Professional Documents
Culture Documents
50
This paper described the Marlin TLP oil export pipeline wax Increased flowrate
Introduction
Heat loss to the surrounding seawater causes the fluid
The Marlin Tension Leg Platform (TLP) is located in Viosca temperature to drop below its wax appearance temperature
Knoll Block 915 in the Gulf of Mexico. The water depth at the (WAT, which is approximately 95oF to 100oF) in the first few
platform location is approximately 3,250 feet. miles. Since the pipe wall has the lowest temperature, the
heavy molecular weight paraffinic hydrocarbons begin to
The Marlin TLP is host to three Marlin Field dry tree wells, solidify and deposit on the pipe wall over time and eventually
two Marlin Field subsea wells, two subsea King Field wells, give rise to an exponentially increasing pressure drop (due to
one subsea King West Field well and one Nile Field well reduction in the flow diameter and / or increases in the pipe
These multiphase production well fluids are separated and roughness.)
processed on the Marlin TLP prior to export via two dedicated
pipelines, a 14-inch gas export and a 10-inch oil export to Wax deposition models run for the Marlin oil export pipeline
neighboring shallow water facilities; Main Pass 260 and Main earlier in the project indicated that a wax buildup of 0.009
Pass 225, respectively. Both of the Main Pass (MP) facilities inches thickness occurs in the Marlin oil export line at 40
are not operated by BP. mbod flow rate after 40 days (Figure 2). The models also
indicated that the most of the wax is deposited in the first
Wax Management for Marlin Oil Export Pipeline System 30,000 ft (5.7 miles) of the Marlin oil export line. Total
Original Design volume of wax deposited for this case is estimated at 135 bbls.
The Marlin TLP to Main Pass 225 Platform oil export line is a
non-insulated pipeline approximately 22 miles long.
pipeline was already clean. Around 12:21 PM, the Marlin oil export pipeline pump
The pipeline pressure drop was still higher than shutdown due to low flowrate (~2200 bopd) and high
expected. Decision made to not increase production backpressure. The Marlin Operations team tried to re-start the
levels until the oil export pipeline pressure drops pump immediately but were unsuccessful due to sustained
were reduced to the early January 2004 levels. high backpressure.
Events Leading Up To The Utilization of A More Aggressive Using oil flowrate calculations, the stuck pig was estimated to
Cup Pig be approximately nine (9) miles from the Marlin facility and
The team decided to continue pigging the pipeline with a thirteen (13) miles from the MP 225 facility (Figure 7) in
slightly more efficient pig. The existing pigs at the Marlin approximately 1200 of water depth.
TLP at the time of the decision are shown in Figure 5.
June 11 Pigging Run
Yellow Super Mag Pig launched ~ 8:00am
50000 2500
45000 Flowrate
MP225 Pressure
2000
40000
Marlin Pressure
35000
1500
30000
Pressure Psi
Flow Bopd
25000
1000
20000
15000
(a) Poly Pig 4 available (b) Red &White Disc Pig 4 available 500
10000
5000
Pig Launched 0
8:00am
0
12:00:00 AM 2:24:00 AM 4:48:00 AM 7:12:00 AM 9:36:00 AM 12:00:00 PM 2:24:00 PM 4:48:00 PM 7:12:00 PM
-5000 -500
Time
(c) Orange Cup Pig 1 available (d) Yellow Super Mag Pig 11 available Marlin 10" Oil Export Pipeline Profile
Estimated Stuck Pig
500
MP225
Figure 5 - Existing Pigs at Marlin TLP Marlin TLP 100% fillup: 10,900
bbls
0
The team decided to use the Yellow Super Mag Pig (d) also -500
known as a Poly Tri Cup pig. Other factors effecting the Touchdown:300 bbls
Elevation [ft]
-1000
selection of this pig were:
-1500
Pig Stop location 12:21 pm
It had been used in the Marlin oil export line many -3500
-10000 10000 30000 50000 70000 90000 110000 130000
times with good results. Horizontal Distance from Marlin TLP [ft]
Install equipment to inject 5000 gallons of wax inhibitor injection phase-out and the optimization of the
solvent at the front of the buyback crude. pigging program, all of the conservatism in the original wax
Install equipment to inject 300 ppm of wax inhibitor management strategy had been removed. An alternative wax
with the buyback crude. management strategy /protocol should have been developed
Set up crude oil buyback agreement from Main Pass and communicated to the offshore operations team.
