fantastic General, Project Management015 2015 ,

The Contract
GENERAL PROVISIONS
Contract Agreement
Letter of Acceptance
Letter of Tender
Specifications
Drawings
Schedules
Appendix to Tender
Tender
Bill of Quantities
Day-work Schedule
) ( Party
Employer
Contractor
Engineer
Site
Contractors Representative
Employers Personnel
Personnel Contractors
Subcontractor

: DAB
FIDIC .
Commencement Date
Time for Completion
Tests on Completion
Taking Over Certificate
Defects Notification Period
Performance Certificate
Money And Payments
Contract Price
Cost
Final Payment Certificate
Final Statement
Interim Payment Certificate
Payment Certificate
Provisional Sum
Retention Money
Statement
Works and Goods
Contractors Equipment
: Materials
Permanent Works
Plant
Temporary Works
Force Majeure
Unforeseeable
Performance Security
Variation
Interpretation
Definitions
Priority of Documents
Assignment
Care and Supply of Documents
Delayed Drawings or Instructions
Employers Use of
ContractorsDocuments
Compliance with Laws
: Joint and Several Liability
: Right of Access to the Site
Permits, Licenses or Approvals
Employers Financial Arrangements
: Employers Claims
Engineers Duties and Authority
Delegation by the Engineer
: Instructions of the Engineer
: Replacement of the Engineer
: Determinations
: Contractors General Obligations
Performance Security
Assignment of Benefit of Subcontract
Co-operation
: Setting Out
: Safety Procedures
: Quality Assurance
: Progress Reports
: Evidence of Payments
: Rates of Wages and Conditions of Labour
: Facilities for Staff
: Disorderly Conduct
: Manner of Execution
: Samples
: Inspection
Rejection
Remedial Work
: Extension of Time for Completion
Rate of Progress
Delay Damages
: Suspension of Work
: Consequences of Suspension
: Prolonged Suspension
: Resumption of Work
: Delayed Tests
: Retesting