilities,
rights and interests are clearly stated in the labor contract.
- The project implementation in this land is in accordance with the socio- economic
development plan of Hai Duong province, in accordance with the 2017s land use plan of
Gia Loc district.
- Along with many companies development in Hai Duong province, the expansion
of produciton base of Hung Viet Co., ltd also contributes to promote the socio-economic
development of Hai Duong province; in which creates more stable jobs for people,
improves their material life, preserves the social order and safety, thus contributes to the
State budget from the companys profit tax.
Including:
- Inputs costs:
QUANTIT
No. GOOODS UNIT Y PRICE TOTAL PRICE
- Labor costs:
Working
No. Categories Workers time Salary Price
TOTAL 19.582.80.0
Payback period
1.9. Incentives on exemptions from land rent payment, land usage, land taxes:
- According to point 9 of the appendix of sectors eligible for special investment
incentives in agricultural and rural development promulgated under the Governments
Decree No. 210/2013/ND-CP issued on December 19, 2013.
- According to Clause 5, Article 3; and Clause 4, Articale 6 under the Decree No.
210/2013/ND-CP issued on December 19, 2013.