Oil Gathering System.
Set up the Marlin facility to receive the crude oil 3) A better pig launcher/receiver valve design should have
from MP 225 which entailed: been incorporated. The pig launcher/receiver valve design is
critical to the operability of an offshore facility as it usually
Lining up to re-route the buyback crude oil into
requires a complete platform shutdown and pipeline
the heated King subsea flowline system since
depressurization in order to replace the valves around the pig
Marlin has no oil storage capabilities.
launcher/receiver. A very common valve failure is due to
Mobilize a diver to lock open the oil export pressure/flow equalization during the pigging operation. Care
pipeline subsea check valve. should be made in design to minimize valve cutting during pig
launching and receiving operations. Simple sacrificial needle
Stuck Pig Removal Event valve bypass modifications can be added around an existing
The Yellow Super Mag pig was successfully removed from pig launcher/receiver. (Figure 9)
the Marlin oil export pipeline on June 22, 2005 using the back
flowing technique. Use of the real time automation system
which allowed both the Houston office and the Marlin TLP to
monitor real time pressures and flowrates along the entire
system was invaluable in this removal process. Figure 8
shows what the pig looked like after it was retrieved back on
the Marlin platform.
2) An alternative strategy / protocol should have been in place The field data is highly subjective due to many different
in case pigs could not be run for any reason. With the wax factors such as the observers experience, the pig receiver
6 OTC 18387
operation mode (bypass open/close), the time between pig In the middle of the stuck pig recovery planning, a method
arrival and pig removal from the pig receiver, etc. was developed to allow observation into the pipeline system
behaviors and trends during pigging operation. The method
As a part of the incident investigation, the Marlin operation provides a scientific/non-subjective means to determine when
team visited the MP 225 facilities on June 12, 2004. Figure 10 pigging is required and how effective the pigging operation is
shows the picture of the 8" Poly Pig that was launched on May even before the pig arrives at the pig receiver. Figure 13
18, 2004. This pig had been lodged in the pig receiver. MP shows an example of the recorded pigging run raw data trend
225 personnel stated that after 3 hours, the pig was safely while Figure 14 shows the same data after being post-
retrieved and it was in good shape. processed.
1600
45,000
1400
40,000 1200
Flowrate BOPD
1000
35,000 Flowrate
MP225 Pressure 800
Marlin Pressure
30,000 600
400
25,000
Pig Launched 200
9:30am
Time
Figure 11 shows parts of one of the 10" Poly Pig that was
recovered at MP 225. Figure 13 May 27 Pig Run raw data trend
34
Suspected Deposition Location Length
Time = 9:30am - 12:17am = 167 min
32 Location ~4.88 ft/s = 0 - 48898 ft (9.26miles) total length
Horizontal Length = 46700 ft (8.84 miles)
30
PKG Value
20
12:00:00 2:24:00 AM 4:48:00 AM 7:12:00 AM 9:36:00 AM 12:00:00 2:24:00 PM 4:48:00 PM 7:12:00 PM 9:36:00 PM 12:00:00
AM PM AM
Time
Conclusions
This paper describes the Marlin TLP oil export pipeline wax
management strategy, the circumstances that led to the stuck
pig incident, and the lessons learnt from the incident.
Acknowledgement
The authors would like to thank BP America and Shell E&P
for permission to publish this paper. The authors also express
their sincere appreciation to the Marlin Team for their support
in collection of data and sharing of information and lessons
learnt on the stuck pig incident.